http://nodal.ercot.com 1Lead from the front
Texas Nodal
Integrated ERCOT Readiness and Transition (IRT)
TPTF - November 6th, 2006
http://nodal.ercot.com 2Lead from the front
Texas Nodal
Purpose of today's presentation
• Share QSE & CRR Qualification Approach• Share EDS 3 Approach• Confirm Delivery Dates of IRT’s Key Deliverables• Seek direction concerning a sub-group for IRT related activities
http://nodal.ercot.com 3Lead from the front
Texas Nodal
IRT Scope
• Business readiness & transition plan for each ERCOT department by Director
• Updated ERCOT Operating Guides based on Nodal Protocols and placed under change control
• Updated Control Room Desk Procedures based on Nodal Protocols and place under change control
• Market Participant Qualification Plan, execution and tracking (including entry and exit criteria)
• EDS 3 and 4 plans and daily schedule and execution• Readiness Criteria, tracking, and reporting• Readiness declarations• ERCOT Nodal Go Live Plan • Zonal “closure” strategy and implementation
http://nodal.ercot.com 4Lead from the front
Texas Nodal
Project Status Summary
• Business readiness & transition plan– ERCOT employees mapped to Nodal Training Course Curriculum– Working with Vendors to define software package curriculums– Detailed Process Inventory and Impact Assessment underway
• Updated ERCOT Operating Guides – 7 of 8 under change control– Participating in OGRTF review sessions
• Updated Control Room Desk Procedures– Scheduled for 2007; dependent on operating guides and CSDs
• Market Participant Qualification Plan– Approach to be reviewed today
• EDS 3 Approach – Internal review ongoing
• ERCOT Readiness Criteria– Final stages of contracting for third-party
• ERCOT Nodal Go Live Plan– Scheduled for late 2007
• Zonal “closure” strategy and implementation– Scheduled for Q2 2008
http://nodal.ercot.com 5Lead from the front
Texas Nodal
Why is qualification required? ERCOT protocols
Each Market Participant must “demonstrate to ERCOT’s reasonable satisfaction that it is capable of performing the functions” required of the Market Participant under the protocols.
Transition to the nodal market introduce Change in protocols Changes in transactions between ERCOT and Market Participants Changes in systems at ERCOT and market Participants Changes in personnel
To assure MPs are capable of performing their functions, ERCOT will: Define and communicate readiness activities for all MPs Perform qualification tests required by protocols
QSEs CRR Account Holders
Qualification for the nodal market
http://nodal.ercot.com 6Lead from the front
Texas Nodal
CRR Account Holder Qualification Requirements Registration Agreements Satisfaction of credit requirements Training
QSE qualification steps (Existing) Registration Agreements Communication Functional Testing
Market Operations System Operations (Ancillary Services)
Credit Requirements Training Others…
Qualification for the nodal market
http://nodal.ercot.com 7Lead from the front
Texas Nodal
QSEs without Resources
Registration- No changes
Agreements – No changes
Communication Portal (TML) or API
Functional Testing Market Operations functional testing
Credit Requirements Refined classification of counter-parties with new requirements
Training
Qualification for the nodal market
http://nodal.ercot.com 8Lead from the front
Texas Nodal
QSEs with Resources (Ancillary Services) QSE Qualification tied to Resource qualification
“Each QSE and the Resource providing Ancillary Service must meet qualification criteria to operate satisfactorily with ERCOT”
Registration No changes to QSE Registration Resource Registration (“Each QSE that represents a Resource must submit parameters to ERCOT for that
Resource “
Agreements – No changes Communication (Voice and Data Circuits between control centers)-No change Communication
Portal (TML) or API Telemetry, Redundant Data communication (* Example)
Functional Testing Market Operations functional testing (Offers, Schedules, COPs) System Operations (Ancillary Services)
QSE system qualification Resource qualification
Credit Requirements Refined classification of counter-parties with new requirements
Training
Qualification for the nodal market
http://nodal.ercot.com 9Lead from the front
Texas Nodal
Qualification Timeline
Resource Registration Q4 ‘07
Communication (Telemetry) Q2-Q3 ‘07
Market Operations Q4 ‘07
System Operations Ancillary Services qualification
Performed at the beginning of EDS-3
Q1 ‘08
Qualification for the nodal market
ResourceRegistration
Communication
Q3 Q4 Q1 Q2Q2
Market OperationsFunctional Testing
AS Qualification
Training, Credit Requirements
2007 2008
EDS-3
EDS-1,2
Majority of QSEs would have to complete each activity in the time periods shown to meet EDS criteria. Qualification activities may continue past
dates shown above.
http://nodal.ercot.com 10Lead from the front
Texas Nodal
EDS 3 – Market Trials Timeline
Mar 08Feb 08Jan 08 May 08 Jun 08Dec 07 Apr 08
LMP Market Readiness Criteria
MET
Cycle 10
Nov 07
Market Trials Start
AS QualificationAS Qualification
ALL QSEsALL QSEsWeekly CycleWeekly Cycle
Cycle 1
LMP w.Controls
Single Entry Model
GO LIVE
Resource RegistrationResource Registration
MP Sandbox, Pre-EDS validationMP Sandbox, Pre-EDS validation
LMP w Controls: ERCOT will submit all market data covering various scenarios to validate the system and begin the LMP publishing
1/2/08 to 1/15/08 Initial:
Duration two weeks (1/21/08 to 2/1/08) 2 QSEs willing to work through probable process and system issues to resolution
Cycle 2 to 9: Duration one week each (2/4/08 to 3/28/08) 5-10 QSEs each
Cycle 10: Duration two weeks (3/31/08 to 4/11/08) Makeup & contingency testing window for all remaining QSEs which could not successfully complete a cycle during
Cycles 1 to 9 Real-time Parallel Ops:
All QSEs in live EDS mode. 4/14/08 to 6/27/08
Cycle 2-9 Real-time Parallel Ops
…
http://nodal.ercot.com 11Lead from the front
Texas Nodal
EDS 3 Scope
EDS 1/2 – Single Entry Model
Basic Network Model & SE Criteria NMMS (UI internal only) ICCP (RTU migration) Nodal EMS (non-live)
EDS 3 – Real Time Operations
NMMS (without Planning model) Nodal EMS Outage Scheduler SCED RUC SASM COP Emergency Operations Trades, Schedules Offers (3 part) CRR (settled in RT) CMM (part) MIS (part) Commercial operations (for RT) EDW (for RT) Integration (part) LMPs published 8*5 support
EDS 4 – Day Ahead Market/CRR
NMMS (full) DAM CRR (full) CMM (full) MIS (full) Full back-end (x4) 8*5 support (24*7 for MP ITEST) ERCOT & Market Readiness Criteria
approved
EDS 4 Trial outcomes
All MP Registration complete for Go Live All market facing interfaces complete Testing of all markets complete 168 Hour test complete All interfaces validated Training complete MP financial & operational qualification complete Market Readiness Declarations met “Home Team” transitioned (as needed)
Production GO/NO GO
EDS 3 Trial outcomes
6 month SCED test completed EMS enhancements complete MP offers LFC, OS, RPP complete All MP Registration complete for Go
Live “Home Team” transitioned (as needed)
LMP Market Readiness Criteria- MET
EDS4 - GO/NO GO
Q2 2008 Q4 2008Q3 2008Q2 2007Q1 2007 Q4 2007 Q1 2008 Q1 2009Q3 2007
EDS 3
EDS 4 Go-live Trans.
EDS 3 Mote and ERCOT UATEDS 1/2
EDS 1/2 Trial outcomes
SE Criteria achieved Telemetry criteria achieved
Single Entry Model (with stable and capable SE)
GO/NO GO
EDS3 Training
http://nodal.ercot.com 12Lead from the front
Texas Nodal
Deliverable Timeline
Covers Next ~90 days
– EDS
• EDS 3 Approach………………………………………….11/28
• Market Operations Sandbox Approach………………...Jan ‘07
– Readiness Criteria
• Initial review……………………………………………….Mid-Jan ‘07
• Final review………………………………………………..Early Feb ‘07
– Registration & Qualification
• QSE Qualification Approach……………………………..12/4/06
• QSE Qualification Guide………………………………….Jan ‘07
• Registration Approach…………………………………….Jan ‘07
• Registration Guide…………………………………………Feb ‘07
http://nodal.ercot.com 13Lead from the front
Texas Nodal
IRT / Market Participant Sub-group
• ERCOT Desires a forum to collaboratively develop:– Qualification Plans– Readiness Criteria– Market Trials– Go-live Transition
• Immediate Need:– Weekly meetings from November 13th through January 31st to
develop readiness criteria• Need participation from TOs, QSEs, Resource Entities
http://nodal.ercot.com 14Lead from the front
Texas Nodal
Summary & next steps
• QSE & CRR Qualification Approach • EDS 3 Approach• Key Dates & Deliverables• Market Trials Forum• Next steps