Kodiak Electric Association, Inc. Darron Scott, President/CEO

description

KEA’s Renewable Vision. Kodiak Electric Association, Inc. Darron Scott, President/CEO. KEA’s Vision. Kodiak Electric Association, Inc. Locally-Owned Electric Cooperative Provides Electricity to approximately 5,800 Meters Isolated Electric Grid Peak Load – 26 MW Minimum Load – 11 MW - PowerPoint PPT Presentation

Transcript of KEA’s Renewable Vision

Page 1: KEA’s Renewable Vision

Kodiak Electric Association, Inc.Darron Scott, President/CEO

Page 2: KEA’s Renewable Vision
Page 3: KEA’s Renewable Vision

Kodiak Electric Association, Inc.Locally-Owned Electric CooperativeProvides Electricity to approximately 5,800

MetersIsolated Electric Grid

Peak Load – 26 MWMinimum Load – 11 MW

Diverse Power Generation PortfolioTerror Lake Hydroelectric Plant: Two 11.5 MW UnitsPillar Mountain Wind Project: Three 1.5 MW UnitsFour Diesel Generating Stations

Generator size ranges from 140 kW to 6.5 MW Total diesel generating capacity of 33 MW

Page 4: KEA’s Renewable Vision

KEA’s System Prior to 2009

20% Diesel

80% Hydro

Page 5: KEA’s Renewable Vision

•Three 1.5 MW General Electric (GE) Wind Turbines

•Operating since July 2009

Photo courtesy of Dake Schmidt

Pillar Mountain Wind Project

Page 6: KEA’s Renewable Vision

Pillar Mountain and Terror Lake Hydroelectric Facility

• Terror Lake Works like a battery• Lowers fuel costs• Stabilizes power costs• Lowers Emissions

Page 7: KEA’s Renewable Vision

Load Variability

Page 8: KEA’s Renewable Vision

•Approximately 98% availability

•28,472,822 kWh generated since July 2009

•2,005,128 gallons of diesel saved

•22,559 tons of CO2 saved

Page 9: KEA’s Renewable Vision

Net Savings to CommunityAt $3.30 per gallon for diesel,

approximately $4.5 million net savings.

Page 10: KEA’s Renewable Vision

KEA’s Current Power Sources• 80% Hydro• 11% Diesel • 9% Wind

Page 11: KEA’s Renewable Vision

Generation Comparison

20% Diesel

80% Hydro

80% Hydro

9% Wind

11% Diesel

Old System

New System

Page 12: KEA’s Renewable Vision

Road Work and Building the Foundation

Page 13: KEA’s Renewable Vision

Underground and Overhead Power Lines

Page 14: KEA’s Renewable Vision

Transportation

Page 15: KEA’s Renewable Vision

Assembly

Page 16: KEA’s Renewable Vision

First Completed Wind Turbine

Page 17: KEA’s Renewable Vision

Next Steps to Vision• Terror Lake Third Hydroelectric Turbine• Additional Three Wind Turbines• Energy Storage System

Page 18: KEA’s Renewable Vision

Terror Lake Third Hydroelectric Turbine

Page 19: KEA’s Renewable Vision
Page 20: KEA’s Renewable Vision

Energy Storage System• Xtreme Power Battery System

Page 21: KEA’s Renewable Vision

82% Hydro

16% Wind

2% Diesel