June 19, 2012 Board Presentation

download June 19, 2012 Board Presentation

of 7

Transcript of June 19, 2012 Board Presentation

  • 7/31/2019 June 19, 2012 Board Presentation

    1/7

    1 Bond First Issuance 34,999,104$

    2 Expended to Date (See Exhibit A) (20,515,599)$

    3 2012 Summer Construction (See Exhibit B) (16,075,287)$

    4 Sub-Total (1,591,782)$

    5 Committed Projects (See below) (20,022,729)$

    6 Total (21,614,511)$

    Estimated CostCommitted Projects

    7 Save Our Schools Security Grant 250,000$

    8 Window Covering Replacement Phase I 300,000$

    9 Portables to Hayes * 1,003,500$

    10 ADA/Security Locksets 330,000$

    11 Security Safety Fencing 611,000$

    12 IMC ADA Restroom Remodel 120,000$

    13 Foothill Sewage Lift Station 120,000$

    14 Marina High Water Line 230,000$

    15 District Office Heating 1,257,525$

    16 SHS Bleachers & Fields 1,396,209$

    17 SHS Phase II & III Heating 2,510,970$

    18 Los Arboles Building & Modernization 5,631,525$

    19 Technology Master Plan Build Out 5,162,000$

    20 District Wide Intrusion Alarm 500,000$

    21 Building/Energy Management System 600,000$

    22 Total 20,022,729$

    *

    BOND FUNDING OVERVIEW - Present Status

    The need for the Hayes portable addition will be re-evaluated once SIG

    funding has expired.

  • 7/31/2019 June 19, 2012 Board Presentation

    2/7

    1 Bond Authorization 110,000,000$

    2 Expended to Date (Exhibit A) (20,515,599)$

    3 2012 Summer Construction (See Exhibit B) (16,075,287)$

    4 Committed Projects (See above) (20,022,729)$

    5 Remaining Authorization 53,386,385$

    6 Future Projects (See below) 54,437,806$

    (1,051,421)$

    Estimated CostPossible Future Projects

    7 Complete Heating Project District Wide 30,037,806$

    8 ADA Restroom Remodels 13,200,000$

    9 Renewable Energy System (photovoltaic) 10,000,000$

    10 Portable Removal & New Buildings at SHS, Foothill

    11 Interior Modernizations

    12 Colton Storm Drain Project * 1,200,000$

    13 Total 54,437,806$

    *

    BOND FUNDING OVERVIEW - Overall Status

    Colton Storm Drain could be funded from Deferred Maintenance should

    that fund be restored after the November election.

  • 7/31/2019 June 19, 2012 Board Presentation

    3/7

    Financial Report - By Program Number and Year Exhibit A

    A B C D C+D=E

    Expended Expended

    Program # 10/11 11/12 Total

    1 Administrative Costs

    2 Administrative Costs (legal) 5000 720,257.66$ 158,740.36$ 878,998.02$

    3 Lease Obligation Retirement 5001 8,280,243.25$ -$ 8,280,243.25$

    4 Wide Area Network Review 5002 48,123.79$ 175,797.98$ 223,921.77$5 Cabrillo District Programs

    6 Exterior Paint -$

    7 Central Coast High (Hayes)

    8 Fire Alarm System Replacement 5040 12,248.18$ 79,982.54$ 92,230.72$

    9 Wireless Upgrades 5041 9,523.02$ 19,144.96$ 28,667.98$

    10 Intrusion Alarm Installation 5042 9,931.00$ 9,931.00$

    11 Computer Lab Installations 5043 48,287.94$ 48,287.94$

    12 Site Fencing 5044 29,879.00$ 29,879.00$

    13 Portable Install & Site Modernization 5045 41,505.00$ 41,505.00$

    14 Colton MS

    15 HVAC Replacement 5070 121,414.42$ 1,966,349.77$ 2,087,764.19$

    16 Phone, Intercom, Data, & Clock Improvements 5071 35,462.30$ 273,793.44$ 309,255.74$

    17 Multi Use Floor Replacement 5072 28,902.00$ 10,940.00$ 39,842.00$

    18 Crumpton ES

    19 Multi Use Floor Replacement 5100 48,863.00$ 48,863.00$

    20 Portable Demolition -$

    21 Del Monte Adult School & ROP

    22 Portable Removal & Playground Improvement 5130 84,949.00$ 84,949.00$

    23 Exterior Paint -$

    24 Del Rey Woods ES

    25 HVAC Replacement 5160 133,902.98$ 137,869.71$ 271,772.69$

    26 Admin Floor & Paint, Power Upgrades, Door Replace 5161 514,597.59$ 514,597.59$

    27 Multi-Use Floor Replace, Paint MU & Admin 5162 3,669.38$ 3,669.38$

    28 Wireless/Phones/Intercom -$

    29 District Offices

    30 HVAC Replacement 5190 28,787.60$ 55,162.36$ 83,949.96$

    31 Window Replacement 5191 9,899.65$ 147,641.44$ 157,541.09$

    32 Department Remodel 5193 37,335.00$ 37,335.00$

    33 Foothill ES

    34 ADA Accessibility Upgrades 5220 4,950.00$ 90,670.00$ 95,620.00$

    35 Phone, Intercom, Data, & Clock Improvements 5221 38,794.02$ 241,688.19$ 280,482.21$

    36 Sewer Improvements 5222 4,177.74$ 4,177.74$

    37 Portable Demolition -$

    38 Highland ES

    39 Toilet Room Renovation 5250 6,160.00$ 19,697.00$ 25,857.00$

    40 Phone, Intercom, Data, & Clock Improvements 5251 -$

    41 King, Martin Luther ES

    42 HVAC Replacement 5280 61,678.38$ 61,678.38$

    3

  • 7/31/2019 June 19, 2012 Board Presentation

    4/7

    Financial Report - By Program Number and Year Exhibit AA B C D C+D=E

    Expended Expended

    Program # 10/11 11/12 Total

    43 La Mesa ES

    44 Toilet Room Renovation & DSA Close-out 5310 7,840.00$ 60,523.08$ 68,363.08$

    45 Phone, Intercom, Data, & Clock Improvements 5311 22,870.12$ 237,620.30$ 260,490.42$

    46 Los Arboles MS

    47 Multi Use Floor Replacement 5340 29,640.00$ 29,640.00$

    48 Modernization & New Construction 5341 46,451.83$ 46,451.83$

    49 Manzanita ISM (charter)

    50 3 Classroom Floor Replacement 5370 30,306.02$ 30,306.02$

    51 Wireless/Phones/Intercom -$

    52 Marina Del Mar ES (MCC)

    53 4 Portable Classroom Demo 5400 51,946.00$ 51,946.00$

    54 Marina HS

    55 ROP Classroom Improvements 5430 77,709.69$ 77,709.69$

    56 4 Portable Classroom Relocation 5431 197,105.69$ 197,105.69$

    57 Water Main Improvement 5432 6,626.50$ 6,626.50$

    58 Restroom Partitions & Paint -$

    59 Marina Vista ES60 Toilet Room Renovation & DSA Close-out 5460 6,400.00$ 72,751.82$ 79,151.82$

    61 Phone, Intercom, Data, & Clock Improvements 5461 416,913.61$ 416,913.61$

    62 Multi Use Floor Replacement, Paint MU & Admin 5462 41,586.00$ 41,586.00$

    63 Marshall ES

    64 Phone, Intercom, Data, & Clock Improvements 5490 30,270.63$ 229,355.06$ 259,625.69$

    65 3 Classroom Floor Replacement 5491 24,390.00$ 24,390.00$

    66 Marshall West

    67 5520 -$

    68 Monte Vista ES

    69 Phone, Intercom, Data, & Clock Improvements 5550 29,609.77$ 205,935.46$ 235,545.23$

    70 School Re-opening Project 5551 575,663.15$ 575,663.15$

    71 Intrusion Alarm Installation 5552 8,831.00$ 8,831.00$

    72 US Army Reimbursement Project 5553 -$73 Monterey HS

    74 Toilet Room Renovation & ADA path of travel 5580A 24,181.32$ 169,505.59$ 193,686.91$

    75 Pool Equipment Upgrade 5581 8,902.92$ 651,746.85$ 660,649.77$

    76 Paint Exterior Campus 5582 122,628.19$ 162,805.81$ 285,434.00$

    77 Network Upgrades 5583 -$

    78 Flooring Upgrades 5584 8,340.00$ 8,340.00$

    79 Computer Lab Installations 5585 15,512.33$ 15,512.33$

    80 Phone, Intercom, Data, & Clock Improvements 5586 712.50$ 712.50$

    4

  • 7/31/2019 June 19, 2012 Board Presentation

    5/7

    Financial Report - By Program Number and Year Exhibit AA B C D C+D=E

    Expended Expended

    Program # 10/11 11/12 Total

    81 Olson ES

    82 Phone, Intercom, Data, & Clock Improvements 5610 382,947.95$ 382,947.95$

    83 Multi Use Floor Replacement & Paint 5611 36,071.00$ 36,071.00$

    84 Ord Terrace ES

    85 HVAC Replacement 5640 286,432.02$ 109,041.88$ 395,473.90$

    86 Phone, Intercom, Data, & Clock Improvements 5641 257,204.44$ 257,204.44$

    87 Admin Floor, Power Upgrades, Door Replacement 5642 521,615.48$ 521,615.48$

    88 Playground Improvements 5643 13,566.14$ 13,566.14$

    89 Exterior Paint -$

    90 Seaside Children's Center

    91 5670 -$

    92 Seaside HS

    93 HVAC Replacement 5700 90,532.56$ 123,942.50$ 214,475.06$

    94 Miscellaneous Other 5701 3,273.96$ 10,833.00$ 14,106.96$

    95 Seaside Portable Demolition 5702 1,880.92$ 199,248.99$ 201,129.91$

    96 Flooring Upgrades 5703 12,150.00$ 12,150.00$

    97 Athletic Field Renovation 5704 6,602.50$ 6,602.50$98 Seaside MS (Fitch)

    99 5730 -$

    100 Miscellaneous Other

    101 2011 Summer Projects 5760 128,598.08$ 128,598.08$

    102 Furniture Purchase 5761 739,869.64$ 739,869.64$

    103 Lockset Project District Wide 5762 10,375.34$ 10,375.34$

    104 Irrigation Improvements 5763 841.68$ 841.68$

    105 District Security Fencing upgrades 5764 7,710.11$ 7,710.11$

    106 Renewable Energy Projects 5765 80,000.00$ 80,000.00$

    107 Hazardous Material Testing 5766 27,160.00$ 27,160.00$

    108 Window Blind Replacement -$

    109 Whiteboard Replacement -$

    110 Instructional Materials Center111 IMC Conference Center 5192 -$

    112 VoIP Core Upgrade 5790 -$

    113 Transportation Flooring Replacement -$

    114 Restroom Remodel -$

    115 June 16 to 30 payments 150,000.00$

    Sub-Totals 10,975,031.22$ 9,390,567.86$

    Grand Total 20,515,599.08$

    5

  • 7/31/2019 June 19, 2012 Board Presentation

    6/7

    Exhibit B

    2012 SUMMER PROJECTS Construction Status ProbabLocation Project Cost Project C

    Bond Projects (large)

    1 DO Windows 538,097$ June 18 meeting 618,$

    2 FOOTHILL Restrooms/ADA/Locksets 1,105,553$ Awarded 1,271$

    3 HIGHLAND Restrooms/ADA/Locksets 910,696$ Awarded 1,047$

    4 La MESA Restrooms/ADA/Locksets 1,375,611$ Awarded 1,581$

    5 Ma VISTA Restrooms/ADA/Locksets 1,156,023$ Awarded 1,329$6 FH, LM, MV, HL ADA/Security Locksets (door handles) In above awards $

    7 KING Heating 1,441,643$ Awarded 1,657$

    8 MHS Heating/Restrooms/ADA @ upper wings 2,388,357$ Awarded 2,746$

    9 MHS Library move IT racks, demo walls, move check counter In above award $

    10 SHS PH I Heating 2,505,894$ Awarded 2,881$

    11 SHS SP.ED. abate & tile, remove island, in-fill casework In above award $

    12 SHS SP.ED. window replacement In above award $

    13 MHS tennis court resurface/fence/backboard In above award $

    14 SHS tennis court resurface/fence In above award $

    15 SHS basketball court overlay In above award $

    16 Cabrillo School reopening clean up 152,811$ June 18 - Paint, wall removal, Slurry 175,$

    Exterior School Painting17 Del Monte Exterior Paint & Abate 71,825$ June 18 meeting 82,$

    18 Ord Terrace Exterior Paint & Abate 85,850$ June 18 meeting 98,$

    Roofing

    19 Olson 15 ROOF REPLACEMENT 7,632$ Quoted 9,$

    Flooring

    20 Transportation abate & tile, moving issue 20,335$ Quote for flooring & abatement 23,$

    21 Marshall Room 4 & 20 carpet 18,445$ Quote for flooring & abatement 21,$

    22 MHS P1-P3 carpet 8,400$ Quote for flooring & abatement 9,$

    23 SHS B-24 carpet 6,625$ Quote for flooring & abatement 7,$

    24 ISM abate & tile 2 rms = 5&6 20,505$ Quote for flooring & abatement 23,$

    25 King Staff Lounge 5,000$ estimate 5,$

    6

  • 7/31/2019 June 19, 2012 Board Presentation

    7/7

    Exhibit B

    Miscellaneous

    26 DRW whiteboards 8,700$ install 9,$

    27 King whiteboards 2,000$ install 2,$

    28 La Mesa whiteboards 2,000$ install 2,$

    29 MHS whiteboards 17,400$ install 19,$

    30 Purchase whiteboards 50,506$ material 55,$

    31 Marina HS toilet partitions & restroom upgrade 5,791$ material 6,$

    32 Del Monte restroom upgrade (partitions) 3,474$ material 3,$33 Crumpton restroom upgrade K1 super clean 5,000$ estimate 5,$

    34 LAMS Entrance Plot walkway 5,000$ estimate 5,$

    35 SHS Tables & benches 5,000$ estimate 5,$

    36 MaHS Basketball slurry 20,000$ estimate 22,$

    Technology

    37 Del Rey Woods wireless/phones/intercom 295,000$ Awarded 324,$

    38 ISM Manzanita wireless/phones/intercom 375,000$ Awarded 412,$

    39 MHS wireless/phones/intercom 765,000$ Awarded 841,$

    40 WAN Upgrades District Wide Area Network Upgrades 225,000$ Awarded 247,$

    Play Structures

    41 Del Monte Bayview Academy play structures 25,187$ June 18 meeting 28,$

    42 Marina Del Mar Tire Grant 20,000$ plus cost for excavate/remove 23,$

    43 Marina Vista Tire Grant 31,031$ plus cost for excavate/remove 35,$

    44 Olson Tire Grant 112,898$ plus cost for excavate/remove 129,$

    45 Crumpton Tire Grant 20,000$ plus cost for excavate/remove 23,$

    46 ISM Manzanita Edwards Quote 44,963$ June 18 meeting 51,$

    Furniture

    45 Crumpt grd 3-5 7rms, Bayvw Acad k-2 6rms, Marsh 4-5 1rm 134,000$ 134$

    Recent

    46 MaHS Basket ball slurry, new standards 20,000$ 22,$

    47 SHS Benches 5,000$ 5$

    48 MHS Cafeteria Paint & Flooring 20,000$ 22,$

    49 Hayes Room 22 carpet to tile 6,000$ 6$

    50 Monte Vista Replace underground gas line 33,690$ 37,$

    16,075$

    7