Assume that Kristen’s most important customer has just submitted an order for one dozen cookies, and that she wants to give the highest priority to this order. How long will it take to fill this order?

The time required to fill the “rush order” is:

Process’s Throughput Time =26 minutes

Page 4: Kristen's Cookies Operations

4

Assuming that Kristen’s Cookie Company is open for four hours each

night, how many orders can be filled each night?

The process’s bottleneck is 10 minutes

So accordingly 6 order can be completed in hour and 24 in 4 hours.

Which activity is the process’s bottleneck? Load and bake

Page 5: Kristen's Cookies Operations

From the Slide 2 Kristen roommate is working for 2 process

To put cookies in the oven and set the thermostat and timer which takes 1 minute.

Packing the cookies in the box takes 2 minutes per dozen and accepting payment takes 1 minute.

Time taken by own for mix & spoon is 8 minutes .

So together total time is 12 minutes out of total throughput time is 26 minutes.

5

How much of your own and your room mate valuable time will it take to fill each order?

Page 6: Kristen's Cookies Operations

6

Assume that Kristen pays herself and her roommate $12 per hour.

If Kristen and her roommate are not paid for idle time, what is the minimum amount Kristen should charge for one dozen cookies?

If Kristen and her roommate are paid regardless of whether they are busy or idle, what is the minimum amount Kristen should charge for one dozen cookies?

From the previous slide, recall that, in each 10-minute cycle, Kristen and her roommate work a total of

8 + 4 =12 minutes

Kristen’s and the roommate’s wage is

$12/hr or $0.20 /min

From the case, the materials cost per dozen is $0.60 for ingredients and $0.10 for the box, for a total of

$0.70

MATERIALS $0.70 MATERIALS $0.70

LABOR ($0.20/min)(12 min) = $2.40 LABOR [($12/hr)(4 hrs)(2 persons)]/(24 dozen) = $4.00

TOTAL $3.10 TOTAL $4.70

LABOR IS A VARIABLE COST (not paid when idle)

LABOR IS A FIXED COST (paid when idle)

Nightly capacity is

24 dozen

Page 7: Kristen's Cookies Operations

Should you give any discount for people who ordered 2 or more dozen cookies ? If so how much ? Will it take any longer to fill a 2 dozen cookie order then 1 dozen cookie order ?

Assuming that Kristen pays himself and his roommate Rs. 120 per hour i.e. Rs. 2 per minute

If they started working on 2 dozen orders simulatneuously, they are completing the process in 36 minutes.

If they work on 2 dozen orders one after other, it takes 26 min * 2 = 52 minutes

So total time saved = 52 min – 36 min =16 min Now raw material and package cost it fixed irrespective of order. The

total cost incurred would be 70 + (26*4)=174(for 1 dozen).So for 2 dozen it will be 348.If they produce 2 dozens simultaneously we have 140 +(36 * 4)= 284,so we save Rs.64.

So we can pass the saving of 25% that is 16 Rs to the customer who gives 2 dozen orders. So it will cost the customer 348-16=332 Rs (5% discount)

In a similar manner we can give discounts to customers who order 2 or more dozens simultaneously.

7

Page 8: Kristen's Cookies Operations

How many food processors and baking trays will you need ?

We will need 1 processor,2 baking trays and 1 oven. This will lead to maximum utilization of the available resources(as we are starting 2 process within 26 minutes of throughput time, we need one more tray to minimize the time)

8

Page 9: Kristen's Cookies Operations

9

How many food processors and baking trays will Kristen need?

Page 10: Kristen's Cookies Operations

Are there any changes you can make in your production plan that will allow to make better cookies or more cookies in less time or at lower cost?

What is the effect of adding another oven ? How much would you be willing to pay to

rent an additional oven? Is there any bottleneck operation in your

production process that you can expand cheaply?

10

Page 11: Kristen's Cookies Operations

11

If we are adding another oven our throughput time will be reduced to 21 minutes.

Now bottleneck for the process will be Mix & Spoon and time it will take is 8 minutes.

Output will be now 7.5 dozens per hour.

Now output per night ( 4 Hour shift) is increased from 6 to 7.5 dozens so overall in one night we can have additional o/p of 6 dozens. Therefore, the value of the 2-nd oven equals

(6 dozens)[(Selling Price per Dozen)-(Variable Cost per Dozen)]

Variable cost per dozen is Rs.70 ( i.e. Rs 60 per dozen for ingredients and Rs. 10 per box & per dozen). So renting of second oven depends upon the rent and selling price of cookies. From the above formula we can calculate whether we are making profit or not ? So accordingly he can take decision

Page 12: Kristen's Cookies Operations

Process is continues operation i.e. is operates at a steady state with no start up and shut down issues

An adequate capital equipment and availability of resource is available i.e. one food processor, cookie trays and spoon and oven which can hold one tray at a time

Landlord pays for the electricity and variable cost involved are cost of ingredients which is Rs.60 per dozen, cost of box Rs.10 per box and each box can hold up to 12 cookies ( 1Dozen).

There are no variations and statistical fluctuation so that time estimates are fixed and constant.