Japan Proton Accelerator Research Complex J-PARC - Nuclear and Particle Physics Facility -
description
Transcript of Japan Proton Accelerator Research Complex J-PARC - Nuclear and Particle Physics Facility -
December 1, 2005 Shin'ya Sawada @ Hadron Structure at J-PARC
1
Japan Proton Accelerator Research Complex J-PARC
- Nuclear and Particle Physics Facility -
Shin’ya SawadaKEK
(High Energy Accelerator Research Organization, Japan)
December 1, 2005 Shin'ya Sawada @ Hadron Structure at J-PARC
2
Accelerator Configuration
Cascaded Accelerator Complex:
Linac
3GeV Rapid Cycling (25Hz) Synchrotron
50GeV Synchrotron
Materials and Life Science Facility
Hadron Hall (Slow Extracted Beams)
Neutrino Beamline to Super-Kamiokande
December 1, 2005 Shin'ya Sawada @ Hadron Structure at J-PARC
3
J-PARC:
J-PARC aims for the high intensity frontier for – materials/life sciences (3GeV),
and – nuclear/particle physics (50GeV)
High intensity proton beam leads to high intensity secondary (neutron, meson, …) beam. – The power (= Energy x Current)
is a good measure. Neutron: from 0.16MW (ISIS) to
1MW K meson: 5 to 10 times more
intense than existing BNL-AGS.
the High Intensity Frontier
December 1, 2005 Shin'ya Sawada @ Hadron Structure at J-PARC
4
Phase 1 & 2
The budget for about 2/3 of the entire project has been approved by the Japanese government from JFY2001 as Phase 1.
Phase 1 (~151 billion Yen) consists of major accelerator components and a part of experimental facilities.
December 1, 2005 Shin'ya Sawada @ Hadron Structure at J-PARC
5
Construction Schedule & Commissioning (Phase-1)
Linac
3 GeV
50 GeV
Materials + Life
Nuclear-Particle
Neutrino (plan)
Others
Salt Farms
Bldg. construction
Equip. constructionBeamtest
Bldg. constructionEquip. construction
Beamtest
Bldg. constructionEquip. construction
Beamtest
Bldg. construction
Equip. constructionBeamtest
Bldg. construction
Equip. constructionBeamtest
Bldg. construction
Equip. constructionBeamtest
Construction
Archelogical studies
Construction Schedule (as of Oct., 2003)
FY2001 FY2002 FY2003 FY2004 FY2005 FY2006 FY2007 FY2008
BeamConstruction Start
study report
December 1, 2005 Shin'ya Sawada @ Hadron Structure at J-PARC
6
Scenes of Construction
December 1, 2005 Shin'ya Sawada @ Hadron Structure at J-PARC
7
Performance of the 50-GeV PS
Beam Energy : 50 GeV(30GeV for Slow Beam)(40GeV for Fast Beam)
Repetition: 3.4 ~ 5-6s Flat Top Width : 0.7 ~ 2-3s Beam Intensity: 3.3x1014ppp, 15A
(2×1014ppp, 9A) ELinac = 400MeV (180MeV)
Beam Power: 750kW (270kW)
Numbers in parentheses are ones for the Phase 1.
December 1, 2005 Shin'ya Sawada @ Hadron Structure at J-PARC
8
Scenes of Construction
50 GeV Area
December 1, 2005 Shin'ya Sawada @ Hadron Structure at J-PARC
9
Neutrino Facility- Fast Extracted Beam -
December 1, 2005 Shin'ya Sawada @ Hadron Structure at J-PARC
10
T2K (Tokai-to-Kamioka) Neutrino Experiment
Status of oscillation and neutrino mass:– Atmospheric experiments
(SK…) discovered neutrino oscillation and thus finite masses of neutrinos.
– K2K disappearance experiment confirmed the existence of the neutrino oscillation with “man-made” neutrinos.
Motivations of T2K (Tokai to Kamioka): Precise measurement of disappearance to x. Discovery of e appearance: High flux of enables us to observe it.
– Flux () at the 50 GeV PS > 100 x Flux () at KEK 12 GeV PS Future upgrade … towards CP violation in the lepton sector
~1GeV beam(100 of K2K)
J-PARC0.75MW 50GeV PS
Super-K: 50 ktonWater Cherenkov
Phase2:4 MW ?
Phase2:Hyper-K?
December 1, 2005 Shin'ya Sawada @ Hadron Structure at J-PARC
11
Neutrino Facility
サスペンション型
(20t x 2)クレーン
ニュートリノ・ビームライン
FQ1
ビーム振り下げ 34.0
32. 8 19
. 2
9.7
ロス・ポイント( 250W)最大で
PH3PV2
PQ5PQ4
PV1 PD21.92 deg. bend
PQ3
PQ1PQ2A
1.9 2 d eg. ben dPD1 PH2 PH1
R104433.5
R107700R106400R100400R99600
PC1PC2PC3
PC4
引き出し基準点x=49615028.58, y=69561283.94
ニュートリノ標的
アーク中心x=49650.877m, y=69450.356
DEサブトンネル
Dサブトンネル
7550
アラインメント用穴 T1
アラインメント用穴 T2
6363.4
FV1 179.92°
FH1
FVD
2FQ
4FV
D1
FQ3
FH2
FVD
2FQ
2
1397
8.6
6164.5
1418
6.5
8571
17000
, ( )遮蔽扉 気密扉 気密は地上開口部で取ってもよい
1630
0
20800
1180
0
20800
5300
21x5.5=115.5m2
21x12=252m2
21x16.5=346.5m2
25800
7000
34x16=544m2
15800
3380
0
20t 2クレーン 基
inward beam extraction proton line with SC combined- function magnets variable off-axis angle between 2-3 degrees 130m long decay section a near detector at 280 m another detector planned at 2km
December 1, 2005 Shin'ya Sawada @ Hadron Structure at J-PARC
12
Osc. Prob.=sin2(1.27m2L/E)
m2=3x10-3eV2
L=295km■ WBB (=0) with an intentionally misaligned beam line from the detector axis ==> Quasi monochromatic beam with higher Intensity than NBB os
c.m
ax.
E
Off-axis Beam
Target Decay Pipe
Super-K.Horn
OA3°
OA0°OA2°
OA2.5°
flux
@ S
K<= On axis
December 1, 2005 Shin'ya Sawada @ Hadron Structure at J-PARC
13
Hadron Physics Facility- Slow Extracted Beam -
December 1, 2005 Shin'ya Sawada @ Hadron Structure at J-PARC
14
Slow Extraction Beamline (Phase 1)
NP-HALL56m(L)×60m(W)
50-GeV PS
T1 Target
30% LossBeam Dump
750kW
Switch Yard A-Line
T0 Target
0.5% Loss
Split Point
2% Loss
December 1, 2005 Shin'ya Sawada @ Hadron Structure at J-PARC
15
Hadron Hall
December 1, 2005 16
T1 Target R&D (by Yamanoi)
Beam
Ttarget disk5.4cm Thick50cm Diam.
Cooling water
~18m
~10m
Beam
2mWaterpump
December 1, 2005 Shin'ya Sawada @ Hadron Structure at J-PARC
17
Water Pipe (SUS)8.4 Sv/h2.4 Sv/h
5m
T1 Vessel2.2 Sv/h850 mSv/h Collimator
380 mSv/h100 mSv/h
Beam
Concrete7.9 Sv/h0.03 Sv/h
Collimator710 mSv/h420 mSv/h
q1B110 mSv/h49 mSv/h
Iron Base560 mSv/h210 mSv/h
Service Space
Trench
30Days Operation/1Day Cooling1Year Operation/Half Year Cooling
D1530 mSv/h270 mSv/h
Q162 mSv/h33 mSv/h
T1 Target650 Sv/h230 Sv/h
Vacuum DuctSUS 3.2 Sv/h 1.2 Sv/hTi 1.1 Sv/h 97 mSv/h
Vacuum Seal30 Sv/h11 Sv/h
Residual DoseConcrete5.3 mSv/h1.6 Sv/h
Iron60 Sv/h11 Sv/hIron
430 Sv/h160 Sv/h
Iron1.1 mSv/h460 mSv/h
Iron170 mSv/h460 mSv/h
December 1, 2005 Shin'ya Sawada @ Hadron Structure at J-PARC
18
Upstream of Secondary Beam Lines
Magnets → Upstream Collimator Beam Ducts → Big Vacuum Chamber instead of Ducts
How to solve 200kW Heat Problem?
Ni target (10kW)
D1(7.2kW) Q1(<1kW)
Beam
K1.8
Cu collimator(76kW)
2.4mDump
Vacuum Chamber
Cu collimator(55kW)
2.9m K1.1 KL
December 1, 2005 Shin'ya Sawada @ Hadron Structure at J-PARC
19
Big Vacuum ChamberService Space Vacuum
Chamber
5m
Collimator
Magnet
Iron Block
Concrete Block
Beam
T1 Target
•Shield blocks are also inside the vacuum chamber.•Each magnet/collimator has module structure unified with shield blocks.•Chamber lid is at the service space level.•Electric power and cooling water are provided from the service space.
December 1, 2005 Shin'ya Sawada @ Hadron Structure at J-PARC
20
5050mm
Phase 2 Phase 3
Phase 1
Beam Dump: Traveling to 50m downstream for Phase 2
• 1000ton ( Full Weight including Core, Shield, Cooling---)
• Traveling should be completed within 1 day (eight hours)
beambeam
December 1, 2005 Shin'ya Sawada @ Hadron Structure at J-PARC
21
BeamDump
• 750kW Heat/Radiation Load
• Movable!Proton Proton beambeam
Service Service spacespace
CuCuFeFe
ConcreConcretete
9.5m9.5m
6m6m99mm
(背面(背面図)図)
(正面(正面図)図)
December 1, 2005 Shin'ya Sawada @ Hadron Structure at J-PARC
22
Heat analysis by MARS & ANSYS (calculated by A. TOYODA & M. MINAKAWA)
Proton beam
Cu:6900
mm
Fe:1050
mm3000mm
ビーム入口Φ350mm
Tmax:202℃
熱伝達係数:1000W/m2 ・ K
6300mm
1000mm
• 無酸素銅– ρ=8.9[g/cm3]– 熱伝導率 390 [W/m/K]
Proton beam50GeV-15A
(750kW)
December 1, 2005 Shin'ya Sawada @ Hadron Structure at J-PARC
23
Maintenance
Maintenance Maintenance SpaceSpace
Pillow Pillow SealSeal
Ex. Ex. DuctDuct
Water Water ManifoldManifold
Vacuum
Exhaust
December 1, 2005 Shin'ya Sawada @ Hadron Structure at J-PARC
24
Structure of traveling devices
Complete remote operation with just LAN Cable!
beambeam電源・油圧ユニット
December 1, 2005 Shin'ya Sawada @ Hadron Structure at J-PARC
25
K1.8 and K1.8BR
ES1
ES2
MS2MS1
IF-window
TG-window
FF
SKS+SPES-II
December 1, 2005 Shin'ya Sawada @ Hadron Structure at J-PARC
26
K1.1/0.8 Beam Line (S-Type) and KL
MS2
MS1
IF
FF
T1
ES1
ES2
C-Type
December 1, 2005 27
Beamline Parameters
K1.8 K1.8BR K1.1 (S-Type)
Max. Mom. ~2 GeV/c 1.2 GeV/c 1.1 GeV/c
Length 45.853 m 17.573 m 27.05 m
Acceptance 1.4 msr.% 2.5 msr.% 4.1msr.% \
Intensity(ppp)#
K- (×106) K- (×106) K- (×106) K+ (×106)50GeV15A 30GeV9A 50GeV15A 30GeV9A 50GeV15
A30GeV9A 50-15 30-9
1.8 GeV/c 6.6 1.4
1.1 GeV/c 0.38 0.08 5.5 1.2 9.1 2.0 81 11
0.8 GeV/c 1.0 0.2 1.7 0.4 18 2.5
0.6 GeV/c 0.2 0.05 2.6 0.4
DC-Separator
750kV/10cm6m×2
500kV/10cm 6m
750kV/10cm 2m×2
K/$ 8 (1.8GeV/c) 6.9 7.5 (1.1GeV/c) 6.8 4.3(1.1GeV/c) 4.7
X/Ysize @ FF 19.8/3.2 mm(FWHM) 5.9/2.9 mm(FWHM) 10/6 mm(FWHM)
\ MS1 opening: ±1mm, MS2: ±2mm# using Sanford-Wang formula, assuming 1pulse=3.53s ( 0.7s flat top) $ Cloud are not taken into account.
December 1, 2005 Shin'ya Sawada @ Hadron Structure at J-PARC
28
Construction Schedule:
Magnets etc. at NP-Hall : 2007(H19)
2004(H16)
2003 (H15)
2005 (H17)
2006(H18)
KH:2006(H18)
Magnets etc. at SY:2006(H18)
:2008(H20)
The first Beam to NP-Hall : 2008(H20) -Beam :2009(H21)
SY:2005(H17)
December 1, 2005 Shin'ya Sawada @ Hadron Structure at J-PARC
29
Dates of Remember
• April 2005: We can start recycling magnets!– January 2005 : K2K shut down– December 2005 : KEK-PS shut down. The most of Hadron Hall construction team should take care of external beam lines of the KEK-PS until then.
• March 2006: We can start SY settings & The most magnets should be ready until then!• March 2007: We can start Hadron Hall settings.• Jan. 2008 (Nov. 2007?): Start of 50GeV-PS commissioning! • Sept. 2008: The construction should be completed (officially) &
The First External Beam!
December 1, 2005 Shin'ya Sawada @ Hadron Structure at J-PARC
30
Recycling of ν-line Magnets
December 1, 2005 Shin'ya Sawada @ Hadron Structure at J-PARC
31
Plan View
3.75°Bend -3.75°Bend
50-GeV BM (Proto-type)
7040
QFP inVEP
q01 q02 h03 h05
v04
q03 q04 q05h01
v02
Magnet Recycling in the Matching Section
18D72(SLAC)
v06
6D220,QC1,QC2(K2K/TRISTAN)
4C220(KEK-EP2)
December 1, 2005 Shin'ya Sawada @ Hadron Structure at J-PARC
32
Magnet Collection ProjectThe Latest Contribution for High-p Beamline
18D72 Magnet from FNAL/ANL
~4Tm, 150mm Gap,
40mm Pole Width
December 1, 2005 Shin'ya Sawada @ Hadron Structure at J-PARC
33
Summary
Neutrino Facility– Fast extracted beamline.– Expect first beam in 2009.
Hadron Facility– Slow extracted beamline.– Expect first bean in 2008.– At the day-1, we will have one primary beamline, one
production target, and one secondary beamline.– Other beamlines are under consideration.– The hadron hall should be extended to the downstream in
the (near) future.