Issues Associated with Retrofitting Coastal Power Plants · PDF fileIssues Associated with...

24
Issues Associated with Retrofitting Coastal Power Plants John S. Maulbetsch Once-through Cooling: Results Symposium University of California Davis, California January 16, 2008

Transcript of Issues Associated with Retrofitting Coastal Power Plants · PDF fileIssues Associated with...

Page 1: Issues Associated with Retrofitting Coastal Power Plants · PDF fileIssues Associated with Retrofitting Coastal Power Plants John S. Maulbetsch Once-through Cooling: Results Symposium

Issues Associated withRetrofitting Coastal Power Plants

John S. Maulbetsch

Once-through Cooling:Results Symposium

University of CaliforniaDavis, CaliforniaJanuary 16, 2008

Page 2: Issues Associated with Retrofitting Coastal Power Plants · PDF fileIssues Associated with Retrofitting Coastal Power Plants John S. Maulbetsch Once-through Cooling: Results Symposium

Topics for the next 20 minutes

• Estimating capital costs of retrofit• Some comparisons• Additional costs of retrofitting

Page 3: Issues Associated with Retrofitting Coastal Power Plants · PDF fileIssues Associated with Retrofitting Coastal Power Plants John S. Maulbetsch Once-through Cooling: Results Symposium

Estimating capital costs

Two approaches1. Bottom up---build up from design,

component costs and installation costs2. Top down---

• Establish a range based on known costs of other projects

• Place in range based on a “degree of difficulty” judgment

Page 4: Issues Associated with Retrofitting Coastal Power Plants · PDF fileIssues Associated with Retrofitting Coastal Power Plants John S. Maulbetsch Once-through Cooling: Results Symposium

Establishing the range

• Correlation of reported project costs– 50 plants– Coal/gas/nuclear– Fresh/brackish/saline water source– Wide range of climates

• Circulating water flow used as correlating factor

• Costs fell into three clusters– Low; average; high

Page 5: Issues Associated with Retrofitting Coastal Power Plants · PDF fileIssues Associated with Retrofitting Coastal Power Plants John S. Maulbetsch Once-through Cooling: Results Symposium

Graphical correlationsRetrofit Project Costs---Degree of Difficulty

0

200

400

600

800

1,000

1,200

0 500,000 1,000,000 1,500,000 2,000,000 2,500,000 3,000,000

Circulating Water Flowrate, gpm

Ret

rofit

Cos

t, M

illio

ns o

f $

Easy Average Difficult

~ $425/gpm

~ $165/gpm

~ $275/gpm

Page 6: Issues Associated with Retrofitting Coastal Power Plants · PDF fileIssues Associated with Retrofitting Coastal Power Plants John S. Maulbetsch Once-through Cooling: Results Symposium

Things that set degree of difficulty

• Siting tower– Relocation of structures– Land acquisition– Grading of site for gravity return

• Excavation for circ. water lines and sump– Interferences– Soil conditions

• Wet, unstable• Bedrock• Contaminated

Page 7: Issues Associated with Retrofitting Coastal Power Plants · PDF fileIssues Associated with Retrofitting Coastal Power Plants John S. Maulbetsch Once-through Cooling: Results Symposium

More things

• Noise control– Special fans– Wind walls

• Plume abatement– Higher cost tower– Harder to site

Page 8: Issues Associated with Retrofitting Coastal Power Plants · PDF fileIssues Associated with Retrofitting Coastal Power Plants John S. Maulbetsch Once-through Cooling: Results Symposium

Another thing

Base-load plant with long remaining life– Re-optimize

• Lower circulating water flow• Higher range

– Probable re-tubing of condenser– Relocation of inlet exit lines– Extended outage for modifications

Page 9: Issues Associated with Retrofitting Coastal Power Plants · PDF fileIssues Associated with Retrofitting Coastal Power Plants John S. Maulbetsch Once-through Cooling: Results Symposium

Some comparisons

• Maulbetsch Consulting/TetraTech– Direct comparison at 15 plants– MC/TT = 1.03 (Total for all 15 plants)

Page 10: Issues Associated with Retrofitting Coastal Power Plants · PDF fileIssues Associated with Retrofitting Coastal Power Plants John S. Maulbetsch Once-through Cooling: Results Symposium

Comparison with “Average”

0

50

100

150

200

250

300

0 50 100 150 200 250

Maulbetsch Consulting "Average", $ millions

Tetr

aTec

h, $

mill

ions

Scattergood

Huntington Beach

Pittsburg

+ 20%+ 40%

Page 11: Issues Associated with Retrofitting Coastal Power Plants · PDF fileIssues Associated with Retrofitting Coastal Power Plants John S. Maulbetsch Once-through Cooling: Results Symposium

Comparison with “Difficult”

0

100

200

300

400

500

600

700

800

0 100 200 300 400 500 600 700 800

Maulbetsch Consulting "Difficult", $ millions

Tetr

aTec

h, $

mill

ions Nuclear plants

Page 12: Issues Associated with Retrofitting Coastal Power Plants · PDF fileIssues Associated with Retrofitting Coastal Power Plants John S. Maulbetsch Once-through Cooling: Results Symposium

Comparison with Estimate

0

50

100

150

200

250

300

0 50 100 150 200 250 300 350

Maulbetsch Consulting Estimate, $ millions

Tetr

aTec

h E

stim

ate,

$ m

illio

ns

+ ~20%

- ~20%

Haynes

Alamitos

Pittsburg

Scattergood

El Segundo

Page 13: Issues Associated with Retrofitting Coastal Power Plants · PDF fileIssues Associated with Retrofitting Coastal Power Plants John S. Maulbetsch Once-through Cooling: Results Symposium

Plants with differences

• Alamitos: 6 units; 1982 MW; 800,000 gpm– MC; rated as “difficult” ($325 million)

• Plume abatement• High circ. water line installation costs• Demolition costs

– T’Tech ($210 million; ~ MC “average”)• No plume abatement (~ $60 million)• 3 towers vs. 6 towers (large savings on circ. line costs)

Page 14: Issues Associated with Retrofitting Coastal Power Plants · PDF fileIssues Associated with Retrofitting Coastal Power Plants John S. Maulbetsch Once-through Cooling: Results Symposium

Plants with differences

• Scattergood: 3 units; 803 MW; 344,000 gpm– MC; rated as “average” to “difficult” ($120 MM)

• Plume abatement• One tower per unit• Moderate but not severe line costs

– T’Tech ($160 million; > MC “difficult”)• Plume abatement• Two towers for Unit 3• Costs related to switchyard• Noise abatement

Page 15: Issues Associated with Retrofitting Coastal Power Plants · PDF fileIssues Associated with Retrofitting Coastal Power Plants John S. Maulbetsch Once-through Cooling: Results Symposium

Additional (non-capital) costs

• Drift/PM10 offsets• Plant downtime• Land acquisition/security zone enhancement• Permitting time

Page 16: Issues Associated with Retrofitting Coastal Power Plants · PDF fileIssues Associated with Retrofitting Coastal Power Plants John S. Maulbetsch Once-through Cooling: Results Symposium

Drift/PM10 Offsets

• Assuming– Seawater make-up– Drift eliminators spec’d at 0.0005%– All drift solids considered PM10

• For a 250 MW plant operating at 80% c.fPM10 emissions ~ 60 tons/year

Page 17: Issues Associated with Retrofitting Coastal Power Plants · PDF fileIssues Associated with Retrofitting Coastal Power Plants John S. Maulbetsch Once-through Cooling: Results Symposium

Plant downtime

• Primarily affected by tie-in to condenser and intake/discharge facilities

• Estimates vary from < 1 month to ~ 1 year

• If condenser is re-optimized, time is much longer

• Costs are dependent on scheduling

Page 18: Issues Associated with Retrofitting Coastal Power Plants · PDF fileIssues Associated with Retrofitting Coastal Power Plants John S. Maulbetsch Once-through Cooling: Results Symposium

Land acquisition/security zone

• Situations where insufficient area is available on-site

• Establish a buffer zone from near neighbors• Special considerations for nuclear plants….

– Location of tower may extend security zone– Additional fencing, perimeter monitors, etc.– Increased security staff

Page 19: Issues Associated with Retrofitting Coastal Power Plants · PDF fileIssues Associated with Retrofitting Coastal Power Plants John S. Maulbetsch Once-through Cooling: Results Symposium

Permitting costs

• No basis for estimating but might be substantial– Significant time requirements – Legal and consulting assistance

Page 20: Issues Associated with Retrofitting Coastal Power Plants · PDF fileIssues Associated with Retrofitting Coastal Power Plants John S. Maulbetsch Once-through Cooling: Results Symposium

Operating costs

• Additional operating power requirements– Pumping power– Fan power

• Penalty costs—effect of cooling system on plant performance– Heat rate– Plant capacity

Page 21: Issues Associated with Retrofitting Coastal Power Plants · PDF fileIssues Associated with Retrofitting Coastal Power Plants John S. Maulbetsch Once-through Cooling: Results Symposium

Additional pumping power

• Head losses in circ. water lines

• Getting water to top of tower

• Assume….– 1000’ line– 40’ rise

• Pump power ~ 0.5%

Page 22: Issues Associated with Retrofitting Coastal Power Plants · PDF fileIssues Associated with Retrofitting Coastal Power Plants John S. Maulbetsch Once-through Cooling: Results Symposium

Fan Power

• ~ 10,000 gpm/cell• ~200 HP fan• Fan power ~ 1%

Page 23: Issues Associated with Retrofitting Coastal Power Plants · PDF fileIssues Associated with Retrofitting Coastal Power Plants John S. Maulbetsch Once-through Cooling: Results Symposium

Effect on condensing temperature

Terminal Temperature Difference (TTD)

Range

Tcond

Thot

Tcold

Circ. Water Flow

Source water temperature

Terminal Temperature Difference (TTD)

Range

Tcond

Thot

Tcold

Circ. Water Flow

Source water temperature

Terminal Temperature Difference (TTD)

Range

Tcond

Thot

Tcold

Circ. Water Flow

Source water temperature

Terminal Temperature Difference (TTD)

Range

Tcond

Thot

Tcold

Circ. Water Flow

Source water temperature

Condenser TTD

Approach

Range

Tcond

Tamb. wb

Circ. Water Flow

Thot water

Tcold water

Condenser TTD

Approach

Range

Tcond

Tamb. wb

Circ. Water Flow

Thot water

Tcold water

Condenser TTD

Approach

Range

Tcond

Tamb. wb

Circ. Water Flow

Thot water

Tcold water

Condenser TTD

Approach

Range

Tcond

Tamb. wb

Circ. Water Flow

Thot water

Tcold water

Condenser TTD

Approach

Range

Tcond

Tamb. wb

Circ. Water Flow

Thot water

Tcold water

Page 24: Issues Associated with Retrofitting Coastal Power Plants · PDF fileIssues Associated with Retrofitting Coastal Power Plants John S. Maulbetsch Once-through Cooling: Results Symposium

Cold water comparisons

Moss Landing Environmental Temperatures

50

52

54

56

58

60

62

64

66

68

70

01-Oct-05 20-Nov-05 09-Jan-06 28-Feb-06 19-Apr-06 08-Jun-06 28-Jul-06 16-Sep-06

Date

Tem

pera

ture

, F

Ocean Water Temperature Wet Bulb Max