Investement Opportunity in Power Sector in Bihar and Jharkhand
Transcript of Investement Opportunity in Power Sector in Bihar and Jharkhand
-
8/8/2019 Investement Opportunity in Power Sector in Bihar and Jharkhand
1/18
1
INTROCUCTION:-
Continued growth of Indian economy will depend on large-scale investments in its energy sector.
As per the planning commissions estimates, India needs an installed capacity of 1200 GW by
2020 which is 7 times the existing capacity, to sustain the future economic growth. India has an
installed capacity of around 163669.80 MW as on 31 July 2010(CEA). The Central PowerSector Utilities and the state utilities have not been able to match up to the requirement. Most of
the previous plan targets have been missed and the government is now expecting the private
sector to support in the future generation and transmission capacity additions. Various policy
level initiatives for facilitating private investments in power sector has been introduced post the
notification of Electricity Act 2003. There have been significant capacity additions in the past
few years. While the total transmission line length (220 kV and above) increased at a CAGR of
6.64% during the past three years, total transmission transformation capacity (220 kV and above)
grew at a CAGR of 4.87%.
With over 75% of coal reserves and 45% of countrys hydro-
electricity potential located in the eastern and north-eastern states of India, these states can
transform themselves into a power hub for India. To achieve this goal, the state governments of
these states should initiate and sustain policy measures to attract investments. Considering the
fact that development of infrastructure, especially in these parts of India, will be always
associated with socio-political issues e.g. acquisition of land (including forest land) and
displacement of people (including indigenous tribes), the policy and support measures of the
Central and State Governments should also address these issues for faster implementation of
projects. Further, since any development in the generation and transmission sub-transmission
infrastructure can only be sustained through continuous cash-flow from end consumers, adequate
focus needs to be given to the strengthening of the distribution sector through administrative and
management reforms, the Central Government sponsored schemes such as the R-APDRP, and
development of the human resources through appropriately designed training and development
programs.
-
8/8/2019 Investement Opportunity in Power Sector in Bihar and Jharkhand
2/18
2
ALL INDIA GENERATING INSTALLED CAPACITY (MW) (As on 31-07-10)
POWER SCENERIO OF BIHAR:-
Following the separation of Jharkhand in the year 2000,
which saw a majority of the generation assets getting transferred to Jharkhand, Bihar was left
with only two thermal power stations at Barauni and Muzaffarpur, both in a dilapidated
condition and generated almost no electricity The state has an installed capacity of 590 MW and
has a share of 1,379 MW in the Central Sector Generating Stations. In 2008-09 the state
experienced a 1,726 MU (16.4%) energy shortage and a 509 MW (27.6%) peak demand deficit.
This energy shortage has lead to wide-scale rationing of power to all categories of consumers.
Reform and restructuring of the sector has been initiated and independent Regulatory
Commission BERC has been constituted in May 2005. Bihar has been the second fastest growing
economy with economy growing more than 11% in 2008-09. However, this growth needs to be
seen in the context of low base and the State has a long way to go to catch up with other
developed states. Future, investment and growth in the power sector would be pre-requisite for
-
8/8/2019 Investement Opportunity in Power Sector in Bihar and Jharkhand
3/18
3
sustaining the economic growth and also improving the socio-economic conditions of people in
the state.
INSTALLED CAPACITY (MG) as on 31 March 2008 of BIHAR
HYDRO DIESEL NUCLEAR
THERMAL
RENEWABLE
ENERGY
SOURCE
TOTAL
STATE 540.00 540.00 50.40 594.40
PRIVATE 0.00 0.00 0.00 0.00 0.00
CENTRAL 1306.59 1306.59 73.00 0.00 1379.59
SUB
TOTAL
1846.59 1846.59 73.00 50.40 1969.99
(Source: TERI 2009)
Installed Capacity (MW)
-
8/8/2019 Investement Opportunity in Power Sector in Bihar and Jharkhand
4/18
4
Source: 2001 Census, CEA,
-
8/8/2019 Investement Opportunity in Power Sector in Bihar and Jharkhand
5/18
5
POWER SUPPLY POSITION IN BIHAR
During the year 2006-07, Bihar faced energy and peak
power shortages of 8.1% and 16.9%, respectively. During April-May, 2007, the state had energy
shortage of 7.9% and peak deficit of 12.2%. Considering actual capacity addition of 21180 MW
in the 10th Plan and proposed capacity addition of 78577 MW in the country in the 11th Plan,
the anticipated power supply position has been worked out. It is expected that at the end of 11th
Plan though the country by and large will be able to meet its energy requirement and peak
demand, Bihar may face energy & peak shortage of about 41% and 58%, respectively.
-
8/8/2019 Investement Opportunity in Power Sector in Bihar and Jharkhand
6/18
6
THERMALPOWER STATIONS INSTALLED IN BIHAR IN STATE SECTOR:-
At present, Barauni (2x50 + 2x110 MW) and Muzaffarpur
(2x110 MW) are two Thermal Power Stations in Bihar in State Sector. A meeting was held under
chairpersonship of Principal Adviser, in Planning Commission GoI, on 10.05.2005 regarding
Residual Life Assessment (RLA)/ R&M of all units of Barauni TPS and of Muzaffarpur TPS
under Rashtriya Sam Vikas Yojna (RSVY). A sum of Rs. 75 crores was released to BHEL by
Ministry of Power / Planning Commission, as advance payment for the above R&M works,
during the year 2005-2006 for both the power stations. A sum of Rs. 120 Crores was also
released to BHEL by MoP/ Planning Commission as advance payment for the R&M works
during the year 2006-07 for both power stations.
HYDRO ELECTRIC DEVELOPMENT IN BIHAR
As per the Reassessment of Hydro Electric Potential of the
Country, carried out by Central Electricity Authority (CEA) during 1978-87, the Hydro Electric
potential in Bihar is assessed at 60 MW at 60 % load factor. The corresponding probable
installed capacity of these schemes is estimated at about 70 MW. As on 1.8.2006, 64.1% of the
total potential in terms of installed capacity has been developed and 35.9% of the potential
remains yet to be developed.
Following six hydro stations with an aggregate installed capacity of 46.1. MW is in operationin Bihar:
-
8/8/2019 Investement Opportunity in Power Sector in Bihar and Jharkhand
7/18
7
PENDING HYDRO SCHEMES
TRANSMISSION SYSTEM DEVELOPMENT:-
To strengthen the sub transmission and
distribution system in Bihar a comprehensive scheme for strengthening of sub transmission
system was formulated under Rashtriya Sam Vikas Yojana for Bihar in consultation with BSEB.
The scheme is funded through central assistance under the Special Plan for Bihar component of
Rashtriya Sam Vikas Yojana. The total scheme has been envisaged to be implemented in phases
as under:
i)Bihar Sub-transmission Scheme Phase-1
ii) Bihar Sub-transmission Scheme Phase-2, Part-1
iii) Bihar Sub-transmission Scheme Phase-2, Part-2
-
8/8/2019 Investement Opportunity in Power Sector in Bihar and Jharkhand
8/18
8
BIHAR SUB TRANSMISSION SCHEME PHASE-I
Bihar sub transmission scheme phase-I (approved
estimated cost Rs. 526.28 crores) involves construction of 18 no (2 no 220 kV, 15 no 132 kV
and 1 no 33 kV) new substation, bay extension works at 12 no 220/132 kV existing substations
of BSEB and construction of 1240 ckt km (220 kV 170 ckm, 132 kV -1030 ckm and 33 kV- 40
ckm) transmission line. Details are at Annex-III. Implementation of the scheme is being done by
PGCIL on behalf of BSEB and the same has been completed.
BIHAR SUB-TRANSMISSION SCHEME PHASE-2, PART-1
Phase-II, Part-I of the scheme at an estimated cost of
Rs 629.22 crores was approved by BSEB in May 2006 The scope of works included works to be
implemented by PGCIL on behalf of BSEB and certain works to be implemented by BSEB.
Subsequently, BSEB has requested for inclusion of certain additional scope under the scheme to
be implemented by POWERGRID. Details of the scope of works including additional scope are
as per Annex-IV. The scheme is under implementation and as per PGCIL some of the contracts
for major Transmission Lines and Road Map for Development of Power Sector in Bihar A
Report of the Special Task Force on Bihar 39 Sub-Station packages have already been awarded
and for balance packages bids have been received/ NIT have been issued. PGCIL have also
submitted revised cost estimate of Rs 1005.72 crores including cost for additional scope of works
for approval.
BIHAR SUB-TRANSMISSION SCHEME PHASE-2, PART-2
Feasibility cum Detailed project Report at an estimated
cost of Rs 1240.86 crores has been prepared and submitted by PGCIL for approval. Details of the
scope of works covered under Phase-2, Part-2 are at Annex-V. Implementation of the scheme is
proposed to be taken up after completion of Phase-2, part-I of the scheme. 36. After the
implementation of the above schemes sub-transmission requirements of Bihar would generally
be adequate for meeting the increased load requirements for the next three to four years.
However, depending upon areas/pockets of future load growth certain sub-transmission
-
8/8/2019 Investement Opportunity in Power Sector in Bihar and Jharkhand
9/18
9
strengthening works and augmentation of transformation capacity at 220/132/66/33 KV may be
required for which BSEB would need to assess their requirements and take further necessary
action.
ELECTRICITY DEMAND FOR BIHAR STATE:-
Final report of the 17th Electric Power Survey
Committee includes electricity demand & energy of Bihar for the year 2011-12 as 3607 MW and
19905 MU, respectively and in the year 2016-17 as 5598 MW and 32857 MU, respectively. This
gives a CAGR of about 19% in energy consumption which is very high and extremely optimistic.
ACCELERATED POWER DEVELOPMENT AND REFORMS PROGRAMME
The Government of India approved during 2000-01
a scheme called Accelerated Power Development Program (APDP) - now rechristened as
Accelerated Power Development and Reforms Program (APDRP) to provide systematic finance
to enable SEBs/Utilities to take up distribution sector reform. APDRP has been formulated to
finance specific projects for up gradation of sub-transmission and distribution (ST&D) network.
Under this programme strengthening of distribution system has been taken up to improve the
quality and reliability of power supply and reduce T&D losses. In Bihar, APDRP schemes
broadly cover following works:
i. Establishment of new power sub-stations;
ii. Installation of consumer and feeder metering;
iii. Re-conducting of over loaded 33 and 11 kV lines;
iv. Renovation and modernization (R&M) of power sub-station (33/11 kV) and distribution
Transformers;
v. Installation of new distribution transformers (DTs) and augmentation of existing DTs; and
vi. Computerization of various functions in distribution systems and implementation of DMS,
Supervisory control and data acquisition (SCADA) system for PESU (Patna).
STATUS OF RURAL ELECTRIFICATION
Rajiv Gandhi Grameen Vidyutikaran Yojna: Central Govt. has launched a new scheme
Rajiv Gandhi Grameen Vidyutikaran Yojana (RGGVY) of Rural Electricity Infrastructure and
-
8/8/2019 Investement Opportunity in Power Sector in Bihar and Jharkhand
10/18
10
Household Electrification on 4th April, 2005 for providing access to electricity to all
households in the country in five years. As per the report prepared by CEA on monthly basis, the
present position of Rural Electrification in Bihar (as on 31 March 2007)is shown below:
Total number of villages 39,015
Total no of villages
electrified
20,620
Percentage electrified 52.9%
(Source: TERI 2009)
In 2007/08 also there is power deficit in Bihar, required meter unit is 9155, and available meter
unit is 7933 so there is -13.3 %( TERI 2009)
SURGING DEMAND IN FUTURE:
Demand for power in the state is expected to surge with
accelerated electrification of villages and households under the RGGVY (Rajiv Gandhi Gramin
Vidyutikaran Yojana) scheme, and peak demand is expected to increase by 500% in 2021-22.
Governments policies to promote industrial activity will increase industrial consumption. It is
estimated that at the end of 11th plan (FY 2012), state will have an energy shortage of 8150 MU
(41%) and peak deficit of 2073 MW (58%). Thus there is an urgent need to look for additionalgeneration capacity to meet this rising demand and an opportunity for potential investors.
INADEQUATE PRIVATE SECTORPARTICIPATION IN POWER SECTOR:
Bihars power sector, in the past, remained unattractive for private
sector participation because of the lack of strong administrative and policy support by the
Government to create an amicable investment climate, including addressing issues related to law
& order, acquisition of land, rehabilitation of displaced people etc. The Government of Bihar hastaken few steps, including certain policy measures, to address the concerns of private investors.
Some of the key initiatives are:
a) Assistance to developers in obtaining all initial consents/clearances for the development of
power projects through the State Investment Promotion Board (SIPB).
-
8/8/2019 Investement Opportunity in Power Sector in Bihar and Jharkhand
11/18
11
b) Permission to sell up to 50 per cent of the power generated outside the state
c) Promotion of captive power generation by industries using any of their waste, by-product or
similar substances like biogases-based cogeneration in the sugarcane industry these measures are
expected to gradually increase the investment flow. However, the sustainability would depend on
the implementation success achieved by the early investments.
INVESTEMENT OPPORTUNITY FORPRIVATE PLAYERS:-
Government of Bihar is now encouraging private
player to participate in power generation, transmission and distribution. Also there is huge
demand of power in Bihar, to fulfill the need of (Rajiv Gandhi Gramin Vidyutikaran Yojana) and
Accelerated Power Development and Reforms Program (APDRP). Government is also focusing
on industrial sector. So investment opportunity in the field of power in Bihar is huge.
POWER SCENERIO OF JHARKHAND:-
With the reorganization of the state into two smaller
states, Jharkhand was endowed with mineral and industry rich belt along with the major share of
installed power capacity. Since then the government of Jharkhand has decided to take quantum
jumps in generating capacity addition and today the state has total installed capacity of 1394
MW and MoU for more than 15000 MW (including one UMPP at Tilaiya) has been signed.
Although the state has performed well in capacity addition front some of the problems it has
inherited from the parent state like high AT&C losses, low PLF and poor network condition is
proving to be deterrent for the development of sector. The availability of coal in abundance
makes Jharkhand an ideal state for setting up thermal power plants. A large number of new steel
plants are coming up in the region with their own captive generation facility.
EXISTING POWER SUPPLY AND POSITION
Presently the load demand of Jharkhand is met by six utilities namely JSEB, TVNL, NTPC,
DVC, NHPC and Tata Power. JSEB meets the requirement by generating from its power plant
and bulk purchase of power from DVC, NTPC, TVNL and NHPC. In DVC licensed area JSEB
has its own Distribution System. The state has also been allocated share of about 134 MW in
-
8/8/2019 Investement Opportunity in Power Sector in Bihar and Jharkhand
12/18
12
Central Sector Power Stations. The total installed capacity of the state is 1390 MW. The
maximum peak load and minimum load under JSEB command are 507 MW and 258 MW
respectively.
INSTALLED CAPACITY (MG) as on 31 March 2008 of Jharkhand
HYDRO DIESEL NUCLEAR
THERMAL
RENEWABLE
ENERGY
SOURCE
TOTAL
STATE 1260.00 1260.00 130.00 4.50 1394.00
PRIVATE 360.OO 360.00 0.00 0.00 360.00
CENTRAL 352.00 352.00 46.00 0.00398.52
SUB
TOTAL
1972.52 1972.52 176.00 4.05 2152.57
(SOURCE: TERI year book 2009)
Installed Capacity (MW)
-
8/8/2019 Investement Opportunity in Power Sector in Bihar and Jharkhand
13/18
13
With 31% village electrification, the State has one of the lowest electricity access levels in thecountry. The progress under RGGVY scheme also has been slow. The socio-economic
development of the state would be dependent on the pace of household electrification. Large
investments in augmenting the sub-transmission and distribution network in the state would be
required in next few years. Distribution reforms and improving the financial viability would be
essential to attract investments in generation sector. Jharkhand would be looking to take
advantage of supply deficits in Western and Northern region states to maximize the benefits from
sale of electricity outside state. Sale to other states would be dependent on the strengthening of
the transmission corridors and significant investments is expected in both building intra-state and
inter-state transmission systems to support the evacuation of large generation capacity addition.
-
8/8/2019 Investement Opportunity in Power Sector in Bihar and Jharkhand
14/18
14
SWOT Analysis
-
8/8/2019 Investement Opportunity in Power Sector in Bihar and Jharkhand
15/18
15
TRANSMISSION NETWORK: The transmission network is divided into two zones. Under
each transmission zone there are four transmission circles which functions through divisions and
sub-division.
Transmission NetworkZone Ranchi Transmission Zone Dumka Transmission Zone
CircleRanchi Deoghar
Jamshedpur Dumka
DISTRIBUTION NETWORK: Distribution network is divided into five supply areas. The
supply areas in turn are divided into circles, divisions, sub-divisions and sections. There are
eleven circles in all.
Distribution NetworkArea Ranchi Jamshedpur Hazaribagh Dhanbad Dumka
Circle
RanchiJamshedpur Hazaribagh Dhanbad Dumka
Gumla
Chaibasa Giridih Loyabad DheogharDaltonganj
Position of the transmission and distribution network of JSEB is as under:
Voltage CKT( Kms) Capacity (MVA)
220 KVS/C 135 450
200 KVD/C 145 450
132KVS/C 609 978.50
132KVD/C 329 978.50
33KV 3346 N.A
11KV 17663 N.A
LT 20490 N.A
-
8/8/2019 Investement Opportunity in Power Sector in Bihar and Jharkhand
16/18
16
KEY CHALLENGES, ISSUES
Low access to electricity: The state has very only 31% of the villages electrified against the
target of 100% by 2012. Faster implementation of RGGVY scheme is needed to achieve
100%village electrification. Huge investments in sub-transmission and distribution network
would become through in next few years.
Socio-political issues: Large part of state has witnessed increased socio-political disturbances
over the past few years and this has posed problems in acquiring land for projects and safety of
the workers which has delayed many of the projects. This has also affected coal supply from
time to time by affecting rail transport infrastructure. Improving the Law and Order position
would be the biggest challenge for State government to retain and attract the investors coming to
state.
Rehabilitation and ResettlementProblems: A lot of multi-national companies have shown
interest in setting up large industries (mainly in metal and mineral sector) in the state to exploit
abundant of mineral resources. Most of these projects are facing rehabilitation and resettlement
problems. Policy initiative facilitating land acquisitions with proper R & R measures would be
required to expedite the project implementation in both metal and power.
OPPORTUNITIES FORPRIVATE PLAYERS:-
The availability of Coal in abundance makes
Jharkhand an ideal state for setting up Thermal Power Plants at the Coal Pits. With the abolition
of freight-equalization, there is tremendous cost advantage in setting up thermal power plants at
the Coal pit itself. The Present total installed power capacity is 2590 MW. In view of future
requirements NTPC, DVC and State PSUs setting up different plants with total capacity of 4736
MW. Due to several new investments in manufacturing setups coming up, the demand for Power
both within the state and the nearby states will increase manifold. There is also scope for setting
up Hydel power plants. 67 Hydel Power generation sites have been identified for this purpose.
Government of Jharkhand is also formulating
policies for growth of power sector and it also encourages private players to participate in the
process of power sector growth in the state. The steps taken by the govt. are as follows:
-
8/8/2019 Investement Opportunity in Power Sector in Bihar and Jharkhand
17/18
17
y The State Government has signed Memorandum of Understanding with Government of
India as a token of Its commit to the reforms in the power sector as formulated by the
Union Government, Department of power, on 30.04.2001.
y Decision has been taken to open the state power sector for private Investment and extend
all due facilitation and incentive to the investors.
y The distribution system is planned for privatization at appropriate time.
y Rural electrification has been accorded top priority. All the 32000 villages are to be
electrified by the year 2007. Present electrification level is hardly 15%. This will Increase
the power demand and also scope for power generation through small power schemes
like small hydro, Biomass, etc.y The work on renovation & modernization of existing power generating station as well as
transmission and distribution system has already commenced in line with the guidelines
Issued by Government of India under Accelerated Power Development Reform
Programme (APDRP) and other schemes of national and International Financial
Institutions.
Private sector in distribution: A number of private distribution licensees are already operating
in the State. The limited distribution investment in past provides an opportunity for private sector
distribution players to enter this segment. The large scale industrialization in future provides a
good opportunity for investments in distribution sector.
Keeping in view the future demand of energy, the country requires doubling its generation by
2012. This requires a massive investment in the sector and to help the sector, Electricity Act
2003 provides the lead, by making provision for the private investment to play vital role. For
economising the cost of generation certain steps will help such as:
1. Cost of transporting coal will reduce the cost of generation to a great extent.
2. For thermal power, generation plants can be installed where coal, water and transmission line
are easily available at cheaper rate.
3. Cheap land and labour will also reduce the cost of generation.
-
8/8/2019 Investement Opportunity in Power Sector in Bihar and Jharkhand
18/18
18
With above points in mind, Jharkhand seems to be an obvious choice for setting up generating
plants. Jharkhand has about 33% of nation's steam coal reserve, it has water, cheap labour and
the State Government has promised easy availability of land for setting of plants. Transporting
coal will be costlier than transmitting energy to any part of the country.
CONCLUSION:-
After the separation of Jharkhand from Bihar, it is left
out with a very small no of power generation capacity because major generation capacity fall
into the lap of Jharkhand. Now the govt. of Bihar is giving importance on industrialization and it
has to also fulfill the power requirement mentioned in 11th
five year plan. It has to also electrify
its villages under Rajiv Gandhi Gramin Vidyutikaran Yojana (RGGVY). So there is need and
the government is also encouraging private sector to participate. Hence the opportunity for
investment in power sector in Bihar is huge.
Jharkhand is rich with minerals and coal. So large numbers
of industries are coming up there and they will require energy. Due to availability of coal in
abundance if thermal power plants will be established there then cost reduction is possible.
Government of Jharkhand is also inviting private players to participate in power generation,
transmission and distribution. So investment opportunity in the state of Jharkhand is huge
because there is a need and also the availability of natural resources.