Ron,
Attached are the descriptions of three case studies. Would you like to review the outcomes?
#1. To improve upon the design of a CT suite recommended by a vendor.
#2. To expedite the installation of a radiographic room for use by the Emergency Department.
#3. To refine the design of filmless reading rooms for the transition from film-based reading rooms to digital reading stations.
Ken
![Page 3: Kj case studies to rk ending point](https://reader031.fdocuments.in/reader031/viewer/2022021923/5a679e5f7f8b9a360c8b59d3/html5/thumbnails/3.jpg)
Example #1. Vendor’s recommended CT Design
Questions, concerns, suggestions for improvement?
![Page 4: Kj case studies to rk ending point](https://reader031.fdocuments.in/reader031/viewer/2022021923/5a679e5f7f8b9a360c8b59d3/html5/thumbnails/4.jpg)
4’ 11”
Questions, concerns, suggestions for improvement?
Key TakeawayBe extremely cautious of installation advice provided by vendors.
![Page 5: Kj case studies to rk ending point](https://reader031.fdocuments.in/reader031/viewer/2022021923/5a679e5f7f8b9a360c8b59d3/html5/thumbnails/5.jpg)
5
Example #2. Actual Case Study Expedite installation of an emergency radiographic room
Starting Point:• Current room to be taken out of service within 30 days
• Am not to look at anything else whatsoever for following reasons:
1. Any other changes would jeopardize getting this room installed quickly.
2. There are – and will NOT be - any funds approved for doing anything else for at least one year if not more.
Room dimensions:20’ x 24’
![Page 6: Kj case studies to rk ending point](https://reader031.fdocuments.in/reader031/viewer/2022021923/5a679e5f7f8b9a360c8b59d3/html5/thumbnails/6.jpg)
Typical radiographic equipment• Chest board for chest x-rays on back wall• Radiographic table on which some patients lay• X-ray tube hangs from ceiling mounting so it can move
about the room to aim in any direction• Casework for supplies
Source: Google: Radiographic room design. Then select: “Images for radiographic room design”,
Key TakeawayAlways identify an existing site to use as a benchmark for your design early in your planning process.
![Page 7: Kj case studies to rk ending point](https://reader031.fdocuments.in/reader031/viewer/2022021923/5a679e5f7f8b9a360c8b59d3/html5/thumbnails/7.jpg)
*To see this drawing as well as many photographs of radiographic rooms, Google: Radiographic room design. Then select: “Images for radiographic room design”, “Images for . . .”
AssignmentSeen below is a layout for a radiographic room that pops up if you go to the Google site listed below*. Using this layout or other information from this web site, create a layout on the attached slide which is to be turned in at the start of class on Tuesday.
Key TakeawayBe extremely cautious of advice from Internet. Watch for red flags.
![Page 8: Kj case studies to rk ending point](https://reader031.fdocuments.in/reader031/viewer/2022021923/5a679e5f7f8b9a360c8b59d3/html5/thumbnails/8.jpg)
8
Print Name (legibly) _________________
Classroom exercise #1 for ISE 541Recommended design for a radiographic roomTurn in at start of class on Tuesday
![Page 9: Kj case studies to rk ending point](https://reader031.fdocuments.in/reader031/viewer/2022021923/5a679e5f7f8b9a360c8b59d3/html5/thumbnails/9.jpg)
9
Actual Case Study Expedite installation of an emergency radiographic room
Starting Point:• Current room to be taken out of service within 30 days
• Am not to look at anything else whatsoever for following reasons:
1. Any other changes would jeopardize getting this room installed quickly.
2. There are – and will NOT be - any funds approved for doing anything else for at least one year if not more.
Room dimensions:20’ x 24’
![Page 10: Kj case studies to rk ending point](https://reader031.fdocuments.in/reader031/viewer/2022021923/5a679e5f7f8b9a360c8b59d3/html5/thumbnails/10.jpg)
10
ED
Supplies
1
4
3
2
EmergencyDepartment
Key TakeawayCreate a “Functional Drawing” for conducting an initial current state assessment to understand the big picture.
Existing Conditions1. Current ED Radiographic Room to be taken out of service within 30 days to create new Corridor
2. CT for Emergency use is in NE corner of Radiology Department
3. Single slice CT is obsolete, not used for Emergency work. CT to be replaced in future.
4. Second MRI needed. Plans being developed to install in vacant interventional room.
![Page 11: Kj case studies to rk ending point](https://reader031.fdocuments.in/reader031/viewer/2022021923/5a679e5f7f8b9a360c8b59d3/html5/thumbnails/11.jpg)
11
New corridor
Outcomes:1.Expanded space allocated from renovation from Angio Supply Room only to that seen above2.Gained approval to install new CT within this space..
![Page 12: Kj case studies to rk ending point](https://reader031.fdocuments.in/reader031/viewer/2022021923/5a679e5f7f8b9a360c8b59d3/html5/thumbnails/12.jpg)
12
New corridor
Outcomes:1.Created an MRI suite which also freed up space for future interventional work..
Key TakeawayUse “Functional Drawing Tools and Techniques to improve upon drawngs done by architects..
![Page 13: Kj case studies to rk ending point](https://reader031.fdocuments.in/reader031/viewer/2022021923/5a679e5f7f8b9a360c8b59d3/html5/thumbnails/13.jpg)
• Radiographic room was enlarged and redesigned.
• An Emergency Room suite was created with CT and Radiographic Rooms along with ancillary support spaces..
• A second MRI was justified and installed within space previously occupied by a CT
Net Result of Intervention and Use of Tools
![Page 14: Kj case studies to rk ending point](https://reader031.fdocuments.in/reader031/viewer/2022021923/5a679e5f7f8b9a360c8b59d3/html5/thumbnails/14.jpg)
Example #3: Dartmouth-Hitchcock Medical Center
“Minimizing the spaghetti.”
![Page 15: Kj case studies to rk ending point](https://reader031.fdocuments.in/reader031/viewer/2022021923/5a679e5f7f8b9a360c8b59d3/html5/thumbnails/15.jpg)
KJA
1. “To look only at design of new filmless radiology reading rooms (PACS) and nothing else.”
2. “Do not expect to make any changes as project is over budget and behind schedule.”
3. “CT suite is absolutely off limits. It is done.”
Conditions of Engagement:
![Page 16: Kj case studies to rk ending point](https://reader031.fdocuments.in/reader031/viewer/2022021923/5a679e5f7f8b9a360c8b59d3/html5/thumbnails/16.jpg)
KJ/MCExample
Example of one of the proposed designs for filmless reading room. What, if any, changes would you propose for this reading room?
![Page 17: Kj case studies to rk ending point](https://reader031.fdocuments.in/reader031/viewer/2022021923/5a679e5f7f8b9a360c8b59d3/html5/thumbnails/17.jpg)
Optimizing Radiology Workflow and Productivity
Monte G. Clinton, FAHRAAdministrative Director
Dartmouth-Hitchcock Medical [email protected]
Kenneth C. JohnsonPresident
Kenneth Johnson and Associates, [email protected]
AHRA 2003 Annual Meeting
![Page 18: Kj case studies to rk ending point](https://reader031.fdocuments.in/reader031/viewer/2022021923/5a679e5f7f8b9a360c8b59d3/html5/thumbnails/18.jpg)
Dartmouth-Hitchcock Medical Center
![Page 19: Kj case studies to rk ending point](https://reader031.fdocuments.in/reader031/viewer/2022021923/5a679e5f7f8b9a360c8b59d3/html5/thumbnails/19.jpg)
Dartmouth-Hitchcock Medical Center Hospital Corridor
![Page 20: Kj case studies to rk ending point](https://reader031.fdocuments.in/reader031/viewer/2022021923/5a679e5f7f8b9a360c8b59d3/html5/thumbnails/20.jpg)
Workflow Analysis Techniques
Create drawing to illustrate workflow at 15,000’Case Study: Dartmouth-Hitchcock Medical Center
“No changes to be made to basic design, but was givenapproval to suggest refinements.”
![Page 21: Kj case studies to rk ending point](https://reader031.fdocuments.in/reader031/viewer/2022021923/5a679e5f7f8b9a360c8b59d3/html5/thumbnails/21.jpg)
IP
OP, ED
Workflow Analysis Techniques
Continue to zoom in and analyze workflow from everyone’s perspective.
![Page 22: Kj case studies to rk ending point](https://reader031.fdocuments.in/reader031/viewer/2022021923/5a679e5f7f8b9a360c8b59d3/html5/thumbnails/22.jpg)
Color Code
Red = Patient
Blue = Technologist
Green = Radiologist
Workflow Analysis Techniques Analyze workflow by tracing everyone’s footsteps
Key TakeawayUse “Spaghetti Drawings” to first understand workflow, then improve upon it.
![Page 23: Kj case studies to rk ending point](https://reader031.fdocuments.in/reader031/viewer/2022021923/5a679e5f7f8b9a360c8b59d3/html5/thumbnails/23.jpg)
Yellow shaded area represents operator’s line of vision when looking at console. To see patient, operator looks to left.
Note challenge in getting patient into room, particularly if IV pole, etc.
Workflow Analysis Techniques
Zoom in until at “ground level.”
![Page 24: Kj case studies to rk ending point](https://reader031.fdocuments.in/reader031/viewer/2022021923/5a679e5f7f8b9a360c8b59d3/html5/thumbnails/24.jpg)
Workflow Analysis Techniques
Simulate the design using scale models putting yourself in the driver’s seat.
Proposed design before simulation
![Page 25: Kj case studies to rk ending point](https://reader031.fdocuments.in/reader031/viewer/2022021923/5a679e5f7f8b9a360c8b59d3/html5/thumbnails/25.jpg)
Workflow Analysis Techniques
Involve radiologists and all staff in simulating various designs.
Design resulting from simulation.
Key TakeawayConduct full-scale mock-ups or use scale models to develop designs and illustrate the final outcome you desire..
![Page 26: Kj case studies to rk ending point](https://reader031.fdocuments.in/reader031/viewer/2022021923/5a679e5f7f8b9a360c8b59d3/html5/thumbnails/26.jpg)
Workflow Analysis Techniques
Strive to minimize the travel for all parties
(Minimize the spaghetti)
Design resulting from simulation.
4th CT moved to Emergency Department.
![Page 27: Kj case studies to rk ending point](https://reader031.fdocuments.in/reader031/viewer/2022021923/5a679e5f7f8b9a360c8b59d3/html5/thumbnails/27.jpg)
• One CT was moved to ED.
• CT Suite was redesigned to improve workflow.
• Designs of PACS reading rooms were significantly improved upon.
Net Result of Intervention and Use of Tools
KJ/MC
![Page 28: Kj case studies to rk ending point](https://reader031.fdocuments.in/reader031/viewer/2022021923/5a679e5f7f8b9a360c8b59d3/html5/thumbnails/28.jpg)
Comments?
Questions?
Feedback?
Monte G. Clinton, CRA, [email protected]