Kansai Airport 2005

23
Kansai International Airport (Phase-I) Foundation Case Study By Rajul Teredesai CE 5333-Foundation Engineering Spring 2005

description

kansai airport

Transcript of Kansai Airport 2005

Page 1: Kansai Airport 2005

Kansai International Airport (Phase-I) Foundation Case Study

ByRajul Teredesai

CE 5333-Foundation EngineeringSpring 2005

Page 2: Kansai Airport 2005

Overview

Kansai International Airport (KIA)

Page 3: Kansai Airport 2005

Key Features Located on a biggest man-made island in

Osaka Bay, Japan Constructed cost over $14 billion The island of 4 X 1 km, constructed in

around 18m of water, entirely from landfill Project Started in 1986 Opened for flights in 1996 The ASCE named KIA the #2 civil

engineering project of the 20th century, second only to the Panama Canal

Page 4: Kansai Airport 2005

Kansai Airport Aerial View

Page 5: Kansai Airport 2005

Construction of Airport

Stage Activity Time

I Subsurface Investigation 1 year

II Sea Wall Construction 2 years

III Landfilling 4 years

IV Terminal Construction 2 years

Page 6: Kansai Airport 2005

Bore Hole Locations

Page 7: Kansai Airport 2005

Subsurface of the Kansai Airport Foundation

Page 8: Kansai Airport 2005

Seawall Construction

Up to 40 ft. above sea level Tripod blocks on seaward side for

dissipation of wave energy

Page 9: Kansai Airport 2005

Seawall After Completion

Seawall Construction

Page 10: Kansai Airport 2005

Mechanism of Sand Drains

Page 11: Kansai Airport 2005

Advantage of Sand Drains

The weight of the piled sand forces the water in the clay to move outward along the sand piles.

Page 12: Kansai Airport 2005

Application of One Million Sand Drain at KIA

Page 13: Kansai Airport 2005

Reclamation Three distinct

grades of sand, gravel and rock from nearby mountains

Four years and 750 million cubic feet of fill

Transportation on Ground: Conveyor Water: Barges

Page 14: Kansai Airport 2005

KIA Terminal Building

Architect: Renzo Piano

Page 15: Kansai Airport 2005

Settlement Predictions

Lack of experience with construction on deep deposit of diluvial clay

Expected settlement = 19 to 25 ft Actual settlement = 27 ft (by the end

of island construction in 1990) It continued at the rate of 2 in/month

Page 16: Kansai Airport 2005

Settlement Calculations Consolidation Settlement:

Time Rate of Consolidation (Terzaghi 1925):

'

'log

1,vo

vo

o

cultc e

CH

2

2

z

uc

t

u ev

e

Page 17: Kansai Airport 2005

What Went Wrong in Predictions?

Un-conservative estimation of consolidation settlement

Wrong estimate of the time required for completion of consolidation settlement

Ineffectiveness of the sand drains in achieving the required success 100%

Page 18: Kansai Airport 2005

Incomplete Consolidation

Page 19: Kansai Airport 2005

Underestimation of Excess Pore Water Pressure

Airport Started

Settlement Continued

Page 20: Kansai Airport 2005

Coping With The Problem of Continued Settlement

Basement of the terminal was lined with a quarter of a million tons of iron ore.

Result: Island sank faster than the building it is trying to hold

Installation of hydraulic jacks under the colums

Result: No differential settlement between the columns of entire building

Page 21: Kansai Airport 2005

Learning From Mistakes

Using data actual settlement data obtained from 1st phase of project

Analysis of 400-m-deep boring exploration

State-of-the-art soil test methods Expected Settlement = 18 m http://

www.kald.co.jp/eindexframe.html

Page 22: Kansai Airport 2005

References

A report by Justin Phalen, UC-Davis, 2002

The official website of KIA http://www.kald.co.jp/eindexframe.html

Page 23: Kansai Airport 2005

Questions?