Joe Alvarez EIA Engineer Kumurana Project status: Limestone Channels and abandoned mine sealing Engineers in Action Building a better future for tomorrow

Transcript of Joe Alvarez EIA Engineer Kumurana Project status: Limestone Channels and abandoned mine sealing...

Page 1: Joe Alvarez EIA Engineer Kumurana Project status: Limestone Channels and abandoned mine sealing Engineers in Action Building a better future for tomorrow.

Joe Alvarez

EIA Engineer

Kumurana Project status:Limestone Channels and abandoned mine sealing

Engineers in ActionBuilding a better future for tomorrow

Page 2: Joe Alvarez EIA Engineer Kumurana Project status: Limestone Channels and abandoned mine sealing Engineers in Action Building a better future for tomorrow.

Limestone Delivery

Monthly Limestone Delivery

DECEMBER JANUARY FEBRUARY

Week 5th-11th 12th-18th 2nd-8th 9th-15th 16th-22nd 23rd-29th Jan30-Feb5      

Limestone[metric tons] ~15 ~82.5 ~87.05 ~82.5 ~97.5 ~15 ~112.5      

*This includes the abandoned mine delivery

Channels:~358m tons

Abandoned Mine:~135m tons

Page 3: Joe Alvarez EIA Engineer Kumurana Project status: Limestone Channels and abandoned mine sealing Engineers in Action Building a better future for tomorrow.
Page 4: Joe Alvarez EIA Engineer Kumurana Project status: Limestone Channels and abandoned mine sealing Engineers in Action Building a better future for tomorrow.
Page 5: Joe Alvarez EIA Engineer Kumurana Project status: Limestone Channels and abandoned mine sealing Engineers in Action Building a better future for tomorrow.

Limestone Channels

Limestone delivery Required Volume for channles:2027m3

Amount of Limestone Delivered:~358 Metric tons for the channels [About 14% of the total limestone delivery]

m tons2535~25.1*2027

Page 6: Joe Alvarez EIA Engineer Kumurana Project status: Limestone Channels and abandoned mine sealing Engineers in Action Building a better future for tomorrow.

Required:108m3Delivered: ~135m tons

Required:213m3Delivered: ~262.5m tons

Required:132m3Delivered: ~27m tons

LEGENDDelivery completed

Partial Delivery

No delivery

Required:348m3Delivered: ~67.5m tons

Map source EWB-OU

Page 7: Joe Alvarez EIA Engineer Kumurana Project status: Limestone Channels and abandoned mine sealing Engineers in Action Building a better future for tomorrow.

Limestone Channels Cont’d

Installation The installation of limestone into the

channels is pending Taking advantage of trucks Community support to install the

limestone Water analysis coordination with CIMA

and Universidad Tomas Frias

Page 8: Joe Alvarez EIA Engineer Kumurana Project status: Limestone Channels and abandoned mine sealing Engineers in Action Building a better future for tomorrow.

Limestone Channels Cont’d

Constructions issues Project issues

Accessibility issues Distance [about 100miles/trip] Heavy Rain/Hail

Working with the government Bureaucracy at the government No continuous of flow work Borrowed trucks

Page 9: Joe Alvarez EIA Engineer Kumurana Project status: Limestone Channels and abandoned mine sealing Engineers in Action Building a better future for tomorrow.

Accessibility issues

Page 10: Joe Alvarez EIA Engineer Kumurana Project status: Limestone Channels and abandoned mine sealing Engineers in Action Building a better future for tomorrow.

Rain

Page 11: Joe Alvarez EIA Engineer Kumurana Project status: Limestone Channels and abandoned mine sealing Engineers in Action Building a better future for tomorrow.
Page 12: Joe Alvarez EIA Engineer Kumurana Project status: Limestone Channels and abandoned mine sealing Engineers in Action Building a better future for tomorrow.
Page 13: Joe Alvarez EIA Engineer Kumurana Project status: Limestone Channels and abandoned mine sealing Engineers in Action Building a better future for tomorrow.

Bureaucracy

Page 14: Joe Alvarez EIA Engineer Kumurana Project status: Limestone Channels and abandoned mine sealing Engineers in Action Building a better future for tomorrow.

Abandoned Mine sealing Limestone

Delivered 108m3 of limestone delivery-complete Limestone installation is pending

Oxidation pond 90% completed Some improvements needed to finish Inaccessible with a heavy equipment to continue

digging and finish. [wetlands] Wall sealing

Construction starts when the worksite area becomes accessible

Estimated length of conclusion of the wall about 2-3 weeks

Page 15: Joe Alvarez EIA Engineer Kumurana Project status: Limestone Channels and abandoned mine sealing Engineers in Action Building a better future for tomorrow.

OTHER PHOTOS

Page 16: Joe Alvarez EIA Engineer Kumurana Project status: Limestone Channels and abandoned mine sealing Engineers in Action Building a better future for tomorrow.
Page 17: Joe Alvarez EIA Engineer Kumurana Project status: Limestone Channels and abandoned mine sealing Engineers in Action Building a better future for tomorrow.
Page 18: Joe Alvarez EIA Engineer Kumurana Project status: Limestone Channels and abandoned mine sealing Engineers in Action Building a better future for tomorrow.
Page 19: Joe Alvarez EIA Engineer Kumurana Project status: Limestone Channels and abandoned mine sealing Engineers in Action Building a better future for tomorrow.
Page 20: Joe Alvarez EIA Engineer Kumurana Project status: Limestone Channels and abandoned mine sealing Engineers in Action Building a better future for tomorrow.
Page 21: Joe Alvarez EIA Engineer Kumurana Project status: Limestone Channels and abandoned mine sealing Engineers in Action Building a better future for tomorrow.
Page 22: Joe Alvarez EIA Engineer Kumurana Project status: Limestone Channels and abandoned mine sealing Engineers in Action Building a better future for tomorrow.
Page 23: Joe Alvarez EIA Engineer Kumurana Project status: Limestone Channels and abandoned mine sealing Engineers in Action Building a better future for tomorrow.
Page 24: Joe Alvarez EIA Engineer Kumurana Project status: Limestone Channels and abandoned mine sealing Engineers in Action Building a better future for tomorrow.
Page 25: Joe Alvarez EIA Engineer Kumurana Project status: Limestone Channels and abandoned mine sealing Engineers in Action Building a better future for tomorrow.
Page 26: Joe Alvarez EIA Engineer Kumurana Project status: Limestone Channels and abandoned mine sealing Engineers in Action Building a better future for tomorrow.
Page 27: Joe Alvarez EIA Engineer Kumurana Project status: Limestone Channels and abandoned mine sealing Engineers in Action Building a better future for tomorrow.
Page 28: Joe Alvarez EIA Engineer Kumurana Project status: Limestone Channels and abandoned mine sealing Engineers in Action Building a better future for tomorrow.
Page 29: Joe Alvarez EIA Engineer Kumurana Project status: Limestone Channels and abandoned mine sealing Engineers in Action Building a better future for tomorrow.