Kansai Airport 2005
description
Transcript of Kansai Airport 2005
Kansai International Airport (Phase-I) Foundation Case Study
ByRajul Teredesai
CE 5333-Foundation EngineeringSpring 2005
Overview
Kansai International Airport (KIA)
Key Features Located on a biggest man-made island in
Osaka Bay, Japan Constructed cost over $14 billion The island of 4 X 1 km, constructed in
around 18m of water, entirely from landfill Project Started in 1986 Opened for flights in 1996 The ASCE named KIA the #2 civil
engineering project of the 20th century, second only to the Panama Canal
Kansai Airport Aerial View
Construction of Airport
Stage Activity Time
I Subsurface Investigation 1 year
II Sea Wall Construction 2 years
III Landfilling 4 years
IV Terminal Construction 2 years
Bore Hole Locations
Subsurface of the Kansai Airport Foundation
Seawall Construction
Up to 40 ft. above sea level Tripod blocks on seaward side for
dissipation of wave energy
Seawall After Completion
Seawall Construction
Mechanism of Sand Drains
Advantage of Sand Drains
The weight of the piled sand forces the water in the clay to move outward along the sand piles.
Application of One Million Sand Drain at KIA
Reclamation Three distinct
grades of sand, gravel and rock from nearby mountains
Four years and 750 million cubic feet of fill
Transportation on Ground: Conveyor Water: Barges
KIA Terminal Building
Architect: Renzo Piano
Settlement Predictions
Lack of experience with construction on deep deposit of diluvial clay
Expected settlement = 19 to 25 ft Actual settlement = 27 ft (by the end
of island construction in 1990) It continued at the rate of 2 in/month
Settlement Calculations Consolidation Settlement:
Time Rate of Consolidation (Terzaghi 1925):
'
'log
1,vo
vo
o
cultc e
CH
2
2
z
uc
t
u ev
e
What Went Wrong in Predictions?
Un-conservative estimation of consolidation settlement
Wrong estimate of the time required for completion of consolidation settlement
Ineffectiveness of the sand drains in achieving the required success 100%
Incomplete Consolidation
Underestimation of Excess Pore Water Pressure
Airport Started
Settlement Continued
Coping With The Problem of Continued Settlement
Basement of the terminal was lined with a quarter of a million tons of iron ore.
Result: Island sank faster than the building it is trying to hold
Installation of hydraulic jacks under the colums
Result: No differential settlement between the columns of entire building
Learning From Mistakes
Using data actual settlement data obtained from 1st phase of project
Analysis of 400-m-deep boring exploration
State-of-the-art soil test methods Expected Settlement = 18 m http://
www.kald.co.jp/eindexframe.html
References
A report by Justin Phalen, UC-Davis, 2002
The official website of KIA http://www.kald.co.jp/eindexframe.html
Questions?