Lead from the front Texas Nodal 1 EDS 4 DAM/RUC/SASM 4.9 Market Call March 21, 2008.

25
http://nodal.ercot.com 1 Lead from the front Texas Nodal EDS 4 DAM/RUC/SASM 4.9 Market Call March 21, 2008

Transcript of Lead from the front Texas Nodal 1 EDS 4 DAM/RUC/SASM 4.9 Market Call March 21, 2008.

http://nodal.ercot.com 1Lead from the front

Texas Nodal

EDS 4 DAM/RUC/SASM

4.9 Market Call

March 21, 2008

http://nodal.ercot.com 2Lead from the front

Texas Nodal

ERCOT Anti-Trust Admonition

ERCOT strictly prohibits Market Participants and their employees who are participating in ERCOT activities from using their participation in ERCOT activities as a forum for engaging in practices or communications that violate the antitrust laws. The ERCOT Board has approved guidelines for members of ERCOT Committees, Subcommittees and Working Groups to be reviewed and followed by each Market Participant attending ERCOT meetings. If you have not received a copy of these Guidelines, copies are available at the Client Relations desk. Please remember your ongoing obligation to comply with all applicable laws, including the antitrust laws.

http://nodal.ercot.com 3Lead from the front

Texas Nodal

Agenda

• DAM/RUC EDS 4.9.1– Master Schedule Update– Dashboard Update– Release 9.3 details– Release 8 Update – Q&A and Roll Call

• Appendix

http://nodal.ercot.com 4Lead from the front

Texas Nodal

DAM/RUC 4.9.1 Tracking: Master Schedule for Next Week

FINAL WEEK of Release 9.1

http://nodal.ercot.com 5Lead from the front

Texas Nodal

DAM/RUC 4.9.1 Tracking: Dashboard

• To view the most updated copy refer to the readiness center at:http://nodal.ercot.com/readiness/eds4/documents/index.html Under Weekly Status – new posting every Friday night

http://nodal.ercot.com 6Lead from the front

Texas Nodal

Update on next phase- EDS4 Initial DAM/RUC 4.9.3 Testing

• Objectives beginning in April 2008- – QSE submit offers DAM/RUC– ERCOT executes DAM/RUC (in limited manner)– ERCOT posts awards and settlement point prices– Targeting to support out of Austin Control Center (ensure firewalls comply with

Appendix)

• Schedule-– Run Day-Ahead markets on Tuesday and Thursday each week– Planned first DAM run is 10am on April 3rd – ERCOT system and data preparation still in progress to make April 3 date

• Summary of how testing will evolve:– Execution functionality to be taken in steps (crawl > walk > run)

• Weeks 1&2 – – Energy-only DAM – No A/S, no RUC, no constraints, no PtP Obligations, no credit limit

• Week 3 – – Energy and A/S in DAM– Include self-selected credit limits and PtP Obligations

• Weeks 4 & 5– Execute DAM with constraints on Tuesday, include RUC on Thursday

http://nodal.ercot.com 7Lead from the front

Texas Nodal

Update on next phase- EDS4 Initial DAM/RUC 4.9.3 Testing (con’d)

– ERCOT plans to provide more updates via these Friday market calls and emails leading into April testing

– ERCOT will provide summary of timeline and expected submissions for each week

• Testing will need to adhere to posted guidelines and limits communicated.

– Starting today, we will send an email to each QSE with Load containing their stubbed-in Load Ratio Share (LRS)

– Stubbed in LRS data from zonal production in February 2008

– Note that this stubbed-in data may not be reflected in MMS tables initially but we will move toward this more realistic data

– In April, we will send ERCOT test data (in blue on the spreadsheet) for QSEs to copy-paste and determine their bidding levels, AS obligations

http://nodal.ercot.com 8Lead from the front

Texas Nodal

Update on next phase- EDS4 Initial DAM/RUC 4.9.3 Testing (con’d)

– Reminders below to involve business in building bids and offers

************************– For testing purposes there will be guard-rails on data, but it will not scripted by

ERCOT• So QSE BUSINESS INVOLVEMENT IS CRITICAL for reasonable pricing and business

activities

– All QSEs (with and without Load and Resources)- • May submit a limited amount of DAM Energy Only Offers and DAM Energy Bids

that do not represent actual Resources or Loads (virtual bids and offers)

• QSEs can only bid/offer up to 50MW total (later becomes 500MW)

• Bids/Offers should net to 0MW total (later allowed to take position of up to 200MW)

• It is important that the submitted bids be reasonably priced for producing appropriate prices and results.

http://nodal.ercot.com 9Lead from the front

Texas Nodal

Update on next phase- EDS4 Initial DAM/RUC 4.9.3 Testing (con’d)

Status of DAM Award Communication (as of 3/21/08)• Due to integration issues, Notifications delivery moving toward mid-May

• Query Get AwardSet will conform to a temporary xml schema and will not conform to EIP specification in the beginning. We will post the XSD today on the Readiness Center. Note that this is an interim measure.

– Awards queries will likely return compressed payloads given the size of the reports

– GetAwardSet composed of:• AwardedEnergyOffer

• AwardedEnergyOnlyOffer

• AwardedEnergyBid

• AwardedAS

• AwardedCRR

• AwardedPTPObligation

• Awards to be available via Market Manager (display of GetAwardSet)

http://nodal.ercot.com 10Lead from the front

Texas Nodal

Release 8 Update

CRR Auction Invoices produced

• Release 7.2 Auction has cleared, Settlements created CRR Auction Invoices

• CRR Auction Invoices posted to Readiness website for review (banking information has been removed)

• Results of 7.2 Auction can be found at: http://nodal.ercot.com/docs/pd/eds/r7/eds7_3_market_call_materials_march_14th.zip

• Issues related to CRR that appear on the Invoices (explanation will be provided today on Release 3.7 Market call at 2pm CT).

New Statements and Invoices posted to the Readiness Website:

• DAM and RTM Resettlement Statements, CRR Auction Invoices posted this week to the Readiness Website (http://nodal.ercot.com/readiness/reports/si/index.html)

• Send acknowledgement to [email protected] by 4/1/08

Send notice of intent to submit Verifiable Costs:• QSEs with Resources, please send notice to [email protected] by 5/1/08• Include number of units you are intending to submit VC for

Settlement Contact:• EDS team assumes your contact for Release 8 is the same as for Release 9. If this is not the case, please

send settlement contact information to [email protected].

No Logged Issues • There have been no issues logged to date for Release 8

http://nodal.ercot.com 11Lead from the front

Texas Nodal

Q&A / Open Forum

Roll-Call

http://nodal.ercot.com 12Lead from the front

Texas Nodal

-DAM notifications available in Sandbox-Upcoming Network Changes-Current Issues (Web Services)-Connectivity and Digital Certificate information-Links to Key Documentation -Metrics-Test Case Summary-How to log issues-Data preparation-QSEs not signed up for testing

APPENDICES

http://nodal.ercot.com 13Lead from the front

Texas Nodal

DAM Awards

DAM awards notification availability in the nodal Sandbox• There is a scheduled job running in Sandbox that sends out

notifications once a day (around 11:53 AM CST)• To receive them, you must have your listener configured in the

Sandbox environment – if you need it configured, send us an email with your URL (send to [email protected])

• NOTE: These notifications are generated from static files (pre-formed xmls)

– AwardedCRR– AwardedAS– AwardedEnergyBid– AwardedEnergyOffer– AwardedEnergyOnlyOffer– AwardedPTPObligation– ConfirmedTrades– UnConfirmedTrades– OutageSet– ASObligations– StartupShutdownInstructions

http://nodal.ercot.com 14Lead from the front

Texas Nodal

Forthcoming Network Changes

Network Changes / site to site fail-over testing

(please communicate to your network / firewall teams)

• Test to be conducted mid / late March

• All QSEs need to have network changes in place no later than 3/14

• The changes should enable receiving / sending data to / from::

» 66.128.16.0/24

» 66.128.17.0/24

» 66.128.18.0/24

• Reminder: required ports do not change (443/80)

• Reminder: required protocols do not change (http/https)

http://nodal.ercot.com 15Lead from the front

Texas Nodal

Update on EDS 4 Environment - Current Issues

• WebServices Known Issues/Limitations– Query using short mRID is not available for:

• “PTP Obligation” / “DAM Energy Only Offer” / “Energy Bid” / “CRR Offer”– Negative test for Energy Bid not working (submission of curve <1MW)

• Will pass QSE without this test– DC Tie Schedule

• NERC tag data not yet set up to be used for testing– PtP Obligation Bids

• <crrAccountHolderId/> is REQUIRED (different from M2M/API spec)• Set crrAccountHolderId = TSTQSE

– EIP Specification omitted a Reply Code• Reply Code from ERCOT can be “OK”, “ERROR”, or “FATAL”

http://nodal.ercot.com 16Lead from the front

Texas Nodal

APPENDIX- DAM/RUC 4.9.1 Testing: Basic Communications Test (“Ping” Test)

• BASIC COMMUICATION TEST

• Prior to this test QSE’s using External Web Services will need to have their network and security teams make the following changes:

– QSE’s Market System must be able to access:https://nodaleds.ercot.com:80/2007-08/Nodal/eEDS/EWS/ NOTE: this SSL URL is on port 80NOTE: this is changed from Release 3.5

– QSE’s must be able to receive messages from 66.128.17.136

– QSE’s must be able to send messages to EDS Environment: 66.128.17.32Sandbox Environment: 66.128.16.84

• QSE’s using MIS User Interface will need to have their network and security teams make the following changes:

– Must be able to access: MIS URL: https://nodaleds.ercot.com/misportal/ NOTE: MMS User Interface will have link from MISNOTE: MIS/MMS UI are on port 443

http://nodal.ercot.com 17Lead from the front

Texas Nodal

APPENDIX- DAM/RUC 4.9.1 Testing: Digital Certificates

• DIGITAL CERTIFICATES

• 1 digital certificate w/ a Generic Userid (NODALTEST) will be Generated for Each QSE and Sub-QSE

– The MP’s USA does not need to take any action– This is the only certificate that will work in the EDS environment– This certificate will also work in the Nodal Sandbox environment– It will not work in production, MOTE, or any other ERCOT environment– The Digital Certificate will be sent to the MP USA

• Distribution will occur after the QSE signs up for a Testing Window and Just Prior to the Support Call

– (for those requiring the basic communications test, it will be sent prior to that session)

http://nodal.ercot.com 18Lead from the front

Texas Nodal

APPENDIX- DAM/RUC 4.9.1 Reference: Relevant Documents

EDS 4.9.1 – DAM/RUC/SASM Test Package

http://nodal.ercot.com/readiness/eds4/documents/index.html

Settlement Point Listing http://nodal.ercot.com/readiness/eds4/documents/index.html

QSE Short Name Listing

To post by end-of-day

http://nodal.ercot.com/readiness/eds4/documents/index.html

Dashboard of Metrics and Schedule

http://nodal.ercot.com/readiness/eds4/documents/index.html

EDS Issue Submission Form

http://nodal.ercot.com/readiness/eds4/documents/r9/ercot_eds_issue_submission_form.xls

EIP External Interface Specification

http://nodal.ercot.com/docs/pd/eip/od/misp/eip_external_interfaces_specification_v1_06.zip

Explanation of Market Submissions v0.25

http://nodal.ercot.com/readiness/eds4/documents/index.html

http://nodal.ercot.com 19Lead from the front

Texas Nodal

APPENDIX- DAM/RUC 4.9.1 Reference: Relevant Documents

ERCOT Nodal Transition Plan

http://nodal.ercot.com/docs/po/pd/ntp/ERCOT_Nodal_Transition_Plan_110305.doc

EDS 4 Approach v1.0 http://nodal.ercot.com/readiness/eds4/documents/index.html

EDS 4 - DAM/RUC/SASM Market Participant Handbook v1.0

http://nodal.ercot.com/readiness/eds4/documents/index.html

Market Management System User Guide

http://nodal.ercot.com/docs/pd/eds/eds4/eds4mmsuidum/eds_4_mms_ui_draft_user_manual_20080128.doc

http://nodal.ercot.com 20Lead from the front

Texas Nodal

APPENDIX- DAM/RUC 4.9.1 Tracking: Readiness Metrics

• READINESS METRICS:• Sign-Up Testing Window Scheduled

– QSE signs up by 1/4/2008 – Status is GREEN– QSE’s that have not signed up by

• 01/04/08 – Will turn Amber until signed up• 03/15/08 – Will turn red

• MP8 - QSE Ability to Submit Transactions Via MIS– Expected completion date March 15

• MP9 – QSE Ability to Submit Web Service Transactions– Expected completion date March 15

• Execution – MP’s that have met readiness metric M8 or M9 by 3/15/08 are GREEN– MP’s that have attempted readiness metric M8 or M9 by 3/15/08 are AMBER– MP’s that have not yet attempted readiness metric M8 or M9 by 3/15/08 are RED

• MP16 - MP EDS-4 Trials Participation (phase 2)

• ERCOT is calling all QSEs that have not signed up for EDS4

http://nodal.ercot.com 21Lead from the front

Texas Nodal

Appendix- DAM/RUC 4.9.1 Testing: Support Call Test Cases

Primary QSE Sub-QSE

Create / Query / Update / Cancel (if applicable)

CRR OFFER All Scenarios

NOIE / PCRR Holders Only

Create Only

PTP Obligation All Scenarios Create Only

Three Part Supply Offer All Scenarios

QSE w/ Resources Only

Create Only

Capacity Trade All Scenarios Create Only

Energy Trade All Scenarios Create Only

AS Trade All Scenarios Create Only

DAM Energy-Only Offer All Scenarios Create Only

DAM Energy Bid All Scenarios Create Only

AS Self Arrangement All Scenarios

QSE w/ Load Only

Create Only

AS Offer All Scenarios

QSE w/ Resources Only

Create Only

Self Schedule All Scenarios Create Only

DC Tie Schedule All Scenarios Create Only

http://nodal.ercot.com 22Lead from the front

Texas Nodal

Appendix- Reminder of support window and issues process

• Issues encountered on the Support Call will have a high priority• Issues encountered during the remainder of the 7 day Test Window

should be reported via the ERCOT EDS Issue Submission Form – Form is located at:

http://nodal.ercot.com/readiness/eds4/documents/index.html – Submit form to [email protected]  – Internal testing will occur in parallel with all EDS activities – MP issues will be logged when submitted

• MP submitted issues will be compared to internal defects and addressed in parallel– When completing the Issue form, provide:

• Web Services: the XML files used • MIS User Interface: Screen Shots and/or error message• Both: The detailed scenario to reproduce the issue

http://nodal.ercot.com 23Lead from the front

Texas Nodal

Appendix- DAM/RUC 4.9.1 Reference: QSE Activity Summary

• Download and review the EDS 4 Test Package– For API WebServices users only-

• Send sample XML to ERCOT no less than 2 weeks prior to Testing Window• Make Corrections/Modifications (if any) to XMLs that ERCOT provides• Prepare final XML files for Support Call

– For MMS-UI/Market Manager, download the user guide– Support calls are for troubleshooting submissions in real-time

• Read and be familiar with key Documents (references in Appendix)

• Known issues will be posted to the Nodal Readiness Center under EDS 4: – File will be updated by COB 2/1– http://nodal.ercot.com/readiness/eds4/documents/index.html

• When environments upgraded (issues resolved), a Market Notice will be sent

• Send all questions to [email protected]

http://nodal.ercot.com 24Lead from the front

Texas Nodal

Appendix- DAM/RUC 4.9.1 Reference: QSE Data Preparation

Reminder to Download Settlement Points and QSE Short Name List(both files posted on Readiness- http://nodal.ercot.com/readiness/eds4/documents/index.html)

• Both data sets are subject to change

• QSE Short Names used in transactions– Your QSE short name is needed as <source> in XML Header– All QSE short names listed, but may change

• Can use ERCOT test QSE of “TSTQSE” to avoid populating and changing QSE list in your systems

• Settlement Point used as points of business in submission testing– Market Participants revisiting Resource Node SPs– Considering change from Low side to High side– Change would result in many SP name changes

http://nodal.ercot.com 25Lead from the front

Texas Nodal

EDS 4 Release 9

QSEs that have not signed up for a testing window for EDS4 (as of COB 3/21/08)

Ambridge Energy

Aquila

Citadel Energy Products

Clearview Electric

Glacial Energy

Kansas City Power and Light

National Power Company

Sitara Energy

Texpo Power

Urban Energy Source

WCW International