J.V. Besix - Orascom Nile Corniche Project 31/01/2008 Page 1 of 9 BO-RE-LO-MR-001 Nile Corniche Project Substructure Package PK-1 Monthly Progress Report 31 st January 2008
-
Upload
hammam-el-meseiry -
Category
Documents
-
view
130 -
download
2
Transcript of Jan-Dec 2008
J.V. Besix - Orascom Nile Corniche Project
31/01/2008 Page 1 of 9
BO-RE-LO-MR-001
Nile Corniche Project Substructure Package PK-1
Monthly Progress Report
31st January 2008
J.V. Besix - Orascom Nile Corniche Project
29/02/2008 Page 1 of 9
BO-RE-LO-MR-002
Nile Corniche Project Substructure Package PK-1
Monthly Progress Report
29th February 2008
J.V. Besix - Orascom Nile Corniche Project
31/03/2008 Page 1 of 18
BO-RE-LO-MR-003
Nile Corniche Project Substructure Package PK-1
Monthly Progress Report
31P
stP March 2008P