INTERNATIONALTROFICALTIMBERORGANIZTION (ITTO) · 2014. 3. 20. · ITTO PROJECTPPD 53/02REV. I(I) r~...

29
INTERNATIONALTROFICALTIMBERORGANIZTION (ITTO) EXECUTINGAGENCY: FORESTRYRESEARCHINSTITUTEOFGHANA (FORIG) FINALTECHNICALREFORTN0.3 I~ TITLEOlRFRE-PROJECT: SIZINGCONGENERATIONPLANT USINGWOODRESIDUEASFUEL SERIALNl. IMEER: DEVELOPMENTOFENERGYALTERNATIVES FORTHEEFFICIENT UTILIZATIONOF WOOD PROCESSINGRESIDUE: CO-GENERATION ANDBRIQUETTEPRODUCTION. PLACE OF ISSUE: r~ I_ DATEOFISSl. IE: MARCH2005 ITTO PROJECTPPD 53/02REV. I(I) r~ KUMASl, GHANA

Transcript of INTERNATIONALTROFICALTIMBERORGANIZTION (ITTO) · 2014. 3. 20. · ITTO PROJECTPPD 53/02REV. I(I) r~...

  • INTERNATIONALTROFICALTIMBERORGANIZTION

    (ITTO)

    EXECUTINGAGENCY: FORESTRYRESEARCHINSTITUTEOFGHANA

    (FORIG)

    FINALTECHNICALREFORTN0.3

    I~TITLEOlRFRE-PROJECT:

    SIZINGCONGENERATIONPLANT

    USINGWOODRESIDUEASFUEL

    SERIALNl. IMEER:

    DEVELOPMENTOFENERGYALTERNATIVES

    FORTHEEFFICIENT UTILIZATIONOF WOOD

    PROCESSINGRESIDUE: CO-GENERATION

    ANDBRIQUETTEPRODUCTION.

    PLACE OF ISSUE:

    r~

    I_

    DATEOFISSl. IE: MARCH2005

    ITTO PROJECTPPD 53/02REV. I(I)

    r~

    KUMASl, GHANA

  • I_ _

    ,-^

    I~

    ,^

    Abstract ........................................................................................ it

    1.0 Introduction. ............................,.................................,.,,,,,,,,,,,,,, I

    2.0 Co-generation in wood processing mills in Ghana. ................................. I

    3.0 Techntcal options for biomass co- generation ........................................ 2

    3.1 Direct combustion boiler/ steam technology. ............................... 2

    3.2 Gasificationtechaology. ...................................................... 4

    3.3 The Stirlingengines. .......................................................... 5

    4.0 Identification of sites for good co-generation potential. ........................... 5

    4.1 Methodology .................................................................... 5

    4.2 Selection of potential sites. .................................................. 6

    Selected potential sites. .................................................. 64.2. I

    4.2.1.1 Asuo Bornosadu Timbers and Sawmills (ABTS Ltd)............ 6

    4.2.1.2 Logs and Lumber Limited (LLL)................................... 7

    4.2.1.3 Omega Wood Processing Limited (OWPL)........................ 7

    TABLEOlr'CONTENTS

    I_ .

    5.0 Deterrnination of thennal energy demand profiles. ................................. 7

    5.1 Methodology. .................................................................... 8

    5.2 Results. ........................................................................... 8

    6.0 Detennination of electrical demand profiles. ........................................ 8

    6.1 Methodology .................................................................... 9

    6.2 Results ......................-------..........-~~~~~~~~"""""""""""""' '

    Page

    I' ~

    ,

    I~

    r~

    7.0 Determination of the specification for co-generation plants ....................... 12

    7.1 Introduction ..................................................................... I 2

    7.2 Electrical loadmatching. ...................................................... 13

  • ,--

    7.3 ThemIalloadmatching. ........................................................ 13

    7.4 Methodology. .................................................................... 13

    7.5 Results ........................................................................... I 5

    8.0 Conclusion. ............................................................................... I 7

    9.0 Recoinmendation ........................................................................ 18

    References. ............................................................................... I 9

    Appendix I ....................................................................,......... 20

    Appendix 2 ............................................................................. 22

    I~~'

    I~ ~

    L

    I~

    I~

  • I~

    Currently growing awareness of biomass as a potentially environmentally friendly sourceof energy is leading to an increased number of initiatives and projects in the wood energyfield. In Ghana the existing wood processing mills generate wood residue, a portion ofwhich is used to fire on-site boilers to generate steam or hot water fortheirprocess heatneeds. The remaining residue is burntin the open air causing environmental pollution.To determine cogeneration potential at the Ghanaian wood processing mills, certaincriteria were used to selectthree woodprocessing mills as case study. The mills selectedwereAsuo BornosaduTimbers and Sawmills Limited (ABTS LTD), Log andLumberLimited (LLL) and Omega WoodProcessing Limited (OWPL) which have annual woodresidue of about 27,360 in', 32,610 in' and 19,230 in' respectively.

    The power requirements forthe mills, necessary for sizing cogeneration wits, werederived from their monthly electricity bills. A bill for a particular month indicated themaximum demand of the month andthetotalenergy consumed forthe month. Asthemills do not have instr^Gritationto monitorthennalenergy consumption, their peakprocessrequirement was assumed to be the installed thennal capacity at the site. Themills have high steam consumption compared to availability of wood residue.Consequently, the backpressure steam turbine was selected. Its size was detenninedtomeet anthe thermal demand at the site.

    ABSTRt^. CT

    I'~"

    The size of the cogeneration plant was calculated for typical inlet pressures of 20, 30, and40 bars and at superheated temperatures of 300'C and 400'C. The calculations weredone assuming typical boiler, generator and turbine efficiency of 76, 96 and 60%respectively and a boiler feed-water temperature of 90'C.

    From the results of the calculations the power ratings for cogeneration units at OWPL,LLL and ABTS were specified as 2,000 kWe, 1,200 kWe and 400 kWe respectively.These gave reasonable heatto power ratios of 19, 21 and 19 respectively. Thecorresponding fuel consuinptions were about 80,000 in'/year, 32,000 in'/year and17,000 in lyear.

    I~~'

    I~ ~

    I~

    ^--,

    11

  • SIZING CONGENERATIONPLANTl. ISINGWOODRESIDl. IEAS

    FUEL

    I. INTRODUCTION

    Cogeneration is the simultaneous production of heat and electricity from a single primaryenergy source. This mode of energy conversion is also known as combined heat andpower generation (CHP)(Prasertson at a1, 2001). More electricity and heat are generatedfor a lesser amount of fuel by a cogeneration urnt than by electricity-only and thennal-only units. The overall efficiency of energy conversion by means of cogeneration can beup to 80 percent and above with certain technologies(Energy Tips-Steam, 2004;ESDD, 2000; Sims & Gigler, 2002).

    According to the sequence of energy use, a cogeneration system can be classified aseither atopping or bottoming cycle (ESDD, 2000):

    (a) A topping cycle: the primary fuelis used to first produce electricity and then thermalenergy is obtained as by-product. A topping cycle cogeneration system is used wherelow pressure steam or hot water is required for process heat. A typical area ofapplication is the wood products industries.

    (b) A bottoming cycle: the primary fuelis used to produce high temperature thermalenergy and the heat rejected from the process is used to generate electricity.Industries using bottoming cycle cogeneration include cement, steel andpetrochemical industries.

    A cogeneration system can incorporate a vapour absorption chiller to also producecooling (Introduction to CHP Catalog of Technologies ;.... ESDD, 2000). A low qualityheat exhausted from the cogeneration plant can drive these absorption chiners. Thisconcept of deriving three different fonns of energy from the primary energy source isternied tri-generation or combined heating, cooling and power generation (CHCP). Thisis particularly of interest in Ghana where buildings require comfort cooling throughoutthe year.

    I~~

    I~'

    ,

    I~ 2. COGENERATIONINWOODPROCESSINGMILLSINGHANA

    The wood processing mills in Ghana generates large volume of wood residue annuallyduring production process. The wood residue includes sawdust, shavings, trillrrnings,slabs, edgings and off-cuts. A substantial portion of the residue is reprocessed into usefulproducts such as flooring parquets, flooring strips and triangular mouldings.

    The existing mills obtain electricity supply from the national grid and use a small fractionof their unused residue to fire on-site boilers to generate steam or hot water to meet alltheirprocess heat demand. The remainder of the unused residue is disposed of as waste in

    I'~ '

  • I~

    I _

    open burning and dumping sites creating environmental problems in the surroundingcommunities.

    Using the unused residue for on-site cogeneration will not only offer both environmentaland economic benefits but also higher energy conversion efficiency. Notwithstanding,cogeneration technology has not been adopted in Ghanaian wood processing mills. Thehindering factors include the following:

    (a) Lack of successful references.(b) Lack of technical and economic inforrnation to make a decision.(c) Uncertainty of sustainable fuelsupply.(d) High investment cost as a result of the fact that all system components must be

    imported.(e) Inability to operate the cogeneration plant as grid-connected system.

    i-~

    I_

    I~~' 3. TECHNICALOPTIONSlF'ORBIOMASSCOGENERATION

    I ~

    The well established technology for converting biomass to heat and electricity is theAdditionaldirect-combustion boiler/steam technology (Sims & Gigler, 2002).

    technologies involving gasification of biomass fuels are either at very near to coriumercialavailability or at demonstration orresearch and development stage (Sims & Gigler, 2002,Biopower).

    ,-3.1. Direct-combustion boiler/steam technology

    This technology has matured over years and it is wellproven in industries having demandfor both electricity and large quantity of steam at high and low pressures. In thistechnology, the biomass is burntto produce steam in boilers. The steam is then used toproduce electricity by means of steam turbines and to also provide process heat. The twotypes of steam turbines most widely used are the backpressure and the extractioncondensing types(CECA, 2002-2003).

    In the backpressure turbine, incoming high pressure steam is reduced to low pressuresteam which provides thennal energy for the plant process heat. In the process, shaftpower is produced which turns a generator coupled to the shaft to produce electricity.Where process heat is required at two different pressure or temperature levels someamount of steam can be extracted from the turbine after being expanded to a certainpressure level.

    In the extraction-condensing turbine, a portion of the steam is extracted at one of thestages of the steaniturbine for process heat and the remainder goes from the turbine intoa condenser to ensure that the maximum amount of heatis converted into electricity. Theextraction-condensing turbine plant has higher power to heat ratio. It requires auxiliaryequipment such as the condenser and cooling towers. However it provides a bettermatching of electric power and heat demand where electricity demand is much higher

    I~ ~

    I~'

    2

  • I _

    I~

    I~'than the steam demand and the load patterns are highly fluctuating (ESDD, 2000). Thebackpressure turbine cogeneration plant on the other hand has higher heatto power ratioand higher overall efficiency. Since it needs less auxiliary equipment, the initialinvestment costs are low.

    The choice between backpressure turbine and extraction-condensing turbine depends onthe quantities of power and heat, quality of heat and economic factors. Heat to-powerratios and other parameters of the two systems are given in Table I(ESDD, 2000).

    I~

    I~

    Table I: Heatto power ratios and other parameters of steam turbine cogenerationsystems

    ^

    Cogenerationsystem

    Backpressure steamturbine

    Extraction-

    condensing steamturbine

    A complete steam turbine cogeneration system consists of several components: fuelpreparation; handling and storage; fuel combustion, heat conversion, electrical energygeneration; and automation and controls for the entire system. There are suppliers whichcan provide the complete tumultey supply of cogeneration mitts packaged as "of-the-shelf'products and guarantee their themIal and electrical perlonnance. The package units canbe installed in a few days with very little structural or engineering work at the site.

    Biomass-fired steam turbine cogeneration plants are available in the power range from0.5 MW, up to around 50 MW, . Plants smaller than I MW, , are usually operated asbackpressure CHP plants and aim at electrical net efficiencies of typically 10 % to 12 %.For large steam turbines, higher efficiencies can be attained. It is around 25 % in plantsof5 to 10 MW, and up to more than 30 % in plants around 50 MW, (Power Generationand Cogeneration, 2003).

    Heat-to-powerratio (kWth/kWe)

    4.0 - 14.3

    2.0 - 10.0

    Power output(aspercent offuel

    in ut

    14 -28

    22 - 40

    Overallefficiemcy(percent)

    84-92

    60 - 80

    I~

  • I__

    3.2. Gasification technology

    This is another potentially attractive technology for producing bio-power. In thistechnology, the wood residue is converted to medium- or low-calorific gas and the gasused to produce heat and electricity by any of the prime movers or technology optionsdescribed below. Even though some of the technologies are mature, for example, internalcombustion engines, problems occur when using biomass fuels due to the quality of thefuel gas produced by a gasification system. Research to improve gasification technologyis ongoing (Sims and Gigler, 2002).

    Gas IIJrbines. . The gas is used to heat air which passes through a turbine to createelectricity and the energy released at high temperature in the exhaust stack is recoveredfor process heat. If more power is required at the site, it is obtained by using the gasturbine in a combined cycle with a backpressure or extraction condensing steam turbinebottoming cycle. The exhaust or extracted steam from the steam turbine then providesthe process heat. With this system the overall efficiency of the cogeneration plant canexceed 80 %.

    I~

    I~

    Gas turbines are a mature technology, but biomass-fired gas turbines coupled togasification systemsremain in research stage. They have potential in 5 to 20 MW, rangeor above (Sims and Gigler, 2002).

    Intornol combustion engines. . The gas from the gasification plant provides fuel for thegas engine. The process heatis harnessed from the exhaust gas at high temperatures andengine jacket cooling water system at low temperatures. Power produced can beincreased here also using it in a combined cycle with a steam turbine. One of the majoradvantages of internal combustion engines over the other prime movers is their higherelectrical efficiency. They can achieve electrical efficiencies of around 25-30 % (Simsand Gigler, 2002).

    The system finds application in smaller energy consuming facilities having greater needfor electricity than thennal energy and where the quality of heat required is not high e. g.low pressure steam or hot water. This system has low initial invesiment cost but highoperating and maintenance costs. The units under development are in the range of 5 to25 kWe (Sims and Gigler, 2002).

    Fuelce/Is. . Biomass gasification system can provide fuelto fuel cell. Several fuel cellsdesigns are under development. They have such advantages as high system efficiencies,low noise levels, low emissions and good reliability. This technology needs several moreyears of research and development before they become economicalIy and technicalIyfeasible at powerscales of 50 kW* to 5 MW, .

    Microt"Ibines. . These are relatively new development. Microturbines and internalcombustion engines integrated with gasification technologies are promising cost-effectiveand small-scale systems but further research into gas cleaning is still needed in order toimprove system perfonnance.r'

    r

    4

  • \-

    L_

    {-

    r~

    Different biomass-fired microturbines systems are under development in the range 2 -250 kWe. Microturbines are compact and lightinweight and have low noise levels.

    3.3. The Stirling Engines

    These are externalIy fired engines suitable for small-scale biomass power production. Ina Stirling engine, a gas in a sealed system expands and contracts as it is subjected toheating and cooling cycles. The resulting pressure cycles are then used to drive a pistonand crankshaft, which, in turn, power an electrical generator (Hislop).

    The Stirling engines are just reaching the coriumercialtechnology phase. They havepotential in the power range of 10 to 150 kW, . They have many advantages at the smallscale such as reasonable efficiencies (up to 30 %), low noise levels, low maintenance,and expected long engine lifetime (Sims and Gigler, 2002). They can be coupled tocombustion or gasification system.

    I~

    4. IDENTIFICATIONOFSITESFORGOODCOGENERATIONPOTENTIAL

    I~

    Wood processing mills which are potential candidates for biomass-firedcogeneration should have the following characteristics ( ESDD):

    (a) adequate thermal energy demand, matching with the electrical energy demand(b) reasonably highelectricalloadfactor(c) reasonably high annual operating hours(d) fairly constant and matching electrical and themIal demand profiles(e) availability of unused woodresidue

    The availability of unused wood residue and guarantee of its long-tenn supply are amajor factor detennining the potential site for cogeneration. Since stoppages forscheduled maintenance or unscheduled breakdown are inevitable, the site should alsohave back-up power to ensure continuity of essential activities at the site.

    Most of the existing wood processing mills in Ghana fulfilthe requirements for goodcogeneration potential. For the purposes of this study, numerous mills were visited andthree of them, finally selected for further technical and economic feasibility studies.

    r

    I_

    4.1. Methodology

    Identification of potential sites for cogeneration was achieved by visits to a number ofimportant and well-known wood processing mills in the country. During on-site visits tothese mills structured questionnaires were filled out and direct discussions held with themill management.

    5

  • I'

    4.2. Selection of Potential Sites

    Most of the wood processing mills fulfil the technical requirements for goodcogeneration. To selecttliree out of the lot visited, the following criteria were used:

    (a) minisimportant consumer of electricity and heat(b) millhas higher thermal energy demand than electricity(c) management is willing to implement the cogeneration technology(d) millhaslarge annual operating hours(6) unused wood residue is available in large quantity and there is a guarantee of its

    long-term supply

    4.2. I. Selected Potential Sites

    The three wood processing mills selected are presented below:

    4.2.1.1. Asuo Bornosad" Timbers & Sawmills Limited (Abts Ltd)

    Asuo Bornosadu Timbers & Sawmill Limited is located at Berekum in Brong AhafoRegion of Ghana. The mill has two main sections, namely sawmill and moulding millsection; and ply mill section. It produces lumber, veneer, plywood, flooring parquet andflooring strips for both local and international markets. The Sawmill and Moulding millsection operates 16 hours a day and 305 days a year and the ply mill section operates 24hours a day and 305 days ayear.

    Its monthly log input is approximately 6000 in , with 2500 in and 3,500 in going intosawing and veneer production respectively.

    WoodResidue

    The wood residue generated consists principalIy of sawdust, bark, veneer chippings,slabs, edgings, peeler cores and off-cuts.

    Used Residue

    The sawdust and dry veneer chippings are used for boiler fuel, peeler cores arereprocessed into boards using woodmizer and about 20% of the slabs and edgingsreprocessed into flooring parquets, flooring strips and triangular mouldings.

    Unused Residue

    This includes slabs, bark, sapwood edgings and wet veneer chippings. Theresidue constitutes about 38% of the total log input which is about 6000 in .

    I~

    I~

    L_

    F'.

    6

    unused

  • L

    4.2.1.2. Log And Lumber Limited (LLL)

    This is one of the largest wood processing mills in Kuniasi. The mill has lumberproduction, slice veneer and rotary veneer sections. Its main products are lumber, veneer,plywood and T&G for export. It operates 24 hours a day in two shifts and a minimum of7512 hours per amIrun. Its log input for January 2004 was approximately 7,152,024 inwith 27.03%, 23.40% and 49.56% going into production of sliced veneer, ply mill andlumber respectively.

    4.2.1.3. Omega Wood Processing Limited (OWPL)

    This minis located in Kmnasi. It has four sections: sawmill, moulding, rotary veneer, plywood and slice veneer. Its products are lumber, veneer and plywood for domestic andinternational markets. The mill operates 24 hours a day and 6 days a week which resultsin annual working hours of 7512.

    The avera e monthly log input for the plywood and rotary veneer sections was about4007.57 in .

    WoodResidue

    The main fomis of residue generated by the mill are sawdust, slabs, edgings, trimmings,bark, off-cuts and veneer core. Its secondary process, which is practiced by few mills inGhana, produces mainly sawdust and wood shavings.

    The total monthly average volume of bark, sawdust and off-cuts for the period was966.73 in'. That of veneer, core, trimmings and defective veneer and plywood was about16/7.98 in3.

    5. DETERMINETHERMALENERGYDEMANlDIPROFILES

    Thermal energy requirements of selected mills are as follows:

    A.

    The mill has two thermal oil boilers and one hot water boiler providing process heat forits kiln dryers. The supply and return temperatore of the hot water boiler are 90'C and80'C respectively. It has maximum operating temperature and pressure of 95'C and 3bars and apedonnance of 1600 kW.

    Each thennal oil boiler has maximum operating temperature of 300'C, an output pressureof 3.5 to 4 bars, a capacity of 2,000,000 kg/}I, volume of 2,278 in and a themIal capacityof 3,000,000 kcal/h (3488 kW)

    ABTSLIMITED

    The fuel for the boilers consists of all the sawdust generated on site, dry veneerchippings, branches harvested in the forest and forest residues.

    r~'

    7

  • L

    The sawdustproduced is about 480.92 in'/month. This represents about 25% of the totalfuelrequirement forthe boiler.

    B.

    The millhastwo boilers which provide steam for kiln dryers with a third one to be addedin the near future. Each boiler has a maximum steam rate capacity of 10,000 kg/}I. Theboilers have an outlet pressure of 15 bars and temperature of 201'C. About 50 % of thesawdust generated on site is used as fuel for the too boilers.

    LLL

    C.

    I_

    The millhas four saw-dust fired boilers which provide steam for kiln dryers. Each boilerproduces steam at a pressure of 10 bars and a temperature of 150'C. Maximum steamflow rate for each boiler is 10,000 kg/h.

    OMEGA

    5.1. Methodology

    The three mills do not have any record of thennal energy consumption due to lack ofinstrumentation. Since infonnation on themIal energy usage patterns was lacking, thepeak process heat requirement was assumed to be the installed thennal capacity at thesites.

    5.2. Results

    The process heat requirement was assumed to be the installed thennal capacity givenabove. The themIal energy needs for each mill was supposed to be constantthroughoutthe operation of the mill.

    6. Determination of the Electrical Energy demand Profiles

    The three selected mills obtain their electricity supply from the national grid and havediesel generator sets to provide power for their essential loads in the event of poweroutage. Their electrical energy requirements are swimiarized as follows:-

    ABTS

    It obtains its electric power from the national grid via two transformers, each rated IMVA. One of the transfomiers services the sawmill and moulding millsection and theother the ply mill section. The mill owns three standby diesel generator sets, each rated630 kVA.

    8

  • .

    I~~~

    LLL

    Electric power is supplied from the national grid through fourtransfonners having a totalcapacity of 3.8 MVA. It owns one diesel-generatorsetrated 975 kW.

    OMEGA

    Three 800-kVA transfonners supply power to the mill from the national grid. Threediesel-generator sets of total capacity of 1350 kVA provide partial backup in case ofpower outage.

    6.1. Methodology

    In the absence of instrornentation for regular monitoring of electrical energy consumed,the electricity consumption patterns were derived from the monthly electricity bills over aperiod of one year. A bill for a particular month indicates the maximum demand forthemonth and the total energy consumed for the month.

    r^

    6.2. Results

    I~~

    The annual load curves plotted from monthly demand derived from the electricity billsare shown in Figure I. Monthly energy consumptions for a period of one year are alsoshown in Figure 2. analysis of the monthly electricity consumption of the mills in aperiod of one year gives the data in Table 2 relevant forthe study

    Table 2: the total installed thermal capacities the applied factors and estimatedthermal energy consumptions for 3 wood processing mills

    . .

    Maximum monthly electricityconsumption (i?20nih/energy in kWh)Minimum monthly electricityconsumption (month"energy in kWh)Maximum monthly demandOrionth4?ower in kll?

    I

    Minimum monthly demandOrionth470wer in kll?

    I~

    Total electricity consumption07eriod/energy in kWh)

    I~

    I~

    Aug/ 210,400Ply mill

    ABTS

    Jan I 74,155

    June I 510

    Nov I 576,500

    Sawmill

    Jan I 186

    Mar/ 70,970

    Jan-Dec, 2003/1,970,340

    Oct/ 318

    LLL

    Aug/758,736

    July I 269

    Jan/ 596,985

    Jan-Dec, 2003/1,508,465

    OMEGA

    Jan I 1,550

    May/ 315,650

    June I 1440

    July/ 212,840

    Oct 2003- Sept2004/ 8065512

    May/846

    9

    Mar/ 607

    Oct 2003- Sept2004/2959040

  • 140,000

    120,000

    = 100,000"̂ 80,000>

    E' 60,000,,= 40,000Ul

    20,000

    o

    ^

    ^

    Figure ,: Electricity consumption at ABTS sawmills

    Mar

    330

    320

    ^ 310" 300^

    , 290^ 280o 270o 260

    250

    240

    May

    Figure2: Annual Load curve of ABTS sawmills

    JulJun

    year2003

    D Energy(kWh)

    Feb

    ALU

    Mar

    Sep

    ^ 200,000250,000

    ^. 150,000>

    P 100,000o=

    50,000IU

    o

    Od

    May

    Nov

    Figure3: Electricity consumption at ABTS Plymill

    JulJun

    Year2003

    ~- Demarxi (kW)

  • 600

    ^ 500^. 400

    ^ 300"

    E 200oo 100

    o

    Figure4: Annual Load curve of ABTS Plumill

    e-

    >,

    2' 150,000a,

    ^5 100,00050,000

    o

    S'*

    Figure5: Electricity consumption at Omega

    Year2003

    ~-Demarid(kW)

    ^\ ,.* ^? *

    ^.

    0,143 buts

    ,.,Q

    900

    800

    _ 700

    , 600, 50015 400o 300Q

    D. e-03

    ^*"

    ^O

    ^

    J. n44

    ^$,0'

    F. bC4

    200

    100

    o

    Figure6: Annual Load curve of Omega

    Apr. 04". r. 04

    Months

    Energy (kWh)

    Od43

    ". y44

    Nov43

    J""-04

    Deco3

    Jul. 04

    J. n44

    Aug. 04

    Feb44

    Sep-04

    Apr-04MarC4

    Month

    -- Demarxi (kW)

    May^4 Jun44 Jul4, Aug44 Sep44

  • 50 . ...

    .. ..,

    ... ...

    .. ...

    .. ..,

    .. ...

    ., .,.

    .. ...

    .

    7. DETERMINETHESPECIFICATIONF'ORCOGENERATIONPLANTS

    7.1. Introduction

    In general, cogeneration plant may be sized in four ways leading to four operatingschemes described below (ESDD, 2000):

    Base electrical load matching

    In this operating scheme, the plantis sized to meetthe minimum electric power demandof the site and the extra power required is imported from the Utility grid. Ifthe thennalenergy generated is not enough, additional boilers are used to generate the deficit.

    Base thermal load matching

    Here, the plant is sized to supply the minimum thennal energy need of the site. Excessthermal demand overthe base is met by stand-by boilers. Electricity is imported from or

    12

  • exported to the Utility grid depending on whether the power produced by the plant fallsshort of or exceedsthe power requirement of the site.

    7.2. Electrical load matching

    In this scheme, the plant is sized to meet anthe power requirement of the site thusmaking it independent of Utility grid. If there is deficit of thermal energy, additionalboilers are used. Ifon the other hand there is excess thennal energy, it is either exportedto neighbouring facilities or wasted.

    I__

    7.3. Thermal load matching

    In this case, the plant is sized to meetthe thermal energy requirement of the site at anytime. In the event of the power generated by the cogeneration plant not matching theelectricity demand of the site, the excess or deficitis sold to or purchased from the Utilityasthe case may be.

    7.4. Methodology

    Wood processing mills in Ghana obtain electric power from the national grid and use on-site boilers to meet the thennal energy need. The introduction of cogeneration in themills is meant to achieve higher utilization efficiency of the wood residue by convertingpart of the wasted primary energy associated with the existing energy conversion systeminto electricity. Consequently the cogeneration plant is sized for thermal load matching.The mills, having access to the national electricity grid, can either import or export powerat any instantifthe power produced by the cogeneration plant does notmatch its demand.Since infonnation on thermal energy usage patterns was lacking, the peak process heatrequirement was assumed to be the installed themIalcapacity at the sites.

    The backpressure steam turbine was selected due to the high steam consumption in themills compared to availability of wood residues. The size of a single-stage backpressuresteam turbine topping cycle cogeneration plant was determined for typical inlet pressuresof 20, 30 and 40 bars and at superheated temperatures of 300'C and 400'C. The actualwork done by the turbine was calculated by multiplying the isentropic efficiency by thework done by an ideal turbine under the same conditions. For smallturbines, the turbineefficiency is generally 60 to 80 %, for large turbines, it is generally about 90 %(Engineers Edge 2002. ). The calculations were done assuming typical boiler, generatorand tarbine efficiencies of 78, 96 and 50 % respectively (Steam Tip Sheet # 20, 2004,Steam Tip Sheet # 22, 2002) and a boiler feed-water temperature and pressure of 90'Cand 2.5 bar gauge respectively. Anthe relevant fomiulas are as follows:

    . Electric Power

    p = IfZ(hin ~ h, ",,, }7,677g, " (kW. )

    13

  • Where,

    in =massflowrateofsteam, kg/s

    h, =specificenthalpyofsteamenteringtheturbine, kJ/kg

    h, ,r, , = specificenthalpyofsteamleavinganidealturbine, kJ/I, g771b =turbineefficiency

    77, ,, =generatorefficiency

    I~

    . Outlet Enthalpy of Real Turbine

    h, ,,,, = hi, ~ ty, b (fom ~ ham, , )(kJ/ICg)

    Where,

    h, ,l, , = specificenthalpyofsteamleavingtheacttialturbine, kJ/kg

    . Thermal Power

    S = Ifzh, ,,,, (kWth )

    Where,

    S = heatgenerated, kW

    In cases where thennal power rather than steam rate is specified the above fomiula isstillrequired for the calculation of the corresponding steam rate.

    . Power to Heat Ratio

    .

    pHR=PISFuel Consumption in kW

    Fk\Ifz(hin - hf)in _ I (kW)

    Where,

    'ib

    h =specificenthalpyoffeedwater, kill:g

    tyb = boiler efficiency

    14

  • I_

    I .

    r

    . Fuel Consumption intolines/year

    Fk\ 3.6F*, HR (,,, ines/ ear)C

    Where,

    HR = actual working hoursperyearC = calorificvalueoffuel, kJ/kg

    I~

    7.5. Results

    The results are given in Tables 3 to 5

    Table 3. Results for OmegaSteam rate (kg/lit)

    I~

    Outlet pressure (bar)Armual working hours (lit)Turbine inlettemperature ('C)Turbine inlet pressure (bar)Electric power(kW)Thermal power(kW)Heatto power ratioFuelconsumption (kW)Fuel consumption (tomies/year)Fuelconsumption (in lyear)

    40,00010

    7512

    L

    20

    L_

    962

    300

    Steam rate (kg/}IT)

    3 1,884

    Outlet pressure (bar)

    33

    30

    Armualworking hours(lit)

    L . _

    38,635

    1,433

    Turbine inlettemperatore ('C)

    58,045

    31,723

    I_

    Turbine inlet pressure (bar)

    73,850

    22

    20

    38,190

    400

    1,162

    Electric power(kW)

    57,377

    34,854

    ThemIalpower(kW)

    75,900

    30

    30

    Heat to power ratio

    41,940

    1,759

    Fuelconsumption (kW)

    Table 4. Results for LLL

    41,940

    34,045

    Fuelconsumption (tonnes/year)

    80,160

    19

    Fuelconsumption (in lyear)

    30,000

    41,694

    15

    41,694

    7512

    79,700

    20

    316

    300

    16,557

    30

    78

    28,976

    715

    43,533

    31,723

    40

    66

    55.39

    28,643

    957

    43,033

    23,638

    20

    25

    54.75

    28,279

    382

    400

    42,486

    26,650

    30

    54,05

    70

    31,455

    878

    15

    47,258

    25,994

    40

    60.12

    30

    31,270

    1,194

    46,980

    25,521

    59.77

    21

    31,08046,69559.41

  • I~

    L_

    L .

    Thennalpower(kW)Outlet pressure (bar)Annual working hours (lit)Turbine inlettemperature ('C)Turbine inlet pressure (bar)

    C'~

    Electric powerThemIalpowerHeat to power ratio

    ,-

    Steam rate

    Table 5. Results for ABTS

    Corresponding electric power(kW)Corresponding fuelconsumption (kW)

    r~

    Corresponding fuelconsumption (tonnes/year)

    steam rate of 1000kg/}I(kW)

    Corresponding fuelconsumption (in

    steam rate of 1000kg/h (kW)

    thermal power of 8,600 kW

    r~

    8,60010

    7320

    20

    24,050

    300

    797.1

    L_

    33

    30

    lyear)

    r

    8,903

    35.83

    214

    793.08

    8,599

    22

    20

    r'~

    9,008

    12,589

    29.05

    L

    400

    322.76

    16,020

    871.35

    8,600

    30

    30

    I_

    12,590

    8,202

    43.98

    238.27

    16,018

    851.13

    8,600

    19

    12,590

    8,251

    L__

    16,018

    362.87

    r-

    8,60012,59016,018

    r~

    L.

    I~

    16

  • I.

    I~

    8. Conclusion

    The wood processing mills in Ghana use on-site boilersto generate steam or hot water tomeet antheirthennaldemand. Hence the cogeneration plants forthe three selected millswere sized forthennalload matching. As the steam consumption in the mills was high,the backpressure steam turbine was selected.

    Several turbine inlet pressures and temperatures were considered forthe sizing of thecogeneration plants and from the results of the study, the inlettemperature was specifiedas 400'C at anthe three sites and the inlet pressure taken as 30 bars at both OWPL andABTS and 40 bars at LLL. These led to power ratings of 2,000 kWe, 1,200 kWe and 400kWe and heat to power ratios of about19, 21 and 19 at OWPL, LLL and ABTSrespectively. The corresponding fuel consumptions were about 80,000 in lyear, 32,000in'/year and 17,000 in'/year. The fuelrequirement forthe plants at LLL and ABTScompares favourably with the annual volume of residue generated which is estimated as32,610 in' and 27,360 in' at LLL and ABTS respectively.

    r

    I~

    17

  • I~9. Recommendations

    I. Carry out a detailed demonstration co-generation project studies at one of thethree selected sites, namely, ABTS, LLL AND OMEGA.

    2. Undertake studies to monitorthe thermal and power demand patterns for correctsizing of the cogeneration unit.

    \ .

    r~.

    r~-

    I_

    18

  • Reference

    I) Prasertsan Suteera; Krukanont Pongsak; NgamsritragulPanyarak andKirirat Pairoj: Strategy for optimal operation of a biomass- firedcogeneration power plant;Institution of Mechanical Engineers Part A :Power and Energy, 215(41): 13- 26, 2001 imp://WWW.clib. psu. an. th/00ad-441psuteel. html

    2) Energy Tips - Steam: Consider installing high- pressure boilers with backpressure tarbine generators;Industrial Technologies Programme. SteamTip Sheetn0. 22. Us Department of energy; Energy Efficiency andRenewable Energy, September, 2004

    3) Sims Ralph and Gigler JOTg: The brilliance of bioenergy- smallprojectsusing biomass. Renewable Energy World ; James and James (sciencepublishers) ; January-February, 2002.

    I_

    htt ://WWW. 'x'. conyma sand'/rew/2002-011sims/himI

    4) Biopower: Gasificationtechnology for clean cost-effective biomasselectricity generation. Department of energy, Library .htt://WWW. eere. ener . ov. /bio ower/b lib/libra In- asification. htm

    5) Hislop Drummond: Development of abiomass fuelled gasifier/ Stirlinggenerator for developing countries: Reliable, low-cost power generation,Innovation in Europe: Research and Results; Energy, Sustainable EnergySystems Ltd. Ref. Jou2-CT 92 -0160, Prograrnme Joule 11

    6) Debra Jenkins: Researchand development of markets and supplystrategies for short rotation forestry, forest residue and conversiontechnology for CHP- electricity from wood: Integrated Production andprocessing chain - Electricity from wood: Fair co-operative Research forSMEs. July, 2000. htt ://mayw. incaws. ov. bc. call d/pol-research/ubcnV1993/B47-Co-generation-potential. html

    7) Engineers Edge : Power plant components- Thennodynamics, 2000

    8) Introduction to CHP Catalog of Technologies:http:// WWW. e a. ov/ch I dinntr0%20 to%20cat%200f% 200f%20tech. pdf

    19

  • Year

    2003

    2003

    Month

    2003

    January

    APPENDIXl

    2003

    February

    2003

    March

    2003

    April

    2003

    May

    2003

    Energy (kWh)

    June

    ABTS Ply mill

    2003

    July

    2003

    August

    2003

    September

    2003

    74,155

    October

    120,690

    November

    115,015

    Demand(KVA)

    December

    210,240

    Year

    163,240163,000

    2003

    163,400210,400

    2003

    Month

    200

    2003

    192,400

    January

    Demand(kW)

    251

    2003

    153,600

    February

    216

    2003

    193,800

    March

    224

    210,400

    2003

    April

    251

    2003

    May

    548

    2003

    Energy (kWh)

    186

    ABTS Sawmill

    June

    436

    2003

    233

    July

    504

    2003

    201

    August

    506

    2003

    208

    September

    352

    2003

    81,470

    233

    October

    352

    71,220

    November

    510

    432

    Demand(KVA)

    70,970

    405

    December

    82,305

    469

    72,600

    471

    72,600

    327

    76,600

    327

    100,200

    402

    302

    108,000

    Demand(kW)

    302

    116,200

    315

    115,500

    320

    79,800

    315

    286

    296

    274

    296

    300

    309

    304

    314

    324

    309

    318

    280

    304

    269

    294

    298

    3 18

    312

    20

    298

  • L .

    Year

    r-

    2003

    2003

    Month

    2003

    October

    2004

    November

    2004

    December

    2004

    January

    2004

    February

    2004

    Energy (kWh)

    March

    2004

    April

    OMEGA

    2004

    May

    2004

    June

    226,610

    2004

    July

    Year

    250,690

    August

    179,330

    Demand(KVA)

    September

    223,540

    2003

    241,230

    2003

    Month

    246,770

    2003

    October

    292,320

    2004

    November

    315,650

    2004

    December

    690

    215,880

    2004

    January

    740

    Demand(kW)

    212,840

    2004

    February

    700

    277,720

    2004

    Energy (kWh)

    March

    720

    276,460

    2004

    April

    680

    2004

    LLL

    May

    690

    2004

    656

    June

    870

    688,521

    2004

    688

    July

    910

    652,635

    637

    August

    880

    527,943

    662

    Demand(KVA)

    September

    870

    596,985

    632

    880

    619,182

    607

    870

    702,009

    774

    662,283

    846

    693,111

    2,388

    818

    688,137

    1,788

    809

    Demand(kW)

    749,295

    1,560

    827

    758,736

    1,632

    818

    726,675

    1,5121,584

    2,101

    1,560

    1,699

    1,584

    1,529

    1,500

    1,550

    1,608

    1,467

    1,572

    1,521

    1,632

    1,4981,5211,4401,5281,4931,518

    21

  • Site Information:

    I.

    2.

    3.

    4.

    5.

    mestiomnaire for Co emeration in a Sawmill

    APPENDIX2

    Main Activity:Hours of Operation:Working Days:Total Armual Operating Hours:Period and Duration of Annualshutdown:

    Einer

    I. Electricity Data (at least for last 12 months)

    Demand and FuelReso"rce Data

    Year Month

    2. Transfonner Capacity (kVA)3. amualPeakDemand (kW/ICVA)4. Any changes in the future demand patterns expected:5. Ally alternative source of power apart from ECG:6. Ifyes, please specify hypo of plant):7. Whatisthe capacity of the alternative:8. What do you when currentsource fails:

    Whatisthe capacity of back-up system:At what cost:

    ConsumptionMWh

    I.

    11.

    PeakHours

    Wh

    I. Whatis current source of thennan}IeatrequirementSteam from boiler .Electrical heating .

    2. Ifsteamfrom boiler

    Off-peakHo"rs

    MWh

    i. Boiler outletpressure(Bar)andtemperature('C)ii. Processheatrequirementpressure (Bar)andtemperature ('C):

    3. Hotwater:

    r

    Thermal/Heat Data

    Yes . No.

    22

  • I .I~

    i. Supplytemperature('C)ii. RetumTemperature(')

    Thermal Requirement(for last12 months)

    4.

    Year Month

    5. Any alternative should currentsource fail:6. Any changes in the future demand patterns expected:

    Boiler fuelcons"inption (for last 12 months)

    7.

    I~ ~

    Year

    Steam

    Ton

    Month

    8. Capacity of Boiler facility:9. Does the Boiler require retrofitting/replacement?

    Wood Waste/Sawdust data

    I.

    HotWater

    G

    Whattype of sawdustis produced (eg. Weti'dry)(List by type of wood ifpossible)

    ................................................

    Fuel

    ...............................................

    2.

    I, _

    ...............................................

    What other type of wood waste is produced (eg. Bark, wood chippings, etc. )...............................................

    ..................................................

    3.

    ..............................................,.....

    How much volume of each do you produce (monthly/daily estimated)

    Other Fuel

    T Gofwoodwaste

    ........................................

    ...............................................

    .......................................

    Age:

    .................................................

    ...................................

    ...................................

    ...................................

    ...................................

    ...................................

    ...................................

    Volume

    ...................................

    23

    ...................................

    ...................................

    ...................................

  • 4. Ally uses forthe wood waste:Solid/Given out(B)Used (A)Recycled (E)Burnt'Disposed off(D)

    i. Sawdust: ........................................

    ii. Bark: ............................................

    I __

    111.

    IV.

    V.

    5.

    ...................................................

    ...................................................

    Ifsold or given out, what does buyer/recipient use it for:UseIL:{^

    ...................................................

    ...................................

    ...................................

    ...................................

    6.

    ...................................

    Any problem(s) being caused by wood waste:ProblemI^P^

    ...................................

    ...................................

    7.

    ...................................

    Any changes in wood waste handling expected.

    Fuel(C)

    ...............................

    ...............................

    ...............................

    ...............................

    ...............................

    ...............................

    ...............................

    24

  • I_

    Project Coordinator

    DTDanielSekyere, FORIG, Box 63 ,KNUST, Kumasi, Ghana

    Email:dsek ere fori. or

    Project Technical and Scientific staffs:

    r~~

    Dr. P. Y. Okyere

    Department of Electrical and Electronic Engineering, Kl\IUST, Kumasi, Ghana

    Dr. N. A. Darkwah

    Institute of Renewable Natural Resources, KNUST , Kuinasi, Ghana

    Mr. K. S. Nketiah

    Up 982, KNUST, Kmnasi, Ghana

    Email: ksnketiah ahoo. coin

    25