Operations Management Session 4: Kristine Cookies Case.

31
Operations Management Session 4: Kristine Cookies Case

Transcript of Operations Management Session 4: Kristine Cookies Case.

Page 1: Operations Management Session 4: Kristine Cookies Case.

Operations Management

Session 4: Kristine Cookies Case

Page 2: Operations Management Session 4: Kristine Cookies Case.

Session 4 Operations Management 2

Last Class in Process Analysis Module

What did we learn?

Throughput rate Capacity

What’s the difference between capacity and throughput rate?

Bottleneck resource Utilization rate Throughput time WIP Little’s Law:

Throughput Time = (Average) WIP / Throughput Rate

Page 3: Operations Management Session 4: Kristine Cookies Case.

Session 4 Operations Management 3

Today

Team Presentations

Lecture (Kristen’s cookies and additional comments on capacity management)

Page 4: Operations Management Session 4: Kristine Cookies Case.

Session 4 Operations Management 4

Team Presentations

Page 5: Operations Management Session 4: Kristine Cookies Case.

Session 4 Operations Management 5

What is it all about?What is it all about?

Process CharacteristicsProcess Characteristics

Capacity of a System How much can you process in a week/day?

Response Time How quickly can you meet demand?

Page 6: Operations Management Session 4: Kristine Cookies Case.

Session 4 Operations Management 6

Process Flow

What are the inputs?

What are the outputs?

What are the activities?

Page 7: Operations Management Session 4: Kristine Cookies Case.

Session 4 Operations Management 7

Process Flow Chart

MIXLOADTRAY

SETOVEN

BAKE COOL PACK PAY

DOUGH

YOU

MIXER

YOU

TRAY

ROOMIEOVENTRAY

OVENTRAY TRAY

ROOMIE

TRAY

ROOMIE

Page 8: Operations Management Session 4: Kristine Cookies Case.

Operations Management 8

4 8 12 16 20 24 28 32 36

Acti

vit

yR

esou

rce

Time

Page 9: Operations Management Session 4: Kristine Cookies Case.

Operations Management 9

4 8 12 16 20 24 28 32 36

MIX

LOADSET OVEN

BAKE

COOLPACK

PAY

26

Acti

vit

y

Time

You

Oven

Tray

RM

Resou

rce

Page 10: Operations Management Session 4: Kristine Cookies Case.

Session 4 Operations Management 10

Kristine Cookies and Measures

What is the Throughput time? From the moment an order arrives till it is

finished, it takes 26 min.

Can the throughput time be reduced?

Page 11: Operations Management Session 4: Kristine Cookies Case.

Operations Management 11

4 8 12 16 20 24 28 32 36

MIX

LOADSET OVEN

BAKE

COOLPACK

PAY

26

Time

You

Oven

Tray

RM

Acti

vit

yR

esou

rce

Page 12: Operations Management Session 4: Kristine Cookies Case.

Operations Management 12

4 8 12 16 20 24 28 32 36

MIX

LOADSET OVEN

BAKE

COOLPACK

PAY

26

Acti

vit

y

Time

You

Oven

Tray

RM

Resou

rce

Page 13: Operations Management Session 4: Kristine Cookies Case.

Session 4 Operations Management 13

Kristine Cookies and Measures

What is the capacity of the system?

What is the slowest resource? (Assume that the we have enough trays.)

Page 14: Operations Management Session 4: Kristine Cookies Case.

Operations Management 14

4 8 12 16 20 24 28 32 36

MIX

LOADSET OVENBAKE

COOL

PACK

PAY

26

Acti

vit

y

Time

You

Oven

Tray

RM

10

Resou

rce

Page 15: Operations Management Session 4: Kristine Cookies Case.

Session 4 Operations Management 15

Bottleneck Analysis

It is clear that the bottleneck is the Oven It is the only resource that once we start

producing is not idle. It is the slowest resource: One dozen every 10

min.

Page 16: Operations Management Session 4: Kristine Cookies Case.

Session 4 Operations Management 16

Capacity

It seems that if they have enough trays they can produce a dozen of cookies every 10 min.

1.2 cookies per min. In 4 hours (240 min) you can finish 22 trays:

240 – 26 = 214 214 / 10 = 21.4 or 21 trays.

Given the bottleneck is the oven, to maximize capacity we must ensure that the oven runs continuously: once every 10 min.

Page 17: Operations Management Session 4: Kristine Cookies Case.

Session 4 Operations Management 17

Process Flow Chart

MIXLOADTRAY

SETOVEN

BAKE COOL PACK PAY

DOUGH

TIME:

YOU

MIXER

YOU

TRAY

ROOMIEOVENTRAY

OVENTRAY TRAY

ROOMIE

TRAY

ROOMIE

YOU:

TOTAL TIME

ROOMIE:

MIXER:

OVEN:

TRAY:

6 2 1 9 5 2 1

6 + 2= 8 minutes

1 + 2 +1 = 4 minutes 1+ 9 = 10 minutes

6 minutes 19 minutes

Order Size (Dozens): 1 Dozens

Page 18: Operations Management Session 4: Kristine Cookies Case.

Session 4 Operations Management 18

Process Flow Chart

MIXLOADTRAY

SETOVEN

BAKE COOL PACK PAY

DOUGH

TIME:

YOU

MIXER

YOU

TRAY

ROOMIEOVENTRAY

OVENTRAY TRAY

ROOMIE

TRAY

ROOMIE

YOU:

TOTAL TIME

ROOMIE:

MIXER:

OVEN:

TRAY:

6 2 1 9 5 2 1

6 + 2= 8 minutes

1 + 2 +1 = 4 minutes 1+ 9 = 10 minutes

6 minutes 19/2 minutes

Dozens / Day = 22

Order Size (Dozens): 1 Dozen

Page 19: Operations Management Session 4: Kristine Cookies Case.

Session 4 Operations Management 19

Process Flow Chart

MIXLOADTRAY

SETOVEN

BAKE COOL PACK PAY

DOUGH

TIME:

YOU

MIXER

YOU

TRAY

ROOMIEOVENTRAY

OVENTRAY TRAY

ROOMIE

TRAY

ROOMIE

TOTAL TIME

6 4 2 18 10 4 1

Order Size: 2 Dozens

YOU:

ROOMIE:

MIXER:

OVEN:

TRAY:6 + 2= 8 minutes

1 + 2 +1 = 4 minutes 2+ 18 = 20 minutes

6 minutes

Page 20: Operations Management Session 4: Kristine Cookies Case.

Operations Management 20

4 8 12 16 20 24 28 32 36

MIX

LOAD

SET OVEN

BAKE

COOL

PACK

PAY

26

Acti

vit

y

Time

You

Oven

Tray 1

RM

10

RM

Tray 2

Resou

rce

Page 21: Operations Management Session 4: Kristine Cookies Case.

Session 4 Operations Management 21

How many dozen per day?

60 minutes x 4 = 240 available minutes each evening

240-36=204 available minutes after the first two dozen is finished

204/20=10.2 two dozens finished in the remaining 204 minutes

2x11=22 dozens per day

Does it make sense to give a discount for an order size of two dozen?

Page 22: Operations Management Session 4: Kristine Cookies Case.

Session 4 Operations Management 22

Capacity Investment

Should we invest in a second Oven?

Page 23: Operations Management Session 4: Kristine Cookies Case.

Operations Management 23

4 8 12 16 20 24 28 32 36

MIX

LOAD

SET OVEN

BAKE

COOL

PACK

PAY

26

Acti

vit

y

Time

You

Oven

Tray

RM

8

Two Ovens. Order Size: 1 dozen

RM

You

Resou

rce

Page 24: Operations Management Session 4: Kristine Cookies Case.

Session 4 Operations Management 24

Bottleneck Analysis

Who is the bottleneck now? The entrepreneur

Why did the bottleneck shift?

Could the numbers (as opposed to the graph) indicate were the bottleneck is?

Now should we give a discount for ordering 2 dozen?

Page 25: Operations Management Session 4: Kristine Cookies Case.

Session 4 Operations Management 25

Bottleneck Analysis

Your capacity: 1 dozen cookies / 8 minutes = 0.125 dozen cookies per

minute (or 1 dozen cookies every 8 minutes)

Oven capacity: 1 dozen cookies / 10 minutes 2 ovens x .1 dozen cookies per minute = 0.2 dozen cookies

per minute (or 1 dozen cookies every 5 minutes)

Mixer: 1/6=0.167 dozen cookies per minute

Roommate ¼=0.25 dozen cookies per minute

What is the slowest resource?

Note: same calculation as made in the previous class in Burger’s example.

Page 26: Operations Management Session 4: Kristine Cookies Case.

Session 4 Operations Management 26

Dozens per day with two ovens

240-26=214 minutes for the first dozen

214/8=26.75 dozens in the next 214 minutes

27 dozen per day with two ovens.

Page 27: Operations Management Session 4: Kristine Cookies Case.

Session 4 Operations Management 27

Economic Analysis

Having two ovens increase the capacity from 60/10=6 dozens per hour to 60/8=7.5 dozens per hour.

What is the value of the additional oven?

(27-22)*300*Profit per dozen =

Additional profit = $1,500*profit per dozen

New capacity # of selling days

Old capacity

Page 28: Operations Management Session 4: Kristine Cookies Case.

Session 4 Operations Management 28

Economic Analysis Example

Suppose we sell each dozen cookies for $1.50 per dozen.

Assume there is no cost on your time. The profit per dozen is then $1.50-$0.60-

$0.10=$0.80. Therefore, the additional profit after being open

300 days is: 5x300x$0.80=$1200. We are willing to buy another oven if it costs less

than $1200 and we have enough demand so that it will be in use.

Page 29: Operations Management Session 4: Kristine Cookies Case.

Operations Management 29

4 8 12 16 20 24 28 32 36

MIX

LOAD

SET OVEN

BAKE

COOL

PACK

PAY

26

Acti

vit

y

Time

You

Oven

Tray

Two OvensOrder Size: 2 Dozens

RM

You

Resou

rce

Page 30: Operations Management Session 4: Kristine Cookies Case.

Session 4 Operations Management 30

Process Flow Chart

MIXLOADTRAY

SETOVEN

BAKE COOL PACK PAY

DOUGH

TIME:

YOU

MIXER

YOU

TRAY

ROOMIEOVENTRAY

OVENTRAY TRAY

ROOMIE

TRAY

ROOMIE

YOU: 6+4 = 10

TOTAL TIME

ROOMIE:

MIXER:

OVEN: (18 +2) /2 = 10

TRAY:

6 4 2 18 10 4 2

OVENS = 2 and Order size =2 Dozen

Dozens / Day = 44 doz / day

Page 31: Operations Management Session 4: Kristine Cookies Case.

Session 4 Operations Management 31

Summary

Tools & Techniques Identification of Bottleneck System Capacity Throughput Time

Concepts Bottleneck & Capacity depend of product mix In high variety systems bottlenecks shift