  • Interface Milestone Plan

    CONTRACTOR shall:

    (a)Develop and maintain an Interface Milestone Plan detailing essential interfaces which support the logical network of the schedule related to the WORK (e.g. other EPC Contractors performing RELATED WORK, design, procurement, fabrication and construction) reflecting the timing of interface work and allowing resolution of any potential conflicts or discrepancies

    (b)Update the Interface Milestone Plan on a monthly basis and issue the update to COMPANY together with the PROGRAMME