June 19, 2012 Board Presentation
-
Upload
monterey-peninsula-unified-school-district -
Category
Documents
-
view
216 -
download
0
Transcript of June 19, 2012 Board Presentation
-
7/31/2019 June 19, 2012 Board Presentation
1/7
1 Bond First Issuance 34,999,104$
2 Expended to Date (See Exhibit A) (20,515,599)$
3 2012 Summer Construction (See Exhibit B) (16,075,287)$
4 Sub-Total (1,591,782)$
5 Committed Projects (See below) (20,022,729)$
6 Total (21,614,511)$
Estimated CostCommitted Projects
7 Save Our Schools Security Grant 250,000$
8 Window Covering Replacement Phase I 300,000$
9 Portables to Hayes * 1,003,500$
10 ADA/Security Locksets 330,000$
11 Security Safety Fencing 611,000$
12 IMC ADA Restroom Remodel 120,000$
13 Foothill Sewage Lift Station 120,000$
14 Marina High Water Line 230,000$
15 District Office Heating 1,257,525$
16 SHS Bleachers & Fields 1,396,209$
17 SHS Phase II & III Heating 2,510,970$
18 Los Arboles Building & Modernization 5,631,525$
19 Technology Master Plan Build Out 5,162,000$
20 District Wide Intrusion Alarm 500,000$
21 Building/Energy Management System 600,000$
22 Total 20,022,729$
*
BOND FUNDING OVERVIEW - Present Status
The need for the Hayes portable addition will be re-evaluated once SIG
funding has expired.
-
7/31/2019 June 19, 2012 Board Presentation
2/7
1 Bond Authorization 110,000,000$
2 Expended to Date (Exhibit A) (20,515,599)$
3 2012 Summer Construction (See Exhibit B) (16,075,287)$
4 Committed Projects (See above) (20,022,729)$
5 Remaining Authorization 53,386,385$
6 Future Projects (See below) 54,437,806$
(1,051,421)$
Estimated CostPossible Future Projects
7 Complete Heating Project District Wide 30,037,806$
8 ADA Restroom Remodels 13,200,000$
9 Renewable Energy System (photovoltaic) 10,000,000$
10 Portable Removal & New Buildings at SHS, Foothill
11 Interior Modernizations
12 Colton Storm Drain Project * 1,200,000$
13 Total 54,437,806$
*
BOND FUNDING OVERVIEW - Overall Status
Colton Storm Drain could be funded from Deferred Maintenance should
that fund be restored after the November election.
-
7/31/2019 June 19, 2012 Board Presentation
3/7
Financial Report - By Program Number and Year Exhibit A
A B C D C+D=E
Expended Expended
Program # 10/11 11/12 Total
1 Administrative Costs
2 Administrative Costs (legal) 5000 720,257.66$ 158,740.36$ 878,998.02$
3 Lease Obligation Retirement 5001 8,280,243.25$ -$ 8,280,243.25$
4 Wide Area Network Review 5002 48,123.79$ 175,797.98$ 223,921.77$5 Cabrillo District Programs
6 Exterior Paint -$
7 Central Coast High (Hayes)
8 Fire Alarm System Replacement 5040 12,248.18$ 79,982.54$ 92,230.72$
9 Wireless Upgrades 5041 9,523.02$ 19,144.96$ 28,667.98$
10 Intrusion Alarm Installation 5042 9,931.00$ 9,931.00$
11 Computer Lab Installations 5043 48,287.94$ 48,287.94$
12 Site Fencing 5044 29,879.00$ 29,879.00$
13 Portable Install & Site Modernization 5045 41,505.00$ 41,505.00$
14 Colton MS
15 HVAC Replacement 5070 121,414.42$ 1,966,349.77$ 2,087,764.19$
16 Phone, Intercom, Data, & Clock Improvements 5071 35,462.30$ 273,793.44$ 309,255.74$
17 Multi Use Floor Replacement 5072 28,902.00$ 10,940.00$ 39,842.00$
18 Crumpton ES
19 Multi Use Floor Replacement 5100 48,863.00$ 48,863.00$
20 Portable Demolition -$
21 Del Monte Adult School & ROP
22 Portable Removal & Playground Improvement 5130 84,949.00$ 84,949.00$
23 Exterior Paint -$
24 Del Rey Woods ES
25 HVAC Replacement 5160 133,902.98$ 137,869.71$ 271,772.69$
26 Admin Floor & Paint, Power Upgrades, Door Replace 5161 514,597.59$ 514,597.59$
27 Multi-Use Floor Replace, Paint MU & Admin 5162 3,669.38$ 3,669.38$
28 Wireless/Phones/Intercom -$
29 District Offices
30 HVAC Replacement 5190 28,787.60$ 55,162.36$ 83,949.96$
31 Window Replacement 5191 9,899.65$ 147,641.44$ 157,541.09$
32 Department Remodel 5193 37,335.00$ 37,335.00$
33 Foothill ES
34 ADA Accessibility Upgrades 5220 4,950.00$ 90,670.00$ 95,620.00$
35 Phone, Intercom, Data, & Clock Improvements 5221 38,794.02$ 241,688.19$ 280,482.21$
36 Sewer Improvements 5222 4,177.74$ 4,177.74$
37 Portable Demolition -$
38 Highland ES
39 Toilet Room Renovation 5250 6,160.00$ 19,697.00$ 25,857.00$
40 Phone, Intercom, Data, & Clock Improvements 5251 -$
41 King, Martin Luther ES
42 HVAC Replacement 5280 61,678.38$ 61,678.38$
3
-
7/31/2019 June 19, 2012 Board Presentation
4/7
Financial Report - By Program Number and Year Exhibit AA B C D C+D=E
Expended Expended
Program # 10/11 11/12 Total
43 La Mesa ES
44 Toilet Room Renovation & DSA Close-out 5310 7,840.00$ 60,523.08$ 68,363.08$
45 Phone, Intercom, Data, & Clock Improvements 5311 22,870.12$ 237,620.30$ 260,490.42$
46 Los Arboles MS
47 Multi Use Floor Replacement 5340 29,640.00$ 29,640.00$
48 Modernization & New Construction 5341 46,451.83$ 46,451.83$
49 Manzanita ISM (charter)
50 3 Classroom Floor Replacement 5370 30,306.02$ 30,306.02$
51 Wireless/Phones/Intercom -$
52 Marina Del Mar ES (MCC)
53 4 Portable Classroom Demo 5400 51,946.00$ 51,946.00$
54 Marina HS
55 ROP Classroom Improvements 5430 77,709.69$ 77,709.69$
56 4 Portable Classroom Relocation 5431 197,105.69$ 197,105.69$
57 Water Main Improvement 5432 6,626.50$ 6,626.50$
58 Restroom Partitions & Paint -$
59 Marina Vista ES60 Toilet Room Renovation & DSA Close-out 5460 6,400.00$ 72,751.82$ 79,151.82$
61 Phone, Intercom, Data, & Clock Improvements 5461 416,913.61$ 416,913.61$
62 Multi Use Floor Replacement, Paint MU & Admin 5462 41,586.00$ 41,586.00$
63 Marshall ES
64 Phone, Intercom, Data, & Clock Improvements 5490 30,270.63$ 229,355.06$ 259,625.69$
65 3 Classroom Floor Replacement 5491 24,390.00$ 24,390.00$
66 Marshall West
67 5520 -$
68 Monte Vista ES
69 Phone, Intercom, Data, & Clock Improvements 5550 29,609.77$ 205,935.46$ 235,545.23$
70 School Re-opening Project 5551 575,663.15$ 575,663.15$
71 Intrusion Alarm Installation 5552 8,831.00$ 8,831.00$
72 US Army Reimbursement Project 5553 -$73 Monterey HS
74 Toilet Room Renovation & ADA path of travel 5580A 24,181.32$ 169,505.59$ 193,686.91$
75 Pool Equipment Upgrade 5581 8,902.92$ 651,746.85$ 660,649.77$
76 Paint Exterior Campus 5582 122,628.19$ 162,805.81$ 285,434.00$
77 Network Upgrades 5583 -$
78 Flooring Upgrades 5584 8,340.00$ 8,340.00$
79 Computer Lab Installations 5585 15,512.33$ 15,512.33$
80 Phone, Intercom, Data, & Clock Improvements 5586 712.50$ 712.50$
4
-
7/31/2019 June 19, 2012 Board Presentation
5/7
Financial Report - By Program Number and Year Exhibit AA B C D C+D=E
Expended Expended
Program # 10/11 11/12 Total
81 Olson ES
82 Phone, Intercom, Data, & Clock Improvements 5610 382,947.95$ 382,947.95$
83 Multi Use Floor Replacement & Paint 5611 36,071.00$ 36,071.00$
84 Ord Terrace ES
85 HVAC Replacement 5640 286,432.02$ 109,041.88$ 395,473.90$
86 Phone, Intercom, Data, & Clock Improvements 5641 257,204.44$ 257,204.44$
87 Admin Floor, Power Upgrades, Door Replacement 5642 521,615.48$ 521,615.48$
88 Playground Improvements 5643 13,566.14$ 13,566.14$
89 Exterior Paint -$
90 Seaside Children's Center
91 5670 -$
92 Seaside HS
93 HVAC Replacement 5700 90,532.56$ 123,942.50$ 214,475.06$
94 Miscellaneous Other 5701 3,273.96$ 10,833.00$ 14,106.96$
95 Seaside Portable Demolition 5702 1,880.92$ 199,248.99$ 201,129.91$
96 Flooring Upgrades 5703 12,150.00$ 12,150.00$
97 Athletic Field Renovation 5704 6,602.50$ 6,602.50$98 Seaside MS (Fitch)
99 5730 -$
100 Miscellaneous Other
101 2011 Summer Projects 5760 128,598.08$ 128,598.08$
102 Furniture Purchase 5761 739,869.64$ 739,869.64$
103 Lockset Project District Wide 5762 10,375.34$ 10,375.34$
104 Irrigation Improvements 5763 841.68$ 841.68$
105 District Security Fencing upgrades 5764 7,710.11$ 7,710.11$
106 Renewable Energy Projects 5765 80,000.00$ 80,000.00$
107 Hazardous Material Testing 5766 27,160.00$ 27,160.00$
108 Window Blind Replacement -$
109 Whiteboard Replacement -$
110 Instructional Materials Center111 IMC Conference Center 5192 -$
112 VoIP Core Upgrade 5790 -$
113 Transportation Flooring Replacement -$
114 Restroom Remodel -$
115 June 16 to 30 payments 150,000.00$
Sub-Totals 10,975,031.22$ 9,390,567.86$
Grand Total 20,515,599.08$
5
-
7/31/2019 June 19, 2012 Board Presentation
6/7
Exhibit B
2012 SUMMER PROJECTS Construction Status ProbabLocation Project Cost Project C
Bond Projects (large)
1 DO Windows 538,097$ June 18 meeting 618,$
2 FOOTHILL Restrooms/ADA/Locksets 1,105,553$ Awarded 1,271$
3 HIGHLAND Restrooms/ADA/Locksets 910,696$ Awarded 1,047$
4 La MESA Restrooms/ADA/Locksets 1,375,611$ Awarded 1,581$
5 Ma VISTA Restrooms/ADA/Locksets 1,156,023$ Awarded 1,329$6 FH, LM, MV, HL ADA/Security Locksets (door handles) In above awards $
7 KING Heating 1,441,643$ Awarded 1,657$
8 MHS Heating/Restrooms/ADA @ upper wings 2,388,357$ Awarded 2,746$
9 MHS Library move IT racks, demo walls, move check counter In above award $
10 SHS PH I Heating 2,505,894$ Awarded 2,881$
11 SHS SP.ED. abate & tile, remove island, in-fill casework In above award $
12 SHS SP.ED. window replacement In above award $
13 MHS tennis court resurface/fence/backboard In above award $
14 SHS tennis court resurface/fence In above award $
15 SHS basketball court overlay In above award $
16 Cabrillo School reopening clean up 152,811$ June 18 - Paint, wall removal, Slurry 175,$
Exterior School Painting17 Del Monte Exterior Paint & Abate 71,825$ June 18 meeting 82,$
18 Ord Terrace Exterior Paint & Abate 85,850$ June 18 meeting 98,$
Roofing
19 Olson 15 ROOF REPLACEMENT 7,632$ Quoted 9,$
Flooring
20 Transportation abate & tile, moving issue 20,335$ Quote for flooring & abatement 23,$
21 Marshall Room 4 & 20 carpet 18,445$ Quote for flooring & abatement 21,$
22 MHS P1-P3 carpet 8,400$ Quote for flooring & abatement 9,$
23 SHS B-24 carpet 6,625$ Quote for flooring & abatement 7,$
24 ISM abate & tile 2 rms = 5&6 20,505$ Quote for flooring & abatement 23,$
25 King Staff Lounge 5,000$ estimate 5,$
6
-
7/31/2019 June 19, 2012 Board Presentation
7/7
Exhibit B
Miscellaneous
26 DRW whiteboards 8,700$ install 9,$
27 King whiteboards 2,000$ install 2,$
28 La Mesa whiteboards 2,000$ install 2,$
29 MHS whiteboards 17,400$ install 19,$
30 Purchase whiteboards 50,506$ material 55,$
31 Marina HS toilet partitions & restroom upgrade 5,791$ material 6,$
32 Del Monte restroom upgrade (partitions) 3,474$ material 3,$33 Crumpton restroom upgrade K1 super clean 5,000$ estimate 5,$
34 LAMS Entrance Plot walkway 5,000$ estimate 5,$
35 SHS Tables & benches 5,000$ estimate 5,$
36 MaHS Basketball slurry 20,000$ estimate 22,$
Technology
37 Del Rey Woods wireless/phones/intercom 295,000$ Awarded 324,$
38 ISM Manzanita wireless/phones/intercom 375,000$ Awarded 412,$
39 MHS wireless/phones/intercom 765,000$ Awarded 841,$
40 WAN Upgrades District Wide Area Network Upgrades 225,000$ Awarded 247,$
Play Structures
41 Del Monte Bayview Academy play structures 25,187$ June 18 meeting 28,$
42 Marina Del Mar Tire Grant 20,000$ plus cost for excavate/remove 23,$
43 Marina Vista Tire Grant 31,031$ plus cost for excavate/remove 35,$
44 Olson Tire Grant 112,898$ plus cost for excavate/remove 129,$
45 Crumpton Tire Grant 20,000$ plus cost for excavate/remove 23,$
46 ISM Manzanita Edwards Quote 44,963$ June 18 meeting 51,$
Furniture
45 Crumpt grd 3-5 7rms, Bayvw Acad k-2 6rms, Marsh 4-5 1rm 134,000$ 134$
Recent
46 MaHS Basket ball slurry, new standards 20,000$ 22,$
47 SHS Benches 5,000$ 5$
48 MHS Cafeteria Paint & Flooring 20,000$ 22,$
49 Hayes Room 22 carpet to tile 6,000$ 6$
50 Monte Vista Replace underground gas line 33,690$ 37,$
16,075$
7