IPS Connect 2017
WESTERN AUSTRALIA’S NUMBER 1 ISLAND TOURISM DESTINATION
3
As a Nature Reserve:
✓ happy and healthy visitors✓ Protect our landscapes/ wildlife/ and wealth of culture and
heritage✓ Mindful of our land use
✓ To visit the Island – needs to be equitable & fair
✓ Effective management of resources is critical to short and long term sustainability as a self funded tourism destination
✓ Rottnest Island is an Isolated Community Reliant upon own resources for provision of essential services.
Principal Areas of Management:
Management of the Island –RIMP 2014-2019
4
Energy Review & Roadmap Conducted by Hydro Tasmania in 2014
5
▪ Asset condition
▪ System performance
▪ Energy Use
▪ Energy efficiency & renewable energy
▪ opportunities
▪ Solar – abundant resource
▪ Wind – favourable resource
6
Need for a Power Generation upgrade:
➢ Power system operation was a significant cost to Rottnest Island Authority
•Subsidies provided to island customers
•Renewable energy (RE) is cost effective and fits the island’s brand
•Existing wind turbine saves around 30% of expensive polluting diesel
•ARENA funding was available to help develop innovative RE projects
•Hydro Tasmania had the expertise in island power systems and was able to apply for ARENA funding
✓ 3-way collaboration between ARENA, Rottnest Island Authority and Hydro Tasmania to develop the project
Project Funding:
▪ The project - Water Renewable Energy Nexus (WREN) attracted significant grant funding from ARENA
▪ ARENA is the federal government agency providing grants for innovative renewable energy projects
▪ WREN competed for ARENA grant funding on the basis of:
– Unique and innovative nature of project scope
– Addresses energy use for water supply in remote areas
– Opportunity to use project technology elsewhere
– Knowledge share obligation
– Highly credible delivery team (Hydro Tasmania previous ARENA project success)
7
Rottnest Island – Power Overview Prior to WREN
8
▪ 2.1MW diesel system ▪ 7x 300kW units ▪ 600kW wind turbine (30%) ▪ 1 ML of diesel / $1.5m p.a
Rottnest Island – Power Overview Now with WREN
9
600kW600kW
2,040kW
Operated to makeuse of renewable energy.
Where surplus energy is converted to reserve.
Rottnest Island Water Renewable Energy Nexus
• 45% renewable energy (RE) contribution
• 95% instantaneous RE
• Integrates Water Desalination as Energy Storage
• New Hybrid Control & Diesel Control
• Extensive Training
• Operator Remote Interface
• Education App
Rottnest Island – Solar Array
11
• 600 kW DC Solar PV Array
• Direct fibre fast acting control link to power station
• Site selection
• Away from main tourist attractions
Rottnest Island – Control upgrade and dynamic resistor
▪ Industry standards PLC based modular system
▪ Complete control system upgrade (diesels, LLD, feeders, solar, wind, resistor & DSM)
▪ Manages the variability in renewable generation, improves system security
12
Rottnest Island – Desalinisation control
13
▪ Water on Rottnest Island is desalinated = major use of energy
▪ Timing of desalinisation isn’t critical (as long as we have water)
▪ Desalinate at time of high renewable energy availability
▪ Use water as a battery!
▪ Control has been automated
▪ Greater savings from better use of RE
14
Real time remote operator toolsremote annunciator and Phone App ?
15
Real time remote operator toolsremote annunciator and Phone App ?
How is it working? (24/8/17)
16
~ 5pm ~ 7pm
~ 9pm ~ 11pm
How does WREN perform?
17
Knowledge Sharing
18
Energy Roadmap: Increase RE - Reduce cost
19
Future Potential: •Additional renewables (wind, solar) •Additional enabling technologies (batteries, flywheels, LLD)
Flinders Island Hybrid Energy Hub
▪ HT EPC
▪ Modular Solution
▪ Test off site
▪ Strong Community Engagement
▪ Whole of system Hybrid Control Upgrade
▪ Undergoing Final Commissioning
▪ 100% RE Penetration
▪ 60% RE Contribution
Coober Pedy Renewable Hybrid Project
▪ HT Design, Owners Eng, Supply of
▪ D-UPS, Dynamic Resistor, LV-HV Switchgear, Hybrid Control to EDL
▪ 70% RE Contribution target
▪ 100% Penetration
▪ Hybrid Control ‘talks to’ Existing Diesel Control
▪ Multiple Party Interfacing – Physical and Control
22