Kestabilan Tambang Bawah Tanah
description
Transcript of Kestabilan Tambang Bawah Tanah
The Stability of The Stability of UndergroundUnderground OpeOpeningning
Lufi Rachmad
2
Review from Last WeekReview from Last Week
Insitu Stress (gravitational, tectonic, residual
stresses)
An underground opening changes the stress
condition Induced Stress
Induced Stress could triger unstability
Understanding stresses is an important part
in designing underground opening
3
Review from Last WeekReview from Last Week
Empirical equation to estimate insitu stresses
e.g. Shoerey
)z1
(0.001E 70.25k h ++=
4
Stress distribution around various opening Stress distribution around various opening shapes (circle, horseshoe, square, ellipse)shapes (circle, horseshoe, square, ellipse)
Review from Last WeekReview from Last Week
Underground opening design methodologyUnderground opening design methodology
5
Case Study ACase Study A
An orebody XYZ has been defined as a block caving deposit. What we should design first?
Plan View Section A-A’
A A’Orebody
XYZ
Orebody XYZ
Surface
7 km 1.4
km
6
Case Study ACase Study A
ACCESS
Orebody XYZ
Surface shaft
decline
adit
7
Case Study ACase Study A
The access for the orebody are decided to be twin adits, 6.8 m wide and 6.0 m high.
The opening size considers the following factors:Biggest dimension
Effective size after ground support
Drainage pipe & trench
Intake airways
8
Case Study ACase Study AFor the design purpose, how far apart should these two adits be?
Access Adits
(A-A’)
Surface
?
Orebody XYZ
Access Adits Plan View
A A’
The farther the more
ineffective
9
Case Study ACase Study A
Assuming the simplest condition, the axisymmetric stress distribution could be used.
0.00
0.50
1.00
1.50
2.00
0 2 4 6 8 10
Jarak dari batas terowongan, r/R
Teg
anga
n In
duks
i/T
egan
gan
Aw
al
Tegangan radial
Tegangan tangensial
r = 5R, the pre-mining stress would not be significantly different from the virgin stress field.
r = 17 meter as an early indication.
Might be further analyzed using pillar stability calc and numerical modeling
10
Insitu StressInsitu Stress
For a depth of 1,400 m, the equation gives the vertical stress σv = 38 MPa , the ratio k = 0.5 (for Eh = 25 GPa) and hence the average horizontal stress σh= 19 MPa
During preliminary design, the empirical stress equation can be used to obtain a first rough estimate of the vertical and average horizontal stress in the vicinity of the tunnel
11
Stress Distribution around Stress Distribution around ““HorseHorse--ShoeShoe”” TunnelTunnel
σσhh = = σσvvσσθθAA = 2.2 = 2.2 σσvv
σσθθBB = 1.3 = 1.3 σσvv
σσhh = 0.5 = 0.5 σσvvσσθθAA = 0.6 = 0.6 σσvv
σσθθBB = 1.8 = 1.8 σσvv
σσhh = 0.33 = 0.33 σσvvσσθθAA = 0.1 = 0.1 σσvv
σσθθBB = 1.9 = 1.9 σσvv
A
B B
σv
σh
12
Insitu StressInsitu Stress
Given the rock mass strength is around 70-80 MPa, a preliminary analysis of the stresses induced around the proposed tunnel shows that these induced stresses are likely to exceed the strength of the rock and that the question of stress measurement must be considered in more detail
13
Insitu Stress MeasurementInsitu Stress Measurement
Various ways to measure insitu stress Overcoring - Triaxial Strain CellHydraulic FracturingFlatjack MeasurementBorehole BreakoutAcoustic Emission
The most common set of procedures is based on the determination of strains in the wall of a borehole, induced by overcoring that part of the hole containing the measurement device.
14
OvercoringOvercoring (CSIRO Cell)(CSIRO Cell)
The CSIRO cell, referred to as a hollow inclusion The CSIRO cell, referred to as a hollow inclusion cell. It consists of a thin epoxy tube, with three cell. It consists of a thin epoxy tube, with three strain gage rosettes, embedded within the strain gage rosettes, embedded within the epoxy.epoxy.
Strain Gages
Epoxy
15
Overcoring methods are measuring in situ stress Overcoring methods are measuring in situ stress based on the stress relief around the borehole. based on the stress relief around the borehole. The relief of external forces by overcoring The relief of external forces by overcoring causes the changes in strain on the borehole causes the changes in strain on the borehole wall.wall.
OvercoringOvercoring (CSIRO Cell)(CSIRO Cell)
The field procedures consist of drilling a The field procedures consist of drilling a concentric EXconcentric EX--size borehole, installation of the size borehole, installation of the deformation gage, and overcoring a stress relief deformation gage, and overcoring a stress relief borehole.borehole.
If the elastic properties of the rock are known, If the elastic properties of the rock are known, the changes in borehole diameter or strains can the changes in borehole diameter or strains can be converted to in situ stress in the rock.be converted to in situ stress in the rock.
16
The CSIRO cell is designed to measure diametral The CSIRO cell is designed to measure diametral deformations of an EXdeformations of an EX--size (1.5" in diameter) size (1.5" in diameter) borehole during overcoring a concentric borehole during overcoring a concentric borehole (6" in diameter). The diametral borehole (6" in diameter). The diametral deformations are measured in three directions deformations are measured in three directions (60 degree apart) in the same diametral plane.(60 degree apart) in the same diametral plane.
17
OvercoringOvercoring (CSIRO Cell)(CSIRO Cell)
Need Need YoungYoung’’ss modulus and Poissonmodulus and Poisson’’s inputss inputs
LimitedLimited to within to within 1010--3030 meters of existing meters of existing openingopening
Overcoring Cost Overcoring Cost –– CSIRO Cells (2 sites)CSIRO Cells (2 sites)NIRM US$ 61KNIRM US$ 61KES&S US$ 44K approx. 20K per siteES&S US$ 44K approx. 20K per site
Price does not include drilling which will be Price does not include drilling which will be around US$ 120K / maround US$ 120K / m
18
Hydraulic FracturingHydraulic Fracturing
Typically hydraulic fracturing is conducted in Typically hydraulic fracturing is conducted in vertical boreholes. A short segment of the hole vertical boreholes. A short segment of the hole is sealed off using an straddle packer. This is is sealed off using an straddle packer. This is followed by the pressurization of the fracturefollowed by the pressurization of the fracture--free segment of the hole by pumping in water. free segment of the hole by pumping in water.
19
The pressure is raised until The pressure is raised until the rock surrounding the the rock surrounding the hole fails in tension at a hole fails in tension at a critical pressure. critical pressure.
Hydraulic FracturingHydraulic Fracturing
Following breakdown, the Following breakdown, the shutshut--in pressure, the in pressure, the lowest testlowest test--interval interval pressure at which the pressure at which the hydrofrac closes hydrofrac closes completely under the completely under the action of the stress acting action of the stress acting normal to the normal to the hydrofracturehydrofracture
20
Hydraulic FracturingHydraulic Fracturing
Limited to drill/pump equipment and ground Limited to drill/pump equipment and ground conditions conditions –– Max range 300m Max range 300m –– 1000m1000m
““QualitativeQualitative””
AssumptionsAssumptionsS1 Maximum Principle Stress is Vertical or S1 Maximum Principle Stress is Vertical or aligned with aligned with holehole
HydofracingHydofracingNIRMNIRM US$ 87KUS$ 87KGolder US$ 188KGolder US$ 188K
21
Borehole BreakoutBorehole Breakout
Extensive field evidence and laboratory Extensive field evidence and laboratory experiments suggest that borehole breakouts, experiments suggest that borehole breakouts, defined as borehole crossdefined as borehole cross--section elongations section elongations resulting from preferential rock failure, is a resulting from preferential rock failure, is a direct consequence of the in situ stress in the direct consequence of the in situ stress in the rock. rock.
22
Borehole BreakoutBorehole Breakout
One of the early observations of breakouts was One of the early observations of breakouts was in the quartzite and conglomerates of the in the quartzite and conglomerates of the Witwatersrand gold mine in South Africa Witwatersrand gold mine in South Africa (Leeman, 1964). The spalling was observed to (Leeman, 1964). The spalling was observed to occur at diametrically opposed points on the occur at diametrically opposed points on the borehole wall perpendicular to the direction of borehole wall perpendicular to the direction of the maximum principal stress. the maximum principal stress.
23
Borehole BreakoutBorehole Breakout
The most publicized The most publicized observation of breakouts observation of breakouts was in the 3 m diameter was in the 3 m diameter drift at 420 m level in the drift at 420 m level in the Underground Research Underground Research Laboratory (URL), Canada. Laboratory (URL), Canada. Two diametrically opposed Two diametrically opposed breakouts were breakouts were approximately aligned with approximately aligned with the vertical stress, which is the vertical stress, which is the overall least principal the overall least principal stress at URL. stress at URL.
24
Case Study ACase Study A
From insitu stress measurement, the bearing of the major principal stress is around 38-40 degree. What is the preferable panel/undercut drift orientation?
Plan View
Orebody XYZ
Plan View
Orebody XYZ
Panel/Drill Drift
σ1 σ1
25
Case Study ACase Study A
Ideally, the panel/undercut drift and the direction of cave advance are aligned with the principal horizontal in situ stresses.
If the direction of advance is perpendicular, the levels of stress in the abutmentahead of the undercut will be high and will increase as the undercut advances
Undercut Advance Direction
Plan View
Orebody XYZ
σ1
26
Stress Induced in the Stress Induced in the Extraction and Undercut LevelExtraction and Undercut Level
High abutment stresses induced in the vicinity of an advancing undercut front is resulted from undercutting activity.
Abutment stress
Cave Advance
27
Stress Induced in the Stress Induced in the Extraction and Undercut LevelExtraction and Undercut Level
The magnitude of abutment stresses in the cave vicinity could reach up 2 to 3 times the insitu stress magnitude.
This abutment stress could devastate development drifts if does not maintain properly
For XYZ Mine, the vertical stress σv = 38 Mpa. The abutment stress = 76 - 114 MPa
28
Failure of yielding arch support Failure of yielding arch support El Salvador Mine, Chile El Salvador Mine, Chile
Photo: M. L. Van Sint Jan
29
Rockburst at Extraction Level, Rockburst at Extraction Level, DOZ Mine, IndonesiaDOZ Mine, Indonesia
30
Collapse of an extraction level drift, Collapse of an extraction level drift, El Teniente Mine, Chile, 1989El Teniente Mine, Chile, 1989
CONCRETEDAMAGE
CONCRETEDAMAGE
1.5 m
31
Panel 15, 28 June 2003
Panel 15, 23 August 2003Panel 15, 7 August 2003
32
Stress Induced in the Stress Induced in the Extraction and Undercut LevelExtraction and Undercut Level
Several factors have the potential to influence the levels of stress induced in the extraction level excavation:
Distance between Undercut and ExtractionCave Hydraulic Radius
Undercut directionIn situ Stress regime
The timing of undercut relative to the extraction level developmentUndercut face shape
33
Case Study ACase Study A
The timing of undercut relative to the extraction level development relates to the selected undercutting method. In general, there are three main undercutting strategies:
1.Post Undercutting
2.Pre Undercutting
3.Advanced Undercutting
For XYZ BC Mine, an undercutting method should be selected.
34
TerminologyTerminologyDrill Drift - Undercut
Fan Drilling
Draw Bell Drift
Draw Bell
Major Apex
Panel Drift -Extraction
Minor Apex
Draw PointOrepass
35
ConventionalConventional PanelPanel CavingCaving
Undercutting and drilling takes place after development of the underlying extraction level has been completed.
Drawbells and DB drifts are prepared ahead of the undercut and are ready to receive the ore blasted from the undercut level
36
AdvanceAdvance UndercutUndercut PanelPanel CavingCaving
Undercutting and drilling takes place above a partially developed extraction level.
The partial development on the extraction level can consist of either extraction drift only or extraction drift and drawpoint drift
37
AdvanceAdvance UndercutUndercut PanelPanel CavingCaving
Drawbells are always prepared in the de-stressed zone behind the undercut, usually adhering to the 45 degree rule.
38
Comparing Abutment Stress ImpactComparing Abutment Stress Impact
Measuring abutment stress changes could be done indirectly by monitoring its impact.
The stress impact reflects in displacement / deformation occurred in the underground opening.
There are many different methods for monitoring displacement. The simplest and most common among them is a convergence gage
39
Comparing Abutment Stress ImpactComparing Abutment Stress Impact
A convergence gage usually consists of a tape, wire, rod, or tub in series with a deformation indicator.
Precision is typically around 0.005 in (0.13 mm)
40
33--Point ConvergencePoint Convergence
41
Case Study ACase Study A
Near XYZ BC Mine, there is an active BC mine, called KLM Mine, where the trial between Post Undercut and Advanced Undercut will take place.
Plan View
Orebody XYZ
KLM Mine
4 km
42
Undercut Trial at KLM MineUndercut Trial at KLM Mine
Panel 15Post
Undercut
Panel 16 Advanced Undercut
43
Undercut Trial at KLM MineUndercut Trial at KLM Mine
CaveUC Lvl
Extr Lvl
Cave Advance
Convergence Station
Last Blasting
Row
Abutment
18 m
44
Result of KLM Mine TrialResult of KLM Mine TrialAdvanced Undercut vs Post UndercutAdvanced Undercut vs Post Undercut
Stable after Cave Front
PassingPost Undercut
Anomaly
Cave Advance
45
Result of KLM Mine TrialResult of KLM Mine TrialAdvanced Undercut vs Post UndercutAdvanced Undercut vs Post Undercut
Anomaly
Cave AdvanceStable after Cave Front
Passing
46
AnomalyAnomaly
The anomaly from KLM Mine Trial could be explained as the result of remnant undercut pillar or stump.
Stump is created when the undercut blasting fails to break the rock completely.
Cave
Cave Advance
Last Blasting Row
Remnant Pillar
Abutment Stress
47
ExamplesExamples of of RemnantRemnant Pillars / StumpPillars / Stump
48
Case Study ACase Study A
The KLM Mine trial shows that the advanced undercut has the advantage to reduce the stress induced impact to undercut and extraction level.
Considering the KLM Mine trial result, XYZ BC Mine will implement the advanced undercutting method.
A note has been made that XYZ BC should establish undercut blasting control such that a remnant pillar will be avoided.
49
Stress Induced in the Stress Induced in the Extraction and Undercut LevelExtraction and Undercut Level
Several factors have the potential to influence the levels of stress induced in the extraction level excavation:
Distance between Undercut and ExtractionCave Hydraulic Radius
Undercut directionIn situ Stress regime
The timing of undercut relative to the extraction level developmentUndercut face shape
50
Case Study ACase Study A
The undercut face shape is controlled by the undercut opening sequence and the lead and lag among drill drift cave front
Irregularities of cave front could create unfavorable conditions in term of stress concentration in the production level
51
Undercutting SequenceUndercutting Sequence
52
Lead and LagLead and Lag
Lead and Lag: the distance between the caving front on adjacent panels
Cave Front
Lead and Lag
53
Undercutting SequenceUndercutting Sequence
Since trial with different undercut sequence is quite impossible, a numerical modeling will be used to evaluate the most preferable sequence for XYZ BC Mine.
54
Undercutting SequenceUndercutting Sequence
When comparing the results of the undercut sequence models, the main useful criteria to examine have proven to be:
1.Peak stress levels (in the stronger ground) induced on the production level elevation.
2. Average and maximum values of strain (as a measure of the severity of damage and deformation) induced on the production level elevation.
55
Undercutting SequenceUndercutting Sequence
3. Areas of damage on the production level elevation, measured in terms of areas where shear strains exceed a set limit of 2 x 10-3 (2 millistrains). This value was chosen because it includes damage in the stronger ground and not just the weaker ground areas, which are known to become extensively damaged, whatever undercut sequence is chosen.
56
Undercut Opening SequenceUndercut Opening Sequence
From modeling result, a wedge type sequenceappears preferable. Mining in weak ground should be over a short front, and bordered by panels that are mining in stronger ground, which bears load and limits rock mass deformation in the weak ground area.
57
Undercut Opening SequenceUndercut Opening Sequence
The undercut wedge apex should advance into the weaker ground, close to the boundary with stronger ground, with the apex angle broad rather than narrow.
58
Lead and LagLead and Lag
To evaluate the lead To evaluate the lead and lag, convergence and lag, convergence information from information from KLM mine is used.KLM mine is used.
Cave Front
Displacement (mm/day)
Convergence data is Convergence data is presented in velocity presented in velocity (mm/day) contour(mm/day) contour
Displc. = LtDisplc. = Lt--L0L0
Increasing of horizontal and vertical velocity due to lead and lag (60 meter)
No Advanced
horizontalvertical
070501 140501
0.0 mm/day
070501 140501
-1.3 mm/day
-0.2 mm/day
-1.12 mm/day
Decreasing of horizontal and vertical velocity after reducing lead and lag distance (54 meter)
horizontal vertical
140501 290501
-1.3 mm/day
140501 290501
-0.74 mm/day
-1.12 mm/day
-0.1 mm/day
Advance 6 m
Decreasing of horizontal and vertical velocity after reducing lead and lag distance (45 meter)
horizontal vertical
290501 120601
-0.74 mm/day
290501 120601
-0.5 mm/day
-0.1 mm/day
0.3 mm/day
Advance 9 m
Increasing of horizontal velocity due to noadvanced of lead and lag distance (45 meter)
horizontal vertical
120601 260601
-0.5 mm/day
120601 260601
-0.65 mm/day
0.3 mm/day
-0.2 mm/day
No Advance
Decreasing of horizontal and vertical velocity after reducing lead and lag distance
(30 meter)
horizontal vertical
260601 130701
-0.65 mm/day
260601 130701
-0.4 mm/day
-0.2 mm/day
0.0 mm/day
Advance 15 m
Increasing of horizontal velocity due to no advanced of lead and lag distance (30 meter)
horizontal vertical
130701 070801
-0.4 mm/day
130701 070801
-0.8 mm/day
0.0 mm/day
-0.1 mm/day
No Advance
Decreasing of horizontal and vertical velocity after reducing lead and lag distance (25 meter)
horizontal vertical
070801 230801
-0.8 mm/day
070801 230801
-0.1 mm/day
-0.1 mm/day
0.0 mm/day
Advance 5 m
Increasing of horizontal and vertical velocity due to no advanced of lead and lag distance (25 meter)
horizontal vertical
230801 150901
-0.1 mm/day
230801 150901
-0.75 mm/day
0.0 mm/day
-0.4 mm/day
No Advance
Decreasing of horizontal and vertical velocity after reduce lead and lag distance (8 meter)
horizontal vertical
150901 260901
-0.75 mm/day
150901 260901
-0.4 mm/day
-0.4 mm/day
0.1 mm/day
Advance 17 m
Decreasing of horizontal and vertical velocity in the same of lead and lag distance (8 meter)
horizontal vertical
260901 091001
-0.4 mm/day
260901 091001
-0.1 mm/day
0.1 mm/day
0.0 mm/day
No Advance
Decreasing of horizontal and vertical velocity below 8 meter of lead and lag distance (5 meter)
horizontal vertical
091001 261001
-0.1 mm/day
091001 261001
0.0 mm/day
0.0 mm/day
0.0 mm/day
Advance 3 m
Constant stable of horizontal and vertical velocity below 8 meter of lead and lag distance (5 meter)
horizontal vertical
261001 071101
0.0 mm/day
261001 071101
0.0 mm/day
0.0 mm/day
0.0 mm/day
No Advance
71
Lead & Lag IssueLead & Lag IssueReading
DateLead
and Lag Distance (m)
CaveAdvanced (m)
Horizontal Displacement
Velocity (mm/day)
Vertical Displacement
Velocity (mm/day)
07-May-01 Cave not started
0 0.0 0.2
14-May-01 60 0 1.3 (↑) 1.12 (↑)
29-May-01 54 6 0.74 (↓) 0.1 (↓)
12-Jun-01 45 9 0.5 (↓) -0.3 (↓)
26-Jun-01 45 0 0.65 (↑) 0.2 (↑)
13-Jul-01 30 15 0.4 (↓) 0.0 (↓)
07-Aug-01 30 0 0.8 (↑) 0.1 (↑)
23-Aug-01 25 5 0.1 (↓) 0.0 (↓)
15-Sept-01 25 0 0.75 (↑) 0.4 (↑)
26-Sept-01 8 17 0.4 (↓) -0.1 (↓)
09-Oct-01 8 0 0.1 (↓) 0.0 (↓)
29-Oct-01 5 3 0.0 (↓) 0.0≈
72
Lead & Lag IssueLead & Lag Issue
From the convergence measurement, From the convergence measurement, the ideal the ideal lead and lag is between 5 to 8 meterslead and lag is between 5 to 8 meters, cave , cave front can be stopped without any significant front can be stopped without any significant displacementdisplacement
If the lead and lag is over the 12 m, the cave If the lead and lag is over the 12 m, the cave face cannot be stopped for more than one week face cannot be stopped for more than one week because excessive damage will occur in the because excessive damage will occur in the panelspanels
73
Case Study ACase Study A
XYZ Mine
Plan ViewAccess Adits
Undercut Sequence and
DirectionExtraction Drift Orientation