Ken Rosewall Arena - New Roof Structure
Transcript of Ken Rosewall Arena - New Roof Structure
Tennis NSW
Ken Rosewall Arena - New Roof
Structure
Structural DA Report
Rev A | 1 March 2019
This report takes into account the particular
instructions and requirements of our client.
It is not intended for and should not be relied
upon by any third party and no responsibility
is undertaken to any third party.
Job number 266402
Arup Pty Ltd ABN 18 000 966 165
Arup
Level 5
151 Clarence Street
Sydney NSW 2000
Australia
www.arup.com
| Rev A | 1 March 2019 | Arup
J:\266000\266402-00 KRA TENNIS\WORK\INTERNAL\DESIGN\STRUCT\REPORT\DA\190301 KRA STRUCTURAL DA REPORT_ISSUE REV A.DOCX
Document Verification
Job title Ken Rosewall Arena - New Roof Structure Job number
266402
Document title Structural DA Report File reference
Document ref
Revision Date Filename
Draft 1 22 Feb
2019
Description First draft
Prepared by Checked by Approved by
Name
Andrew
Johnson/Hannah
Lazenby
Xavier Nuttall Andrew Johnson
Signature
Issue 25 Feb
2019
Filename 190225 KRA Structural DA Report_Issue.docx Description Development Application
Prepared by Checked by Approved by
Name
Andrew
Johnson/Hannah
Lazenby
Xavier Nuttall Andrew Johnson
Signature
Rev A 1 Mar
2019
Filename 190301 KRA Structural DA Report_Issue Rev A.docx Description Revised for Development Application
Prepared by Checked by Approved by
Name
Andrew
Johnson/Hannah
Lazenby
Xavier Nuttall Andrew Johnson
Signature
Filename
Description
Prepared by Checked by Approved by
Name
| Rev A | 1 March 2019 | Arup
J:\266000\266402-00 KRA TENNIS\WORK\INTERNAL\DESIGN\STRUCT\REPORT\DA\190301 KRA STRUCTURAL DA REPORT_ISSUE REV A.DOCX
Signature
Issue Document Verification with Document ✓
Tennis NSW Ken Rosewall Arena - New Roof Structure Structural DA Report
| Rev A | 1 March 2019 | Arup
J:\266000\266402-00 KRA TENNIS\WORK\INTERNAL\DESIGN\STRUCT\REPORT\DA\190301 KRA STRUCTURAL DA REPORT_ISSUE REV A.DOCX
Contents Page
1 Introduction 1
2 Design Life 2
2.1 Existing Structure 2
2.2 New Structure 2
3 Proposed Structural System 3
3.1 Existing Structure 3
3.2 New Roof Structure & Modifications to Existing Frame 5
3.3 Construction Sequence 7
3.4 Miscellaneous Works 8
4 Design Standards & Sources of Reference 9
4.1 BCA Structural Provisions 9
4.2 Design standards 9
4.3 Other references 10
4.4 Structural Software 10
5 Loading 11
5.1 General 11
5.2 Dead Loads 11
5.3 Superimposed dead and live loads 11
5.4 Roof Loads 12
5.5 Wind Loads 13
5.6 Seismic 14
5.7 Notional loads 14
5.8 Accidental horizontal loads on handrails, barriers, and parapets 14
5.9 Imposed Movements 15
5.10 Blast loads 15
5.11 Geotechnical data 16
6 Performance Criteria 18
6.2 Serviceability 18
6.3 Dynamics 18
6.4 Reinforced and post-tensioned concrete durability 19
6.5 Structural steel corrosion protection 19
6.6 Fire Resistance levels 19
1.1 Protection of Basements from Groundwater 20
7 Materials 21
Tennis NSW Ken Rosewall Arena - New Roof Structure Structural DA Report
| Rev A | 1 March 2019 | Arup
J:\266000\266402-00 KRA TENNIS\WORK\INTERNAL\DESIGN\STRUCT\REPORT\DA\190301 KRA STRUCTURAL DA REPORT_ISSUE REV A.DOCX
7.1 Concrete 21
7.2 Reinforcement & Post-tensioning 21
7.3 Structural steel 21
7.4 Wire Rope (Structural Cables) 22
7.5 Sustainable Design 22
Tables
Table 1: BCA Annual probabilities of exceedance
Table 2: Relevant codes and standards
Table 3: Reference documents
Table 4: Structural software schedule
Table 5: Design loading schedule
Table 6: Superimposed dead loads
Table 7: Roof live and rigging loads
Table 8: Wind loading parameters
Table 9: Seismic design parameters
Table 10: Handrail and barrier design loads
Table 11: Imposed movement schedule
Table 12: Geotechnical site investigation reports
Table 13: Serviceability criteria
Table 14: Pfeifer wire rope capacities for selected diameters
Figures
Figure 1: Proposed geometry of new roof - section
Figure 2: Existing superstructure typical section
Figure 3: Existing substructure typical section
Figure 4: Original construction sequence
Figure 5: Proposed roof structure
Figure 6: Proposed roof structure – section
Figure 7: Axial force plot under dead load and cable prestress after erection and stressing
Tennis NSW Ken Rosewall Arena - New Roof Structure Structural DA Report
| Rev A | 1 March 2019 | Arup
J:\266000\266402-00 KRA TENNIS\WORK\INTERNAL\DESIGN\STRUCT\REPORT\DA\190301 KRA STRUCTURAL DA REPORT_ISSUE REV A.DOCX
Page 1
1 Introduction
This report summarises the proposed structural form and design criteria for a new
lightweight roof enclosure to Ken Rosewall Arena at the Sydney Olympic Tennis
Centre. The existing perimeter roof canopy will be removed entirely.
The new roof will be a PTFE coated woven glass-fibre fabric clad steel tensile
structure supported from the existing structural framing and foundations, utilising
the circular form of the existing bowl to provide an extremely structurally
efficient and transparent roof structure, maximising the uniformity of natural light
within the arena.
The roof is intended to be a shade and rain cover only, and the stadium operate as
an “outdoor” venue primarily naturally ventilated, and with minimal insulation
and acoustic properties. The roof will not be acoustically or thermally insulated.
With reference to Figure 1 below, the intent is to provide a minimum clearance of
17m to court level and a 4m eaves zone for external views and ventilation. A
central raised roof area will also be provided for ventilation and smoke extract
purposes.
Figure 1: Proposed geometry of new roof - section
The existing structure was designed by Arup between 1997 & 1999 and
completed for the 2000 Olympics.
4m
Tennis NSW Ken Rosewall Arena - New Roof Structure Structural DA Report
| Rev A | 1 March 2019 | Arup
J:\266000\266402-00 KRA TENNIS\WORK\INTERNAL\DESIGN\STRUCT\REPORT\DA\190301 KRA STRUCTURAL DA REPORT_ISSUE REV A.DOCX
Page 2
2 Design Life
2.1 Existing Structure
The existing structure was designed for a nominal 50-year design life. It will be
20 years old at the completion of the works.
It is not the intent of this project and the scope of works within to increase the
original design life from the completion of the new works. Elements such as the
existing piles, in-ground concrete works, concrete frame, tiered seating plats, and
structural steel elements will not be investigated, inspected, and tested in order to
certify an increase to the original design life under this scope of works. They will
remain as originally designed with approximately 30 years of their original design
life remaining.
Minimal maintenance to the structure of the building has been undertaken during
its life to date. The following works are intended to be undertaken as part of the
works to ascertain that the existing structure is in adequate condition to continue
in its current function and to support the new roof enclosure:
Reinforced and Prestressed Concrete:
• Inspection and testing of the exposed areas of insitu and precast concrete;
• Specification of any necessary maintenance or repair works to maintain
ongoing serviceability of the superstructure; &
• Specification of ongoing inspection and maintenance programme.
This will be undertaken by a specialist sub-contractor experienced in these works
as briefed by Arup.
Structural Steel including connections:
• Assessment of existing protective coatings (predominantly galvanising)
performance and remaining life;
• Assessment of any locations of loss of structural steel thickness due to
breakdown of existing corrosion protection system;
• Specification of repair works prior to any architectural finishes or coatings.
This will be undertaken by a specialist sub-contractor experienced in these works
as briefed by Arup.
2.2 New Structure
All new structure will be designed for a nominal 50-year design life.
Structural steel will require maintenance and/or re-coating of the corrosion
protection system during the life of the structure.
Tennis NSW Ken Rosewall Arena - New Roof Structure Structural DA Report
| Rev A | 1 March 2019 | Arup
J:\266000\266402-00 KRA TENNIS\WORK\INTERNAL\DESIGN\STRUCT\REPORT\DA\190301 KRA STRUCTURAL DA REPORT_ISSUE REV A.DOCX
Page 3
3 Proposed Structural System
3.1 Existing Structure
With reference to Figure 2 and Figure 3 the existing structure is a circular bowl
approximately 100m in diameter at the top of the bowl, with 24 repetitive primary
grids consisting of the following components:
• Insitu concrete bored piles founded within shale bedrock supporting the main
concourse and upper bowl;
• Reinforced concrete pad footings supporting the lower bowl;
• Reinforced concrete ground bearing slab for the east and west terraces;
• Reinforced concrete columns and beams with precast plats for the lower bowl;
• Steel raking beams supported by steel columns with precast plats for the upper
bowl. It is noted that this is a three-dimensional structure. The
circumferential ties at the top of the raker and the top of the roof contribute to
the support the bowl structure. The raker was pre-deflected up during the
original construction and released in two stages after the plats and roof were
constructed; &
• Steel framed roof with metal sheeting erected in prefabricated panels.
The court is asphaltic concrete on granular sub-base layers over natural subgrade.
Tennis NSW Ken Rosewall Arena - New Roof Structure Structural DA Report
| Rev A | 1 March 2019 | Arup
J:\266000\266402-00 KRA TENNIS\WORK\INTERNAL\DESIGN\STRUCT\REPORT\DA\190301 KRA STRUCTURAL DA REPORT_ISSUE REV A.DOCX
Page 4
Figure 2: Existing superstructure typical section
Figure 3: Existing substructure typical section
Tennis NSW Ken Rosewall Arena - New Roof Structure Structural DA Report
| Rev A | 1 March 2019 | Arup
J:\266000\266402-00 KRA TENNIS\WORK\INTERNAL\DESIGN\STRUCT\REPORT\DA\190301 KRA STRUCTURAL DA REPORT_ISSUE REV A.DOCX
Page 5
Figure 4: Original construction sequence
3.2 New Roof Structure & Modifications to Existing
Frame
The new roof structure is a tension structure, with the tension forces from the
primary radial cables resolved through circular compression rings supported on
the existing columns. These rings resolve the tension in the cables internally
within the structure (similar to a bicycle wheel) such that primarily the gravity and
external loads are transmitted to the existing structure and foundations.
With reference to Figure 5 and Figure 1, the new structure comprises the
following elements:
• New internal columns from top of raker to upper compression ring – attached
to raker at the location of the existing roof column. This column is replaced
due to the need to extend it approximately 1.5m to achieve the required
clearance over to court level;
• Extension of existing raker cranked to the location of the lower compression
ring. This element also manages a component of the tolerance between the
existing as-constructed position and the new roof set-out position;
• New D450 CHS lower compression ring resolving the hogging radial cables –
supported above raker level;
• New D500 CHS upper compression ring resolving the sagging radial cables –
supported at the top of the new columns;
• Struts and bracing elements between the rings;
• Inner tension rings approximately D250 and D300 CHS, with strutting and
bracing between;
• Radial cables (locked-coil wire rope) between the outer compression and
internal tension rings. These cables are up to 50mm in diameter and the
hogging cables split to pass the through column location;
• Circumferential CHS “hoops” for fabric curvature with circumferential ties
resolving hoop axial forces;
• Central secondary roof structure spanning the 20m diameter upper tension
ring. This structure is a series or radial cable trusses supported from the upper
tension ring with a central king-post to upper CHS rafters.
Tennis NSW Ken Rosewall Arena - New Roof Structure Structural DA Report
| Rev A | 1 March 2019 | Arup
J:\266000\266402-00 KRA TENNIS\WORK\INTERNAL\DESIGN\STRUCT\REPORT\DA\190301 KRA STRUCTURAL DA REPORT_ISSUE REV A.DOCX
Page 6
Figure 5: Proposed roof structure
Figure 6: Proposed roof structure – section
Tennis NSW Ken Rosewall Arena - New Roof Structure Structural DA Report
| Rev A | 1 March 2019 | Arup
J:\266000\266402-00 KRA TENNIS\WORK\INTERNAL\DESIGN\STRUCT\REPORT\DA\190301 KRA STRUCTURAL DA REPORT_ISSUE REV A.DOCX
Page 7
Figure 7: Axial force plot under dead load and cable prestress after erection and stressing
The roof prestress forces and contraction of the compression rings in the final
position provide an equivalent supporting condition to the existing rakers as the
original design and existing constructed condition.
3.3 Construction Sequence
The following overall construction sequence is envisaged. This may be modified
with the specialist roof sub-contractor as the construction details are developed.
• Establish propping frames at the rear of each raker;
• Jack each raker to de-stress existing roof and bowl ties;
• Remove existing roof and internal supporting column back to level of raker;
• Reduce jacking load to raker to documented force;
• Undertake modifications to existing structure:
• Modify connection at base of existing roof column to accept new column
as required;
• Add extension to rear of existing raker to manage tolerance between
existing and new structure and accept new lower compression ring;
• Strengthen existing column/connections below raker.
• Erect new lower and upper compression rings, inner column, and bracing;
• Erect inner lower and upper tension rings and pop-up roof framing;
• Lay out radial cables, struts, and circumferential cables. Stress roof to defined
position, set prestress to documented level, and attach to permanent
connections;
• Install hoops and tension radial cables (if not done during step above);
• Tension inner (pop-up) roof bowstring elements;
Tennis NSW Ken Rosewall Arena - New Roof Structure Structural DA Report
| Rev A | 1 March 2019 | Arup
J:\266000\266402-00 KRA TENNIS\WORK\INTERNAL\DESIGN\STRUCT\REPORT\DA\190301 KRA STRUCTURAL DA REPORT_ISSUE REV A.DOCX
Page 8
• Check and confirm prestress in all cable elements;
• Install fabric and tension;
• Check and confirm prestress in all cable elements;
• Remove jacks and jacking frames;
• Complete remedial works to steelwork corrosion protection systems.
3.4 Miscellaneous Works
The following miscellaneous works are intended to be undertaken:
• Repair of existing concrete elements that have suffered spalling or loss of
cover;
• Repair of corrosion protection systems to existing steel elements and
rectification of any loss of steel area that has impacted structural capacity;
• Removal of up to two precast seating plats to increase the height of the court
access opening from the loading dock – both for construction and permanent
function. Trimming works to support adjacent structure will be required.
Tennis NSW Ken Rosewall Arena - New Roof Structure Structural DA Report
| Rev A | 1 March 2019 | Arup
J:\266000\266402-00 KRA TENNIS\WORK\INTERNAL\DESIGN\STRUCT\REPORT\DA\190301 KRA STRUCTURAL DA REPORT_ISSUE REV A.DOCX
Page 9
4 Design Standards & Sources of Reference
The design and documentation of the building and associated works shall comply
with the Design Brief Documents and Australian Standards.
Standard Specifications or Codes of the British Standards Institute (BS), German
Standards (DIN), or the American Society for Testing and Materials (ASTM) are
referenced only when a relevant Standards Australia publication does not exist.
4.1 BCA Structural Provisions
Importance Level:
• 3 - Structures designed to contain a large number of people
Table 1: BCA Annual probabilities of exceedance
Design Events for Safety Annual Probability of Exceedence
Wind 1:1000
Earthquake 1:500
4.2 Design standards
Current editions of the following codes and standards will form the basis of the
design:
Table 2: Relevant codes and standards
Code Title
AS/NZS 1170.0 Structural design actions – General Principles
AS/NZS 1170.1 Structural design actions – Permanent, imposed, and other
actions
AS/NZS 1170.2 Structural design actions - Wind actions
AS 1170.4 Structural design actions – Earthquake actions in Australia
AS 1720 Timber Structures Code
AS 2121 Cold Formed Steel Structures Code
AS2159 Piling Code
AS/NZS 2312 Guide to the protection of structural steel against atmospheric
corrosion
AS 2327 Composite structures
AS 3600 Concrete Structures Code
AS 3700 Masonry Code
AS 3735 Concrete Structures for Retaining Liquids
AS 4100 Steel Structures Code
AS 5131 Structural Steelwork – Fabrication and Erection
Tennis NSW Ken Rosewall Arena - New Roof Structure Structural DA Report
| Rev A | 1 March 2019 | Arup
J:\266000\266402-00 KRA TENNIS\WORK\INTERNAL\DESIGN\STRUCT\REPORT\DA\190301 KRA STRUCTURAL DA REPORT_ISSUE REV A.DOCX
Page 10
BS 5950-8 Structural use of steelwork in building – Code of practice for fire
resistant design
BS 8102 Code of practice for protection of structures against water from
the ground
BCA Building Code of Australia
4.3 Other references
Additional design guides specific to best practice will be referenced where
appropriate. These include:
Table 3: Reference documents
Number Title Author
Green Guide Guide to Safety at Sports
Grounds
UK Department for Culture,
Media and Sport
Dynamic performance
requirements for permanent
grandstands subject to crowd
action
IStructE, Nov 2001
CCIP-016 Guide on the Vibrations of
Floors
The Cement & Concrete
Association
4.4 Structural Software
The following programs will be used in the design and analysis of the structure:
Table 4: Structural software schedule
Program Function
Oasys GSA General structural analysis
STRAND7 Finite element analysis program
Oasys Compos Compos (composite beam design)
RAPT Reinforced and prestressed concrete design
Limsteel Structural steel design
Limcon Steel connection design
Tennis NSW Ken Rosewall Arena - New Roof Structure Structural DA Report
| Rev A | 1 March 2019 | Arup
J:\266000\266402-00 KRA TENNIS\WORK\INTERNAL\DESIGN\STRUCT\REPORT\DA\190301 KRA STRUCTURAL DA REPORT_ISSUE REV A.DOCX
Page 11
5 Loading
5.1 General
All design loads shall be selected and applied in accordance with the relevant
Australian Standard, specifically AS/NZS1170.1 to 1170.4, and the BCA.
5.2 Dead Loads
Dead loads should be calculated on the basis of the following densities:
• Reinforced concrete: 25 kN/m³
• Steel: 78.5 kN/m³
• Masonry: As calculated
• Timber: As calculated
5.3 Superimposed dead and live loads
The following Live loads have been adopted for typical areas in accordance with
AS 1170.2 for new works. Reference is made to the existing structural drawings
for design loads of existing structural elements.
Table 5: Design loading schedule
Area Super imposed dead load Live Load
Uniformly
distributed
Concentrated
Tiered seating 5kPa 4.5kN
Circulation/ concourse
Services 0.5kPa Non-structural topping/finishes 2kPa
5kPa 4.5kN
Internal concourse
Ceiling and services 1.0kPa Finishes 0.5kPa
5kPa 4.5kN
External concourse areas
Services 0.5kPa Non-structural topping 2kPa Landscaping and planting As calculated
5kPa 4.5kN
Toilets Ceiling and services
0.25kPa Tile and Grout topping laid to falls (Max 100mm) 2kPa Partitions 2kPa
2kPa 2.7kN
Plant Ceiling and services 1.0kPa 100mm plinths and finishes 2kPa
5.0kPa or (As calculated based on actual equipment)
9kN
Cool storage (eg. keg rooms)
4.5kPa per metre of height. 15kPa minimum
9kN
Substation 10kPa 7.5kPa 13kN
Non-trafficable roofs
As calculated to include cladding, purlins, louvres, acoustic insulation, soffit/ceiling cladding, and hanging services. Refer
drawings and Section 5.4..
0.25kPa 1.4kN
Tennis NSW Ken Rosewall Arena - New Roof Structure Structural DA Report
| Rev A | 1 March 2019 | Arup
J:\266000\266402-00 KRA TENNIS\WORK\INTERNAL\DESIGN\STRUCT\REPORT\DA\190301 KRA STRUCTURAL DA REPORT_ISSUE REV A.DOCX
Page 12
Loading dock Services 0.5kPa
20kPa 66kN
5.4 Roof Loads
5.4.1 Self –weight
Dead load arising from self-weight of the structure will be applied to the analysis
as a gravity load.
Connection details in the cable structure are expected to be clamp connections on
primary cables and fork/fin connections to cable terminations at the cpmpression
and tension rings.
5.4.2 Superimposed dead loads
The following superimposed dead loads are applicable.
Table 6: Superimposed dead loads
Item Description Design superimposed dead load
Fabric cladding Upper surface of roof is clad in PTFE fabric
single layer fabric (no insulation)
Sub-framing support back to primary grid
5kg/ m2
5kg/ m2
Access gantries
(if required)
Self-weight of gantry plus fixings 120kg/m
Sports Lighting Up to 150 lights around the court 50kg per light
Plus 20kg/m for cabling
AV?Speakers Up to equivalent of 8 speakers 500kg
(including speaker and fixings)
500kg (including speaker and
fixings)
Miscellaneous
services
Other possible roof services and rigging
loads not listed above. Including bowl
lighting from roof as well as winch pints to
maintain.
5 kg/m2 over ceiling area
5.4.3 Roof Event loading
The table below provides a summary of different independent maximum loading
scenarios for rigging considered in the design of the roof. These loads are in
addition to the superimposed dead loads above.
These scenarios are not cumulative and cannot be superimposed in full.
Appropriate evaluation of these allowances and combinations thereof to suit
events will need to be developed in future design phases into a reference events
rigging plan that can be consulted.
For high performance events individual assessment and consultation with the
structural engineer will be necessary.
Tennis NSW Ken Rosewall Arena - New Roof Structure Structural DA Report
| Rev A | 1 March 2019 | Arup
J:\266000\266402-00 KRA TENNIS\WORK\INTERNAL\DESIGN\STRUCT\REPORT\DA\190301 KRA STRUCTURAL DA REPORT_ISSUE REV A.DOCX
Page 13
Table 7: Roof live and rigging loads
Loading scenario Load location Load
Uniform load Across the cable net roof 25kg/m2
Dedicated point loads Hanging point load at cable
net node locations
1500kg point load on a nominal
10mx10m grid applied to primary
cable net nodes
Central monitor
scoreboard
Upper tension ring at any 4
of the dedicated hanging
points
4000kg
Tension ring line load Upper or lower tension ring 200kg/m any direction
Centre roof king post Bottom central node 500kg
5.5 Wind Loads
A wind tunnel test will be carried out to determine roof wind loads and will be
undertaken in accordance with AS/NZS1170.2 and the AWES guidelines. This
will be undertaken as simultaneous pressure testing with influence surfaces and
areas developed with the wind engineer based on the conceptual roof design and
performance.
The following design parameters have been assessed in accordance with AS/NZS
1170.2:
Table 8: Wind loading parameters
Parameter Value
Region A2
Basic wind speeds:
Ultimate, V1000
Serviceability, V20
46 m/s
37 m/s
Terrain category, TC As calculated by direction
Structure height, Z Varies by direction
Variation of wind speed with height, M(z,cat) As calculated
Structural importance multiplier, Mi 1.0
Topographic multiplier, Mt As calculated
Shielding multiplier, Ms As calculated
Minimum internal pressure coefficient, Cp,i +0.2/-0.3 generally
Area reduction factor, Ka # As calculated, 0.8 minimum
Combined action reduction factor, Kc # As calculated, 0.8 minimum
Local pressure coefficients As calculated
Note: # denotes minimum Ka x Kc = 0.8.
Tennis NSW Ken Rosewall Arena - New Roof Structure Structural DA Report
| Rev A | 1 March 2019 | Arup
J:\266000\266402-00 KRA TENNIS\WORK\INTERNAL\DESIGN\STRUCT\REPORT\DA\190301 KRA STRUCTURAL DA REPORT_ISSUE REV A.DOCX
Page 14
5.6 Seismic
Earthquake loading applied to the structural elements and detailing of the seismic
stability system will be in accordance with AS 1170.4 – 2007: Earthquake actions
in Australia for building structures:
Specific AS 1170.4 seismic data is summarised as:
Table 9: Seismic design parameters
Parameter Value
Importance level 3
Hazard factor, Z 0.08
Site sub-soil class Be-(Rock)
Importance level, I 2
Annual probability of exceedance 1/500
Probability factor, kp 1.0
Design earthquake category II
Structural system Table 6.5(A) AS 1170.4
Non-ductile building frame.
u/Sp = 2.6
5.7 Notional loads
Notional lateral loading of 1% of gravity loading will be provided simultaneously
at all floors as a minimum stability requirement in accordance with
AS/NZS1170.0. Tying requirements for individual elements will be in
accordance with AS/1170.0.
5.8 Accidental horizontal loads on handrails,
barriers, and parapets
It is not intended to alter the arrangement or loading capacity of handrails and
barriers within the existing stadium unless otherwise advised by the certifier.
Any new or replacement handrails shall be designed to the loads specified by the
certifier to maintain BCA compliance. Until such time as that information is
available, or should no further guidance be provided, the loading adopted will be
in accordance with the “Guide to safety at Sports Grounds (The Green Guide)” for
stadium seating and associated areas and “AS1170-1: Structural Design Actions –
Permanent, Imposed and Other Actions” for all other areas not covered by the
Green Guide.
Tennis NSW Ken Rosewall Arena - New Roof Structure Structural DA Report
| Rev A | 1 March 2019 | Arup
J:\266000\266402-00 KRA TENNIS\WORK\INTERNAL\DESIGN\STRUCT\REPORT\DA\190301 KRA STRUCTURAL DA REPORT_ISSUE REV A.DOCX
Page 15
Table 10: Handrail and barrier design loads
Type of Barrier Horizontal Imposed
Load
Height of applied
load
Barrier for gangways of seating decks,
stairways, landings and ramps aligned at right
angles to direction of spectator movement
3kN/m 1.1m
Barrier for gangways of seating decks,
stairways, landings and ramps parallel to
direction of spectator movement
2kN/m 1.1m
Barrier for gangways of seating decks,
adjacent to end row of seats and protecting
spectators falling sideways
1kN/m 1.1m
Barriers on front row of seats (positioned
within 530mm in front of seats)
1.5kN/m 0.8m
Barriers for gangways in standing areas,
aligned at right angles to direction of spectator
movement
5kN/m 1.1m
Also refer to Diagram 11.1 of the Green Guide.
5.9 Imposed Movements
The effect of imposed movements on the structure will be considered in the
calculations. These include the following types of movement:
Table 11: Imposed movement schedule
Parameter Value
Settlement 1% of footing width at allowable bearing
pressure
Temperature (exterior elements) Maximum range +5°C to +65°C depending
on solar exposure and thermal mass.
Mean temp 20°C. Following variations from
mean:
- Clad steelwork ± 20°C
- Unclad steelwork -20°C to +65°C
- Shaded concrete ± 10°C
Shrinkage As calculated for vertical structure or floor
slabs
Creep As calculated for vertical structure and post-
tensioned floor slabs
Elastic shortening As calculated for vertical structure and post-
tensioned floor slabs
5.10 Blast loads
The building will not be designed for blast forces of any kind.
Tennis NSW Ken Rosewall Arena - New Roof Structure Structural DA Report
| Rev A | 1 March 2019 | Arup
J:\266000\266402-00 KRA TENNIS\WORK\INTERNAL\DESIGN\STRUCT\REPORT\DA\190301 KRA STRUCTURAL DA REPORT_ISSUE REV A.DOCX
Page 16
5.11 Geotechnical data
A site specific geotechnical investigation is not required. The new roof will be
founded on the existing piles, and sufficient information exists from the original
investigations and subsequent investigations on adjacent sites.
5.11.1 Reference Geotechnical reports
The following Geotechnical information has been used:
Table 12: Geotechnical site investigation reports
Author Report
Arup Geotechnics Sydney Olympic Tennis Centre, Homebush Bay, Geotechnical
Site Investigation Report, Ref. 10381/500, February 1998.
5.11.2 Seismic Site Classification
Seismic ground assessment to AS 1170.4 is site class Be.
5.11.3 Groundwater
Groundwater was encountered at an RL102.9 AHD during the original
investigation. This will not impact the new works.
5.11.4 Pile design
Assumed design parameters:
Material description Design Parameters
End Bearing (kPa) Shaft Adhesion (kPa)
Shale Class IV
Working loads
(allowable)
1000kPa 100kPa
ULS
Shale Class III
Working loads
(allowable)
3500kPa 350kPa
ULS
• The geotechnical strength reduction factor at ULS shall be in accordance with
AS2159.
5.11.5 High-level Foundations
The site is classified Class H to AS2870.
Tennis NSW Ken Rosewall Arena - New Roof Structure Structural DA Report
| Rev A | 1 March 2019 | Arup
J:\266000\266402-00 KRA TENNIS\WORK\INTERNAL\DESIGN\STRUCT\REPORT\DA\190301 KRA STRUCTURAL DA REPORT_ISSUE REV A.DOCX
Page 17
Lightly loaded foundations within the residual clay may be designed based on
100kPa allowable bearing pressure, with due consideration of the highly reactive
classification for the site.
Tennis NSW Ken Rosewall Arena - New Roof Structure Structural DA Report
| Rev A | 1 March 2019 | Arup
J:\266000\266402-00 KRA TENNIS\WORK\INTERNAL\DESIGN\STRUCT\REPORT\DA\190301 KRA STRUCTURAL DA REPORT_ISSUE REV A.DOCX
Page 18
6 Performance Criteria
6.1.1 Design Life
Refer to Section 2.
Reference should be made to the relevant material standard regarding
maintenance construction and maintenance assumptions that form the basis of the
design code.
Paint systems used to protect structural elements from corrosion will require
maintenance, typically every 15-25 years.
6.2 Serviceability
The following deflection limits are proposed for the building structure:
Table 13: Serviceability criteria
Element Deflection (total load UNO)
Beams and Slabs: Spans Cantilevers
Generally
Live load only
Supporting articulated masonry
Supporting unjointed masonry
Supporting curtain wall and glazed assemblies
Transfer structures (cumulative at location of
element transferred)
L/250
L/360
L/500 (incremental)
L/1000 (incremental)
L/800 or 15mm max
L/1000 or 12mm max
L/125
L/180
L/250 (incremental)
L/500 (incremental)
L/400 or ±15mm max
L/500 or 12mm max
Roof under wind load L/200 L/100
Wind columns L/240 L/120
Overall wind sway SLS H/500
Storey drift under wind SLS
- Structures supporting glazed walls
in-plane
- Structures supporting glazed walls
out-of-plane
- Free roofs
h/500
h/240
h/120
Storey drift under seismic ULS 1.5%h
Differential settlement L/1000 L/500
6.3 Dynamics
The existing bowl structure is not currently being re-assessed for dynamics under
the scope of this project. Arup recommend that a detailed assessment be
undertaken if the venue is proposed for pop or rock concert use in the future.
Tennis NSW Ken Rosewall Arena - New Roof Structure Structural DA Report
| Rev A | 1 March 2019 | Arup
J:\266000\266402-00 KRA TENNIS\WORK\INTERNAL\DESIGN\STRUCT\REPORT\DA\190301 KRA STRUCTURAL DA REPORT_ISSUE REV A.DOCX
Page 19
6.4 Reinforced and post-tensioned concrete
durability
Appropriate concrete grades and reinforcement cover will be specified in
accordance with AS3600 according to the structural element, climatic
environment and ground conditions of the location of the site.
The degree of crack control to be provided in concrete elements (refer AS3600
Clause 9.4.3) generally will be as follows:
• Moderate where contained within enclosed non wash-down areas of the
building (exposure Classification A1)
• Strong degree of crack control for external or internal wash down slabs.
building (exposure Classification B1)
Special attention will be given to location of crack control joints in long runs of
wall and upstands, at points of stress concentration, and in external elements.
6.5 Structural steel corrosion protection
The corrosion protection for the structural steelwork will be dependent on the
location of the steel elements within the building. Systems will be selected in
accordance with AS/NZS 2312 as a minimum specification.
Internal steelwork which is in marginally damp areas where occasional
condensation may occur, such as around the building perimeter and in the vehicle
and plant room areas, will require a higher level of protection than inside the air-
conditioned office space which is permanently dry. For both these internal
environments it is assumed that there is no access for maintenance, and either a
hot dip galvanised (HDG) or multi-build paint system will be specified.
A high standard corrosion protection system is required for all exposed steelwork,
and will require maintenance during the life of the building. A design life of 25
years and warranty period of 10-15 years from the coating supplier and applicator
may be expected.
Care must be taken during handling, transport, and erection to minimise damage
to the coating system that will require making good on site and compromise long-
term performance. This may include wrapping of elements.
The paint system for corrosion protection must be compatible with any required
Fire Protection.
6.6 Fire Resistance levels
Fire resistance levels for structural elements shall be determined in accordance
with the Building Code of Australia and any subsequent approved relaxations
based on approved fire engineered approaches.
Concrete covers are to be in accordance with AS 3600.
Tennis NSW Ken Rosewall Arena - New Roof Structure Structural DA Report
| Rev A | 1 March 2019 | Arup
J:\266000\266402-00 KRA TENNIS\WORK\INTERNAL\DESIGN\STRUCT\REPORT\DA\190301 KRA STRUCTURAL DA REPORT_ISSUE REV A.DOCX
Page 20
Structural steel elements shall be provided with passive protection or designed
based on limiting temperatures. Passive protection may include:
• Synthetic vermiculite spray;
• Fire board; or
• Epoxy intumescent.
A fire engineered approach was utilised for the existing building and will be
required reduce the extent of passive protection from the deemed-to-satisfy
requirements.
6.7 Protection of Basements from Groundwater
The design of the basement walls and floors are to be such as to provide
acceptable environmental conditions for the Client.
There are no relevant Australian standards. BS 8102:2009 will be used as a
design guide, which describes four grades of environment to be achieved, and
three appropriate types of construction.
Tennis NSW Ken Rosewall Arena - New Roof Structure Structural DA Report
| Rev A | 1 March 2019 | Arup
J:\266000\266402-00 KRA TENNIS\WORK\INTERNAL\DESIGN\STRUCT\REPORT\DA\190301 KRA STRUCTURAL DA REPORT_ISSUE REV A.DOCX
Page 21
7 Materials
The following structural materials are used in the works. Typical design
properties of these materials are listed. These values are to be adjusted and
enhanced as appropriate during the detailed design of the structure.
7.1 Concrete
The requirements of AS 3600 will be applied to all reinforced and post-tensioned
concrete. Typical concrete properties are as follows:
Parameter Value
Grades, f’c 32 to 80 MPa
Short-term E As calculated
Coefficient of thermal expansion 10x10-6 per °C
Basic shrinkage strain As calculated and specified
Basic creep factor As calculated
Poisson’s ratio 0.2
Density
Mass concrete
Reinforced concrete
24 kN/m3
25 kN/m3
7.2 Reinforcement & Post-tensioning
Reinforcement shall comply with AS/NZS 4671 and AS/NZS 4672 respectively.
Parameter Value/Designation
Plain ‘R” bars R250N
Deformed ‘N’ bars D500N
Welded wire fabric D500L & D500N
Young’s modulus 205 x 103 MPa
Post-tensioning strand
(superstrand)
12.7mm fpb = 1870 MPa
15.2mm fpb = 1790 MPa (min)
7.3 Structural steel
Parameter Value
Steelwork density 7850 kg/m3
Yield stress fsy = 250 to 450 MPa
Young’s modulus 205 x 103 MPa
Poisson’s ratio 0.3
Coefficient of thermal expansion 11 x 10 -6 per °C
Tennis NSW Ken Rosewall Arena - New Roof Structure Structural DA Report
| Rev A | 1 March 2019 | Arup
J:\266000\266402-00 KRA TENNIS\WORK\INTERNAL\DESIGN\STRUCT\REPORT\DA\190301 KRA STRUCTURAL DA REPORT_ISSUE REV A.DOCX
Page 22
7.4 Wire Rope (Structural Cables)
Wire rope assemblies used in the roof structure shall be equivalent to Locked Coil
or Spiral Strand Cable by Pfeifer – Galfan Coated. All end sockets shall be by the
same manufacturer of the wire ropes, tested and certified to be greater than the
wire rope capacity.
• Modulus of Elasticity: 160 +/- 10 kN/mm2
• Cables sized on: Nuls ≤ 0.6* Breaking load
N(Dead+ prestress) ≤ 0.4*Breaking Load
Table 14: Pfeifer wire rope capacities for selected diameters
Pfeifer ref Diameter Characteristic Breaking Load
PV40 21 dia 405 kN
PV60 26 dia 621 kN
PV150 40 dia 1520 kN
PV240 50 dia 2380 kN
7.5 Sustainable Design
The following aspects of materials selection will be considered where appropriate:
• Concrete mix requirements – specifically Portland cement and natural aggregate replacement with industrial waste products;
• Steel reinforcement – recycled content and prefabrication; &
• Structural steel – recycled content and design for disassembly.