Lean Tools and Their Implementation

download Lean Tools and Their Implementation

of 46

Transcript of Lean Tools and Their Implementation

  • 7/30/2019 Lean Tools and Their Implementation

    1/46

    Lean Tools and theirImplementation

    Guided by: Project by:

    Prof. Gajanan Patange Bharat Chaudhary (09ME021)

    Kaushal Chhadva ( 09ME021)

    Akshit Kataria (09ME042)

  • 7/30/2019 Lean Tools and Their Implementation

    2/46

    Content Introduction to lean manufacturing

    Objective of Project

    Wastes in Lean Manufacturing

    Lean tools

    Value stream mapping

    5s + Safety

    Total productive maintenance

    Kanban SMED ( Single minute exchange of dies)

    Kaizen

  • 7/30/2019 Lean Tools and Their Implementation

    3/46

    Content Case studies

    1) Navkala Plastic Molding pvt ltd, Ahmedabad

    2) Real Casting pvt ltd, Ahmedabad

    3) G.S brass Enterprise, Jamnagar ( Under process)

    Propose Implantations

    Conclusion

  • 7/30/2019 Lean Tools and Their Implementation

    4/46

    Introduction to lean manufacturing

    It is a whole new way of thinking, to serve the customers

    with high quality Products, low cost and short deliverytimes.

    Lean is a philosophy that seeks to eliminate waste in all

    aspects of a firms production activities: human relations,

    vendor relations, technology, and the management of

    materials and inventory.

  • 7/30/2019 Lean Tools and Their Implementation

    5/46

    Where can it be applied

    Lean is principally associated with manufacturing

    industries equally applicable to both service and administration

    processes.

    Currently it is also being adopted by the food

    manufacturing and meat processing sectors.

  • 7/30/2019 Lean Tools and Their Implementation

    6/46

    Objective of Project

    Lean implementation is focused on getting the right

    things, to the right place, at the right time, in the rightquantity to achieve perfect work flow while minimizing

    waste and being flexible and able to change.

    The objective of this Thesis is to carry out a study,

    proposal and analysis of improvements about

    Manufacturing in Plastic injection molding, Casting andBrass products machining Industries. By getting these

    improvements; it would have some benefits, adding more

    production and easiness work and also an improvement in

    terms of quality.

  • 7/30/2019 Lean Tools and Their Implementation

    7/46

    Wastes in Lean Manufacturing

    Muda (or non value-added work): Muda is discovered after

    the process is in place and is dealt with reactively. It isseen through variation in output.

    Muri (or overburden): It is focused on the preparation andplanning of the process, or what work can be avoided by

    design.

    Mura (or unevenness): It focuses on implementation andthe elimination of fluctuation at the scheduling or

    operations level, such as quality and volume

  • 7/30/2019 Lean Tools and Their Implementation

    8/46

    Muda wastes

    1) Overproduction: Production ahead of demand

    2) Transportation: To move products that is not actually required toperform the processing.

    3) Waiting: Waiting for the next production step.

    4) Inventory: All components, work-in-progress and finished product not

    being processed.

    5) Motion: People or equipment moving or walking more than is required toperform the processing

    6) Over-Processing: Due to poor tool or product design creating activity.

    7) Defects: The effort involved in inspecting for and fixing defects.

  • 7/30/2019 Lean Tools and Their Implementation

    9/46

    Muri wastes

    Work Flow: Logical directions to be taken.

    Takt time: Maximum time allowed producing in order to meet demand. When

    everyone knows the standard condition, and the standardized work

    sequences, the results observed are:

    Employee morale is heightened

    Higher quality is achieved

    Productivity is improved

    Costs are reduced.

  • 7/30/2019 Lean Tools and Their Implementation

    10/46

    Mura wastes It is based on little or no inventory, by supplying the production process with

    the right part, at the right time, in the right amount, and first-in, first out

    component flow. Just in Time systems create a pull system in which each sub-process

    withdraws its needs from the preceding sub-processes, and ultimately from an

    outside supplier.

  • 7/30/2019 Lean Tools and Their Implementation

    11/46

    Lean Tools:-1) Value stream mapping

    Value Stream Mapping is a method of creating a "One page picture" of all theprocesses that occur in a company, from the time a customer places an order

    for a product, until the customer has received that product in their facility.

    The goal is to depict material and information flows across and throughout allValue-Adding Processes required to produce and ship the product to the

    customer. Value Stream Maps document all of the processes used to produceand ship a product, both Value-Adding and Non-Value-Adding (Waste)

    processes.

  • 7/30/2019 Lean Tools and Their Implementation

    12/46

    Steps in VSM Plan the activity,

    Walk the process and collect the process and step data,

    Produce and analyze the current-state value stream map,

    Produce a future-state map,

    Develop a change plan,

    Implement the changes,

    Review the process and repeat

  • 7/30/2019 Lean Tools and Their Implementation

    13/46

    2)5S +Safety

  • 7/30/2019 Lean Tools and Their Implementation

    14/46

    7 Role of 5S in Different Areas of Industry

  • 7/30/2019 Lean Tools and Their Implementation

    15/46

    3)Total Productive Maintenance

    TPM (Total Productive Maintenance) is an excellent method for meeting

    the demands and for continuous flow manufacturing on equipment. TPM

    does the following: It increases OEE (Overall Equipment Effectiveness) using improvement activities.

    It establishes an autonomous maintenance program performed by equipment

    operators.

    It establishes a planned maintenance system.

    It requires training to improve operation and maintenance skill

    It institutes a system for MP (maintenance prevention) design and earlyequipment management.

  • 7/30/2019 Lean Tools and Their Implementation

    16/46

    Types of Losses

    Losses

    BreakDowns

    Setup andAdjustment

    StartupRejects

  • 7/30/2019 Lean Tools and Their Implementation

    17/46

    Difficulties faced in TPM implementation:

    Typically people show strong resistance to change.

    Many people treat it just another Program of the month without

    paying any focus and also doubt about the effectiveness.

    Not sufficient resources (people, money, time, etc.) and assistance

    provided

    Insufficient understanding of the methodology and philosophy by middlemanagement

    TPM is not a quick fix approach, it involve cultural change to the

    ways we do things

  • 7/30/2019 Lean Tools and Their Implementation

    18/46

    4) KANBAN

    The premise of Kanban is to create Visual Indicators to allow the operators to

    be the ones who determine how much of a product to run when to stop or

    change over. Kanban rules also tell the operators What Steps to take whenthey have problems and whom to go when Problems occurs.

    Benefits:

    Reduce inventory by 80%.

    Prevents Overproduction, Which is the mother of all wastes

    Places control at the operations Level

    Improves responsiveness to changes in demand(reduces Throughput Time)

    Minimizes risk of having obsolete Inventory

  • 7/30/2019 Lean Tools and Their Implementation

    19/46

    5)Single Minute Exchange of Die It provides a rapid and efficient way of converting a manufacturing process

    from running the current product to running the next product. This rapid

    changeover is key to reducing production lot sizes and thereby improvingflow.

    Steps:

    Separate internal from external setup operations

    Convert internal to external setup

    Standardize function, not shape

    Use functional clamps or eliminate fasteners altogether Use intermediate jigs

    Adopt parallel operations (see image on next slide)

    Eliminate adjustments

    Mechanization

  • 7/30/2019 Lean Tools and Their Implementation

    20/46

  • 7/30/2019 Lean Tools and Their Implementation

    21/46

    6)Kaizen (Continuous Improvement)

    Kaizen is a combination of two words, kai and Zen. Kai means to change

    or modify and Zen means to Improve or make better.

    Kaizen Principles:

    Focus on improvements

    Blame the process and not the person

    Create work teams

    Develop self-discipline, a sense of personal responsibility and accountability.

    Enable Employees (i.e. Set employees for success)

  • 7/30/2019 Lean Tools and Their Implementation

    22/46

    Kaizen Process

    Defining Problem.

    Understanding current state

    Finding the root cause.

    Planning counter measures

    Improving Counter measures

    Verifying results

    Standardizing and establishing control

  • 7/30/2019 Lean Tools and Their Implementation

    23/46

    Case Study:1

    Company Profile:

    Name: Navkala plastics

    Number of Working People: 40

    Turn Over: 10crores

    Product: Plastic caps, bowls, containers, bottles, etc.

  • 7/30/2019 Lean Tools and Their Implementation

    24/46

    Flow diagram

  • 7/30/2019 Lean Tools and Their Implementation

    25/46

    Identification of problem

    Problem no Problems Weightage out of 101 Too much die changing time 1002 Die life is less 903 New calculations for every die 704 No Inspection unit 205 Time waste during maintenance 906 Manufacturing was not continuous 607 Initial wastage of products 508 Production rate varied a lot 309 Improper space utilization 6010 Die cooling time losses 9011 Improper layout 5012 Cleaning was required in cooling tower 9013 Storage near the production, so no walking

    space

    70

  • 7/30/2019 Lean Tools and Their Implementation

    26/46

    Pareto chart

  • 7/30/2019 Lean Tools and Their Implementation

    27/46

    Why-Why Analysis

    Main cause: - Too much Die changing time

    Why 1 - All the external operations were also performed after stopping themachine

    Why 2 -There was only one operator per machine with no helper, and diewas heavy

    Main cause: Die life was less

    Why1

    Due to the use of recycled plastic material of low grade

    Why2- That material was cheap

    Other reasons- Too hot plastic if inserted inside can decrease die life, Alsoimproper cooling can reduce the die life.

  • 7/30/2019 Lean Tools and Their Implementation

    28/46

    Main cause: Production rate varied continuously

    Why1- Time wastage between removals of product from mold.

    Why2- Machine stops as door opens.

    Why3- Door opening and closing time depends on the operator.

    Other reasons: Some blockage in nozzle also reduces the mass flow rate

    Main cause: Manufacturing was not continuous

    Why1- Hopper size was limited to 125 kg only

    Why2- When color of product change hopper has to emptied

    Why3- Different color require different plastic grains mixture

    Other reason

    Why1- After some time Die gets heated

    Why2- Only water cooling was there, Chillers are better option but notused.

    Why3- Chillers require special arrangement

  • 7/30/2019 Lean Tools and Their Implementation

    29/46

    Main cause: Improper space utilization

    Why1- Whole floor was covered by products, wastes, packing materialsand other things

    Why2- No proper layout and Upper part of factory was not used

    Why3- Lack of 5S Principle implementation

  • 7/30/2019 Lean Tools and Their Implementation

    30/46

    5S analysis sheet

  • 7/30/2019 Lean Tools and Their Implementation

    31/46

    Some pictures showing the need of implementation of 5S

  • 7/30/2019 Lean Tools and Their Implementation

    32/46

    Proposals:

    Sorting

    Extra wooden roof at the top can accommodate all unused item, increasingfloor space

    Use only needed materials, equipment, tooling & supplies when needed.

    Eliminate excess / obsolete equipment & inventory

    Improve space utilization by eliminating space taken up by unneeded items

    and organizing needed items

    Set in Order

    Locate missing tools, documents, instructions, keys and inventory

    Put everything in a useable place

    Make every item visible, reachable & available when needed

  • 7/30/2019 Lean Tools and Their Implementation

    33/46

    Shine in Order

    Remove dirt, oil, scraps and garbage

    Assign cleaning responsibilities - team effort

    Clean on a daily basis - the cleaner the better!

    Audit the cleaning process use cleaning checklists

    Improve equipment maintenance through cleaning

    Clean aisles, walkways, floors, machines, desks

    Standardization

    Maintain and control continual improvement

    Ensure systematic organization, sorting, and scrubbing clean are synchronized

    l i

  • 7/30/2019 Lean Tools and Their Implementation

    34/46

    TPM Implementation

    Problems and solutions

    1) To avoid breakdowns and for increase in production

    Planned maintenance could avoid above problems:

    By cleaning the piping systems

    By cleaning the nozzle

    By replacing door pins

    2) Down time losses due to operator fatigue, setup changeover and materialshortages

    Keeping 2 extra workers per 5 machines so that every operator can get rest after 2

    hours of operation When die has to be changed first all the external operations like moving it by

    crane, adjusting nut and bolts of die, other tool needed should be kept readybefore stopping machine

    One hopper per 2 machines should be kept extra filled with raw material so, it candirectly be attached to machine when it is required

  • 7/30/2019 Lean Tools and Their Implementation

    35/46

    3) Start up rejects

    Above graph shows after starting the machine rejects are very high

    Solution:

    For every die parameters like pressure, temperature, dwell time, feedingrate, etc are different. Instead of using try and error method every time

    whille using the die, some standardised parameters should be used. Theparameters which are found ok should be stored and directly should be

    implemented next time.

  • 7/30/2019 Lean Tools and Their Implementation

    36/46

    4) Production rejects

    There were many rejects due to some machine error, due to impropercooling, plastic getting stick to the die and runner scraps.

    Solution

    Some rejects are always there but by proper cooling of die sticking problem

    can be minimized .

    Die should be made such that runners scrap is less

    Nozzle should be blockage free so mass flow rate is constant

  • 7/30/2019 Lean Tools and Their Implementation

    37/46

    Case study:-2

    Company Profile:

    Name: Real cast foundry

    Number of Working People: 35

    Turn Over: 20crores

    Product: Different casting products like pump casings, flywheels, etc.

  • 7/30/2019 Lean Tools and Their Implementation

    38/46

    Flow chart

  • 7/30/2019 Lean Tools and Their Implementation

    39/46

    Problems: 1) Too much wastes

    2) Sand reclamation system was not there

    3) Improper space Utilization

    4) Too much inventory

    5) Environmental Pollution

  • 7/30/2019 Lean Tools and Their Implementation

    40/46

    Pollution due to Pattern Making

    VOC (volatile organic compound) from glues, epoxies, and paints.

    Waste water: Little or no wastewater generated ,but there is no plan for

    water utilization. Residual Wastes: Scrap pattern materials

    Mold and Core Preparation and Pouring

    Waste mold and core sand potentially containing metals and residual

    chemical binders

    Charging and Melting

    Air Emissions:

    Products of combustion, oil vapors, particulates, metallic oxide fumes

  • 7/30/2019 Lean Tools and Their Implementation

    41/46

    Shakeout, Cooling and Sand Handling

    Dust and metallic particulates; VOC and organic compounds from the sanddisposal as there was no treatment system.

    Air emission

    Sr.

    No.Waste

    Concentration in mg/kg

    Cu Zn Pb Ni

    F1 F2 F3 F1 F2 F3 F1 F2 F3 F1 F2 F3

    1Sand waste

    220 190 182 79 71 67 172 180 158 125 130 118

    2 Dust 166 143 151 169 138 149 263 255 248 206 199 224

    3Slag waste

    520 482 543 306 297 319 49 52 57 484 490 503

    4

    Waste

    From

    Ladle

    141 130 150 340 312 302 30 26 23 239 227 244

    MOEF

    Standard 300 1000 100 50

  • 7/30/2019 Lean Tools and Their Implementation

    42/46

    Result

    The foundries generate lot of Solid waste like sand waste, dust, and slagwaste, waste from ladle which is harmful for human health. There is no

    arrangement for beneficial reuse, disposal, treatment and handling.

    Regarding air emission, foundry is emitting pollutants from differentdepartment namely Furnace operation, Preparation of cores and molds,

    Casting, Shakeout and reclamation. There are drastic deviations in alldepartment compare to MOEF Standard. There is low air emission where

    induction furnace is installed but they are not running with highest efficiency.

  • 7/30/2019 Lean Tools and Their Implementation

    43/46

    Scope of lean tools:

    Just in time manufacturing- It can help in reducing the overproduction,and hence the above mentioned losses can be reduced.

    Total productive maintenance- As per it the regular scheduled maintenanceof various parts like compressors, furnaces, sand mixture, etc. will consumeless power and hence reduce pollution.

    By reducing scrap above pollution can be decreased

    Scrap may be of runners and gates, reworks, final rejected parts, etc.

    KAIZEN- It helps in reducing the overall inventory of the company by properMRP planning, proper control of management over production, etc. So onlythe needed things are ordered reducing inventory, the needed thing are kepton other are switched off, which saves power and cost.

    5S- It involves proper arrangement of all the equipments at right place,proper layout of the factory, proper cleaning, etc. If proper arrangement arethere then everything can be found out easily found when required reducingunnecessary buying of inventory

  • 7/30/2019 Lean Tools and Their Implementation

    44/46

    Why 5S

  • 7/30/2019 Lean Tools and Their Implementation

    45/46

    Proposals: Extra roofs, where unwanted material can be stored so floor space can be

    utilized properly.

    All the Pattern, Cope and Drag which are not in use should be marked andstored in separate section.

    Every section should be separate pattern making, poring, grinding, etc.

    Better cleanliness of Equipment's like Muller machine, Grinders, Containers

    which are used for pulling raisin from tanks.

    Make every item visible, reachable & available when needed

    Ensure systematic organization, sorting, and scrubbing clean are synchronized

    Use safety equipments like safety shoes, Helmets, Hand gloves, etc.

    Give proper safety guidelines to the workers

  • 7/30/2019 Lean Tools and Their Implementation

    46/46

    Conclusion

    There is an infinite number of ways of implement Lean Manufacturing in

    these Industries in future, both the management and the workers have towork together for successful implementation.

    Most of lean tools are not costly and can be implemented easily, afterattainment of its use.

    Indian small and medium scale industries can get large advantage of it.