Item 12 - Surrey...Government guidance (Circular 02/99) on EIA (50,000 tonnes per annum of waste for...
Transcript of Item 12 - Surrey...Government guidance (Circular 02/99) on EIA (50,000 tonnes per annum of waste for...
TO: PLANNING & REGULATORY COMMITTEE DATE: 24 April 2013
BY: PLANNING DEVELOPMENT CONTROL TEAM
MANAGER
DISTRICT(S) RUNNYMEDE BOROUGH COUNCIL ELECTORAL DIVISION(S):
Egham Hythe & Thorpe
Ms Lay
PURPOSE: FOR DECISION GRID REF: 503198 169070
TITLE:
MINERALS AND WASTE APPLICATION RU.12/0870
SUMMARY REPORT
Land north of Norlands Lane, Thorpe, Egham, Surrey
Retention of office, weighbridge, wheel wash, switch room and concrete apron until 31
December 2015 and use of them in connection with the backfilling with inert material and
restoration to agriculture on the land north of Coldharbour Lane.
This application has been submitted concurrently with planning application RU12/0872 which is
for continued infilling at Coldharbour Lane landfill. An overarching Environmental Statement
accompanies both planning applications.
The Norlands Lane and Coldharbour Lane mineral and landfill sites lie next door to each other at
Thorpe and share a common access which is a dedicated haul road from Chertsey Lane (A320)
to Norlands Lane. Both sites lie within the Green Belt. Norlands Lane landfill site has an
extensive planning history dating from the 1960’s. As part of mineral and landfilling activities at
the site plant, equipment and hardstanding were all installed as ancillary to the workings.
Norlands Lane landfill site has now been restored and is in aftercare. Whilst mineral working at
the adjoining Coldharbour Lane site has ceased and all associated plant and equipment for
mineral extraction has been removed, infilling of Coldharbour Lane landfill site with inert waste
to facilitate the restoration of that site is still continuing.
In 2007 planning permission was granted (ref: RU07/0987) to enable the retention of the
remaining elements of the Norlands Lane buildings and infrastructure adjoining the common
access road at the entrance to the site in connection with the infilling and restoration of
Coldharbour Lane landfill for the duration of activities at Coldharbour Lane landfill which at that
time was until December 2010.
Item 12
Page 177
However since that time the applicant has stated that the rates of infilling at Coldharbour Lane
landfill have fallen considerably and have resulted in a delay to the completion of filling and
restoration at Coldharbour Lane. The applicant is now seeking an extension of time until
December 2015 to complete infilling and restoration of the Coldharbour Lane landfill site. To
facilitate this, the applicant also needs the buildings and infrastructure located on land at
Norlands Lane landfill to remain on site for this proposed duration as ancillary structures to the
infilling and restoration of a mineral site. Officers are aware there has been some considerable
delay in the consideration of this application and application ref: RU12/0872 following the
expiration of planning permission in December 2010. More detail of this is set out in the main
body of the report however this has mainly been due to procedural matters.
This application was due to be reported to the 6 February 2013 Planning and Regulatory
Committee but was withdrawn. This was at the applicants request as it became apparent that
the vehicle numbers presented within the Planning Statement and Environmental Statement
(dated July 2012) were an incorrect representation of what Heavy Goods Vehicle (HGV)
movements had been entering/ egressing the application site being higher than that presented.
The County Planning Authority and County Highway Authority subsequently requested under
Regulation 22 of the Town and Country Planning (Environmental Impact Assessment)
Regulations 2011 the applicant submit a Transportation Statement as an appendix to the
overarching Environmental Statement assessing the implications of a higher HGV figure on the
public highway. The applicant submitted a Transport Statement in March 2013 and this
underwent consultation. The County Highway Authority having reviewed the Transport
Statement have raised no objection subject to a condition restricting vehicle movements to the
site on a weekly basis.
Officers consider that the continual use of the existing buildings and infrastructure should have
no significant adverse impact on the local environment and on local amenity, subject to the
imposition of appropriate conditions. Highway works and measures to safeguard the highway
are already in place and no increases in traffic levels result from the proposals in the application.
With regard to the site’s position within the Green Belt, Officers recognise the proposal harms
openness to the Green Belt as the proposal retains on site physical structures that are not listed
in the NPPF as being appropriate or being associated with agricultural activities. Whilst Officers
recognise the application elements harm openness, the structures and plant are a necessary
component to assist in facilitating the restoration involving infilling with imported waste material
of Coldharbour Lane in the form of being the access into the site alongside the weighbridge and
wheel wash. Officers consider the development is not inappropriate development as the
proposal is ancillary to the restoration of a mineral working such that the restored landform does
not conflict with the purposes of including land in the Green Belt and preserves openness. No
letters of representation have been received for this planning application. The Thorpe Ward
Residents Association have raised concerns with regard to the delay in the restoration of
Coldharbour Lane.
The recommendation is, subject to the prior completion of a S106 planning obligation, to
PERMIT subject to conditions.
Page 178
APPLICATION DETAILS
Applicant
Cemex UK Operations Ltd
Date application valid
14 August 2012
Period for Determination
4 December 2012
Amending Documents
Letter dated 14 November 2012 and accompanying restoration and aftercare scheme dated
2012 and Plan P4/193/33, email dated 14 November 2012; Outline Restoration and Five Year
Aftercare Scheme for the Access Road dated January 2013 and accompanying plans P4/193/34
“Haul Route Restoration Detail” and L/FE/25 “Field Gate 3.6m Wide”, letter dated 22 January
2013; letter dated 18 March 2013 and accompanying Transport Statement.
SUMMARY OF PLANNING ISSUES
This section identifies and summarises the main planning issues in the report. The full text
should be considered before the meeting.
Is this aspect of the
proposal in accordance with
the development plan?
Paragraphs in the report
where this has been
discussed
Green Belt Yes 39 – 46
Environment and Amenity Yes 47 – 56
Page 179
Traffic and Access Yes 57 - 64
ILLUSTRATIVE MATERIAL
Site Plan
Plan
Aerial Photographs
Aerial
Site Photographs
Photograph 1: Access road into the site
Photograph 2: Concrete bays within the site
Photograph 3: Weighbridge and site office
BACKGROUND
Site Description
1. The application site is the southern extent of the former Norlands Lane landfill site
immediately abutting Norlands Lane to the south. Aside from the road to the south, the
application site is surrounded on all other sides by the former landfill. The application site
is located approximately 2km south east of Egham and 2km south west of Staines and
lies to the north east of Thorpe Village. The application site lies within the Metropolitan
Green Belt. The Thorpe Hay Meadow Site of Special Scientific Interest (SSSI) lies
approximately 680m north east and the River Thames Site of Nature Conservation
Interest (SNCI) lies approximately 950m to the east. Approximately 200m to the south of
the application site beyond the village of Thorpe lies the Thorpe Park No. 1 Gravel Pit
SSSI and Special Protection Area (SPA) covering St Ann’s Lake. The eastern edge of
Page 180
the Thorpe Village Conservation Area lies approximately 20m to the west. Coldharbour
Lane landfill is situated approximately 160m to the west.
2. The access road serving Coldharbour Lane landfill runs through the application site in a
north/ south direction towards the A320 Chertsey Lane/ Staines Road. The application
site has an area of approximately 0.67 hectares. The application site comprises of an
area of concrete hardstanding, concrete bays, office, a weighbridge, wheel wash and
perimeter gates.
Planning History
3. Norlands Lane quarry and landfill has a long planning history. Planning permission was
granted to extract sand and gravel from land north of Norlands Lane and south of Green
Lane in the 1960’s and 1970’s. Planning permission to infill the mineral void space with
predominantly household, commercial and inert waste was granted in the early 1980’s.
Landfilling took place from this point and was completed by the early 2000’s. In March
1999 an application (Ref: RU99/0288) was submitted to merge the Coldharbour Lane
site with the Norlands Lane landfill to the east resulting in a comprehensive restoration
over some 54 hectares. Permission was refused in February 2000 and a subsequent
appeal dismissed in 2003 mainly due to concerns over odour. Restoration of the site was
completed in 2003 and seeding completed in 2004. Aftercare for the site commenced in
2005 in which the site is used for light grazing and/ or hay production. There is a pro-
active gas management system linked to generators that utilises the gas produced within
the landfill to generate electricity.
4. The most recent and relevant planning permissions for this site include:
• Planning permission ref: RU07/0987 was granted in November 2007 for the retention of
office, weighbridge, wheel wash, switch room, and concrete apron until 31 December
2010 and the use of them in connection with the backfilling of Coldharbour Lane landfill
with inert waste
• Planning permission ref: RU03/1270 was granted in February 2004 for a variation of
Condition 3 of planning permission ref: RU93/0032 to allow the continued importation of
inert waste and soil for a further period of 12 months and retention of office, weighbridge
and other ancillary items for this period.
• Planning permission ref: RU03/1204 was granted in December 2003 for the installation
of a landfill gas engine for the production of electricity
5. In 2010 two planning applications were submitted to the County Planning Authority
seeking
a) an extension of time for back filling of the mineral void space at Coldharbour Lane landfill
site with inert waste until December 2012 (ref: RU10/0818); and
Page 181
b) retention of the office, weighbridge, wheel wash, switch room and concrete apron until 31
December 2012 in conjunction with the infilling of the landfill site (ref: RU10/0832)
6. Advertising the application, notification of neighbouring residential properties and
consultation with statutory consultees took place in August 2010. On 8 September 2010
the County Environmental Assessment Team adopted a Regulation 7 Screening Opinion
in accordance with the (then) Town and Country Planning (Environmental Impact
Assessment (EIA))(England and Wales) Regulations 1999 (now 2011) as no Screening
Opinion had been sought by the applicant from the County Planning Authority prior to the
submission of the planning applications. The Screening Opinion concluded that the two
proposals constituted EIA development as they exceeded the thresholds within the
Government guidance (Circular 02/99) on EIA (50,000 tonnes per annum of waste for
infilling). As such an overarching Environmental Statement was requested from the
applicant.
7. On 22 September 2010 the applicant sought a Screening Direction from the Secretary of
State under Regulation 6 of the EIA Regulations 1999 to make a screening direction on
the matter of whether or not the development as described above is EIA development
within the meaning of the 1999 Regulations. The Secretary of State issued their decision
on 10 November 2010 confirming the proposal was EIA development and that an
Environmental Statement be submitted to accompany the planning application. An
Environmental Statement was submitted in February 2011 and further consultation took
place on this.
8. In March 2011 the applicant submitted a request for a Scoping Opinion under Regulation
10 of the EIA Regulations 1999 and the County Planning Authority issued their Scoping
Opinion on 3 May 2011. The applicant subsequently submitted a revised Environmental
Statement in December 2011. Further information was subsequently requested from the
applicant by the County Planning Authority on the Environmental Statement.
Consequently due to the passage of time and the slow down in filling rates at
Coldharbour Lane landfill, the applicant withdrew both planning applications RU10/0818
and RU10/0832 and resubmitted the two proposals again with a new Environmental
Statement and Planning Statements requesting an extension of time for infilling of
Coldharbour Lane landfill until 31 December 2015 to reflect this.
THE PROPOSAL
9. Coldharbour Lane landfill currently operates using an office, weighbridge, wheel wash,
switch room and concrete apron all located on land which was used in connection with
the former Norlands Lane landfill site. These aspects are ancillary to the operation of
Coldharbour Lane landfill and can be seen in Photograph 3. The applicant seeks
retention of these elements until 31 December 2015 in conjunction with planning
Page 182
application ref: RU12/0872 which is seeking an extension of time for infilling of the void
space at and restoration of Coldharbour Lane landfill. The applicant states that on
cessation of infilling and restoration of Coldharbour Lane landfill all of the elements
outlined above would be removed and the application area, along with the dedicated
internal access route would be restored.
10. Hours of working would remain as those previously used at the site being Monday –
Friday 07:00 – 18:00 hours; and Saturday 07:00 – 13:00 hours with no working on
Sundays, Bank and National Holidays. The applicant has stated that aside from infilling
activities at Coldharbour Lane landfill, no other production processes would take place
on site. The proposal does not seek to alter traffic movements to/ from the site.
CONSULTATIONS AND PUBLICITY
District Council
Runnymede Borough Council
11. - Planning : No objection
12. - Environmental Health : No comments
Consultees (Statutory and Non-Statutory)
13. Health and Safety Executive : No objection
14. BAA Aerodrome Safeguarding : No objection
15. The Environment Agency South East : No objection
16. Natural England : No objection
17. Surrey Wildlife Trust : No comments received
18. Thames Water : No objection
19. Veolia Water Partnership : The site is located within the groundwater
Source Protection Zone (SPZ)
corresponding to Chertsey pumping
station. This is a public water supply. The
construction works and operation of the
proposed development should be done in
accordance with the relevant British
Page 183
Standards and Best Management
Practice to reduce groundwater pollution
risk. If any pollution is found at the site
then the appropriate monitoring and
remediation methods will need to be
undertaken.
20. English Heritage : No objection
21. County Geological Consultant : Can only assume flooding and drainage
dealt with at time of the original
application, through planning conditions
and in the Environmental Permit.
22. County Noise Consultant : No objection
23. County Air Quality Consultant : On the basis that the proposal only
relates to a time extension, there is no
potential air quality effects. No objection.
The recent Transport Statement does not
affect previous advice.
24. County Ecologist : No comments to make
25. Environmental Assessment Team : The Environmental Statement is
compliant with the regulations
26. County Highway Authority : No objection subject to a condition
limiting the number of Heavy Goods
Vehicles accessing the site to no more
than 660 per week with no one day to
exceed 176.
27 Rights of Way : No objection
28 County Archaeologist : No objection
29 County Historical Buildings Officer : No comments made on this application
30. County Landscape Architect : Is satisfied with the restoration scheme
and the haul road restoration scheme
Parish/Town Council and Amenity Groups
31. Thorpe Ward Residents Association : Concerned by delay in restoration
Summary of publicity undertaken and key issues raised by public
Page 184
32. The application was publicised by the posting of three site notices and an advert was
placed in the local newspaper. A total of 44 owner/ occupiers neighbouring properties
were notified. No letters of representation have been received on this application.
Following the receipt of the Transport Statement as amending information, the
application was subsequently published and advertised in accordance with Regulation
22 of the Town and Country Planning (Environmental Impact Assessment) Regulations
2011. This included the posting of three site notices and an advert was placed in the
local newspaper. A total of 44 owner/ occupiers of neighbouring properties were also re-
notified of the amending information. To date no letters of representation have been
received.
PLANNING CONSIDERATIONS
33. The County Council as Waste Planning Authority (for clarity, Officers refer to the County
Council as the County Planning Authority – ‘CPA’ elsewhere in this report) has a duty
under Section 38 (6) of the Planning and Compulsory Purchase Act 2004 and Section
70(2) of the Town and Country Planning Act 1990 to determine this application in
accordance with the Development Plan unless material considerations indicate
otherwise. At present in relation to this application the Development Plan consists of the
Surrey Minerals Plan 2011; the Surrey Waste Local Plan 2008 (SWP 2008), as
amended; and the Runnymede Borough Local Plan 2001 ‘Saved’ Policies.
34. On the 27 March 2012 Government published the National Planning Policy Framework
(NPPF) and Technical Guidance to the National Planning Policy Framework (NPPF Technical Guidance), which took immediate effect. The NPPF replaces 30 Planning Policy Statements, Planning Policy Guidance Notes, Minerals Policy Statements and Minerals Policy Guidance Notes and related Practice Guides, some Circulars and letters to Chief Planning Officers and constitutes guidance for local planning authorities and decision-takers in relation to decision-taking (determining planning applications) and in preparing plans. Planning Policy Statement 10 (PPS10) Planning for Sustainable Waste Management (re-published March 2011) remains in place and in time will be replaced by national waste planning policy published as part of the National Waste Management Plan.
35. At the heart of the NPPF is a presumption in favour of sustainable development, which
the document states “should be seen as a golden thread running through both plan-making and decision-taking.” The NPPF makes clear the purpose of the planning system is to contribute to the achievement of sustainable development, which has three dimensions: economic, social and environmental. These give rise to the need for the planning system to perform a number of mutually dependent roles: an economic role, a social role and an environmental role. The NPPF sets out 12 core land-use planning principles that should underpin both decision-taking and plan making.
36. The NPPF does not change the statutory principle referred to above that determination
of planning applications must be made in accordance with the adopted development plan unless material considerations indicate otherwise. The NPPF is one of those material considerations. The NPPF includes transitional provisions for implementation of the
Page 185
NPPF. For 12 months from the date of publication (27 March 2012) planning authorities can continue to give full weight to relevant policies in adopted development plan documents adopted in accordance with the Planning and Compulsory Purchase Act 2004 since 2004, even if there is a limited degree of conflict with policy in the NPPF. In other cases and following the 12-month period the weight to be given to policies in the adopted development plan documents should be determined according to their degree of consistency with the NPPF.
37. Runnymede Borough Council currently do not have an adopted Core Strategy or sites
allocation Development Plan Document. Consultation has recently finished on the pre-submission version of the Local Plan. A detailed Local Development Scheme is anticipated to be presented to a forthcoming planning committee and this document will provide dates of the development of the Local Plan Core Strategy as well as other documents. In circumstances where a development plan is being prepared or undergoing review, it may be justifiable to refuse planning permission on the grounds of prematurity where to grant planning permission would prejudice the outcome of the plan process and predetermine decisions on scale, location or phasing of development proposals which should be made in the context of the development plan. Officers do not consider that the proposal prejudices the emerging LDF Core Strategy, due to the scale and location of the facility.
38. In assessing the application against development plan policy it will be necessary to
determine whether the proposed measures for mitigating any environmental impact of the development are satisfactory. Key issues to consider include Green Belt, access and the impact from traffic generated by the proposal, the impact on local amenity and the environment in terms of landscape, noise, visual impact, dust and flood risk.
GREEN BELT
Surrey Minerals Plan Core Strategy 2011
Policy MC3 – Spatial strategy – mineral development in the Green Belt
Policy MC17 – Restoring mineral workings
Policy MC18 - Restoration and enhancement
Runnymede Borough Local Plan 2001
Policy GB1 – Development within the Green Belt
39. Norlands Lane landfill site lies within the Green Belt where policies of restraint apply.
Government guidance on Green Belt is set out within the NPPF which states at para 79
that “the fundamental aim of Green Belt policy is to prevent urban sprawl by keeping land
permanently open; the essential characteristics of Green belts are their openness and
their permanence”. Para 80 of the NPPF sets out the five purposes of the Green Belt of
which assist in safeguarding the countryside from encroachment is the most relevant to
this application. There is a presumption against development other than for a small
range of uses deemed to be compatible with the objectives of the Green Belt. Paragraph
90 of the NPPF states that certain forms of development are not inappropriate
development in the Green Belt provided they preserve the openness of the Green Belt
and do not conflict with the purposes of including land in Green Belt. This includes
mineral extraction.
Page 186
40. Policy MC3 of the Surrey Minerals Plan Core Strategy 2011 refers to mineral extraction
but also states that proposals in the Green Belt for mineral development other than
extraction and primary treatment, will only be permitted where the applicant has
demonstrated that very special circumstances exist to outweigh the harm by reason of
inappropriateness and any other harm. Whilst there are no policies within the Surrey
Waste Plan 2008 that are relevant to this proposal in terms of Green Belt, paragraph B46
of the Surrey Waste Plan 2008 recognises that minerals can be worked “only where they
are found” and that mineral working need not be inappropriate development provided
“that high environmental standards are maintained and that the site is well restored”. The
paragraph goes on to state that landfill is most often the means to that restoration and
that “neither landfill nor landraising activities need conflict with the purposes of including
land in the Green Belt. Both can play a positive role in the objectives of the Green Belt:
the after use of a site may provide the opportunities for access to restored open
countryside or improve damaged land around a town”.
41. Policy GB1 of the Runnymede Borough Local Plan contains a strong presumption
against development that would conflict with the purposes of the Green Belt or adversely
affect its open character.
42. Officers recognise the proposal harms openness to the Green Belt as the proposal
retains on site physical structures that are not listed in the NPPF as being appropriate or
being associated with agricultural activities. The structures, hardstanding, buildings and
equipment harm Green Belt openness. However, these are there as they are directly
linked, and are ancillary to, the restoration of the adjoining landfill and by their nature are
temporary. Officers consider that all elements are necessary to facilitate the restoration
and cannot be located elsewhere outside of the Green Belt given the extent of the Green
Belt in the area and the need for the facilitates to be located in close proximity to the
activities they relate to. Without the structures, hardstanding, buildings and equipment at
the application site, restoration of Coldharbour Lane landfill would be unachievable.
Officers are satisfied that the structures and plant are the minimum required to facilitate
restoration and there are no elements surplus to requirements. The retention of these
remaining facilities would remove the need to provide them elsewhere, which would have
a similar impact on the Green Belt. There are also practical reasons for using the
application site in terms of traffic management and control.
43. Officers recognise the current proposal in effect seeks an extension of five years after
the date when the structures, buildings, hardstanding and equipment should have been
originally removed. However, Officers recognise that the need for an extension in time to
retain these elements has been brought about by delays in completing infilling at
Coldharbour Lane landfill to which Officers are satisfied with the applicant’s reasons.
Officers recognise that due to the ancillary nature of the structures, buildings,
hardstanding and equipment that are the subject of this application, that retention of
these structures is necessary to facilitate restoration of Coldharbour Lane landfill. Whilst
their retention causes temporary harm to the openness of the Green Belt Officers
consider the benefits of facilitating the restoration of Coldharbour Lane landfill outweigh
Page 187
this temporary harm and otherwise do not conflict with the purposes of including land in
the Green Belt and preserve openness in the long term. Accordingly Officers are
satisfied that the proposal meets the requirements set out in the NPPF and in Policy
MC3 of the Surrey Minerals Plan Core Strategy 2011 and the text within paragraph B46
of the Surrey Waste Plan 2008.
Restoration
44. Policy MC17 of the Surrey Minerals Plan 2011 Core Strategy requires that restored
mineral sites should be sympathetic to the character and setting of the wider area and
capable of sustaining an appropriate afteruse. The policy goes on to state that
restoration of mineral workings should be completed at the earliest opportunity and
progressive restoration will be required where appropriate. Policy MC18 (Restoration and
enhancement) encourages the mineral planning authority to work with mineral operators
and landowners to deliver benefits such as enhancement of biodiversity interests,
improved public access and provision of climate change mitigation as part of restoration
proposals.
45. The applicant has provided details of how the application site would restored and what
aftercare arrangements would be in place for a period of 5 years post restoration. The
applicant states that the application area would be cleared of all plant, structures and
machinery with a small section of concrete remaining at the entrance to protect the
public highway. The rest of the concrete hardstanding would be removed by a dumper
and excavator. Once the application area has been cleared of all plant, structures,
concrete and waste material the applicant states that the land would be ripped to reduce
compaction and periphery soils replaced and the land seeded with a seed mix that would
complement the Norlands Lane landfill.
46. The current internal haul road that connects Coldharbour Lane landfill site with Norlands
Lane running through the application site would be retained to provide a means of
access to both landfill sites for aftercare reasons. However the concrete that currently
forms the internal haul road would be removed and the applicants intention is that the
retained haul road would resemble that of a farm track being single carriageway width
with over grown grass margins. The County Landscape Architect has reviewed the
proposed restoration and aftercare scheme for the internal haul road and considers the
scheme and design to be acceptable and raises no objection.
ENVIRONMENT AND AMENITY
Surrey Waste Plan 2008
Policy DC3 – General Considerations
Page 188
Surrey Minerals Plan Core Strategy 2011
Policy MC14 – Reducing the Adverse Impacts of Minerals Development
47. Development plan policies seek to protect the local environment and the amenities of
local residents from adverse effects from development. Both Policy DC3 (General
Considerations) of the Surrey Waste Plan 2008 and Policy MC14 of the Surrey Minerals
Plan Core Strategy 2011 require appropriate information to be submitted for waste
related development proposals to demonstrate that any impacts of the development with
regard to a number of criteria including visual impact, dust and noise can be controlled to
achieve levels that will not significantly adversely affect people, land, infrastructure and
resources. The main issues are considered to be occasions of noise and dust, together
with the visual impact of the continued use of the existing buildings and infrastructure for
a further three years alongside potential issues surrounding flooding; and whether any
such occurrences would justify the construction of duplicate facilities a short distance
away within the Coldharbour Lane site or further away from site.
Environmental Assessment
48. This application was accompanied by an overarching Environmental Statement
alongside planning application RU12/0872. The application was considered EIA
development due to the volume of material that required importation on an annual basis.
The Environmental Assessment team have reviewed the Environmental Statement and
the Transport Statement and have commented that it is compliant with the EIA
Regulations 2011. Additionally due to the proximity of the application site to the Thorpe
Park No. 1 Gravel Pit SPA and RAMSAR site there is a requirement on the County
Planning Authority to consider whether an appropriate assessment is required. The
Environmental Assessment team have undertaken this review and have concluded that a
full Habitats Regulations Assessment is not required in this case. This Habitats
Regulations Assessment Screening Report was adopted on 14 November 2012. Natural
England have commented that this proposal, is not likely to have a significant effect on
the interest features for which South West London Waterbodies SPA/RAMSAR have
been classified and have advised that an Appropriate Assessment is not required
Flooding
49. The proposal seeks to retain plant and equipment on an area of concrete hardstanding
at Norlands Lane landfill site. This plant and equipment have been at the application site
for some time previously being used in connection with operations at Norlands Lane
landfill and then latterly with landfilling at Coldharbour Lane landfill. Retention and their
use was originally granted planning permission in 1997. The proposal does not seek to
extend the hard surfacing area or alter it, or amend the structures that are already in
place at the site. The proposal seeks to retain them for a longer period after which the
site would be restored in accordance with the restoration details provided, back to
Page 189
agriculture. The application site, however, lies within Flood Zone 3 which is an area with
a high probability of flooding.
50. The NPPF replaced Planning Policy Statement 25 (PPS25) in March 2012. The main
principle of PPS25 was that inappropriate development in areas at risk of flooding should
be avoided by directing development away from areas at high risk using the Sequential
Test and this has been carried forward into the NPPF. The NPPF also states at para 100
that development proposals should not increase flood risk elsewhere. In accordance
with Table 2: Flood risk vulnerability classification within the NPPF “Technical Guidance
to the National Planning Policy Framework” 2012, waste treatment (this application does
not relate specifically to landfilling, but to the ancillary components which are needed to
be retained to ensure landfilling at Coldharbour Lane can continue please see
application RU12/0872) is classified as a less vulnerable use. In accordance with Table
3: Flood risk vulnerability and flood zone ‘compatibility’ less vulnerable development is
appropriate within Flood Zone 3. The Environment Agency had commented within the
Scoping Opinion for the overarching Environmental Statement that they did not envisage
any significant impact on fluvial flood risk or surface water flooding and they have raised
no objection to this proposal.
Noise
51. The NPPF requires that decisions taken should not result in significant adverse impacts
on health and quality of life with regard to noise and that mitigation measures should be
used. The proposal seeks to retain the structures and set up at the application site as
previously permitted under RU07/0987. In terms of noise, apart from the lorries
themselves which are already required to pass through this area to reach the
Coldharbour Lane landfill site, the other generator of noise is likely to be the use of the
wheel wash on leaving the site. This, however, has been in operation for many years
with the working and then filling of the Norlands Lane landfill site without giving rise to
complaint. Officers have no reason to suspect that there should be any increase or
change in noise from the proposal as it does not seek to change activities from that
previously carried out. The nearest properties comprise one house in Norlands Lane
some 80m away behind an existing bund and nine in Redwood some 130m to 175m
away. The original noise condition relating to the application site would be imposed on
any further consent.
52. Elevated noise levels could also be experienced when the application area commences
restoration in terms of the removal of hardstanding and bunds. The NPPF technical
guidance for mineral development proposals at para 31 states that for particularly noisy
short term activities that cannot meet the limits set for normal operations, a noise limit of
up to 70dB(A) Laeq 1h (free field) for periods of up to 8 weeks in a year should be
considered to facilitate essential restoration work. Officers note that no such condition
was imposed on planning permission ref: RU07/0987 and recommend one being
included now. The County Noise Consultant has commented that he does not consider
noise to be a significant problem and that the work can be completed within the
appropriate site noise limits.
Page 190
53. Officers recognise that the proposal would result in a continuation of activities at the
application site for a further period of five years of which just under three years remains.
However, given the limited duration of the proposal and that the activities undertaken at
the application site have not given rise to noise complaints, Officers are satisfied that the
proposed extension of time should not cause significant harm with regard to noise to the
environment or residents both on its own and in combination with other activities within
the area.
Dust
54. he NPPF technical guidance recognises that unavoidable dust emissions should be
controlled, mitigated or removed at source. All lorries entering the application site with fill
material are required to be sheeted to prevent dust being a problem beyond the
boundaries of the site. A wheel wash is used on site to prevent any deleterious material
being tracked from the site onto the public highway thereby reducing the risk for dust.
The applicant has also stated that a water bowser would be used on site to dampen
down any surfaces when required. The County Dust Consultant has raised no objection
to the proposal and has no concerns. Officers are satisfied that the proposal should not
lead to any significant adverse harm with regard to dust emissions.
Visual Impact
55. The components of this planning application are the office, wheel wash, weighbridge,
hardstanding and concrete bays. These can all be seen within the accompanying
photographs. These are all small in scale and low in height. The site is well screened by
vegetation and perimeter bunds which prevent views into the application site of these
elements and this landscaping would remain in place for the duration of the proposal.
The applicant has provided a restoration and aftercare scheme that provides detail of
how the site would be restored and this is detailed above at paragraph 45 of this report.
The applicant states the application site would be restored by 31 December 2015 and
this would include removing all plant and structures from the application site. The site
would then be restored to enable the site to integrate with the adjoining Norlands Lane
landfill site which was restored in
56. Officers are satisfied that retention of these elements are necessary to facilitate the
restoration of Coldharbour Lane landfill site. Given the application site’s boundary
treatment in the form of established vegetation and bunds, Officers do not consider
retention for the further period of the plant and structures would result in a significant
adverse landscape and visual impact for the remaining three years sought, following
which the application site would be restored.
Page 191
TRAFFIC AND ACCESS
Surrey Waste Plan 2008
Policy DC3 – General Considerations
Surrey Minerals Plan Core Strategy 2011
Policy MC15 – Transport for Minerals
Runnymede Borough Local Plan 2001
Policy MV4 – Access and Circulation Arrangements
57. Surrey Waste Plan 2008 Policy DC3 requires the submission of appropriate information
for waste related development proposals with regard to traffic generation, access and the
suitability of the highway network in the vicinity to demonstrate that any impacts of the
development can be controlled to achieve levels that will not significantly adversely affect
people, land, infrastructure and resources. The policy requires appropriate mitigation to
be identified if necessary. Surrey Minerals Plan Core Strategy 2011 Policy MC15
(Transport for Minerals) states that minerals development involving transportation by
road will be permitted only where there is no practicable alternative to the use of road
based transport, the highway network is of an appropriate standard for use by the traffic
generated; and arrangements for site access and the traffic generated by the
development will not have a significant adverse impact on highway safety, air quality,
residential amenity, the environment or effective operation of the highway network.
58. Policy MV4 of the Runnymede Borough Local Plan 2001 requires all development
proposals to comply with current highway design standards and seeks to ensure that
arrangements for access and circulation are appropriate to the type of development
proposed and the area in which it is located does not aggravate traffic congestion,
accident potential or environmental and amenity considerations.
59. Vehicles enter the application site by a dedicated access point off Norlands Lane as can
be seen on the photographs appended to the report. HGVs entering and leaving the
application site must use the dedicated haul road which goes from Norlands Lane to
Chertsey Lane to the south via the historic Chertsey plant site. This requirement is set
out within a Section 106 Agreement which is to be carried forward as part of this
planning application and for Coldharbour Lane landfill proposal. Consequently there are
no HGV movements associated with this proposal which travel on Norlands Lane except
to cross over to it to go on the dedicated haul road. The application site also seeks the
retention of the wheel wash to ensure no deleterious material enters the public highway.
60. As set out within the report for Coldharbour Lane landfill which is elsewhere on the
agenda, the original Planning Statement and Environmental Statement purported that
there would be some 220 HGVs accessing the site per week (440 movements per
week). The application was assessed using that information. However prior to the
reporting of the application to the February committee, it came to the County Planning
Authority’s attention that more than 220 HGVs were accessing the site per week. The
Page 192
County Planning Authority and County Highway Authority therefore requested that the
applicant provide a Transport Statement to show what HGV numbers had been
accessing the site since 2008 and to assess the impact of a greater number of HGVs on
the highway network than presented in the Planning Statement and Environmental
statement. The applicant has provided a Transport Statement setting out the existing
situation including access arrangements, the highway network and traffic patterns.
61. The Transport Statement sets out the average daily flow for the A320 is 12,262 (2011).
In design terms, a road such as the A320 can accommodate two way traffic flow of up to
2,200 vehicles per hour. The Transport statement also presents accident history for the
A320 from 2008 showing a total of 30 accidents (25 of which are slight).
62. The traffic data shows that whilst average weekly loads to the site prior to 2011 were
circa and below 220 HGVs per week, in 2011 and 2012 average weekly loads were 385
and 386 respectively per week. Daily data from 2012 indicates that the highest number
of inbound movements in any one day was 176 (352 two way movements) which
occurred on 12th April. The average number of loads per day was 79, equating to 158
movements. The busiest week was in March 2012 with 660 loads (1320 movements).
The traffic generated from the application site represents 1.43% of the daily flow of traffic
on the A320. The remaining void at the site is 240,730 tonnes, equating to a total of
12,037 loads (24,074 movements). By way of comparison, the total number of loads in
2012 was 19,979 (39,958 movements).
63. The County Highway Authority (CHA) have reviewed the proposal including the recently
submitted Transport Statement and they are satisfied that the Transport Statement
reflects an accurate picture of the HGV traffic generation from the site. The County
Highway Authority have commented that when the County Highway Authority considered
the application for sand and gravel extraction with restoration by landfilling in 1995, the
access was considered acceptable for 200 loads/ 400 movements per day (i.e. 2200
movements per week) and this proposal will not exceed that. Overall traffic flows on the
highway network have, however, increased since then. The County Highway Authority
confirm that there have been no complaints and they have not been notified of any
highways problems arising as a result of HGVs accessing the site over the past 12
months. The County Highway Authority raise no objection to the continuation of the
infilling at 2012 levels however, in order to ensure that the number of vehicles does not
exceed these levels, the County Highway Authority recommend a condition is attached
to the planning permission restricting the number of HGV inbound traffic movements to
660 per week (330 loads) with a daily cap of 176 movements (88 loads). This is to
accommodate the fluctuations as seen in 2012. As access to the site is gained to
Coldharbour Lane landfill site via Norlands Lane, Officers consider it appropriate that the
condition be imposed on this planning application as in doing so, this would be default
limit the number of HGVs accessing the Coldharbour Lane landfill site.
64. Officers recognise that the proposal would result in HGVs continuing to access the
application site for a period of 5 years beyond that originally envisaged, however these
Page 193
HGVs use a dedicated access road and gain access to an A road which can
accommodate this traffic. The County Highway Authority have also confirmed that the
application site has historically had 400 HGVs movements per day. Officers are satisfied
that subject to a condition limiting the number of HGV movements to the application site
that the proposal meets the requirements of the Development Plan with regard to traffic
and access.
HUMAN RIGHTS IMPLICATIONS
65 The Human Rights Act Guidance for Interpretation, contained in the Preamble to the
Agenda is expressly incorporated into this report and must be read in conjunction with
the following paragraph.
66. In this case, it is the Officers view that the scale of any impact is not considered sufficient
to engage Article 8 or Article 1 of Protocol 1 and any impact can be mitigated by
conditions. as such, this proposal is not considered to interfere with any Convention
right.
CONCLUSION
67. The proposal seeks to retain buildings, hardstanding, equipment and structures at the
application site for use in association with the adjoining Coldharbour Lane landfill site.
The structures were originally brought into use as part of the Norlands Lane landfill site
which is now restored and in aftercare. The structures and plant are ancillary to the
restoration activities that are taking place at Coldharbour Lane landfill to restore a former
mineral site. The application site is in the Green Belt. The NPPF states that mineral
extraction need not be inappropriate development provided the proposal preserves the
openness of the Green Belt. Paragraph B46 of the Surrey Waste Plan 2008 recognises
that landfilling or landraising activities that are a means of restoration of mineral sites
need not conflict with the purposes of including land in the Green Belt.
68. Officers recognise that the proposal harms the openness of the Green Belt by virtue of
the structures, hardstanding, equipment and structures being at the application site.
However, Officers are satisfied that these elements are necessary to assist the
restoration of Coldharbour Lane landfill site given that the application site provides the
means of access to Coldharbour Land landfill alongside the ancillary elements such as a
weighbridge, site office and wheel wash that are integral to the operation of a landfill site.
The proposal is temporary in nature and the applicant has provided details of restoration
of the application site following removal of the plant and structures. Officers are satisfied
Page 194
that the structures and plant cannot be located elsewhere outside of the Green Belt as
required by Policy MC3 of the Surrey Minerals Plan Core Strategy 2011.
69. Officers consider that any amenity or environmental impacts can be controlled by the
imposition of conditions. highway works and measures to safeguard the highway are
already in place and no increases in traffic levels are expected from the proposal.
RECOMMENDATION
The recommendation is, subject to the prior completion of a S106 Agreement, to PERMIT
subject to the following conditions
Conditions:
1. The development hereby permitted shall be carried out in all respects strictly in
accordance with the following plans/drawings:
P4/193/31 Site plan June 2007
P4/193/28B Reference with restoration plan for aftercare scheme May 2012
P4/193/33 Haul Road and Access Restoration November 2012
P4/193/34 Haul Route Restoration Detail
L/FE/25 Field Gate 3.6m wide”
2. The development hereby permitted shall cease on 31 December 2015 by which time all
buildings, fixed plant or machinery, internal access roads and hardstandings, together with
their foundations and bases shall have been removed from the land and the whole of the
site shall be restored.
3. No light shall be illuminated nor shall any operations or activities authorised or required by
this permission be carried out except between the following times:
0700 - 1800 hours Monday to Fridays
0700 - 1300 hours Saturdays; and
there shall be no working on Sundays, Public, Bank or National Holidays
Page 195
4. The applicant shall ensure that the wheels of all HGVs are cleaned before they exit the site
and shall make all reasonable efforts to keep the public highway clean and prevent the
creation of a dangerous surface on the highway.
5. There shall be no more than a total of 330 loads/ 660 inbound HGV movements per week
associated with the engineering, filling and restoration of Coldharbour Lane Landfill site
with no one day to exceed 88 loads/ 176 movements. The site operator shall maintain
accurate records of the number of HGV vehicles accessing the site daily and weekly and
shall make these available to the County Planning Authority on request.
6. The level of noise arising from any operation, plant or machinery on the site, when
measured at or recalculated as at a height of 1.2m above ground level and 3.6m from the
facade of any residential property or other occupied building which faces the site shall not
exceed 55 dB(A) Leq, during any 30 minute period
7. For temporary operations such as site preparation, soil and overburden striping, bund
formation and final restoration, the level of noise arising when measured at, or recalculated
as at, a height of 1.2 metres above ground levels and 3.6 metres from the façade of a
residential property or other noise sensitive building that faces the site shall not exceed 70
LAeq, during any 30 minute period. Such activities shall not take place for a total period
greater than eight weeks in any twelve month period.
8. All vehicles plant and machinery operated within the site shall be maintained in
accordance with the manufacturers specification at all times and where necessary shall be
fitted and used with effective silencers and/or noise insulation.
9. Oil or chemical storage tanks shall be sited on impervious bases and surrounded by a
liquid tight bunded compound; the bunded areas must be capable of containing 110% of
the volume of the largest tank and all fill pipes, draw pipes and sight gauges should be
enclosed within its curtilage. Any vent pipe should be directed downwards into the bund.
10. No activity hereby permitted shall cause dust to be emitted so as to adversely affect
adjacent residential uses and/ or other sensitive uses and/ or the local environment.
Should such an emission occur, the activity shall be suspended until, as a result of
different methods of working, the additional dust suppression measures or changed
weather conditions, it can be resumed without giving rise to that level of dust emissions.
Reasons:
Page 196
1. For the avoidance of doubt and in the interests of proper planning.
2. To comply with the terms of the application and to enable the County Planning Authority to
exercise planning control over the development pursuant to Surrey Waste Plan Policy DC3
and Surrey Minerals Plan 2011 Core Strategy Policy MC17
3. To comply with the terms of the application and to enable the County Planning Authority to
exercise planning control over the development pursuant to the Surrey Waste Plan 2008
Policy DC3 and Surrey Minerals Plan Core Strategy 2011 Policy MC14
4. In order that the development should not prejudice highway safety nor cause
inconvenience to other highway users pursuant to the Surrey Waste Plan 2008 Policy DC3
and Surrey Minerals Plan Core Strategy 2011 Policy MC16
5. To ensure the development should not prejudice highway safety nor cause inconvenience
to other highway users and to maintain HGV limits at 2012 levels.
6. To ensure the minimum disturbance and avoid noise nuisance to the locality and to comply
with Surrey Waste Plan 2008 Policy DC3 and Surrey Minerals Plan Core Strategy 2011
Policy MC14
7. To ensure the minimum disturbance and avoid noise nuisance to the locality and to comply
with Surrey Waste Plan 2008 Policy DC3 and Surrey Minerals Plan Core Strategy 2011
Policy MC14
8. To ensure the minimum disturbance and avoid noise nuisance to the locality and to comply
with Surrey Waste Plan 2008 Policy DC3 and Surrey Minerals Plan Core Strategy 2011
Policy MC14
9. To prevent pollution of the water environment and to comply with Surrey Waste Plan 2008
Policy DC3 and Surrey Minerals Plan Core Strategy 2011 Policy MC14
10. In the interests of local amenity, the environment and/ or human health pursuant to Surrey
Waste Plan 2008 Policy DC3 and Surrey Minerals Plan Core Strategy 2011 Policy MC14
Informatives:
Page 197
1. The applicants attention is drawn to Veolia's letter of 5 September 2012 with regard to
construction works and operation of the proposed development.
2. The County Planning Authority confirms that in assessing this planning application it has
worked with the applicant in a positive and proactive way, in line with the requirements of
paragraph 186-187 of the National Planning Policy Framework 2012.
THE TOWN AND COUNTRY PLANNING (DEVELOPMENT MANAGEMENT PROCEDURE)
(ENGLAND) ORDER 2010
Reasons for the grant of planning permission and development plan policies/proposals
relevant to the decision.
The development
1 will provide the following benefits: assist in facilitating the restoration of a former mineral
site
2 is in accordance with the development plan policies so far as they are relevant to the
application and there are no material considerations which indicate otherwise; and
3 any harm can be adequately mitigated by the measures proposed in the application and
Environmental Statement and the conditions subject to which planning permission is
granted.
The proposal has been considered against the following development plan policies/ provisions:
Surrey Minerals Plan 2011:
Policy MC3 – Spatial strategy – mineral development in the Green Belt
Policy MC14 – Reducing the Adverse Impacts of Minerals Development
Policy MC15 – Transport for Minerals
Policy MC17 – Restoring mineral workings
Page 198
Policy MC18 - Restoration and enhancement
Surrey Waste Plan 2008:
Policy DC3 – General Considerations
Runnymede Borough Local Plan 2001
Policy GB1 – Development within the Green Belt
Policy MV4 – Access and Circulation Arrangements
CONTACT
Samantha Murphy
TEL. NO.
020 8541 7107
BACKGROUND PAPERS
The deposited application documents and plans, including those amending or clarifying the
proposal, responses to consultations and representations received as referred to in the report
and included in the application file and the following:
Government Guidance
National Planning Policy Framework, March 2012
Technical Guidance to the National Planning Policy Framework, March 2012
The Development Plan
Surrey Minerals Plan Core Strategy 2011
Surrey Waste Plan 2008
Runnymede Borough Local Plan 2001
Page 199
Page 200