Introduction to RCM

download Introduction to RCM

of 27

Transcript of Introduction to RCM

  • 8/6/2019 Introduction to RCM

    1/27

    M. Rausand and J. Vatn. Reliability Centered Maintenance. In C. G. Soares, editor, Risk and Reliability in

    Marine Technology. Balkema, Holland, 1998

    Reliability Centered Maintenance

    6800$5> 1, or at least > 1. In special situations wecan even have < 1.

    The expected cost per unit time is:

    &F F : W

    S P

    ( )( )

    =+

    where W(t) = E(N(t)) is the expected number of

    failures in 0, t].

    We will consider a socalled Weibull process

    with W(t) = (t). In this case the time from t= 0until the first failure has a Weibull distribution

    with survivor functionR(t) = exp(-(t)).

    It can be shown that the expected cost per unittime, C(t), is minimized when:

    =

    1

    1

    1

    provided > 1.

    Hence, to optimize the replacement interval,

    estimates for the parameters; cm, c

    p, and are

    required. cm

    is the total cost of a minimal repair,

    including any harm to material, personnel andenvironment. Assessing a value of cm may

    therefore cause controversies. and are theparameters in the failure distribution of the item.

    Often it is more convenient to specify the failure

    distribution in terms of mean time to failure

    (MTTF) and the shape parameter , yielding:

    =+

    077)

    ( )1

    1

    1 1

    Table 1 Optimal replacement interval relative to MTTF. For a given value of and , the tableentry should be multiplied with MTTF to give the optimum replacement interval length

    Cost ratio = cu/c

    p

    2 3 4 5 7 10 20 50 100 200

    1.2 13.40 12.20 12.95 12.62 2.050 .897 .393 .165 .090 .050

    1.5 8.19 7.97 1.22 .85 .590 .432 .253 .133 .083 .052

    1.7 6.60 1.59 .83 .66 .503 .389 .247 .141 .093 .061

    2.0 4.84 .86 .67 .57 .464 .377 .259 .161 .113 .080

    2.5 .99 .71 .60 .54 .461 .394 .294 .202 .152 .115

    3.0 .82 .67 .59 .54 .478 .421 .331 .242 .192 .152

    4.0 .75 .66 .61 .57 .523 .476 .398 .316 .265 .223

    Model 2 Block replacement policy

    The block replacement policy describes a

    singleunit system put into operation at time t=

    0. The unit is replaced at times ktfor k=1,2,...and at failures. The cost of a planned

    replacement is denoted cp, and the total cost of

  • 8/6/2019 Introduction to RCM

    20/27

    Rausand&Vatn Reliability Centered Maintenance

    20

    an unplanned replacement, i.e. a failure is cu. Let

    W(t) denote the renewal function, see e.g.

    Hyland and Rausand (1994), for the lifetime

    distribution of the unit. The average cost per unit

    time is:

    &F F : W

    S X

    ( )( )

    = +

    If the times between failures are Weibull

    distributed, W(t) can be found by the algorithm

    given by Smith and Leadbetter (1963).

    Numerical methods are, however, required to

    find the optimal interval . In Table 1, numericalvalues for the optimal replacement interval is

    given relative to MTTF.

    In order to use Table 1 the value of must bespecified. During the data analysis in Step 5 the

    value of should have been found by e.g. expertjudgment.

    Model 3 - Functional testing

    This model is appropriate for scheduled function

    testing. Consider a protective device with a

    constant failure rate

    . A functional test of the

    device is performed at times k for k=1,2,. . .The cost of a Functional test is c

    t. If a failure is

    detected upon a test, the device is replaced at a

    cost of cr. Further assume that the device is

    demanded with a frequency f, i.e. the rate of

    critical situations. A hazardous situation occurs

    if the protective device fails upon a demand. The

    total cost of such a situation is ch.

    The expected cost per unit time is:

    &F

    F I FW

    U K

    +

    +

    2

    2 2

    yielding an optimal interval :

    F

    I F F

    077) F

    I F F 077)

    W

    K U

    W

    K U

    =

    Model 4 - Scheduled on-condition tasks, the

    concept of P-F-intervalsThe idea behind a scheduled on-condition task is

    that a coming failure is alerted by some

    degradation in performance, or some indicator

    variable is alerting about the failure.

    Time

    Target

    value

    Acceptabledeviation

    Failure

    Performance/

    Condition

    Point where we can find out thatv v s h v y v t ("potential failure")

    P

    F

    P-F interval

    Figure 10 P-F interval

    In Figure 10 the performance is viewed as a

    function of time. The point P is the first point

    in time where we are able to reveal the outset of

    a failure. When the performance is below some

    limiting value a failure will occur. The length

    from a potential failure is detectable until a

    failure occurs is denoted the P-F interval. The

    length of the P-F interval is assumed to vary

    from time to time, and is therefore modeled as a

    random variable. In order to establish an optimal

    maintenance interval, , the following quantitiesmust be defined:

    ' Delay time, i.e. the time from a

    potential failure is revealed until an

    appropriate corrective action is

    completed. For simplicity the delay time

    is considered as a deterministic quantity.

    FL

    : Cost of (manual) inspection.

    FX

    : Cost of (unplanned) failure.

    73 )

    : PF interval (random variable).

    : E(73 )

    ) = Mean value of P-F interval.

    : SD(7PF) = Standard deviation of P-Finterval.

    MTTF:Mean time to failure if no corrective

    maintenance is carried out

    The expected cost per unit time is given by:

    &

    F F H 7 W ' GW L X

    W

    3 )

    ( )

    Pr( )

    =+ +

    0

    where =1/(MTTF-), and we have assumedthat the time from the component is in a perfect

    state until a potential failure reveals is

  • 8/6/2019 Introduction to RCM

    21/27

    Rausand&Vatn Reliability Centered Maintenance

    21

    exponentially distributed.

    In order to optimize Eq. (1) numerical values are

    required for ci, c

    u, MTTF,D, and . Numerical

    methods are usually required to optimize Eq.

    (1). The calculations will be simplified if we

    choose a distribution for TPF with a closed formof the cumulative distribution function.

    Model 5 - Continuos on-condition tasks

    The idea of continuos on-condition monitoring

    is to measure one or more indicator variable.

    The reading of the component in this manner

    can be used to detect a coming failure. The

    variable being monitored is denoted X(t) in

    Figure 11.

    Time

    X(t)

    "Failure Limit"

    Failure

    "Action Limit"

    Figure 11 Continuos monitoring

    In Figure 11 the deteriorating process is shown.

    HereX(t) is can be interpreted as the cumulative

    damage at time t. When the damage exceeds

    some limit, a failure occurs. In Figure 11 we

    have also shown an action limit, upon where

    to take a maintenance action. The challenge here

    is to decide the optimal action limit. No

    general approach seems applicable here since thesolution is highly dependent on how X(t) is

    modeled. Aven (1992) discusses one method

    where an underlying chock model is assumed.

    6WHS 3UHYHQWLYH PDLQWHQDQFHFRPSDULVRQDQDO\VLV

    Two overriding criteria for selecting

    maintenance tasks are used in RCM. Each task

    selected must meet two requirements:

    It must be applicable

    It must be effective

    Applicability: meaning that the task is applicable

    in relation to our reliability knowledge and in

    relation to the consequences of failure. If a task

    is found based on the preceding analysis, it

    should satisfy the Applicability criterion.

    A PM task will be applicable if it can eliminate a

    failure, or at least reduce the probability of

    occurrence to an acceptable level (Hoch 1990) -

    or reduce the impact of failures!

    Cost-effectiveness: meaning that the task does

    not cost more than the failure(s) it is going to

    prevent.

    The PM task's effectiveness is a measure of how

    well it accomplishes that purpose and if it is

    worth doing. Clearly, when evaluating the

    effectiveness of a task, we are balancing thecost of performing the maintenance with the

    cost of not performing it. In this context, we

    may refer to the cost as follows (Hoch 1990):

    1. The cost of a PM task may include:

    the risk of maintenance personnel error,e.g. maintenance introduced failures

    the risk of increasing the effect of a failureof another component while the one is outof service

    the use and cost of physical resources

    the unavailability of physical resourceselsewhere while in use on this task

    production unavailability duringmaintenance

    unavailability of protective functionsduring maintenance of these

    The more maintenance you do the morerisk you will expose your maintenance

    personnel to

    2. On the other hand, the cost of a failure mayinclude:

    the consequences of the failure should itoccur (i.e. loss of production, possible

    violation of laws or regulations, reduction

    in plant or personnel safety, or damage to

    other equipment)

    the consequences of not performing thePM task even if a failure does not occur

  • 8/6/2019 Introduction to RCM

    22/27

    Rausand&Vatn Reliability Centered Maintenance

    22

    (i.e., loss of warranty)

    increased premiums for emergency repairs(such as overtime, expediting costs, or

    high replacement power cost).

    Balancing the various cost elements to achieve a

    global optimum will always be a challenge. The

    conceptual RCM model in Figure 1 may be a

    starting point. If such a model could be

    established, and the various cost elements

    incorporated, the trade-off analysis is reduced to

    an optimization problem with a precisely

    defined mathematical model.

    Often the resources available for the RCM

    analysis do not permit building such an overall

    model, hence we can not expect to achieve aglobal optimum. Sub-optimization can to some

    extent be achieved by simplifying the model in

    Figure 1. For example one could consider only

    one consequence at a time and/or only one

    maintenance task at a time.

    6WHS 7UHDWPHQWRIQRQ06,V

    In Step 4 critical items (MSIs) were selected for

    further analysis. A remaining question is what to

    do with the items which are not analyzed. For

    plants already having a maintenance program it

    is reasonable to continue this program for the

    non-MSIs. If a maintenance program is not in

    effect, maintenance should be carried out

    according to vendor specifications if they exist,

    else no maintenance should be performed. See

    Paglia et al (1991). for further discussion.

    6WHS ,PSOHPHQWDWLRQ

    A necessary basis for implementing the result of

    the RCM analysis is that the organizational and

    technical maintenance support functions are

    available. A major issue is therefore to ensure

    the availability of the maintenance support

    functions. The maintenance actions are typically

    grouped into maintenance packages, each

    package describing what to do, and when to do

    it.

    As indicated in the outset of this paper, many

    accidents are related to maintenance work.

    When implementing a maintenance program it is

    therefore of vital importance to consider the risk

    associated with the execution of the maintenance

    work. Checklists could be used to identify

    potential risk involved with maintenance work:

    Can maintenance people be injured during

    the maintenance work?

    Is work permit required for execution of themaintenance work?

    Are means taken to avoid problems relatedto re-routing, by-passing etc.?

    Can failures be introduced duringmaintenance work?

    etc.

    Task analysis, see e.g. Kirwan & Ainsworth(1992) may be used to reveal the risk involved

    with each maintenance job. See Hoch (1990) for

    a further discussion on implementing the RCM

    analysis results.

    6WHS ,QVHUYLFH GDWD FROOHFWLRQDQGXSGDWLQJ

    As mentioned earlier, the reliability data wehave access to at the outset of the analysis may

    be scarce, or even second to none. In our

    opinion, one of the most significant advantages

    of RCM is that we systematically analyze and

    document the basis for our initial decisions, and,

    hence, can better utilize operating experience to

    adjust that decision as operating experience data

    is collected. The full benefit of RCM is therefore

    only achieved when operation and maintenance

    experience is fed back into the analysis process.

    The process of updating the analysis results is

    also important due to the fact that nothing

    remain constant, best seen considering the

    following arguments (Smith 1993):

    The system analysis process is not perfectand requires periodic adjustments.

    The plant itself is not a constant sincedesign, equipment and operating procedures

    may change over time.

    Knowledge grows, both in terms ofunderstanding how the plant equipment

    behaves and how technology can increase

  • 8/6/2019 Introduction to RCM

    23/27

    Rausand&Vatn Reliability Centered Maintenance

    23

    availability and reduce costs.

    Reliability trends are often measured in terms of

    a non-constant ROCOF (rate of occurrence of

    failures), see e.g. Hyland & Rausand (1994).

    The ROCOF measures the probability of failure

    as a function of calendar time, or global time

    since the plant was put into operation. The

    ROCOF may change over time, but within one

    cycle the ROCOF is assumed to be constant.

    This means that analysis updates should be so

    frequent that the ROCOF is fairly constant

    within one period.

    Opposite to the ROCOF, the failure rate or

    FOM, is measuring the probability of failure as a

    function oflocal time, i.e. the time elapsed since

    last repair/replacement. However, the FOM can

    not be considered constant, if so there is no

    rationale for performing scheduled replace-

    ment/repair.

    The updating process should be concentrated on

    three major time perspectives (Sandtorv &

    Rausand 1991):

    Short term interval adjustments

    Medium term task evaluation

    Long term revision of the initial strategyThe short term update can be considered as a

    revision of previous analysis results. The input

    to such an analysis is updated reliability figures

    either due to more data, or updated data because

    of reliability trends. This analysis should not

    require much resources, as the framework for the

    analysis is already established. Only Step 5 and

    Step 8 in the RCM process will be affected by

    short term updates.

    The medium term update will also review thebasis for the selection of maintenance actions in

    Step 7. Analysis of maintenance experience may

    identify significant failure causes not considered

    in the initial analysis, requiring an updated

    FMECA analysis in Step 6. The medium term

    update therefore affects Step 5 to 8.

    The long term revision will consider all steps in

    the analysis. It is not sufficient to consider only

    the system being analyzed, it is required to

    consider the entire plant with it's relations to theoutside world, e.g. contractual considerations,

    new laws regulating environmental protection

    etc.

    ',6&866,216 $1'

    &21&/86,216

    The following summarizes some main benefits,

    drawbacks and problems encountered duringapplication of the RCM method in some

    offshore case studies.

    *HQHUDOEHQHILWV

    Cross-discipline utilization of knowledge: To

    fully utilize the benefits of the RCM concept,

    one needs contributions from a wider scope of

    disciplines than what is common practice. This

    means that an RCM analysis requirescontribution from the three following discipline

    categories working closely together:

    1. System/reliability analyst

    2. Maintenance/operation specialist

    3. Designer/manufacturer

    All these categories do not need to take part in

    the analysis on a full time engagement. They

    should, however, be deeply involved in the

    process during pre- and post-analysis review

    meetings, and quality review of final results.

    The result of this is that knowledge is extracted

    and commingled across traditional discipline

    borders. It may, however, cost more at the outset

    to engage all these personnel categories.

    Traceability of decisions: Traditionally, PM

    programs tend to be cemented. After some

    time one hardly knows on what basis the initial

    decisions were made and therefore do not want

    to change those decisions. In the RCM conceptall decisions are taken based on a set of

    analytical steps, all of which should be

    documented in the analysis. When operating

    experience accumulates, one may go back and

    see on what basis the initial decisions were

    taken, and adjust the tasks and intervals as

    required based on the operating experience. This

    is especially important for initial decisions based

    on scarce data.

    Recruitment of skilled personnel formaintenance planning and execution: The RCM

    way of planning and updating maintenance

  • 8/6/2019 Introduction to RCM

    24/27

    Rausand&Vatn Reliability Centered Maintenance

    24

    requires more professional skills, and is

    therefore a greater challenge for skilled

    engineers. It also provides the engineers with a

    broader and more attractive way of working with

    maintenance than what sometimes is common

    today.

    Cost aspects: As indicated, RCM will require

    more efforts both in skills and manhours when

    first being introduced in a company. It is,

    however, documented by many companies and

    organizations that the long term benefits will far

    outweigh the initial extra costs. One problem is

    that the return of investment has to be looked

    upon in a long term perspective, something that

    the management is not always willing to take a

    chance on.

    Benefits related to PM-program achievement:

    Based on the case studies we have carried out,

    and experience published by others, the general

    achievements of RCM in relation to a traditional

    PM-programs may be summarized as follows:

    By careful analysis of the failureconsequences, the amount of PM tasks can

    often be reduced, or replaced by corrective

    tasks or more dedicated tasks. We have

    therefore chosen to include corrective

    maintenance as a possible outcome of theRCM analysis.

    Emphasis has been changed from periodicrework or overhaul tasks of the large

    assemblies/units to more dedicated object

    oriented tasks. Consequently, condition

    monitoring has been more frequently used to

    detect specific failure modes.

    Requirement for spare parts has been

    reduced as a result of a better justificationfor replacements.

    Design solutions have been discovered thatwere not optimal from a safety and plant

    economic point of view.

    3UREOHPDUHDVLQWKHDQDO\VLV

    Identification of Maintenance Significant Items:

    In some cases there may be very little to achieve

    by limiting the analysis to only include the

    MSIs. Smith (1993) argues that concentrating on

    critical components (MSIs) is directly wrong

    and that it in most analyses exclude important

    equipment from appropriate attention. He writes

    (page 82):

    . . . we should be very careful

    not to prematurely discard

    components as non-critical until

    we have truly identified their

    proper tie and priority status to

    the functions and functional

    failures.

    Other authors argue that the main objective of

    the RCM process is to create a basis for

    maintenance evaluation and task adjustment.

    The selection of MSIs will reduce this basis and

    result in an insufficient evaluation process.

    The rationale for working with the MSIs onlywas to reduce the analysis work. Thus there is

    always a risk of an insufficient analysis when

    the non-MSIs are not subjected to a formal

    analysis. In our presentation the criterion for

    classifying an analysis item as non-MSI is:

    The item should not affect any of the critical

    system failure modes (Step 4). By using such

    an approach the criterion for disregarding an

    item is traceable, and may be reevaluated later.

    Further we believe that this criterion makes very

    good sense.

    Lack of reliability data: As indicated the full

    benefit of the RCM concept can only be

    achieved when we have access to reliability data

    for the items being analyzed. Is now RCM

    worthless if we have no or very poor data at the

    outset? The answer to this question is no, even

    in this case the RCM approach will provide

    some useful information for assessing

    maintenance tasks. PM intervals will, however,

    not be available. As a result of the analysis, weshould at least have identified the following:

    We know whether the failure involves asafety hazard to personnel, environment or

    equipment

    We know whether the failure affectsproduction availability

    We know whether the failure is evident orhidden

    We have a better criterion for evaluatingcost-effectiveness

  • 8/6/2019 Introduction to RCM

    25/27

    Rausand&Vatn Reliability Centered Maintenance

    25

    Lack of reliability data will always be a

    problem. First of all there are problems with

    getting access to operational data with sufficient

    quality. Next, even if we have data, it is not

    straight-forward to obtain reliability data from

    the operational data. Before we discuss some

    problems with collecting and using operationaldata, it should be emphasized that there will

    never be a complete lack of reliability figures.

    Even if no operational data is available, expert

    judgment will be available. However, the

    uncertainty in the reliability figures can be very

    large.

    Based on our various engagements in the

    OREDA project and other data collection

    projects on offshore installations, we have

    experienced the following common difficultiesrelated to acquisition of failure data:

    Data is generally very repair oriented and notdirected towards describing failure causes,

    modes and effects.

    How the failure was detected is rarely stated(e.g. by inspection, monitoring, PM, tests,

    casual observation). This information is very

    useful in order to select applicable tasks.

    Failure modes can sometimes be deduced,but this is generally left to the data collectorto interpret.

    The true failure cause is rarely found, but thefailure symptom can to some extent be

    traced.

    Failure effect on the lower indenture level isreasonably well described, but may often be

    missing on higher indenture level (system

    level).

    Operating conditions when the failureoccurred is frequently missing or vaguely

    stated.

    As mentioned above, there are often problems

    with estimating reliability data from the

    operational data. Reliability data comprises

    MTTR and MTTF figures together with the

    failure rate function. Reasonable estimates for

    MTTR and MTTF may be found by various

    averaging techniques. The failure rate function,

    i.e. the ageing parameter is much harder to

    obtain. Available estimation techniques require

    no reliability trend (in calendar time) for the

    unit(s) being considered. Further if several units

    are used to enlarge the data set, these units

    should be operated identically under the same

    environmental conditions. The requirements

    above are very seldom fulfilled, hence the

    estimation techniques may collapse. We

    therefore recommend use ofexpert judgment toestablish appropriate ageing parameters. The

    ageing parameter is a measure of how

    deterministic a failure is, and it is reasonable to

    believe that this measure is relatively constant

    for each failure cause. On the other hand, it

    seems meaningless to establish a general set of

    recommended MTTF-figures for the various

    failure mechanisms.

    Trade-off analyses: There are four major criteria

    for the assessment of the consequences of afailure: safety, environment, production

    availability, and economic losses. During the

    analysis, we have to quantify these measures to

    some extent to be able to use them as decision

    criteria. Further, a trade-off analysis is required

    to balance each means against the different

    consequences. Referring to Figure 1 we need to

    consider the effect of the maintenance tasks

    M1,M

    2,.., on the consequences C

    1,C

    2,..,. This will

    require comprehensive reliability models.

    Further, the transformation of the consequences

    C1,C

    2,.., into a unidimensional loss function is at

    best a difficult and controversial task. A

    framework for dealing with these problems is

    given in Vatn et al. 1996.

    Assessing proper interval: The RCM concept is

    very valuable in assessing the proper type of PM

    task, but traditionally RCM does not basically

    include any tool for deciding optimal

    intervals. The "new framework for RCM given

    in Figure 1 together with standard PM-modelslisted under Step 8 are believed to form a very

    sound basis for deciding optimal intervals.

    &RQFOXVLRQV

    RCM is not a simple and straightforward way of

    optimizing maintenance, but ensures that one

    does not jump to conclusions before all the right

    questions are asked and answers given. RCMcan in many respects be compared with Quality

    Assurance. By rephrasing the definition of QA,

    RCM can be defined

  • 8/6/2019 Introduction to RCM

    26/27

    Rausand&Vatn Reliability Centered Maintenance

    26

    All systematic actions

    required to plan and verify

    that the efforts spent on

    preventive maintenance are

    applicable and cost-effective.

    Thus, RCM does not contain any basically new

    method. Rather, RCM is a more structured way

    of utilizing the best of several methods and

    disciplines. Quoting Malik (1990) the author

    postulates: . . . there is more isolation between

    practitioners of maintenance and the

    researchers than in any other professional

    activity. We see the RCM concept as a way to

    reduce this isolation by closing the gap

    between the traditionally more design related

    reliability methods, and the practical related

    operating and maintenance personnel.

    5()(5(1&(6

    R. T. Anderson and L. Neri. Reliability-Centered

    Maintenance. Management and Engineering

    Methods. Elsevier Applied Science, London,

    1990.

    T. Aven. Reliability and Risk Analysis. Elsevier

    Science Publishers, London, 1992.K. M. Blache and A. B. Shrivastava. Defining

    failure of manufacturing machinery &

    equipment. Proceedings Annual Reliability

    and Maintainability Symposium, pages 69-

    75, 1994.

    B. S. Blanchard and W. J. Fabrycky. System

    Engineering and Analysis. Prentice-Hall,

    Inc., Englewood Cliffs, New Jersey 07632,

    1981.

    BS 5760-5. Reliability of systems, equipments and

    components; Part 5: Guide to failure modes,effects and criticality analysis (FMEA and

    FMECA). British Standards Institution,

    London, 1991.

    N. Cross. Engineering Design Methods: Strategies

    for Product Design. John Wiley & Sons,

    Chichester, 1994.

    R. R. Hoch. A Practical Application of Reliability

    Centered Maintenance. The American

    Society of Mechanical Engineers, 90-

    JPGC/Pwr-51, Joint ASME/IEEE Power

    Gen. Conf., Boston, MA, 21-25 Oct., 1990.A. Hyland and M. Rausand. Reliability Theory;

    Models and Statistical Methods. John Wiley

    & Sons, New York, 1994.

    IEC 50(191). International Electrotechnical

    Vocabulary (IEV) - Chapter 191 -

    Dependability and quality of service.

    International Electrotechnical Commission,

    Geneva, 1990.

    IEC 812.Analysis Techniques for System Reliability

    - Procedures for Failure Modes and Effects Analysis (FMEA). International

    Electrotechnical Commission, Geneva,

    1985.

    B. Kirwan and L. K. Ainsworth. A Guide to Task

    Analysis. Taylor & Francis, London, 1992.

    M.A. Malik. Reliable preventive maintenance

    scheduling.AIEE Trans., 11:221-228, 1990.

    M. A. Moss. Designing for Minimal Maintenance

    Expense. The Practical Application of

    Reliability and Maintainability. Marcel

    Dekker, Inc., New York, 1985.

    J. Moubray. Reliability-centred Maintenance.

    Butterworth-Heinemann, Oxford, 1991.

    F. S. Nowlan and H. F. Heap. Reliability-centered

    Maintenance. Technical Report AD/A066-

    579, National Technical Information

    Service, US Department of Commerce,

    Springfield, Virginia, 1978.

    NPD. Regulations concerning implementation and

    use of risk analyses in the petroleum

    activities. Norwegian Petroleum Directorate,

    P.O.Box 600, N-4001 Stavanger, Norway,

    1991.OREDA-97. Offshore Reliability Data. Distributed

    by Det Norske Veritas, P.O.Box 300, N-

    1322 Hvik, Norway, 3 edition, 1997.

    Prepared by SINTEF Industrial

    Management. N-7034 Trondheim, Norway.

    A.M. Paglia, D.D. Barnard, and D.E. Sonnett. A

    Case Study of the RCM Project at V.C.

    Summer Nuclear Generating Station. 4th

    International Power Generation Exhibition

    and Conference, Tampa, Florida, US,

    5:1003-1013, 1991.G. Pahl and W. Beitz. Engineering Design. The

    Design Council, London, 1984.

    M. Rausand and J. Vatn. Reliability Centered

    Maintenance. In C. G. Soares, editor, Risk

    and Reliability in Marine Technology.

    Balkema, Holland, 1997.

    H. Sandtorv and M. Rausand. RCM - closing the

    loop between design and operation

    reliability. Maintenance, 6, No.1:13-21,

    1991.

    A. M. Smith. Reliability-Centered Maintenance.

    McGraw-Hill, Inc, New York, 1993.

    D. J. Smith. Reliability, Maintainability and Risk,

    Practical methods for engineers.

  • 8/6/2019 Introduction to RCM

    27/27

    Rausand&Vatn Reliability Centered Maintenance

    Butterworth Heinemann, Oxford, 4th

    edition, 1993.

    W. L. Smith and M. R. Leadbetter. On the renewal

    function for the Weibull distribution.

    Technometrics, 5:393-396, 1963.

    Weapon Systems and Support Equipment.

    Reliability-Centered Maintenance.

    Requirements for Naval Aircraft. US

    Department of Defense, Washington DC

    20301, 1986.

    C. Valdez-Flores and R.M. Feldman. A survey of

    preventive maintenance models for

    stochastically deteriorating single-unit

    systems. Naval Research Logistics

    Quarterly, 36:419-446, 1989.

    J. Vatn. Maintenance Optimization from a Decision

    Theoretical Point of View. In Proceedings,

    ESREL95, pages 273-285, London, 1995.

    Chameleon Press Limited.

    J. Vatn, P. Hokstad, and L. Bodsberg. An overall

    model for maintenance optimization.

    Reliability Engineering and System Safety,

    51:241-257, 1996.