IT Weekly Report 20101102 (Peru)

download IT Weekly Report 20101102 (Peru)

of 37

Transcript of IT Weekly Report 20101102 (Peru)

  • 8/8/2019 IT Weekly Report 20101102 (Peru)

    1/37

    PERU IT WEEKLY REPORT

    OCT 25THTO 29TH , 2010

    TEAM SITE:HTTP://GOLDNETPERU/C6/BIBLIOTECA/IT%20WEEKLY%20REPORT%20PERU/FORMS/ALLITEMS.ASPX

    DISTRIBUTIONLIST DAVID GOLLAN, THOMAS SAVAGE, JUAN CARLOS MIRANDA, HENRY INFANTE, JORGE GARCIA, RUTH RODRGUEZ, MARISBRACAMONTE, GRUPO SOLUCIONESDE INFORMACIN

    ANNOUNCEMENTS

    No announcements for this week.

    SERVICEAND SOURCING / SERVICE DELIVERY

    SLAs Tickets

    Count of Request

    Per Total Grand Total

    Product Line Status1 D 16-25 E 26-40 F 41-60 G 61-100 H >100

    Scheduled 1 1 1 8 8

    MCS Total 1 1 1 1 17 17

    MNS - Data Scheduled 2 6 6

    MNS - Data Total 2 6 6

    MNS - Telephony Total 2 25 25

    Newmont Apps Total 5 4 21 46 81 81

    Newmont Other Total 43 44 66 16 31 315 315

    USD Open 5 5

    Scheduled 2 9 9

    USD Total 2 14 14Grand Total 70 66 78 40 88 667 667

    Impact to the Operation (Severity 1 y 2)

    0 Severities

    Performed Activities

    Links Upgrade:

    Project with Telefonica its in Closphase

    Infrastructure Renewal

    Started the coordination between IBM a Yanacocha PM. Next week begins planning process of implementation.

    XeroxInventory of printers was reviewed order to have a new proposal for the nyear in support of printers

    Equipment decommissionedFormal document to proceed was presentedAccount area, the following equipment will decommissioned:

    160 Desktop / 01 Car CP

    26 digital cameras / 01 video camera

    04 External CD/DVD / 01 External HDD

    03 Fax / 05 Photocopiers / 33 Printer

    125 Laptops 236 CRT screen / 67 LCD screen

    05 PDA

    04 Phone Extensin

    17 Proyectores

    03 Scaner

    12 Tablet PC

    119 UPS

    Cellular Coverage in Chaquicocha Pit:The Claros truck was moved from CajamarcaChaquicocha pit, during the next 3 days they install the repeater and antennas in trucks mast. Nactivities:

    - Install the electrical generator for powering Claros Truck, 1 week- Install a physical and electronic perimeter for

    truck, 2 weeks- Install a electrical line in 220V for this platform

    month

    Radio Coverage in Chaquicocha Pit:Generate the requirement for Service Order in oto install the new passive radio repeater. In weeks will be executed this work.

    http://goldnetperu/C6/Biblioteca/IT%20Weekly%20Report%20Peru/Forms/AllItems.aspxhttp://goldnetperu/C6/Biblioteca/IT%20Weekly%20Report%20Peru/Forms/AllItems.aspxhttp://goldnetperu/C6/Biblioteca/IT%20Weekly%20Report%20Peru/Forms/AllItems.aspxhttp://goldnetperu/C6/Biblioteca/IT%20Weekly%20Report%20Peru/Forms/AllItems.aspxhttp://goldnetperu/C6/Biblioteca/IT%20Weekly%20Report%20Peru/Forms/AllItems.aspxhttp://goldnetperu/C6/Biblioteca/IT%20Weekly%20Report%20Peru/Forms/AllItems.aspxhttp://goldnetperu/C6/Biblioteca/IT%20Weekly%20Report%20Peru/Forms/AllItems.aspxhttp://goldnetperu/C6/Biblioteca/IT%20Weekly%20Report%20Peru/Forms/AllItems.aspxhttp://goldnetperu/C6/Biblioteca/IT%20Weekly%20Report%20Peru/Forms/AllItems.aspxhttp://goldnetperu/C6/Biblioteca/IT%20Weekly%20Report%20Peru/Forms/AllItems.aspxhttp://goldnetperu/C6/Biblioteca/IT%20Weekly%20Report%20Peru/Forms/AllItems.aspxhttp://goldnetperu/C6/Biblioteca/IT%20Weekly%20Report%20Peru/Forms/AllItems.aspxhttp://goldnetperu/C6/Biblioteca/IT%20Weekly%20Report%20Peru/Forms/AllItems.aspxhttp://goldnetperu/C6/Biblioteca/IT%20Weekly%20Report%20Peru/Forms/AllItems.aspxhttp://goldnetperu/C6/Biblioteca/IT%20Weekly%20Report%20Peru/Forms/AllItems.aspxhttp://goldnetperu/C6/Biblioteca/IT%20Weekly%20Report%20Peru/Forms/AllItems.aspxhttp://goldnetperu/C6/Biblioteca/IT%20Weekly%20Report%20Peru/Forms/AllItems.aspxhttp://goldnetperu/C6/Biblioteca/IT%20Weekly%20Report%20Peru/Forms/AllItems.aspxhttp://goldnetperu/C6/Biblioteca/IT%20Weekly%20Report%20Peru/Forms/AllItems.aspxhttp://goldnetperu/C6/Biblioteca/IT%20Weekly%20Report%20Peru/Forms/AllItems.aspxhttp://goldnetperu/C6/Biblioteca/IT%20Weekly%20Report%20Peru/Forms/AllItems.aspx
  • 8/8/2019 IT Weekly Report 20101102 (Peru)

    2/37

    T PROJECT PORTFOLIONumber of

    Initiatives inthe Portfolio

    Number ofProject in the

    Portfolio

    On GoingProjects

    Projectsclosed inthe week

    FrozenProjects

    Initiatives /Project using

    OperatingBudget

    Initiatives /Project using

    Capital Budget

    IT Portfolio Budg

    12 1 1 0 3 12 1 0 - $ 40.000

  • 8/8/2019 IT Weekly Report 20101102 (Peru)

    3/37

    NITIATIVESAND PROJECTSIT Resources Optimization Program Phase IIMilton Oblitas (PM)

    Status Start Initiatives Business Analysts Project Managers On Going Projects Closed

    February 2010 1 4 3 4 2

    Achievements, Issues and Risks

    Applications Group CADs licenses optimization:

    o No progress.

    Ellipse Support Hours Optimization:o The project team is doing the conciliation process for September period.

    Communications Group Fixed Telephone Optimization:

    o There is an issue with PC Systel reports and the contractor is working for fix it.

    Local Contractso Meeting with contract area to start the bidding process.

    Progress : 76.5%

    IT Service CatalogGilmer Sanchez (PM)

    Achievements, Issues and Risks

    ACHIEVEMENTS:- The training sessions are being developed:

    1. The training was postponed for the next week.- Reviewed action plan draft and the commitments were:

    1.Update Initiative Portfolio: Done

    2. Templates was reviewed and finished.

    NEXT WEEK:- Train the first group in the initiative management process.- Schedule the second training.

    IT Global ProjectsJorge Garcia (SOL Owner), Luis Orna (PM), Giovanna Tito (MineView PM)Infrastructure

    PROJECT SOL

    Manage Service Selection Vendor Project (100%)

    The Legal and Contract areas from Yanacocha are continuing dealing with CSC legal area in order to define the final documents to close the

    contract.

    EUC- Service Desk

    CA Tool Stage 3: Working through scope of implementation, Risks, GAPS, and challenges to determine what system functions will be locked dowfor end of January to support parallel testing and User training and what can continue with implementation through April.

    CA Demo of the Suit of CA Tools was held : Service Catalog, Service Desk, Asset Management, CMDB

    EUC Technicians installed Bomgar and schedule time to become familiar with Bomgar and Active Boot Tools

    EUC Technicians are receiving Knowledge Transfer in tools for remote control and booting.

    EUC was the Go Live on Monday: Global Team has recognized the participation in this effort of all regions.

    WINDOWS 7 & OFFICE 2010 UPGRADE

    Technical Training was scheduled for resolve installation, configuration, logon, printer issues in Windows 7 for next January.

    Hardware for SCCM has been installed. Secondary server for Peru is being made on its ordering and installation

    Next week will start the IE8 Testing for Web Applications with the Key User testers.

    IE8 will become the new browser standard for NMC: Applications based in this browser will be tested by Nov. 18. 30%

    About image creation, the strategy of creating a hybrid image has been adopted

    The SOW for the SCCM SW environment has been presented, and is currently reviewed.

    MINEVIEW PROJECT

    The real time reports tests were postponed until November 8th.

    LEGEND

  • 8/8/2019 IT Weekly Report 20101102 (Peru)

    4/37

    NITIATIVESAND PROJECTSIT Resources Optimization Program Phase IIMilton Oblitas (PM)

    Status Start Initiatives Business Analysts Project Managers On Going Projects Closed

    February 2010 1 4 3 4 2

    Achievements, Issues and Risks

    Applications Group CADs licenses optimization:

    o No progress.

    Ellipse Support Hours Optimization:o The project team is doing the conciliation process for September period.

    Communications Group Fixed Telephone Optimization:

    o There is an issue with PC Systel reports and the contractor is working for fix it.

    Local Contractso Meeting with contract area to start the bidding process.

    Progress : 76.5%

    IT Service CatalogGilmer Sanchez (PM)

    Achievements, Issues and Risks

    ACHIEVEMENTS:- The training sessions are being developed:

    1. The training was postponed for the next week.- Reviewed action plan draft and the commitments were:

    1.Update Initiative Portfolio: Done

    2. Templates was reviewed and finished.

    NEXT WEEK:- Train the first group in the initiative management process.- Schedule the second training.

    IT Global ProjectsJorge Garcia (SOL Owner), Luis Orna (PM), Giovanna Tito (MineView PM)Infrastructure

    PROJECT SOL

    Manage Service Selection Vendor Project (100%)

    The Legal and Contract areas from Yanacocha are continuing dealing with CSC legal area in order to define the final documents to close the

    contract.

    EUC- Service Desk

    CA Tool Stage 3: Working through scope of implementation, Risks, GAPS, and challenges to determine what system functions will be locked dowfor end of January to support parallel testing and User training and what can continue with implementation through April.

    CA Demo of the Suit of CA Tools was held : Service Catalog, Service Desk, Asset Management, CMDB

    EUC Technicians installed Bomgar and schedule time to become familiar with Bomgar and Active Boot Tools

    EUC Technicians are receiving Knowledge Transfer in tools for remote control and booting.

    EUC was the Go Live on Monday: Global Team has recognized the participation in this effort of all regions.

    WINDOWS 7 & OFFICE 2010 UPGRADE

    Technical Training was scheduled for resolve installation, configuration, logon, printer issues in Windows 7 for next January.

    Hardware for SCCM has been installed. Secondary server for Peru is being made on its ordering and installation

    Next week will start the IE8 Testing for Web Applications with the Key User testers.

    IE8 will become the new browser standard for NMC: Applications based in this browser will be tested by Nov. 18. 30%

    About image creation, the strategy of creating a hybrid image has been adopted

    The SOW for the SCCM SW environment has been presented, and is currently reviewed.

    MINEVIEW PROJECT

    The real time reports tests were postponed until November 8th.

  • 8/8/2019 IT Weekly Report 20101102 (Peru)

    5/37

    NITIATIVESAND PROJECTSIT Resources Optimization Program Phase IIMilton Oblitas (PM)

    Status Start Initiatives Business Analysts Project Managers On Going Projects Closed

    February 2010 1 4 3 4 2

    Achievements, Issues and Risks

    Applications Group CADs licenses optimization:

    o No progress.

    Ellipse Support Hours Optimization:o The project team is doing the conciliation process for September period.

    Communications Group Fixed Telephone Optimization:

    o There is an issue with PC Systel reports and the contractor is working for fix it.

    Local Contractso Meeting with contract area to start the bidding process.

    Progress : 76.5%

    IT Service CatalogGilmer Sanchez (PM)

    Achievements, Issues and Risks

    ACHIEVEMENTS:- The training sessions are being developed:

    1. The training was postponed for the next week.- Reviewed action plan draft and the commitments were:

    1.Update Initiative Portfolio: Done

    2. Templates was reviewed and finished.

    NEXT WEEK:- Train the first group in the initiative management process.- Schedule the second training.

    IT Global ProjectsJorge Garcia (SOL Owner), Luis Orna (PM), Giovanna Tito (MineView PM)Infrastructure

    PROJECT SOL

    Manage Service Selection Vendor Project (100%)

    The Legal and Contract areas from Yanacocha are continuing dealing with CSC legal area in order to define the final documents to close the

    contract.

    EUC- Service Desk

    CA Tool Stage 3: Working through scope of implementation, Risks, GAPS, and challenges to determine what system functions will be locked dowfor end of January to support parallel testing and User training and what can continue with implementation through April.

    CA Demo of the Suit of CA Tools was held : Service Catalog, Service Desk, Asset Management, CMDB

    EUC Technicians installed Bomgar and schedule time to become familiar with Bomgar and Active Boot Tools

    EUC Technicians are receiving Knowledge Transfer in tools for remote control and booting.

    EUC was the Go Live on Monday: Global Team has recognized the participation in this effort of all regions.

    WINDOWS 7 & OFFICE 2010 UPGRADE

    Technical Training was scheduled for resolve installation, configuration, logon, printer issues in Windows 7 for next January.

    Hardware for SCCM has been installed. Secondary server for Peru is being made on its ordering and installation

    Next week will start the IE8 Testing for Web Applications with the Key User testers.

    IE8 will become the new browser standard for NMC: Applications based in this browser will be tested by Nov. 18. 30%

    About image creation, the strategy of creating a hybrid image has been adopted

    The SOW for the SCCM SW environment has been presented, and is currently reviewed.

    MINEVIEW PROJECT

    The real time reports tests were postponed until November 8th.

    MINOR INITIATIVES, PROJECTSAND REQUESTS

  • 8/8/2019 IT Weekly Report 20101102 (Peru)

    6/37

    NITIATIVESAND PROJECTSIT Resources Optimization Program Phase IIMilton Oblitas (PM)

    Status Start Initiatives Business Analysts Project Managers On Going Projects Closed

    February 2010 1 4 3 4 2

    Achievements, Issues and Risks

    Applications Group CADs licenses optimization:

    o No progress.

    Ellipse Support Hours Optimization:o The project team is doing the conciliation process for September period.

    Communications Group Fixed Telephone Optimization:

    o There is an issue with PC Systel reports and the contractor is working for fix it.

    Local Contractso Meeting with contract area to start the bidding process.

    Progress : 76.5%

    IT Service CatalogGilmer Sanchez (PM)

    Achievements, Issues and Risks

    ACHIEVEMENTS:- The training sessions are being developed:

    1. The training was postponed for the next week.- Reviewed action plan draft and the commitments were:

    1.Update Initiative Portfolio: Done

    2. Templates was reviewed and finished.

    NEXT WEEK:- Train the first group in the initiative management process.- Schedule the second training.

    IT Global ProjectsJorge Garcia (SOL Owner), Luis Orna (PM), Giovanna Tito (MineView PM)Infrastructure

    PROJECT SOL

    Manage Service Selection Vendor Project (100%)

    The Legal and Contract areas from Yanacocha are continuing dealing with CSC legal area in order to define the final documents to close the

    contract.

    EUC- Service Desk

    CA Tool Stage 3: Working through scope of implementation, Risks, GAPS, and challenges to determine what system functions will be locked dowfor end of January to support parallel testing and User training and what can continue with implementation through April.

    CA Demo of the Suit of CA Tools was held : Service Catalog, Service Desk, Asset Management, CMDB

    EUC Technicians installed Bomgar and schedule time to become familiar with Bomgar and Active Boot Tools

    EUC Technicians are receiving Knowledge Transfer in tools for remote control and booting.

    EUC was the Go Live on Monday: Global Team has recognized the participation in this effort of all regions.

    WINDOWS 7 & OFFICE 2010 UPGRADE

    Technical Training was scheduled for resolve installation, configuration, logon, printer issues in Windows 7 for next January.

    Hardware for SCCM has been installed. Secondary server for Peru is being made on its ordering and installation

    Next week will start the IE8 Testing for Web Applications with the Key User testers.

    IE8 will become the new browser standard for NMC: Applications based in this browser will be tested by Nov. 18. 30%

    About image creation, the strategy of creating a hybrid image has been adopted

    The SOW for the SCCM SW environment has been presented, and is currently reviewed.

    MINEVIEW PROJECT

    The real time reports tests were postponed until November 8th.

    Initiative/Project/Requirement Accountable Sponsor Area Comments

  • 8/8/2019 IT Weekly Report 20101102 (Peru)

    7/37

    NITIATIVESAND PROJECTSIT Resources Optimization Program Phase IIMilton Oblitas (PM)

    Status Start Initiatives Business Analysts Project Managers On Going Projects Closed

    February 2010 1 4 3 4 2

    Achievements, Issues and Risks

    Applications Group CADs licenses optimization:

    o No progress.

    Ellipse Support Hours Optimization:o The project team is doing the conciliation process for September period.

    Communications Group Fixed Telephone Optimization:

    o There is an issue with PC Systel reports and the contractor is working for fix it.

    Local Contractso Meeting with contract area to start the bidding process.

    Progress : 76.5%

    IT Service CatalogGilmer Sanchez (PM)

    Achievements, Issues and Risks

    ACHIEVEMENTS:- The training sessions are being developed:

    1. The training was postponed for the next week.- Reviewed action plan draft and the commitments were:

    1.Update Initiative Portfolio: Done

    2. Templates was reviewed and finished.

    NEXT WEEK:- Train the first group in the initiative management process.- Schedule the second training.

    IT Global ProjectsJorge Garcia (SOL Owner), Luis Orna (PM), Giovanna Tito (MineView PM)Infrastructure

    PROJECT SOL

    Manage Service Selection Vendor Project (100%)

    The Legal and Contract areas from Yanacocha are continuing dealing with CSC legal area in order to define the final documents to close the

    contract.

    EUC- Service Desk

    CA Tool Stage 3: Working through scope of implementation, Risks, GAPS, and challenges to determine what system functions will be locked dowfor end of January to support parallel testing and User training and what can continue with implementation through April.

    CA Demo of the Suit of CA Tools was held : Service Catalog, Service Desk, Asset Management, CMDB

    EUC Technicians installed Bomgar and schedule time to become familiar with Bomgar and Active Boot Tools

    EUC Technicians are receiving Knowledge Transfer in tools for remote control and booting.

    EUC was the Go Live on Monday: Global Team has recognized the participation in this effort of all regions.

    WINDOWS 7 & OFFICE 2010 UPGRADE

    Technical Training was scheduled for resolve installation, configuration, logon, printer issues in Windows 7 for next January.

    Hardware for SCCM has been installed. Secondary server for Peru is being made on its ordering and installation

    Next week will start the IE8 Testing for Web Applications with the Key User testers.

    IE8 will become the new browser standard for NMC: Applications based in this browser will be tested by Nov. 18. 30%

    About image creation, the strategy of creating a hybrid image has been adopted

    The SOW for the SCCM SW environment has been presented, and is currently reviewed.

    MINEVIEW PROJECT

    The real time reports tests were postponed until November 8th.

    PROJECT: Giovanna Tito (PM) Mine Maintenance Electronic Gantt (PPI: 100%)

  • 8/8/2019 IT Weekly Report 20101102 (Peru)

    8/37

    NITIATIVESAND PROJECTSIT Resources Optimization Program Phase IIMilton Oblitas (PM)

    Status Start Initiatives Business Analysts Project Managers On Going Projects Closed

    February 2010 1 4 3 4 2

    Achievements, Issues and Risks

    Applications Group CADs licenses optimization:

    o No progress.

    Ellipse Support Hours Optimization:o The project team is doing the conciliation process for September period.

    Communications Group Fixed Telephone Optimization:

    o There is an issue with PC Systel reports and the contractor is working for fix it.

    Local Contractso Meeting with contract area to start the bidding process.

    Progress : 76.5%

    IT Service CatalogGilmer Sanchez (PM)

    Achievements, Issues and Risks

    ACHIEVEMENTS:- The training sessions are being developed:

    1. The training was postponed for the next week.- Reviewed action plan draft and the commitments were:

    1.Update Initiative Portfolio: Done

    2. Templates was reviewed and finished.

    NEXT WEEK:- Train the first group in the initiative management process.- Schedule the second training.

    IT Global ProjectsJorge Garcia (SOL Owner), Luis Orna (PM), Giovanna Tito (MineView PM)Infrastructure

    PROJECT SOL

    Manage Service Selection Vendor Project (100%)

    The Legal and Contract areas from Yanacocha are continuing dealing with CSC legal area in order to define the final documents to close the

    contract.

    EUC- Service Desk

    CA Tool Stage 3: Working through scope of implementation, Risks, GAPS, and challenges to determine what system functions will be locked dowfor end of January to support parallel testing and User training and what can continue with implementation through April.

    CA Demo of the Suit of CA Tools was held : Service Catalog, Service Desk, Asset Management, CMDB

    EUC Technicians installed Bomgar and schedule time to become familiar with Bomgar and Active Boot Tools

    EUC Technicians are receiving Knowledge Transfer in tools for remote control and booting.

    EUC was the Go Live on Monday: Global Team has recognized the participation in this effort of all regions.

    WINDOWS 7 & OFFICE 2010 UPGRADE

    Technical Training was scheduled for resolve installation, configuration, logon, printer issues in Windows 7 for next January.

    Hardware for SCCM has been installed. Secondary server for Peru is being made on its ordering and installation

    Next week will start the IE8 Testing for Web Applications with the Key User testers.

    IE8 will become the new browser standard for NMC: Applications based in this browser will be tested by Nov. 18. 30%

    About image creation, the strategy of creating a hybrid image has been adopted

    The SOW for the SCCM SW environment has been presented, and is currently reviewed.

    MINEVIEW PROJECT

    The real time reports tests were postponed until November 8th.

    Electronic Gantt - Additional scope was developed

  • 8/8/2019 IT Weekly Report 20101102 (Peru)

    9/37

    NITIATIVESAND PROJECTSIT Resources Optimization Program Phase IIMilton Oblitas (PM)

    Status Start Initiatives Business Analysts Project Managers On Going Projects Closed

    February 2010 1 4 3 4 2

    Achievements, Issues and Risks

    Applications Group CADs licenses optimization:

    o No progress.

    Ellipse Support Hours Optimization:o The project team is doing the conciliation process for September period.

    Communications Group Fixed Telephone Optimization:

    o There is an issue with PC Systel reports and the contractor is working for fix it.

    Local Contractso Meeting with contract area to start the bidding process.

    Progress : 76.5%

    IT Service CatalogGilmer Sanchez (PM)

    Achievements, Issues and Risks

    ACHIEVEMENTS:- The training sessions are being developed:

    1. The training was postponed for the next week.- Reviewed action plan draft and the commitments were:

    1.Update Initiative Portfolio: Done

    2. Templates was reviewed and finished.

    NEXT WEEK:- Train the first group in the initiative management process.- Schedule the second training.

    IT Global ProjectsJorge Garcia (SOL Owner), Luis Orna (PM), Giovanna Tito (MineView PM)Infrastructure

    PROJECT SOL

    Manage Service Selection Vendor Project (100%)

    The Legal and Contract areas from Yanacocha are continuing dealing with CSC legal area in order to define the final documents to close the

    contract.

    EUC- Service Desk

    CA Tool Stage 3: Working through scope of implementation, Risks, GAPS, and challenges to determine what system functions will be locked dowfor end of January to support parallel testing and User training and what can continue with implementation through April.

    CA Demo of the Suit of CA Tools was held : Service Catalog, Service Desk, Asset Management, CMDB

    EUC Technicians installed Bomgar and schedule time to become familiar with Bomgar and Active Boot Tools

    EUC Technicians are receiving Knowledge Transfer in tools for remote control and booting.

    EUC was the Go Live on Monday: Global Team has recognized the participation in this effort of all regions.

    WINDOWS 7 & OFFICE 2010 UPGRADE

    Technical Training was scheduled for resolve installation, configuration, logon, printer issues in Windows 7 for next January.

    Hardware for SCCM has been installed. Secondary server for Peru is being made on its ordering and installation

    Next week will start the IE8 Testing for Web Applications with the Key User testers.

    IE8 will become the new browser standard for NMC: Applications based in this browser will be tested by Nov. 18. 30%

    About image creation, the strategy of creating a hybrid image has been adopted

    The SOW for the SCCM SW environment has been presented, and is currently reviewed.

    MINEVIEW PROJECT

    The real time reports tests were postponed until November 8th.

    - UAT Run 1 was done.

  • 8/8/2019 IT Weekly Report 20101102 (Peru)

    10/37

    NITIATIVESAND PROJECTSIT Resources Optimization Program Phase IIMilton Oblitas (PM)

    Status Start Initiatives Business Analysts Project Managers On Going Projects Closed

    February 2010 1 4 3 4 2

    Achievements, Issues and Risks

    Applications Group CADs licenses optimization:

    o No progress.

    Ellipse Support Hours Optimization:o The project team is doing the conciliation process for September period.

    Communications Group Fixed Telephone Optimization:

    o There is an issue with PC Systel reports and the contractor is working for fix it.

    Local Contractso Meeting with contract area to start the bidding process.

    Progress : 76.5%

    IT Service CatalogGilmer Sanchez (PM)

    Achievements, Issues and Risks

    ACHIEVEMENTS:- The training sessions are being developed:

    1. The training was postponed for the next week.- Reviewed action plan draft and the commitments were:

    1.Update Initiative Portfolio: Done

    2. Templates was reviewed and finished.

    NEXT WEEK:- Train the first group in the initiative management process.- Schedule the second training.

    IT Global ProjectsJorge Garcia (SOL Owner), Luis Orna (PM), Giovanna Tito (MineView PM)Infrastructure

    PROJECT SOL

    Manage Service Selection Vendor Project (100%)

    The Legal and Contract areas from Yanacocha are continuing dealing with CSC legal area in order to define the final documents to close the

    contract.

    EUC- Service Desk

    CA Tool Stage 3: Working through scope of implementation, Risks, GAPS, and challenges to determine what system functions will be locked dowfor end of January to support parallel testing and User training and what can continue with implementation through April.

    CA Demo of the Suit of CA Tools was held : Service Catalog, Service Desk, Asset Management, CMDB

    EUC Technicians installed Bomgar and schedule time to become familiar with Bomgar and Active Boot Tools

    EUC Technicians are receiving Knowledge Transfer in tools for remote control and booting.

    EUC was the Go Live on Monday: Global Team has recognized the participation in this effort of all regions.

    WINDOWS 7 & OFFICE 2010 UPGRADE

    Technical Training was scheduled for resolve installation, configuration, logon, printer issues in Windows 7 for next January.

    Hardware for SCCM has been installed. Secondary server for Peru is being made on its ordering and installation

    Next week will start the IE8 Testing for Web Applications with the Key User testers.

    IE8 will become the new browser standard for NMC: Applications based in this browser will be tested by Nov. 18. 30%

    About image creation, the strategy of creating a hybrid image has been adopted

    The SOW for the SCCM SW environment has been presented, and is currently reviewed.

    MINEVIEW PROJECT

    The real time reports tests were postponed until November 8th.

    - Total issues (165), issues solved (128), issues

  • 8/8/2019 IT Weekly Report 20101102 (Peru)

    11/37

    NITIATIVESAND PROJECTSIT Resources Optimization Program Phase IIMilton Oblitas (PM)

    Status Start Initiatives Business Analysts Project Managers On Going Projects Closed

    February 2010 1 4 3 4 2

    Achievements, Issues and Risks

    Applications Group CADs licenses optimization:

    o No progress.

    Ellipse Support Hours Optimization:o The project team is doing the conciliation process for September period.

    Communications Group Fixed Telephone Optimization:

    o There is an issue with PC Systel reports and the contractor is working for fix it.

    Local Contractso Meeting with contract area to start the bidding process.

    Progress : 76.5%

    IT Service CatalogGilmer Sanchez (PM)

    Achievements, Issues and Risks

    ACHIEVEMENTS:- The training sessions are being developed:

    1. The training was postponed for the next week.- Reviewed action plan draft and the commitments were:

    1.Update Initiative Portfolio: Done

    2. Templates was reviewed and finished.

    NEXT WEEK:- Train the first group in the initiative management process.- Schedule the second training.

    IT Global ProjectsJorge Garcia (SOL Owner), Luis Orna (PM), Giovanna Tito (MineView PM)Infrastructure

    PROJECT SOL

    Manage Service Selection Vendor Project (100%)

    The Legal and Contract areas from Yanacocha are continuing dealing with CSC legal area in order to define the final documents to close the

    contract.

    EUC- Service Desk

    CA Tool Stage 3: Working through scope of implementation, Risks, GAPS, and challenges to determine what system functions will be locked dowfor end of January to support parallel testing and User training and what can continue with implementation through April.

    CA Demo of the Suit of CA Tools was held : Service Catalog, Service Desk, Asset Management, CMDB

    EUC Technicians installed Bomgar and schedule time to become familiar with Bomgar and Active Boot Tools

    EUC Technicians are receiving Knowledge Transfer in tools for remote control and booting.

    EUC was the Go Live on Monday: Global Team has recognized the participation in this effort of all regions.

    WINDOWS 7 & OFFICE 2010 UPGRADE

    Technical Training was scheduled for resolve installation, configuration, logon, printer issues in Windows 7 for next January.

    Hardware for SCCM has been installed. Secondary server for Peru is being made on its ordering and installation

    Next week will start the IE8 Testing for Web Applications with the Key User testers.

    IE8 will become the new browser standard for NMC: Applications based in this browser will be tested by Nov. 18. 30%

    About image creation, the strategy of creating a hybrid image has been adopted

    The SOW for the SCCM SW environment has been presented, and is currently reviewed.

    MINEVIEW PROJECT

    The real time reports tests were postponed until November 8th.

    pending (37)

  • 8/8/2019 IT Weekly Report 20101102 (Peru)

    12/37

    NITIATIVESAND PROJECTSIT Resources Optimization Program Phase IIMilton Oblitas (PM)

    Status Start Initiatives Business Analysts Project Managers On Going Projects Closed

    February 2010 1 4 3 4 2

    Achievements, Issues and Risks

    Applications Group CADs licenses optimization:

    o No progress.

    Ellipse Support Hours Optimization:o The project team is doing the conciliation process for September period.

    Communications Group Fixed Telephone Optimization:

    o There is an issue with PC Systel reports and the contractor is working for fix it.

    Local Contractso Meeting with contract area to start the bidding process.

    Progress : 76.5%

    IT Service CatalogGilmer Sanchez (PM)

    Achievements, Issues and Risks

    ACHIEVEMENTS:- The training sessions are being developed:

    1. The training was postponed for the next week.- Reviewed action plan draft and the commitments were:

    1.Update Initiative Portfolio: Done

    2. Templates was reviewed and finished.

    NEXT WEEK:- Train the first group in the initiative management process.- Schedule the second training.

    IT Global ProjectsJorge Garcia (SOL Owner), Luis Orna (PM), Giovanna Tito (MineView PM)Infrastructure

    PROJECT SOL

    Manage Service Selection Vendor Project (100%)

    The Legal and Contract areas from Yanacocha are continuing dealing with CSC legal area in order to define the final documents to close the

    contract.

    EUC- Service Desk

    CA Tool Stage 3: Working through scope of implementation, Risks, GAPS, and challenges to determine what system functions will be locked dowfor end of January to support parallel testing and User training and what can continue with implementation through April.

    CA Demo of the Suit of CA Tools was held : Service Catalog, Service Desk, Asset Management, CMDB

    EUC Technicians installed Bomgar and schedule time to become familiar with Bomgar and Active Boot Tools

    EUC Technicians are receiving Knowledge Transfer in tools for remote control and booting.

    EUC was the Go Live on Monday: Global Team has recognized the participation in this effort of all regions.

    WINDOWS 7 & OFFICE 2010 UPGRADE

    Technical Training was scheduled for resolve installation, configuration, logon, printer issues in Windows 7 for next January.

    Hardware for SCCM has been installed. Secondary server for Peru is being made on its ordering and installation

    Next week will start the IE8 Testing for Web Applications with the Key User testers.

    IE8 will become the new browser standard for NMC: Applications based in this browser will be tested by Nov. 18. 30%

    About image creation, the strategy of creating a hybrid image has been adopted

    The SOW for the SCCM SW environment has been presented, and is currently reviewed.

    MINEVIEW PROJECT

    The real time reports tests were postponed until November 8th.

    PROJECT: Giovanna Tito (PM) Process - Analysis Phase: 12 tests were documented (To

  • 8/8/2019 IT Weekly Report 20101102 (Peru)

    13/37

    NITIATIVESAND PROJECTSIT Resources Optimization Program Phase IIMilton Oblitas (PM)

    Status Start Initiatives Business Analysts Project Managers On Going Projects Closed

    February 2010 1 4 3 4 2

    Achievements, Issues and Risks

    Applications Group CADs licenses optimization:

    o No progress.

    Ellipse Support Hours Optimization:o The project team is doing the conciliation process for September period.

    Communications Group Fixed Telephone Optimization:

    o There is an issue with PC Systel reports and the contractor is working for fix it.

    Local Contractso Meeting with contract area to start the bidding process.

    Progress : 76.5%

    IT Service CatalogGilmer Sanchez (PM)

    Achievements, Issues and Risks

    ACHIEVEMENTS:- The training sessions are being developed:

    1. The training was postponed for the next week.- Reviewed action plan draft and the commitments were:

    1.Update Initiative Portfolio: Done

    2. Templates was reviewed and finished.

    NEXT WEEK:- Train the first group in the initiative management process.- Schedule the second training.

    IT Global ProjectsJorge Garcia (SOL Owner), Luis Orna (PM), Giovanna Tito (MineView PM)Infrastructure

    PROJECT SOL

    Manage Service Selection Vendor Project (100%)

    The Legal and Contract areas from Yanacocha are continuing dealing with CSC legal area in order to define the final documents to close the

    contract.

    EUC- Service Desk

    CA Tool Stage 3: Working through scope of implementation, Risks, GAPS, and challenges to determine what system functions will be locked dowfor end of January to support parallel testing and User training and what can continue with implementation through April.

    CA Demo of the Suit of CA Tools was held : Service Catalog, Service Desk, Asset Management, CMDB

    EUC Technicians installed Bomgar and schedule time to become familiar with Bomgar and Active Boot Tools

    EUC Technicians are receiving Knowledge Transfer in tools for remote control and booting.

    EUC was the Go Live on Monday: Global Team has recognized the participation in this effort of all regions.

    WINDOWS 7 & OFFICE 2010 UPGRADE

    Technical Training was scheduled for resolve installation, configuration, logon, printer issues in Windows 7 for next January.

    Hardware for SCCM has been installed. Secondary server for Peru is being made on its ordering and installation

    Next week will start the IE8 Testing for Web Applications with the Key User testers.

    IE8 will become the new browser standard for NMC: Applications based in this browser will be tested by Nov. 18. 30%

    About image creation, the strategy of creating a hybrid image has been adopted

    The SOW for the SCCM SW environment has been presented, and is currently reviewed.

    MINEVIEW PROJECT

    The real time reports tests were postponed until November 8th.

    Metallurgical LIMS flows and reports).

  • 8/8/2019 IT Weekly Report 20101102 (Peru)

    14/37

    NITIATIVESAND PROJECTSIT Resources Optimization Program Phase IIMilton Oblitas (PM)

    Status Start Initiatives Business Analysts Project Managers On Going Projects Closed

    February 2010 1 4 3 4 2

    Achievements, Issues and Risks

    Applications Group CADs licenses optimization:

    o No progress.

    Ellipse Support Hours Optimization:o The project team is doing the conciliation process for September period.

    Communications Group Fixed Telephone Optimization:

    o There is an issue with PC Systel reports and the contractor is working for fix it.

    Local Contractso Meeting with contract area to start the bidding process.

    Progress : 76.5%

    IT Service CatalogGilmer Sanchez (PM)

    Achievements, Issues and Risks

    ACHIEVEMENTS:- The training sessions are being developed:

    1. The training was postponed for the next week.- Reviewed action plan draft and the commitments were:

    1.Update Initiative Portfolio: Done

    2. Templates was reviewed and finished.

    NEXT WEEK:- Train the first group in the initiative management process.- Schedule the second training.

    IT Global ProjectsJorge Garcia (SOL Owner), Luis Orna (PM), Giovanna Tito (MineView PM)Infrastructure

    PROJECT SOL

    Manage Service Selection Vendor Project (100%)

    The Legal and Contract areas from Yanacocha are continuing dealing with CSC legal area in order to define the final documents to close the

    contract.

    EUC- Service Desk

    CA Tool Stage 3: Working through scope of implementation, Risks, GAPS, and challenges to determine what system functions will be locked dowfor end of January to support parallel testing and User training and what can continue with implementation through April.

    CA Demo of the Suit of CA Tools was held : Service Catalog, Service Desk, Asset Management, CMDB

    EUC Technicians installed Bomgar and schedule time to become familiar with Bomgar and Active Boot Tools

    EUC Technicians are receiving Knowledge Transfer in tools for remote control and booting.

    EUC was the Go Live on Monday: Global Team has recognized the participation in this effort of all regions.

    WINDOWS 7 & OFFICE 2010 UPGRADE

    Technical Training was scheduled for resolve installation, configuration, logon, printer issues in Windows 7 for next January.

    Hardware for SCCM has been installed. Secondary server for Peru is being made on its ordering and installation

    Next week will start the IE8 Testing for Web Applications with the Key User testers.

    IE8 will become the new browser standard for NMC: Applications based in this browser will be tested by Nov. 18. 30%

    About image creation, the strategy of creating a hybrid image has been adopted

    The SOW for the SCCM SW environment has been presented, and is currently reviewed.

    MINEVIEW PROJECT

    The real time reports tests were postponed until November 8th.

    - Project charter is being prepared.

  • 8/8/2019 IT Weekly Report 20101102 (Peru)

    15/37

    NITIATIVESAND PROJECTSIT Resources Optimization Program Phase IIMilton Oblitas (PM)

    Status Start Initiatives Business Analysts Project Managers On Going Projects Closed

    February 2010 1 4 3 4 2

    Achievements, Issues and Risks

    Applications Group CADs licenses optimization:

    o No progress.

    Ellipse Support Hours Optimization:o The project team is doing the conciliation process for September period.

    Communications Group Fixed Telephone Optimization:

    o There is an issue with PC Systel reports and the contractor is working for fix it.

    Local Contractso Meeting with contract area to start the bidding process.

    Progress : 76.5%

    IT Service CatalogGilmer Sanchez (PM)

    Achievements, Issues and Risks

    ACHIEVEMENTS:- The training sessions are being developed:

    1. The training was postponed for the next week.- Reviewed action plan draft and the commitments were:

    1.Update Initiative Portfolio: Done

    2. Templates was reviewed and finished.

    NEXT WEEK:- Train the first group in the initiative management process.- Schedule the second training.

    IT Global ProjectsJorge Garcia (SOL Owner), Luis Orna (PM), Giovanna Tito (MineView PM)Infrastructure

    PROJECT SOL

    Manage Service Selection Vendor Project (100%)

    The Legal and Contract areas from Yanacocha are continuing dealing with CSC legal area in order to define the final documents to close the

    contract.

    EUC- Service Desk

    CA Tool Stage 3: Working through scope of implementation, Risks, GAPS, and challenges to determine what system functions will be locked dowfor end of January to support parallel testing and User training and what can continue with implementation through April.

    CA Demo of the Suit of CA Tools was held : Service Catalog, Service Desk, Asset Management, CMDB

    EUC Technicians installed Bomgar and schedule time to become familiar with Bomgar and Active Boot Tools

    EUC Technicians are receiving Knowledge Transfer in tools for remote control and booting.

    EUC was the Go Live on Monday: Global Team has recognized the participation in this effort of all regions.

    WINDOWS 7 & OFFICE 2010 UPGRADE

    Technical Training was scheduled for resolve installation, configuration, logon, printer issues in Windows 7 for next January.

    Hardware for SCCM has been installed. Secondary server for Peru is being made on its ordering and installation

    Next week will start the IE8 Testing for Web Applications with the Key User testers.

    IE8 will become the new browser standard for NMC: Applications based in this browser will be tested by Nov. 18. 30%

    About image creation, the strategy of creating a hybrid image has been adopted

    The SOW for the SCCM SW environment has been presented, and is currently reviewed.

    MINEVIEW PROJECT

    The real time reports tests were postponed until November 8th.

    PROJECT: Giovanna Tito (PM) IT - PMO Framework was showed to IBM in order to

  • 8/8/2019 IT Weekly Report 20101102 (Peru)

    16/37

    NITIATIVESAND PROJECTSIT Resources Optimization Program Phase IIMilton Oblitas (PM)

    Status Start Initiatives Business Analysts Project Managers On Going Projects Closed

    February 2010 1 4 3 4 2

    Achievements, Issues and Risks

    Applications Group CADs licenses optimization:

    o No progress.

    Ellipse Support Hours Optimization:o The project team is doing the conciliation process for September period.

    Communications Group Fixed Telephone Optimization:

    o There is an issue with PC Systel reports and the contractor is working for fix it.

    Local Contractso Meeting with contract area to start the bidding process.

    Progress : 76.5%

    IT Service CatalogGilmer Sanchez (PM)

    Achievements, Issues and Risks

    ACHIEVEMENTS:- The training sessions are being developed:

    1. The training was postponed for the next week.- Reviewed action plan draft and the commitments were:

    1.Update Initiative Portfolio: Done

    2. Templates was reviewed and finished.

    NEXT WEEK:- Train the first group in the initiative management process.- Schedule the second training.

    IT Global ProjectsJorge Garcia (SOL Owner), Luis Orna (PM), Giovanna Tito (MineView PM)Infrastructure

    PROJECT SOL

    Manage Service Selection Vendor Project (100%)

    The Legal and Contract areas from Yanacocha are continuing dealing with CSC legal area in order to define the final documents to close the

    contract.

    EUC- Service Desk

    CA Tool Stage 3: Working through scope of implementation, Risks, GAPS, and challenges to determine what system functions will be locked dowfor end of January to support parallel testing and User training and what can continue with implementation through April.

    CA Demo of the Suit of CA Tools was held : Service Catalog, Service Desk, Asset Management, CMDB

    EUC Technicians installed Bomgar and schedule time to become familiar with Bomgar and Active Boot Tools

    EUC Technicians are receiving Knowledge Transfer in tools for remote control and booting.

    EUC was the Go Live on Monday: Global Team has recognized the participation in this effort of all regions.

    WINDOWS 7 & OFFICE 2010 UPGRADE

    Technical Training was scheduled for resolve installation, configuration, logon, printer issues in Windows 7 for next January.

    Hardware for SCCM has been installed. Secondary server for Peru is being made on its ordering and installation

    Next week will start the IE8 Testing for Web Applications with the Key User testers.

    IE8 will become the new browser standard for NMC: Applications based in this browser will be tested by Nov. 18. 30%

    About image creation, the strategy of creating a hybrid image has been adopted

    The SOW for the SCCM SW environment has been presented, and is currently reviewed.

    MINEVIEW PROJECT

    The real time reports tests were postponed until November 8th.

    Networking Infrastructure Renewal start the project planning.

  • 8/8/2019 IT Weekly Report 20101102 (Peru)

    17/37

    NITIATIVESAND PROJECTSIT Resources Optimization Program Phase IIMilton Oblitas (PM)

    Status Start Initiatives Business Analysts Project Managers On Going Projects Closed

    February 2010 1 4 3 4 2

    Achievements, Issues and Risks

    Applications Group CADs licenses optimization:

    o No progress.

    Ellipse Support Hours Optimization:o The project team is doing the conciliation process for September period.

    Communications Group Fixed Telephone Optimization:

    o There is an issue with PC Systel reports and the contractor is working for fix it.

    Local Contractso Meeting with contract area to start the bidding process.

    Progress : 76.5%

    IT Service CatalogGilmer Sanchez (PM)

    Achievements, Issues and Risks

    ACHIEVEMENTS:- The training sessions are being developed:

    1. The training was postponed for the next week.- Reviewed action plan draft and the commitments were:

    1.Update Initiative Portfolio: Done

    2. Templates was reviewed and finished.

    NEXT WEEK:- Train the first group in the initiative management process.- Schedule the second training.

    IT Global ProjectsJorge Garcia (SOL Owner), Luis Orna (PM), Giovanna Tito (MineView PM)Infrastructure

    PROJECT SOL

    Manage Service Selection Vendor Project (100%)

    The Legal and Contract areas from Yanacocha are continuing dealing with CSC legal area in order to define the final documents to close the

    contract.

    EUC- Service Desk

    CA Tool Stage 3: Working through scope of implementation, Risks, GAPS, and challenges to determine what system functions will be locked dowfor end of January to support parallel testing and User training and what can continue with implementation through April.

    CA Demo of the Suit of CA Tools was held : Service Catalog, Service Desk, Asset Management, CMDB

    EUC Technicians installed Bomgar and schedule time to become familiar with Bomgar and Active Boot Tools

    EUC Technicians are receiving Knowledge Transfer in tools for remote control and booting.

    EUC was the Go Live on Monday: Global Team has recognized the participation in this effort of all regions.

    WINDOWS 7 & OFFICE 2010 UPGRADE

    Technical Training was scheduled for resolve installation, configuration, logon, printer issues in Windows 7 for next January.

    Hardware for SCCM has been installed. Secondary server for Peru is being made on its ordering and installation

    Next week will start the IE8 Testing for Web Applications with the Key User testers.

    IE8 will become the new browser standard for NMC: Applications based in this browser will be tested by Nov. 18. 30%

    About image creation, the strategy of creating a hybrid image has been adopted

    The SOW for the SCCM SW environment has been presented, and is currently reviewed.

    MINEVIEW PROJECT

    The real time reports tests were postponed until November 8th.

    - SMEs is working in the equipments and sites

  • 8/8/2019 IT Weekly Report 20101102 (Peru)

    18/37

    NITIATIVESAND PROJECTSIT Resources Optimization Program Phase IIMilton Oblitas (PM)

    Status Start Initiatives Business Analysts Project Managers On Going Projects Closed

    February 2010 1 4 3 4 2

    Achievements, Issues and Risks

    Applications Group CADs licenses optimization:

    o No progress.

    Ellipse Support Hours Optimization:o The project team is doing the conciliation process for September period.

    Communications Group Fixed Telephone Optimization:

    o There is an issue with PC Systel reports and the contractor is working for fix it.

    Local Contractso Meeting with contract area to start the bidding process.

    Progress : 76.5%

    IT Service CatalogGilmer Sanchez (PM)

    Achievements, Issues and Risks

    ACHIEVEMENTS:- The training sessions are being developed:

    1. The training was postponed for the next week.- Reviewed action plan draft and the commitments were:

    1.Update Initiative Portfolio: Done

    2. Templates was reviewed and finished.

    NEXT WEEK:- Train the first group in the initiative management process.- Schedule the second training.

    IT Global ProjectsJorge Garcia (SOL Owner), Luis Orna (PM), Giovanna Tito (MineView PM)Infrastructure

    PROJECT SOL

    Manage Service Selection Vendor Project (100%)

    The Legal and Contract areas from Yanacocha are continuing dealing with CSC legal area in order to define the final documents to close the

    contract.

    EUC- Service Desk

    CA Tool Stage 3: Working through scope of implementation, Risks, GAPS, and challenges to determine what system functions will be locked dowfor end of January to support parallel testing and User training and what can continue with implementation through April.

    CA Demo of the Suit of CA Tools was held : Service Catalog, Service Desk, Asset Management, CMDB

    EUC Technicians installed Bomgar and schedule time to become familiar with Bomgar and Active Boot Tools

    EUC Technicians are receiving Knowledge Transfer in tools for remote control and booting.

    EUC was the Go Live on Monday: Global Team has recognized the participation in this effort of all regions.

    WINDOWS 7 & OFFICE 2010 UPGRADE

    Technical Training was scheduled for resolve installation, configuration, logon, printer issues in Windows 7 for next January.

    Hardware for SCCM has been installed. Secondary server for Peru is being made on its ordering and installation

    Next week will start the IE8 Testing for Web Applications with the Key User testers.

    IE8 will become the new browser standard for NMC: Applications based in this browser will be tested by Nov. 18. 30%

    About image creation, the strategy of creating a hybrid image has been adopted

    The SOW for the SCCM SW environment has been presented, and is currently reviewed.

    MINEVIEW PROJECT

    The real time reports tests were postponed until November 8th.

    inventory.

  • 8/8/2019 IT Weekly Report 20101102 (Peru)

    19/37

    NITIATIVESAND PROJECTSIT Resources Optimization Program Phase IIMilton Oblitas (PM)

    Status Start Initiatives Business Analysts Project Managers On Going Projects Closed

    February 2010 1 4 3 4 2

    Achievements, Issues and Risks

    Applications Group CADs licenses optimization:

    o No progress.

    Ellipse Support Hours Optimization:o The project team is doing the conciliation process for September period.

    Communications Group Fixed Telephone Optimization:

    o There is an issue with PC Systel reports and the contractor is working for fix it.

    Local Contractso Meeting with contract area to start the bidding process.

    Progress : 76.5%

    IT Service CatalogGilmer Sanchez (PM)

    Achievements, Issues and Risks

    ACHIEVEMENTS:- The training sessions are being developed:

    1. The training was postponed for the next week.- Reviewed action plan draft and the commitments were:

    1.Update Initiative Portfolio: Done

    2. Templates was reviewed and finished.

    NEXT WEEK:- Train the first group in the initiative management process.- Schedule the second training.

    IT Global ProjectsJorge Garcia (SOL Owner), Luis Orna (PM), Giovanna Tito (MineView PM)Infrastructure

    PROJECT SOL

    Manage Service Selection Vendor Project (100%)

    The Legal and Contract areas from Yanacocha are continuing dealing with CSC legal area in order to define the final documents to close the

    contract.

    EUC- Service Desk

    CA Tool Stage 3: Working through scope of implementation, Risks, GAPS, and challenges to determine what system functions will be locked dowfor end of January to support parallel testing and User training and what can continue with implementation through April.

    CA Demo of the Suit of CA Tools was held : Service Catalog, Service Desk, Asset Management, CMDB

    EUC Technicians installed Bomgar and schedule time to become familiar with Bomgar and Active Boot Tools

    EUC Technicians are receiving Knowledge Transfer in tools for remote control and booting.

    EUC was the Go Live on Monday: Global Team has recognized the participation in this effort of all regions.

    WINDOWS 7 & OFFICE 2010 UPGRADE

    Technical Training was scheduled for resolve installation, configuration, logon, printer issues in Windows 7 for next January.

    Hardware for SCCM has been installed. Secondary server for Peru is being made on its ordering and installation

    Next week will start the IE8 Testing for Web Applications with the Key User testers.

    IE8 will become the new browser standard for NMC: Applications based in this browser will be tested by Nov. 18. 30%

    About image creation, the strategy of creating a hybrid image has been adopted

    The SOW for the SCCM SW environment has been presented, and is currently reviewed.

    MINEVIEW PROJECT

    The real time reports tests were postponed until November 8th.

    PROJECT: Luis Orna (PM) Mine Maintenance -Defined agenda for NMT People that are coming

  • 8/8/2019 IT Weekly Report 20101102 (Peru)

    20/37

    NITIATIVESAND PROJECTSIT Resources Optimization Program Phase IIMilton Oblitas (PM)

    Status Start Initiatives Business Analysts Project Managers On Going Projects Closed

    February 2010 1 4 3 4 2

    Achievements, Issues and Risks

    Applications Group CADs licenses optimization:

    o No progress.

    Ellipse Support Hours Optimization:o The project team is doing the conciliation process for September period.

    Communications Group Fixed Telephone Optimization:

    o There is an issue with PC Systel reports and the contractor is working for fix it.

    Local Contractso Meeting with contract area to start the bidding process.

    Progress : 76.5%

    IT Service CatalogGilmer Sanchez (PM)

    Achievements, Issues and Risks

    ACHIEVEMENTS:- The training sessions are being developed:

    1. The training was postponed for the next week.- Reviewed action plan draft and the commitments were:

    1.Update Initiative Portfolio: Done

    2. Templates was reviewed and finished.

    NEXT WEEK:- Train the first group in the initiative management process.- Schedule the second training.

    IT Global ProjectsJorge Garcia (SOL Owner), Luis Orna (PM), Giovanna Tito (MineView PM)Infrastructure

    PROJECT SOL

    Manage Service Selection Vendor Project (100%)

    The Legal and Contract areas from Yanacocha are continuing dealing with CSC legal area in order to define the final documents to close the

    contract.

    EUC- Service Desk

    CA Tool Stage 3: Working through scope of implementation, Risks, GAPS, and challenges to determine what system functions will be locked dowfor end of January to support parallel testing and User training and what can continue with implementation through April.

    CA Demo of the Suit of CA Tools was held : Service Catalog, Service Desk, Asset Management, CMDB

    EUC Technicians installed Bomgar and schedule time to become familiar with Bomgar and Active Boot Tools

    EUC Technicians are receiving Knowledge Transfer in tools for remote control and booting.

    EUC was the Go Live on Monday: Global Team has recognized the participation in this effort of all regions.

    WINDOWS 7 & OFFICE 2010 UPGRADE

    Technical Training was scheduled for resolve installation, configuration, logon, printer issues in Windows 7 for next January.

    Hardware for SCCM has been installed. Secondary server for Peru is being made on its ordering and installation

    Next week will start the IE8 Testing for Web Applications with the Key User testers.

    IE8 will become the new browser standard for NMC: Applications based in this browser will be tested by Nov. 18. 30%

    About image creation, the strategy of creating a hybrid image has been adopted

    The SOW for the SCCM SW environment has been presented, and is currently reviewed.

    MINEVIEW PROJECT

    The real time reports tests were postponed until November 8th.

    Light Vehicle GPS from November 15th to 18th for the Project

  • 8/8/2019 IT Weekly Report 20101102 (Peru)

    21/37

    NITIATIVESAND PROJECTSIT Resources Optimization Program Phase IIMilton Oblitas (PM)

    Status Start Initiatives Business Analysts Project Managers On Going Projects Closed

    February 2010 1 4 3 4 2

    Achievements, Issues and Risks

    Applications Group CADs licenses optimization:

    o No progress.

    Ellipse Support Hours Optimization:o The project team is doing the conciliation process for September period.

    Communications Group Fixed Telephone Optimization:

    o There is an issue with PC Systel reports and the contractor is working for fix it.

    Local Contractso Meeting with contract area to start the bidding process.

    Progress : 76.5%

    IT Service CatalogGilmer Sanchez (PM)

    Achievements, Issues and Risks

    ACHIEVEMENTS:- The training sessions are being developed:

    1. The training was postponed for the next week.- Reviewed action plan draft and the commitments were:

    1.Update Initiative Portfolio: Done

    2. Templates was reviewed and finished.

    NEXT WEEK:- Train the first group in the initiative management process.- Schedule the second training.

    IT Global ProjectsJorge Garcia (SOL Owner), Luis Orna (PM), Giovanna Tito (MineView PM)Infrastructure

    PROJECT SOL

    Manage Service Selection Vendor Project (100%)

    The Legal and Contract areas from Yanacocha are continuing dealing with CSC legal area in order to define the final documents to close the

    contract.

    EUC- Service Desk

    CA Tool Stage 3: Working through scope of implementation, Risks, GAPS, and challenges to determine what system functions will be locked dowfor end of January to support parallel testing and User training and what can continue with implementation through April.

    CA Demo of the Suit of CA Tools was held : Service Catalog, Service Desk, Asset Management, CMDB

    EUC Technicians installed Bomgar and schedule time to become familiar with Bomgar and Active Boot Tools

    EUC Technicians are receiving Knowledge Transfer in tools for remote control and booting.

    EUC was the Go Live on Monday: Global Team has recognized the participation in this effort of all regions.

    WINDOWS 7 & OFFICE 2010 UPGRADE

    Technical Training was scheduled for resolve installation, configuration, logon, printer issues in Windows 7 for next January.

    Hardware for SCCM has been installed. Secondary server for Peru is being made on its ordering and installation

    Next week will start the IE8 Testing for Web Applications with the Key User testers.

    IE8 will become the new browser standard for NMC: Applications based in this browser will be tested by Nov. 18. 30%

    About image creation, the strategy of creating a hybrid image has been adopted

    The SOW for the SCCM SW environment has been presented, and is currently reviewed.

    MINEVIEW PROJECT

    The real time reports tests were postponed until November 8th.

    Deployment.

  • 8/8/2019 IT Weekly Report 20101102 (Peru)

    22/37

    NITIATIVESAND PROJECTSIT Resources Optimization Program Phase IIMilton Oblitas (PM)

    Status Start Initiatives Business Analysts Project Managers On Going Projects Closed

    February 2010 1 4 3 4 2

    Achievements, Issues and Risks

    Applications Group CADs licenses optimization:

    o No progress.

    Ellipse Support Hours Optimization:o The project team is doing the conciliation process for September period.

    Communications Group Fixed Telephone Optimization:

    o There is an issue with PC Systel reports and the contractor is working for fix it.

    Local Contractso Meeting with contract area to start the bidding process.

    Progress : 76.5%

    IT Service CatalogGilmer Sanchez (PM)

    Achievements, Issues and Risks

    ACHIEVEMENTS:- The training sessions are being developed:

    1. The training was postponed for the next week.- Reviewed action plan draft and the commitments were:

    1.Update Initiative Portfolio: Done

    2. Templates was reviewed and finished.

    NEXT WEEK:- Train the first group in the initiative management process.- Schedule the second training.

    IT Global ProjectsJorge Garcia (SOL Owner), Luis Orna (PM), Giovanna Tito (MineView PM)Infrastructure

    PROJECT SOL

    Manage Service Selection Vendor Project (100%)

    The Legal and Contract areas from Yanacocha are continuing dealing with CSC legal area in order to define the final documents to close the

    contract.

    EUC- Service Desk

    CA Tool Stage 3: Working through scope of implementation, Risks, GAPS, and challenges to determine what system functions will be locked dowfor end of January to support parallel testing and User training and what can continue with implementation through April.

    CA Demo of the Suit of CA Tools was held : Service Catalog, Service Desk, Asset Management, CMDB

    EUC Technicians installed Bomgar and schedule time to become familiar with Bomgar and Active Boot Tools

    EUC Technicians are receiving Knowledge Transfer in tools for remote control and booting.

    EUC was the Go Live on Monday: Global Team has recognized the participation in this effort of all regions.

    WINDOWS 7 & OFFICE 2010 UPGRADE

    Technical Training was scheduled for resolve installation, configuration, logon, printer issues in Windows 7 for next January.

    Hardware for SCCM has been installed. Secondary server for Peru is being made on its ordering and installation

    Next week will start the IE8 Testing for Web Applications with the Key User testers.

    IE8 will become the new browser standard for NMC: Applications based in this browser will be tested by Nov. 18. 30%

    About image creation, the strategy of creating a hybrid image has been adopted

    The SOW for the SCCM SW environment has been presented, and is currently reviewed.

    MINEVIEW PROJECT

    The real time reports tests were postponed until November 8th.

    -The meeting with maintenance area was held to

  • 8/8/2019 IT Weekly Report 20101102 (Peru)

    23/37

    NITIATIVESAND PROJECTSIT Resources Optimization Program Phase IIMilton Oblitas (PM)

    Status Start Initiatives Business Analysts Project Managers On Going Projects Closed

    February 2010 1 4 3 4 2

    Achievements, Issues and Risks

    Applications Group CADs licenses optimization:

    o No progress.

    Ellipse Support Hours Optimization:o The project team is doing the conciliation process for September period.

    Communications Group Fixed Telephone Optimization:

    o There is an issue with PC Systel reports and the contractor is working for fix it.

    Local Contractso Meeting with contract area to start the bidding process.

    Progress : 76.5%

    IT Service CatalogGilmer Sanchez (PM)

    Achievements, Issues and Risks

    ACHIEVEMENTS:- The training sessions are being developed:

    1. The training was postponed for the next week.- Reviewed action plan draft and the commitments were:

    1.Update Initiative Portfolio: Done

    2. Templates was reviewed and finished.

    NEXT WEEK:- Train the first group in the initiative management process.- Schedule the second training.

    IT Global ProjectsJorge Garcia (SOL Owner), Luis Orna (PM), Giovanna Tito (MineView PM)Infrastructure

    PROJECT SOL

    Manage Service Selection Vendor Project (100%)

    The Legal and Contract areas from Yanacocha are continuing dealing with CSC legal area in order to define the final documents to close the

    contract.

    EUC- Service Desk

    CA Tool Stage 3: Working through scope of implementation, Risks, GAPS, and challenges to determine what system functions will be locked dowfor end of January to support parallel testing and User training and what can continue with implementation through April.

    CA Demo of the Suit of CA Tools was held : Service Catalog, Service Desk, Asset Management, CMDB

    EUC Technicians installed Bomgar and schedule time to become familiar with Bomgar and Active Boot Tools

    EUC Technicians are receiving Knowledge Transfer in tools for remote control and booting.

    EUC was the Go Live on Monday: Global Team has recognized the participation in this effort of all regions.

    WINDOWS 7 & OFFICE 2010 UPGRADE

    Technical Training was scheduled for resolve installation, configuration, logon, printer issues in Windows 7 for next January.

    Hardware for SCCM has been installed. Secondary server for Peru is being made on its ordering and installation

    Next week will start the IE8 Testing for Web Applications with the Key User testers.

    IE8 will become the new browser standard for NMC: Applications based in this browser will be tested by Nov. 18. 30%

    About image creation, the strategy of creating a hybrid image has been adopted

    The SOW for the SCCM SW environment has been presented, and is currently reviewed.

    MINEVIEW PROJECT

    The real time reports tests were postponed until November 8th.

    define the prerequisites, variables to control and

  • 8/8/2019 IT Weekly Report 20101102 (Peru)

    24/37

    NITIATIVESAND PROJECTSIT Resources Optimization Program Phase IIMilton Oblitas (PM)

    Status Start Initiatives Business Analysts Project Managers On Going Projects Closed

    February 2010 1 4 3 4 2

    Achievements, Issues and Risks

    Applications Group CADs licenses optimization:

    o No progress.

    Ellipse Support Hours Optimization:o The project team is doing the conciliation process for September period.

    Communications Group Fixed Telephone Optimization:

    o There is an issue with PC Systel reports and the contractor is working for fix it.

    Local Contractso Meeting with contract area to start the bidding process.

    Progress : 76.5%

    IT Service CatalogGilmer Sanchez (PM)

    Achievements, Issues and Risks

    ACHIEVEMENTS:- The training sessions are being developed:

    1. The training was postponed for the next week.- Reviewed action plan draft and the commitments were:

    1.Update Initiative Portfolio: Done

    2. Templates was reviewed and finished.

    NEXT WEEK:- Train the first group in the initiative management process.- Schedule the second training.

    IT Global ProjectsJorge Garcia (SOL Owner), Luis Orna (PM), Giovanna Tito (MineView PM)Infrastructure

    PROJECT SOL

    Manage Service Selection Vendor Project (100%)

    The Legal and Contract areas from Yanacocha are continuing dealing with CSC legal area in order to define the final documents to close the

    contract.

    EUC- Service Desk

    CA Tool Stage 3: Working through scope of implementation, Risks, GAPS, and challenges to determine what system functions will be locked dowfor end of January to support parallel testing and User training and what can continue with implementation through April.

    CA Demo of the Suit of CA Tools was held : Service Catalog, Service Desk, Asset Management, CMDB

    EUC Technicians installed Bomgar and schedule time to become familiar with Bomgar and Active Boot Tools

    EUC Technicians are receiving Knowledge Transfer in tools for remote control and booting.

    EUC was the Go Live on Monday: Global Team has recognized the participation in this effort of all regions.

    WINDOWS 7 & OFFICE 2010 UPGRADE

    Technical Training was scheduled for resolve installation, configuration, logon, printer issues in Windows 7 for next January.

    Hardware for SCCM has been installed. Secondary server for Peru is being made on its ordering and installation

    Next week will start the IE8 Testing for Web Applications with the Key User testers.

    IE8 will become the new browser standard for NMC: Applications based in this browser will be tested by Nov. 18. 30%

    About image creation, the strategy of creating a hybrid image has been adopted

    The SOW for the SCCM SW environment has been presented, and is currently reviewed.

    MINEVIEW PROJECT

    The real time reports tests were postponed until November 8th.

    vehicles to be installed the GPS

  • 8/8/2019 IT Weekly Report 20101102 (Peru)

    25/37

    NITIATIVESAND PROJECTSIT Resources Optimization Program Phase IIMilton Oblitas (PM)

    Status Start Initiatives Business Analysts Project Managers On Going Projects Closed

    February 2010 1 4 3 4 2

    Achievements, Issues and Risks

    Applications Group CADs licenses optimization:

    o No progress.

    Ellipse Support Hours Optimization:o The project team is doing the conciliation process for September period.

    Communications Group Fixed Telephone Optimization:

    o There is an issue with PC Systel reports and the contractor is working for fix it.

    Local Contractso Meeting with contract area to start the bidding process.

    Progress : 76.5%

    IT Service CatalogGilmer Sanchez (PM)

    Achievements, Issues and Risks

    ACHIEVEMENTS:- The training sessions are being developed:

    1. The training was postponed for the next week.- Reviewed action plan draft and the commitments were:

    1.Update Initiative Portfolio: Done

    2. Templates was reviewed and finished.

    NEXT WEEK:- Train the first group in the initiative management process.- Schedule the second training.

    IT Global ProjectsJorge Garcia (SOL Owner), Luis Orna (PM), Giovanna Tito (MineView PM)Infrastructure

    PROJECT SOL

    Manage Service Selection Vendor Project (100%)

    The Legal and Contract areas from Yanacocha are continuing dealing with CSC legal area in order to define the final documents to close the

    contract.

    EUC- Service Desk

    CA Tool Stage 3: Working through scope of implementation, Risks, GAPS, and challenges to determine what system functions will be locked dowfor end of January to support parallel testing and User training and what can continue with implementation through April.

    CA Demo of the Suit of CA Tools was held : Service Catalog, Service Desk, Asset Management, CMDB

    EUC Technicians installed Bomgar and schedule time to become familiar with Bomgar and Active Boot Tools

    EUC Technicians are receiving Knowledge Transfer in tools for remote control and booting.

    EUC was the Go Live on Monday: Global Team has recognized the participation in this effort of all regions.

    WINDOWS 7 & OFFICE 2010 UPGRADE

    Technical Training was scheduled for resolve installation, configuration, logon, printer issues in Windows 7 for next January.

    Hardware for SCCM has been installed. Secondary server for Peru is being made on its ordering and installation

    Next week will start the IE8 Testing for Web Applications with the Key User testers.

    IE8 will become the new browser standard for NMC: Applications based in this browser will be tested by Nov. 18. 30%

    About image creation, the strategy of creating a hybrid image has been adopted

    The SOW for the SCCM SW environment has been presented, and is currently reviewed.

    MINEVIEW PROJECT

    The real time reports tests were postponed until November 8th.

    INITIATIVE:Anti-collision

    Alan Rueda (BA) Mine Operations The inform of the visit was done.

  • 8/8/2019 IT Weekly Report 20101102 (Peru)

    26/37

    NITIATIVESAND PROJECTSIT Resources Optimization Program Phase IIMilton Oblitas (PM)

    Status Start Initiatives Business Analysts Project Managers On Going Projects Closed

    February 2010 1 4 3 4 2

    Achievements, Issues and Risks

    Applications Group CADs licenses optimization:

    o No progress.

    Ellipse Support Hours Optimization:o The project team is doing the conciliation process for September period.

    Communications Group Fixed Telephone Optimization:

    o There is an issue with PC Systel reports and the contractor is working for fix it.

    Local Contractso Meeting with contract area to start the bidding process.

    Progress : 76.5%

    IT Service CatalogGilmer Sanchez (PM)

    Achievements, Issues and Risks

    ACHIEVEMENTS:- The training sessions are being developed:

    1. The training was postponed for the next week.- Reviewed action plan draft and the commitments were:

    1.Update Initiative Portfolio: Done

    2. Templates was reviewed and finished.

    NEXT WEEK:- Train the first group in the initiative management process.- Schedule the second training.

    IT Global ProjectsJorge Garcia (SOL Owner), Luis Orna (PM), Giovanna Tito (MineView PM)Infrastructure

    PROJECT SOL

    Manage Service Selection Vendor Project (100%)

    The Legal and Contract areas from Yanacocha are continuing dealing with CSC legal area in order to define the final documents to close the

    contract.

    EUC- Service Desk

    CA Tool Stage 3: Working through scope of implementation, Risks, GAPS, and challenges to determine what system functions will be locked dowfor end of January to support parallel testing and User training and what can continue with implementation through April.

    CA Demo of the Suit of CA Tools was held : Service Catalog, Service Desk, Asset Management, CMDB

    EUC Technicians installed Bomgar and schedule time to become familiar with Bomgar and Active Boot Tools

    EUC Technicians are receiving Knowledge Transfer in tools for remote control and booting.

    EUC was the Go Live on Monday: Global Team has recognized the participation in this effort of all regions.

    WINDOWS 7 & OFFICE 2010 UPGRADE

    Technical Training was scheduled for resolve installation, configuration, logon, printer issues in Windows 7 for next January.

    Hardware for SCCM has been installed. Secondary server for Peru is being made on its ordering and installation

    Next week will start the IE8 Testing for Web Applications with the Key User testers.

    IE8 will become the new browser standard for NMC: Applications based in this browser will be tested by Nov. 18. 30%

    About image creation, the strategy of creating a hybrid image has been adopted

    The SOW for the SCCM SW environment has been presented, and is currently reviewed.

    MINEVIEW PROJECT

    The real time reports tests were postponed until November 8th.

    INITIATIVE: Javier Ortiz (BA) Metallurgical Services The cost evaluation for the AFE was

  • 8/8/2019 IT Weekly Report 20101102 (Peru)

    27/37

    NITIATIVESAND PROJECTSIT Resources Optimization Program Phase IIMilton Oblitas (PM)

    Status Start Initiatives Business Analysts Project Managers On Going Projects Closed

    February 2010 1 4 3 4 2

    Achievements, Issues and Risks

    Applications Group CADs licenses optimization:

    o No progress.

    Ellipse Support Hours Optimization:o The project team is doing the conciliation process for September period.

    Communications Group Fixed Telephone Optimization:

    o There is an issue with PC Systel reports and the contractor is working for fix it.

    Local Contractso Meeting with contract area to start the bidding process.

    Progress : 76.5%

    IT Service CatalogGilmer Sanchez (PM)

    Achievements, Issues and Risks

    ACHIEVEMENTS:- The training sessions are being developed:

    1. The training was postponed for the next week.- Reviewed action plan draft and the commitments were:

    1.Update Initiative Portfolio: Done

    2. Templates was reviewed and finished.

    NEXT WEEK:- Train the first group in the initiative management process.- Schedule the second training.

    IT Global ProjectsJorge Garcia (SOL Owner), Luis Orna (PM), Giovanna Tito (MineView PM)Infrastructure

    PROJECT SOL

    Manage Service Selection Vendor Project (100%)

    The Legal and Contract areas from Yanacocha are continuing dealing with CSC legal area in order to define the final documents to close the

    contract.

    EUC- Service Desk

    CA Tool Stage 3: Working through scope of implementation, Risks, GAPS, and challenges to determine what system functions will be locked dowfor end of January to support parallel testing and User training and what can continue with implementation through April.

    CA Demo of the Suit of CA Tools was held : Service Catalog, Service Desk, Asset Management, CMDB

    EUC Technicians installed Bomgar and schedule time to become familiar with Bomgar and Active Boot Tools

    EUC Technicians are receiving Knowledge Transfer in tools for remote control and booting.

    EUC was the Go Live on Monday: Global Team has recognized the participation in this effort of all regions.

    WINDOWS 7 & OFFICE 2010 UPGRADE

    Technical Training was scheduled for resolve installation, configuration, logon, printer issues in Windows 7 for next January.

    Hardware for SCCM has been installed. Secondary server for Peru is being made on its ordering and installation

    Next week will start the IE8 Testing for Web Applications with the Key User testers.

    IE8 will become the new browser standard for NMC: Applications based in this browser will be tested by Nov. 18. 30%

    About image creation, the strategy of creating a hybrid image has been adopted

    The SOW for the SCCM SW environment has been presented, and is currently reviewed.

    MINEVIEW PROJECT

    The real time reports tests were postponed until November 8th.

    Metallurgical Balance concluded. The complete AFE will be revie

  • 8/8/2019 IT Weekly Report 20101102 (Peru)

    28/37

    NITIATIVESAND PROJECTSIT Resources Optimization Program Phase IIMilton Oblitas (PM)

    Status Start Initiatives Business Analysts Project Managers On Going Projects Closed

    February 2010 1 4 3 4 2

    Achievements, Issues and Risks

    Applications Group CADs licenses optimization:

    o No progress.

    Ellipse Support Hours Optimization:o The project team is doing the conciliation process for September period.

    Communications Group Fixed Telephone Optimization:

    o There is an issue with PC Systel reports and the contractor is working for fix it.

    Local Contractso Meeting with contract area to start the bidding process.

    Progress : 76.5%

    IT Service CatalogGilmer Sanchez (PM)

    Achievements, Issues and Risks

    ACHIEVEMENTS:- The training sessions are being developed:

    1. The training was postponed for the next week.- Reviewed action plan draft and the commitments were:

    1.Update Initiative Portfolio: Done

    2. Templates was reviewed and finished.

    NEXT WEEK:- Train the first group in the initiative management process.- Schedule the second training.

    IT Global ProjectsJorge Garcia (SOL Owner), Luis Orna (PM), Giovanna Tito (MineView PM)Infrastructure

    PROJECT SOL

    Manage Service Selection Vendor Project (100%)

    The Legal and Contract areas from Yanacocha are continuing dealing with CSC legal area in order to define the final documents to close the

    contract.

    EUC- Service Desk

    CA Tool Stage 3: Working through scope of implementation, Risks, GAPS, and challenges to determine what system functions will be locked dowfor end of January to support parallel testing and User training and what can continue with implementation through April.

    CA Demo of the Suit of CA Tools was held : Service Catalog, Service Desk, Asset Management, CMDB

    EUC Technicians installed Bomgar and schedule time to become familiar with Bomgar and Active Boot Tools

    EUC Technicians are receiving Knowledge Transfer in tools for remote control and booting.

    EUC was the Go Live on Monday: Global Team has recognized the participation in this effort of all regions.

    WINDOWS 7 & OFFICE 2010 UPGRADE

    Technical Training was scheduled for resolve installation, configuration, logon, printer issues in Windows 7 for next January.

    Hardware for SCCM has been installed. Secondary server for Peru is being made on its ordering and installation

    Next week will start the IE8 Testing for Web Applications with the Key User testers.

    IE8 will become the new browser standard for NMC: Applications based in this browser will be tested by Nov. 18. 30%

    About image creation, the strategy of creating a hybrid image has been adopted

    The SOW for the SCCM SW environment has been presented, and is currently reviewed.

    MINEVIEW PROJECT

    The real time reports tests were postponed until November 8th.

    by the next week with corporate.

  • 8/8/2019 IT Weekly Report 20101102 (Peru)

    29/37

    NITIATIVESAND PROJECTSIT Resources Optimization Program Phase IIMilton Oblitas (PM)

    Status Start Initiatives Business Analysts Project Managers On Going Projects Closed

    February 2010 1 4 3 4 2

    Achievements, Issues and Risks

    Applications Group CADs licenses optimization:

    o No progress.

    Ellipse Support Hours Optimization:o The project team is doing the conciliation process for September period.

    Communications Group Fixed Telephone Optimization:

    o There is an issue with PC Systel reports and the contractor is working for fix it.

    Local Contractso Meeting with contract area to start the bidding process.

    Progress : 76.5%

    IT Service CatalogGilmer Sanchez (PM)

    Achievements, Issues and Risks

    ACHIEVEMENTS:- The training sessions are being developed:

    1. The training was postponed for the next week.- Reviewed action plan draft and the commitments were:

    1.Update Initiative Portfolio: Done

    2. Templates was reviewed and finished.

    NEXT WEEK:- Train the first group in the initiative management process.- Schedule the second training.

    IT Global ProjectsJorge Garcia (SOL Owner), Luis Orna (PM), Giovanna Tito (MineView PM)Infrastructure

    PROJECT SOL

    Manage Service Selection Vendor Project (100%)

    The Legal and Contract areas from Yanacocha are continuing dealing with CSC legal area in order to define the final documents to close the

    contract.

    EUC- Service Desk

    CA Tool Stage 3: Working through scope of implementation, Risks, GAPS, and challenges to determine what system functions will be locked dowfor end of January to support parallel testing and User training and what can continue with implementation through April.

    CA Demo of the Suit of CA Tools was held : Service Catalog, Service Desk, Asset Management, CMDB

    EUC Technicians installed Bomgar and schedule time to become familiar with Bomgar and Active Boot Tools

    EUC Technicians are receiving Knowledge Transfer in tools for remote control and booting.

    EUC was the Go Live on Monday: Global Team has recognized the participation in this effort of all regions.

    WINDOWS 7 & OFFICE 2010 UPGRADE

    Technical Training was scheduled for resolve installation, configuration, logon, printer issues in Windows 7 for next January.

    Hardware for SCCM has been installed. Secondary server for Peru is being made on its ordering and installation

    Next week will start the IE8 Testing for Web Applications with the Key User testers.

    IE8 will become the new browser standard for NMC: Applications based in this browser will be tested by Nov. 18. 30%

    About image creation, the strategy of creating a hybrid image has been adopted

    The SOW for the SCCM SW environment has been presented, and is currently reviewed.

    MINEVIEW PROJECT

    The real time reports tests were postponed until November 8th.

    INITIATIVE:PADs movements control

    Josue Tejada (BA) Mine Planning The servers arrived to the mine by and will b

  • 8/8/2019 IT Weekly Report 20101102 (Peru)

    30/37

    NITIATIVESAND PROJECTSIT Resources Optimization Program Phase IIMilton Oblitas (PM)

    Status Start Initiatives Business Analysts Project Managers On Going Projects Closed

    February 2010 1 4 3 4 2

    Achievements, Issues and Risks

    Applications Group CADs licenses optimization:

    o No progress.

    Ellipse Support Hours Optimization:o The project team is doing the conciliation process for September period.

    Communications Group Fixed Telephone Optimization:

    o There is an issue with PC Systel reports and the contractor is working for fix it.

    Local Contractso Meeting with contract area to start the bidding process.

    Progress : 76.5%

    IT Service CatalogGilmer Sanchez (PM)

    Achievements, Issues and Risks

    ACHIEVEMENTS:- The training sessions are being developed:

    1. The training was postponed for the next week.- Reviewed action plan draft and the commitments were:

    1.Update Initiative Portfolio: Done

    2. Templates was reviewed and finished.

    NEXT WEEK:- Train the first group in the initiative management process.- Schedule the second training.

    IT Global ProjectsJorge Garcia (SOL Owner), Luis Orna (PM), Giovanna Tito (MineView PM)Infrastructure

    PROJECT SOL

    Manage Service Selection Vendor Project (100%