Kpt Long Report_1

29
Karach Port Trust --- Gate Way to Pakistan . Introduction The Karachi Port is administered by a Board of Trustees, comprising Chairman and 10 Trustees. The Chairman is appointed by the Federal Government and is also the Chief Executive of Karachi Port Trust. The remaining 10 Trustees are equally distributed between the public and the private sector. The five public sector Trustees are nominated by the Federal Government. The seats for private sector Trustees are filled by elected representatives of various private sector organizations. This way all port users find a representation in the Board of Trustees. Brief History Karachi due to its geographical and strategic location is known as the gateway to Asia. Considered as a safe Harbor since time immemorial, Karachi was a small fishing village in early Nineteenth Century. Historians identify it with its proximity to a place from where a part of Alexander's Army, boarded the Greek Flotilla in 326 B.C. The first mention of Karachi as a port is found in an Arabic treatise 'Muhit' on navigation relating to the West Coast of India and the Persian Gulf. Written in 1558, this treatise warns the sailors of whirlpools and advises them to seek safety in Karachi Harbor if they found themselves drifting dangerously. It is also significant to mention that the first Muslim Conqueror of India, Mohammad Bin Qasim, landed at Daibal, in vicinity of Karachi in 711 A.D. Karachi also has the distinction of being the birth place of the founder of Pakistan, Quaid-e-Azam Mohammad Ali Jinnah and was the first capital of Pakistan till 1963. It is now the largest city with a bustling and ever increasing population of over ten million. By 1852, Karachi was an established city with a population of about 14,000 with a prosperous trade in over-seas markets. However, the existing Port started taking shape in 1854, when the projects of dredging the main navigable channel and the construction of a mole or causeway joining the main harbor with the rest of the city were undertaken. About 5 years later, construction of Manora Breakwater, Keamari Groyne, the Napier Mole Bridge, Native Jetty and the Chinna Creek were started which gave initial shape to the port. The construction of the wharves started in 1882, and by 1914 the East Wharves and the Napier Mole Boat Wharf had been completed. During the period between 1927 and 1944, the West Wharves of the Port, the Page 1

Transcript of Kpt Long Report_1

Page 1: Kpt Long Report_1

Karach Port Trust --- Gate Way to Pakistan .

IntroductionThe Karachi Port is administered by a Board of Trustees, comprising Chairman and 10 Trustees. The Chairman is appointed by the Federal Government and is also the Chief Executive of Karachi Port Trust. The remaining 10 Trustees are equally distributed between the public and the private sector. The five public sector Trustees are nominated by the Federal Government. The seats for private sector Trustees are filled by elected representatives of various private sector organizations. This way all port users find a representation in the Board of Trustees.

Brief HistoryKarachi due to its geographical and strategic location is known as the gateway to Asia. Considered as a safe Harbor since time immemorial, Karachi was a small fishing village in early Nineteenth Century. Historians identify it with its proximity to a place from where a part of Alexander's Army, boarded the Greek Flotilla in 326 B.C.

The first mention of Karachi as a port is found in an Arabic treatise 'Muhit' on navigation relating to the West Coast of India and the Persian Gulf. Written in 1558, this treatise warns the sailors of whirlpools and advises them to seek safety in Karachi Harbor if they found themselves drifting dangerously.

It is also significant to mention that the first Muslim Conqueror of India, Mohammad Bin Qasim, landed at Daibal, in vicinity of Karachi in 711 A.D. Karachi also has the distinction of being the birth place of the founder of Pakistan, Quaid-e-Azam Mohammad Ali Jinnah and was the first capital of Pakistan till 1963. It is now the largest city with a bustling and ever increasing population of over ten million.

By 1852, Karachi was an established city with a population of about 14,000 with a prosperous trade in over-seas markets. However, the existing Port started taking shape in 1854, when the projects of dredging the main navigable channel and the construction of a mole or causeway joining the main harbor with the rest of the city were undertaken. About 5 years later, construction of Manora Breakwater, Keamari Groyne, the Napier Mole Bridge, Native Jetty and the Chinna Creek were started which gave initial shape to the port.

The construction of the wharves started in 1882, and by 1914 the East Wharves and the Napier Mole Boat Wharf had been completed. During the period between 1927 and 1944, the West Wharves of the Port, the lighterage berths and the ship-repairing berths were constructed. Most of these facilities were obsolete by the time Pakistan came into existence in 1947. Since then, the port administration has embarked on extensive development of the port on modern lines.

At the time of independence in 1947, the Port capacity was about 1.5 million tons of dry cargo and 1.0 million tons of P.O.L. products per annum. Karachi Port is now handling over 11.74 million tons of liquid cargo and 25.45 million tons of dry cargo, including 1,213,744 TEUs which constitute about 60% of import/ export of the country.

Page 1

Page 2: Kpt Long Report_1

Karach Port Trust --- Gate Way to Pakistan .

Flow of Internal Communication

External Communication

In KPT for external communication following ways are in practice.

www.kpt.gov.pk , KPT website is one of main source of external communication where all relevant information about Karachi Port is available, i.e. port tariffs, vessel schedules, cargo handling details, cargo locations which are updated on daily basis on this website.

Letters and fax are also being used for external communication in KPT.

Press releases are also issued & published in famous newspapers.

Page 2

Page 3: Kpt Long Report_1

Karach Port Trust --- Gate Way to Pakistan . MANAGING EXECUTIVES

DESIGNATION EMAIL OFFICE TEL. NO.

Chairman [email protected]

General Manager (Operations) [email protected] Ext.2240

General Manager (Finance) [email protected] Ext.2244

General Manager (Planning & Development) [email protected]

9921431299214530-40 Ext.2230

General Manager (Engineering) [email protected] Ext.2250

General Manager (Administration) [email protected] Ext.2266

General Manager (Civil Works/Engg.) [email protected] Ext.2223

Deputy General Manager (Operations) [email protected] Ext.2294

Secretary, Karachi Port Trust [email protected] Ext.2206

HEADS OF DEPARTMENTS

DESIGNATION EMAIL OFFICE TEL. NO.

  Manager (Management Information Systems) [email protected]

99214352, 9291467999214530-40 Ext. 2276

  Traffic [email protected],      

[email protected] Ext. 2466

  Deputy Conservator [email protected] Ext. 2242

  Chief Accounts Officer [email protected] Ext. 2257

  Chief Mech. & Elect. Engineer [email protected] Ext. 2510

  Manager Finance [email protected], 9921439799214530-40 Ext. 2343

  Chief Engineer -----9921431899214530-40 Ext. 2211

  Chief Auditor -----9921454599214530-40 Ext. 2234

  Manager Coordination ----- 99214530-40 Ext. 2294

  Project Manager (Planning) -----9921434599214530-40 Ext. 2491

  Project Manager (East) -----9921436599214530-40 Ext. 2221

  Project Manager (West) ----- 99214530-40 Ext. 2221

  Project Manager (Mechanical) -----9921437699214530-40 Ext. 2332

  Chief Medical Officer ----- 99263030

  Manager (O&M) -----9921434399214530-40 Ext. 2300

Page 3

Page 4: Kpt Long Report_1

Karach Port Trust --- Gate Way to Pakistan .

  Manager (IR&W) -----9921434899214530-40 Ext. 2285

  Manager Stores [email protected] Ext. 2320

  Manager (Human Resources) [email protected] Ext. 2365

  Manager (Training and Education) [email protected] 99203950

  Estate Manager -----9921434799214530-40 Ext. 2353

Commandant Port Security Force  9921435099214530-40 Ext. 2500

Manager, Pollution Control Department  

9921042599214530-40 Ext. 2561

Manager Port Safety  [email protected] Ext. 2487

Port Intelligence Officer  -----

992143359921471499214530-40 Ext. 2627 

Geographic Location

Page 4

Page 5: Kpt Long Report_1

Karach Port Trust --- Gate Way to Pakistan .

Container Terminals

Karachi International Container Terminal

Page 5

Page 6: Kpt Long Report_1

Karach Port Trust --- Gate Way to Pakistan . The first dedicated container terminal of Karachi Port with an investment of $65 millions is operation since 1997. the terminal has capacity of 350000 TEUs. Initially an APL-ICTSI Venture KICT has been taken by HBH whmpao of Hong Kong and after completion of phase 2 Wirt the fourth gantry crane with 55 meters outreach commissioned in March 2004, further expansion of the terminal is underway.

In the third phase KICT is extending and deepening its births with a further investment of $55 million. KICT is a modern Terminal with an efficiency of 65 TEUs per hour providing fast through put of 75000 TUEs.

Pakistan International Container TerminalThe second port terminal of Karachi Port is located on east wharves. With 600 meter long quay wall having 13.5 meter depths, the terminal has a capacity of 450000 TEUs. The terminals provide 54 meter reach gantry cranes and the state of the art equipment with 7 million investment. IFC and OPEC are core financier of the project . PICT has also made a public offering of 20% of its shares. On completion of phase 3 the terminal would have a through put of 550000 TEUs.

Karachi Port Operational Centre (KPOC)Fully automated Karachi port operational centre is located in the port control tower at east wharf. It is the nerve centre of the port all operations taking place inside the Karachi Port and the harbour. It is managed round the clock and communicates with all concerned and emergency responses are intitated by this centre. It is equipped with 15 cameras on separate places.

Income The income of the Karachi Port Trust is derived from the following main activities as per scale of tariff fixed for the each items as is framed under 43-43 A of the Karachi Port Trust act 1986 and notified by the federal government through SRO.

1. Cargo Handling2. Vessel Handling3. Cargo Storage4. Ships Movement & Services5. Estate Management

Expenditure1. The main areas in which incurred expenses are:2. Salaries and Wages3. Operating material and supplies 4. Outside repair and maintenance5. Administration and Overheads6. Loan Interest

Port Operations/Functions

Primary functions of Karachi Port Trust are CARGO HANDLING and VESSEL HANDLING.

Page 6

Page 7: Kpt Long Report_1

Karach Port Trust --- Gate Way to Pakistan .

CARGO HANDLINGCARGO TYPES Import Export Total

 Containers (TEUs) 1,569       3,183       4,752       Containers (TONs) 20,673       46,086       66,759       TP Cont.      (TEUs) -       -       -       General Cargo 2,880       100       2,980       Sub. Total Gen. Cargo 23,553       46,186       69,739       Bulk Cargo 1,701       9,412       11,113       Total Dry Cargo 25,254       55,598       80,852       Liquid Cargo 56,764       -       56,764      

 GRAND TOTAL 82,018       55,598       137,616      

Container HandlingType of

Handling

Loaded Containers Empty Containers Total Teus20' 40' Over 

40'20' 40' Over

40'Import 795 198 0 68 155 0 1,569Export 1,118 770 0 127 199 0 3,183Total 1,913 968 0 195 354 0 4,752

Shipwise Cargo Handling

Berth No.

Name of Ship Working Berthing Date

Agent Steve-  dore

Discharging LoadingDis. Bal. 24 Hrs Sh. Bal. 24 Hrs

BULK OIL PIERS

OP-II AkakiD.Crude Oil 12-02-12 PNSC - 73,764 Comp. 41,764 - - -

OP-III QuettaD.Crude Oil 11-02-12 PNSC - 69,544 Comp. 15,000 - - -

EAST WHARVES

4 Chungo TresL.Rice 13-02-12 EAST WIND MMS Shifted from

B.No.11/1232,643 13,967 863

5 King HeroD.GC 11-02-12 TRANSBRIDGE MARHABA 8,679 2,326 2,728 - - -

11/12 CF CrystalD.Canola 14-02-12 OC-SERVICES NT - 56,060 - - - -

NMB Country CraftsD.L.GC - - - 152 -

152100 -

100

P.I.C.T     6 – 9 (EAST WHARVES)

6/7 Valerie SchulteD.L.Cnt. 12-02-12 NOT PROVIDED PMS 10,382 Comp. 602 10,321 Comp. 3,896

6/7 HanjinMonacoD.L.Cnt. 13-02-12 NOT PROVIDED PMS 14,406 358 14,406 6,384 6,748 6,384

8/9 Glen CanyonBridgeD.L.Cnt. 12-02-12 NOT PROVIDED PMS 13,010 Comp. 70 14,868 970 9,618

WEST WHARVES

20 Sea MerchantD.Wheat 07-02-12 5 STAR-SH. CMDR 10,173 5,527 1,701 - - -

21 Pacific TrafficL.Rice 06-02-12 GENERAL-SH FC - - - 20,359 8,641 3,109

25 Tabernacle PrinceL.Cement 13-02-12 ARGONAFTIS - - - - 5,440 12,350 5,440

Page 7

Page 8: Kpt Long Report_1

Karach Port Trust --- Gate Way to Pakistan . K.I.C.T    26-30 (WEST WHARVES)

26/27 Hyundai FreedomD.L.Cnt. 13-02-12 U.M.A MTO 10,237 Comp. 4,486 16,728 Comp. 16,070

28/29 LindaviaD.L.Cnt. 12-02-12 NTO PROVIDED MTO 18,796 Comp. 824 13,385 Comp. 10,118

29/30 ViolettaD.L.Cnt. 14-02-12 NTO PROVIDED MTO 285 961 285 - 10,809 -

Vessel Handling1. Arrival Schedule - OFF PORT

Vessel's Name L.O.AStatus

Time/Date

Draft(In Mtrs.) Purpose Berth Alloted Special Request

a) Oil Tanker Ships Maribel 228.0  Off Port 9.1   D.Mogas  OP-III  -

 DL Ace 125.0  0200/15 6.2   L.Ethanol  OP-II  -

b) Container Ships Wan Hai-602 276.0  Off Port 11.5   D.L.Cnt.  8/9  PICT

 Marcampania 163.0  1400/14 8.5   D.L.Cnt.  1/2  East Wharf

 Bravo 208.0  0230/15 10.5   D.L.Cnt.  6/7  PICT

c) General Cargo Ships Wo Long Song 179.0  1200/15 9.9   D.Gen.Cargo  24  West Wharf

d) - BM Pride 165.0  Off Port 6.2   Bunkering  SRB-1  East Wharf

2. Sailing Schedule Vessel's Name  L.O.A  Time/Date  From

Berth Ship Type  Remarks

Glen Canyon Bridge 285.0  1400/14  8/9  Container Ships  -

Hanjin Monaco 261.0  1445/14  6/7  Container Ships  -

King Hero 160.0  0200/15  5  General Cargo  -

3. Shifting Schedule Vessel's Name  L.O.A  From Berth  To Berth  Time/Date  Reason

 Peace Traffic 177.0   21  5 1500/14 - 

Shipping Services

Page 8

Page 9: Kpt Long Report_1

Karach Port Trust --- Gate Way to Pakistan .

Ships RepairRepairs can be carried out at the anchorage, except in the monsoon season. Two ship repair jetties are available in the port. In addition, Karachi Shipyard and Engineering Works Ltd. provide all kinds of repair and ship-building facilities.Immobilization of main Engine:Request for immobilization must be included by the master of the vessel in their arrival messages so that the permission of the Deputy Conservator, Karachi Port Trust may be obtained for the period required to carry out maintenance and necessary repairs. Oil tankers are not permitted to immobilize engines, particularly at oil pier berths.Pilotage

Pilotage is compulsory for vessels of 200 GRT and upwards. Pilot boards at the Outer Anchorage.

Vessels are pilotage day and night, subject to tides, length and draft to berths lying on the East and West of the fairway, which is 4.27 miles long. Pilotage distance is about 5 to 6 miles.Fuel Companies Different fuel companies have provided 3 grades of petroleum for the ships i.e. furnace oil, light diesel oil and high speed diesel oil. All types can be supplied at berth and at anchorage by bargeFresh Water Fresh Water is available at all BOP and berths No. 18 to 25 at West Wharf through shore supply lines for ships and tankers.Tugs And BargesFive Tugs are available at the Port, two are of 40 Tons and 3 are of 25 Tons bollard pull. Tug operations inside the harbor are rendered by Karachi Port Trust on signal from the Pilot. Tug operation is not provided outside the breakwater except in very special circumstances, at the discretion of the Deputy Conservator. This is subject to weather conditions and availability of tugs. Tug operations outside the breakwater are governed under special terms and conditions.

Projects

Page 9

Page 10: Kpt Long Report_1

Karach Port Trust --- Gate Way to Pakistan . As the new generation of container ships comes on the drawing boards, Karachi Port takes the initiative of bracing itself to handle and cater for fifth and sixth generation ships. This involves the development of a deep water container port at Keamari Groyne, which is the natural choice for such a port.  Project consultants are M/s Royal Haskoning and M/s Scot Wilson of UK.  Ten berths at 18m depth, with 5 km of quay wall have been planned. The project shall be carried out in phases and on public-private partnership (PPP). Total cost of the project is US$ 1.6 billion. In Phase I, four berths with 1500 m quay wall is planned to be constructed. Project is scheduled for completion in 2013.

PDWCP Phase-1 - The Concession Agreement

The Phase 1 of PDWCP comprises 4 berths and will have 1500m quay length. A design vessel, (similar to Emma Maersk), of 400 m LOA, 55.0m Beam and l5m Draft with 11,000 TEUs on board, has been used for planning the PDWCP. The channel and berthing face will be dredged to – 16m initially, but the Quay wall is designed for – 18m depth. The container terminal will have both road and rail connections to the hinterland including the proposed Cargo Village in the Western Backwaters of Karachi Port.The viability of PDWCP with respect to the geographical location of the port was proved when in response to the KPT’s request for proposals for setting up of the PDWCP, four world renowned firms responded. After an exhaustive exercise of evaluation of the most competitive bid, M/s Hutchison Port Holdings Limited (HPH) of Hong Kong has been awarded the Concession. HPH is the world’s largest container operator. In 2006, HPH handled 59.1 million TEUs worldwide and of which, 13.1 million were transshipment. HPH operates 257 berths in 45 ports in 23 countries alongwith a number of transportation related service companies.The lease of the terminal will be for an initial period of 25 years extendable for another 25 years, on mutually agreed terms and conditions. M/s. Hutchison Port Holdings Limited (HPH) Hong Kong will be required to develop the site into a full-fledged state of the art Container Terminal capable of receiving and handling Super Post Panamax Container Ships. Terminal Capacity will be 3.1 Million TEUsExpected initial investment by M/s. HPH is US $457 Million. All equipment will be new and current models from internationally accredited manufacturers.

THE SCOPE OF INFRASTRUCTURE DEVELOPMENT BEING CARRIED OUT AT PDWCP BY KPT:

Dredging and Reclamation:  The dredging and reclamation contract has been signed with China International Water and Electric Company (CWE). Total 33 million cum dredging

Page 10

Page 11: Kpt Long Report_1

Karach Port Trust --- Gate Way to Pakistan . including 8 million cum reclamation is planned at a cost of Rs 19 Billion. Completion is scheduled in 2011. The existing Port Approach Channel is to be widened and deepened so as to link it to the new PDWCP harbour. This shall initially increase the depth of existing channel from -12.2 meters to -16.0 meters.

 

From approximately 33.0 million cubic meters of dredging to be carried out, about 8.0 million cubic meters of the material shall be used for reclamation works and for creating stockpiles of material for future use in the terminal construction.The Dredging and Reclamation works shall also complement other modules of the Pakistan Deep Water Container Port namely, the Marine Protection Works and the Quay Wall construction works.

 

Page 11

Page 12: Kpt Long Report_1

Karach Port Trust --- Gate Way to Pakistan .

Marine Protection Works:  The second component is Marine Protection Works (MPW) in

which three breakwaters and a sand dyke are planned to be built. The contract has

been awarded to M/s China Harbour Engineering Company (CHEC) at a cost of Rs 12.8

Billion.  Completion is scheduled in 2012.

 

 

The Marine protection works for the project shall include construction of 3

breakwaters and a sand dyke. The marine protection works have been envisaged to

comprise of three rock or concrete (CORE-LOC units) armoured breakwaters to

provide shelter to the port basin and for preventing sediment transport into the basin.

The scope consists of:

-          Keamari Extension - Repairs as deemed necessary to strengthen existing

Groyne. To be constructed to accommodate a future -18.0mPD dredged

depth at PDWCP harbour entrance.) Repairs to existing Keamari Groyne are

also planned.

-          Oyster Rocks Breakwater - Construction of breakwater (-18.0mPD dredged

depth at PDWCP harbour entrance) and Construction of concrete pedestrian

access along shore side. To be constructed to accommodate a future -

18.0mPD dredged depth at PDWCP harbour entrance. Construction of

concrete pedestrian access along shoreside)

-          Manora Breakwater

To be constructed to accommodate a -18.0mPD dredged depth at Port

entrance)

Page 12

Page 13: Kpt Long Report_1

Karach Port Trust --- Gate Way to Pakistan . Keeping in view the significance of the project, the design parameters have been set keeping in view that the wave conditions at the entrance to the Port of Karachi are dominated by southwesterly (180° to 270°) offshore and waves propagating from the Indian Ocean.

The design life and standard for the breakwaters are 50 years and the Design

standard adopted for a life of 100 years. As per good engineering practice of model

test the final design of large breakwater structures have been tested through physical

modelling.

Quay Wall Construction :  The contract for quay wall been awarded to M/s China Harbour

Engineering Company (CHEC) at a cost of 18 Billion. Completion is scheduled in 2012.

A tied bored pile quay wall has been designed, in which the quay wall is to be built

using 2.5m diameter circular reinforced concrete piles, restrained by steel anchor ties

attached to a piled anchor beam located 50 metres (centre to centre) behind the quay

wall. The anchor beam is supported by 1.6m diameter reinforced concrete piles at 2.6

metre centres. The design is selected to use proven technology and good earthquake

resistance.

The following facilities are provided in relation with the present design:

• A straight quay length of 1,500m, providing a nominal four berths of 375m length with a depth alongside of

-16.5m initially and -18.0m finally, and able to accommodate vessels in the capacity range 750 TEU to

14,500 TEU;

• Crane rail slots for the installation of crane rails to allow operation of STS cranes.

• Appropriate marine furniture including fenders and bollards for the expected vessels and ladders.

 Karachi International Container Terminal ( KICT)

KICT, is already operational at the West Wharf. It was developed in phases. Initially

two phases were operational with terminal area of 135,122 sqm and an annual

capacity of 400,000 TEUs. Previously with only two phases functional, terminal area of

135,122 sq.m. Cost of Phase I & II is USD 65 million.

Phase-III has also been completed. This was inaugurated by Honarable Prime Minister

Syed Yousuf Raza Gilani in November, 2008.

In this phase, the terminal has an area of 260,000 sq.m with an additional investment

of US$ 55 million. The total Terminal capacity shall be increased to 700,000 TEUs. The

Page 13

Page 14: Kpt Long Report_1

Karach Port Trust --- Gate Way to Pakistan .

973 m long berths of the terminal are deepened to cater for 14 meter draught

container ship. The Terminal is equipped with 6 gantry cranes, 15 RTGs, 4 Top lift, 4

empty handler, 50 chasis etc. Presently they are handling 806,000 TEUs per year

Pakistan International Container Terminal (PICT)

The second Container Terminal on BOT was awarded by KPT in June 2002. This

Terminal at Berths 6-9 East Wharf has 600 m quay wall with - 13.5 m depth over an

area of 207,000 sqm. The terminal’s planned capacity is 450,000 TEUs. This was a US

$ 75 million project.

PICT was also developed in Phases. In Phase-I Two modern gantry cranes and

associated equipment were deployed. 

Phase-II was completed in May 2006 with additional deployment of one more ship to

shore gantry crane and Phase-lll has been completed in January 2009. Presently they

are handling 603,000 TEUs per year

 Reconstruction of Berths

KPT has 30 dry cargo berths and 560 meter quay wall at Napier Boat Whraf for

country craft. Out of which 17 # berths situated at East Wharves & 11 # berths @

west Wharves.  Two container terminals (PICT & KICT) occupied 9 # berths (6 to 9

berths for PICT) & (30 to 26 berth for KICT). The rest of berths are operational

under KPT management. Due to collapse of berth # 10 & 14 in August

2007, KPT declared these 9 # berth (ie.10 to 17A) non operational since August 2007. 

Due to shortage of berths, KPT had initiated step in year 2005 to appoint M/s Scott Wilson +ZCL for

planning & detailed designing of old & outlived berths # 10-17A including SRB’s, before this berth collapse

incident occurred in year 2007.  Thereafter KPT decided to commence the berth reconstruction in phases. In

1st phase, KPT awarded  the work  to Contractor M/s Ssangyong +Usmani (JV) and they commenced the

work from 20th  March 2007 and was to be completed in  March 2010, but  said  work could not  completed

within  time  i.e. 24 months due to various technical reasons.

Page 14

Page 15: Kpt Long Report_1

Karach Port Trust --- Gate Way to Pakistan .

 

The supervision of project work is being done by the supervision consultants M/s Lyon

Associate (USA) + Techno (JV) of execution.  The cost of the project is Rs. 5.5 Billon

and funded by KPT own resources. Physical completion progress of work is about 60

%. The total quay wall length is 777.823 meter between berth 10 to 14, included  2

meter dia cast in-situ concrete piles connected /associated with tie rods & other allied

fixture for supporting of the berths structures.

Project completion of phases is October, 2010 and July 2011.

RECONSTRUCTION OF BERTH 15- 17 A INCLUDING SRB’S `1 & 2 AT EAST WHARVES.

The project “Reconstruction of 15 -17A” will be executed in 2nd phase of

reconstruction sequence of reconstruction of berths t at east wharves.  The design &

planning of the project has already been completed. KPT is intending to finance this

project through World Bank soft loan. The negotiation with World Bank is almost

finalized, and it will be materialized very soon. The Concept of project has been

approved by CDWP of Planning & Commission. The cost of the project is Rs 9.224

Billion including some important assignments (KPT’s Institutional Strengthening of

project & EIA report & its improvement) to be carried out under the loan facility.

On the basis of World Bank guidelines, KPT initiated Prequalification stage and invited

contracting local /international firms to participating in PQ stage. In response 9 firms

participated with local JV’s partners in this stage of prequalification.  KPT’s design

Page 15

Page 16: Kpt Long Report_1

Karach Port Trust --- Gate Way to Pakistan .

consultant prepared a prequalification Report and the same has been forwarded to

World Bank for its approval. Recently KPT received some queries from word bank on

PQ report, hence y KPT shall reply on these queries accordingly; however World Bank

is principally agreed to the PQ report for the selection of the contracting firms.

The tender documents have been reviewed by World Bank and send back to KPT for

its minor changes. The tender document shall be floated to the prequalified contractor

very soon.

Port Grand (Food Court)

        Another project is the establishment of a Food Street, at our Native’s Jetty Bridge

and its adjoining area within rotary of Jinnah Bridge.

 

The project is offered on Build Operate and Transfer basis for 21 years. This scenic

stretch, has ample area for landscaping, walkways and joy rides, dinner cruises etc.

Infrastructure has been completed and outlets are being awarded.

Page 16

Page 17: Kpt Long Report_1

Karach Port Trust --- Gate Way to Pakistan .

SECURITY MEASURES AT KARACHI PORT 

1.       Karachi Port with regard to Security has taken a giant leap forward in the area

of technology and sophistication. The Security Sector has been totally revamped with

the induction of Port Security Force. Karachi Port Trust is fully alive to the global

security environments and is proactively poised to meet future formidable security

challenges. The goal of Karachi Port Trust is to provide secure environment in which

trade be conducted with high assurance and equilibrium of security & safety versus

efficiency. KPT after having evaluated the global security environments has embarked

upon revolutionizing security on the port introducing state of art security

infrastructure as per requirements of IMO and implementation of ISPS Code in real

spirit. Following cutting edge equipments / measures has been installed/ implemented

on the port.

 

a)      VIDEO MANAGEMENT SYSTEM (VMS)           As part of mitigation strategies, KPT has installed state of the art harbour and area scanning cameras on the port with following specification:         

i)        Espirit TM Image Pak System, PTZ outdoor colour Digital Camera System.ii)       Spectra III TM Series high Resolution speed Dome, 16 x for surveillance of

gates, plinths and quay wall.iii)      Digital, distributed, Networked integrated for Video Management and

surveillance over Inter Protocol (IP) networks.iv)      Digital recording and surveillance serve as high capacity Data base.        

 

b)      VMS GREATLY ENHANCES SECURITY, SAFETY AND EMERGENCY RESPONSE ON THE PORT AND RENDERS ADVANTAGES AS UNDER:

          i)        It tracks ships right from anchorage to the berth.         

Page 17

Page 18: Kpt Long Report_1

Karach Port Trust --- Gate Way to Pakistan .  ii)       Assists in identification and monitoring of ships without transponders.          iii)      Provides Surveillance and monitoring of all the ships/ crafts inside the harbour.  iv)      Assists in identification of suspicious ships/ crafts in the harbour.   v)      Allows Surveillance and monitoring of the ships at the berths.   vi)     Surveillance and monitoring of cargo operations.  vii)     Surveillance and monitoring of vehicular traffic on the port. viii)     Enable to activate prompt response to meet emergencies.  ix)     Helps in maintaining historical record of movement of ships/ cargo.  

c)       VESSEL TRACKING SYSTEM (VTS):           KPT has installed cutting edge Vessel Tracking System in the port to surveil/ monitor vessels in the Port Area / Territorial Waters/ harbour. The system receives vessel information transmitted by them and displays their position on a shore based computer work station on an electronic chart. User can select both the desired areas and amount of details required; system continuously automatically to logs the reports, records latitude and longitude, speed and course of all tracked vehicles. Historical track information can be recalled and printed out either as chart or data base report in real time along with history of the track. VTS has greatly helped in managing vessel traffic diversity on the port. The system provides: i)                Better Command and Control.ii)               Effective utilization of assets.iii)              Quick emergency response.iv)              Safe and secure passage of ships.v)               Identification and monitoring of aligned/ non aligned ships.vi)              Dynamic data base for recording of information/ activities.vii)             UAIS as per ISPS Code required.     

 

2.              IMPLEMENTATION OF ISPS CODE: 

a)     The Karachi Port has complied with ISPS Code as per requirements of IMO on 01 July 2004. The Karachi Port has been divided into three Port Facilities as under:

           i)        Port Facility - I:

Oil Pier I, II, III, Mooring Area and Anchorage Area  The Port Facility Security Officer –I can be contacted on PFSO-I, Contact No.0333-2378561.

                   ii)      Port Facility – II:                   Berth No.5 and 10 -17 

The Port Facility Security Officer –II can be contacted on

Page 18

Page 19: Kpt Long Report_1

Karach Port Trust --- Gate Way to Pakistan . PFSO –II Contact No.-0334-3159881

 iii)              Port Facility – III:

Berth No.18-25The Port Facility Security Officer –III can be contacted onPFSO – III Contact No.0333-2378562

 b)      The Two Private Terminals in Karachi Port have been declared as two separate identity

and Facility namely: 

i)                   PICT (Pakistan International Container Terminal) Facility:Berth No.6-9PFSO Col (R) Saleemullah Contact No.0321-2430530     

                       ii)                KICT (Karachi International Container Terminal)

 Berth No.26-30PFSO Lt Col. (R) M. Ramzan Contact No.0333-2160970

 c)       All the Port Facilities are being monitored by: 

i)                   Harbour Patrol by boats with armed port security personnel.ii)                Mobile Patrols through Mobile Vans and Motor Cyclist on wharves, Roads and

Jetties.iii)              Excess Control System at Entry/ Exits Gates is equipped with Biometrics,

Smart Card Recorders and CCTV.iv)              Computerized Gate Pass System for Entry with in bonded area.

 

3.       KARACHI PORT OPERATION CENTRE (KPOC)           The State of the art KPOC has been established at a strategic location having panoramic view of the port to supervise, monitor and control activities. The centre is fully computerized and all the reports and returns are being electronically generated. Intranet, Internet and direct communication facilities help in making prompt and real time decision making. KPOC serves as a nerve centre and houses representatives of departments of the Port. Functions of KPOC are:         

i)                   To collect, collate process and disseminate information.ii)                Monitor and control port operations.iii)              Act as communication centre.iv)              Act as focal point to render technical assistance.v)                 Monitor and control marine pollution in the harbour.vi)              Co-ordinate and maintain security activities on the port.vii)            To activate emergency response to handle crises situation.

   Contact No.          OI/C KPOC                     9263050, Ext. 2302

Page 19

Page 20: Kpt Long Report_1

Karach Port Trust --- Gate Way to Pakistan . Operation Room Officer                               9263046, 9214555

                                                          9214530                                                          Ext. 2557, 2539, 2693

 4.       Karachi Port is manned and performs 24 hours a day 7 days a week. In case of any clarification / assistance one can contact on following numbers: S.No. Designation Telephone Numbers

1. General Manager (Ops) 9214375, 92143792. Traffic Manager 9214361, 9214530 Ext.24663. Dt. Conservator 9214354, 9214530 Ext.22424. Commandant Port Security

Force9214350, 9214530 Ext.2291

5. Operation Room Officer 9263046, 9214555, 9214530 Ext.2557, 2539, 2693

6. Manager Port Safety 9214598, Ext. 2487

Page 20

Page 21: Kpt Long Report_1

Karach Port Trust --- Gate Way to Pakistan .

Summary

Karachi Port is one of those public enterprises in Pakistan which has basic and vital role for the nation as well as for the economy of the country, without which the economic development may become stand-still. Significance of this port for Pakistan becomes more prominent when one takes into account the difficulties of the land locked countries like Afghanistan, Central Asian States and Nepal etc. inconnection with their international trade. In case of our country, which has import oriented economy, struggling to boost up its exports in order to reduce the yawning trade gap, and which has very little prospect of regional trade through land routes, the significance of the Karachi Port becomes more important its major sea port.

After 1947, this port jumped to the status of jugular vein for newly created stat and since then it has been functioning as a gateway for its international commerce. If one has a view of the economic of its capacity for dry cargo far before however, containerization came to help and extra burden is being offset, to large extent, in the form of CY container Cargo which constitutes about 50% of the total import container traffic. The burden of the port has also been shed in the way that a considerable volume of dry cargo in build form like, wheat, ores, cement and fertilizers etc. has been shifted to Port Qasim.

Two international container terminals i.e. Karachi International Container Terminal & Pakistan International Container Terminals being administrated by private public sector are very useful addition toward upgrading the Karachi Port. These International container terminals are saving lot of time of vessel agents/operators with the use of stat of the art equipment.

Another Pakistan Deep Sea Water Container Terminal is also under process project of Karachi Port Trust, which is considered as the Asia’s biggest container terminal which will make Karachi Port Trust more effective for Pakistan’s Economy. In spite of this a lot of development which could have made by the authorities but still need to be planned.

Even now, it is not too late to make amends for the pas mistake. The Karachi Port still can be developed upto the modern level requirements and it can be introduced into the regional competition if sincere efforts are made. For this purpose the thing of foremost importance is that maximum share in this developmental and operational activities is to be given to the private sector because from decades old traditional bureacratic set up of this administration which has become used to take each step under directions of the Federal Government, cannot be expected any revolution in this direction.

Page 21

Page 22: Kpt Long Report_1

Karach Port Trust --- Gate Way to Pakistan .

LIST OF ABBREVIATIONS

Page 22

Page 23: Kpt Long Report_1

Karach Port Trust --- Gate Way to Pakistan . AN Amplifying NoteBAN Barges Amplifying NoteBCAN Berth Charges Amplifying NoteBB Break BulkCCAN Country Craft Amplifying NoteCHAN Chain Amplifying NoteCBM Cubic MeterCY Consignee YardCFS Container Freight StationDG Dangerous GoodsECAN Electric Quay Crane Amplifying NoteEGM Export General ManifestFRAN Fire Relief Amplifying NoteFCL Full Container LoadFCAN Floating Crane Amplifying NoteGC General ClausesGDAN Graving Dock Amplifying NoteGoP Government of PakistanHAN Haulage Amplifying NoteHLAN Heavy Lift Crane Amplifying NoteHTAN Hire of Tug Amplifying NoteHFAN Hard and Foreshore Amplifying NoteIGM Import General ManifestIMDG International Maritime Dangerous GoodsLCL Less than Container LoadLFAN License Fee Amplifying NoteMAN Mooring Amplifying NoteMCAN Miscellaneous Craft Amplifying NoteMoC Ministry of CommunicationsMoD Ministry of DefenceOAAN Outer Anchorage Amplifying NoteOV Original VesselPAN Pilotage Amplifying NotePDPT Per Day Per TonPD Per DayPDAN Port Dues Amplifying NotePDPft Per Day Per FootPT Per TonPTO Part thereofSAN Storage Amplifying NoteSLAN Salvage Amplifying NoteSWAN Supply of Water Amplifying NoteTAN Towage Amplifying Note

TEUTwenty Equivalent Unit

WANWharfage Amplifying Note.

Page 23