Installation Reference

download Installation Reference

of 55

Transcript of Installation Reference

  • 8/10/2019 Installation Reference

    1/55

    OptiX RTN 605 Radio Transmission System

    V100R005C00

    Installation Reference

    Issue 01

    Date 2009-12-30

    HUAWEI TECHNOLOGIES CO., LTD.

  • 8/10/2019 Installation Reference

    2/55

  • 8/10/2019 Installation Reference

    3/55

    Copyright Huawei Technologies Co., Ltd. 2009-2009. All rights reserved.

    No part of this document may be reproduced or transmitted in any form or by any means without prior writtenconsent of Huawei Technologies Co., Ltd. Trademarks and Permissions

    and other Huawei trademarks are trademarks of Huawei Technologies Co., Ltd. All other trademarks and trade names mentioned in this document are the property of their respective holders. Notice

    The purchased products, services and features are stipulated by the contract made between Huawei and thecustomer. All or part of the products, services and features described in this document may not be within the

    purchase scope or the usage scope. Unless otherwise specified in the contract, all statements, information,and recommendations in this document are provided "AS IS" without warranties, guarantees or representationsof any kind, either express or implied.

    The information in this document is subject to change without notice. Every effort has been made in thepreparation of this document to ensure accuracy of the contents, but all statements, information, andrecommendations in this document do not constitute the warranty of any kind, express or implied.

    Huawei Technologies Co., Ltd. Address: Huawei Industrial Base

    Bantian, LonggangShenzhen 518129People's Republic of China

    Website: http://www.huawei.com

    Email: [email protected]

    Issue 01 (2009-12-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    i

    http://www.huawei.com/
  • 8/10/2019 Installation Reference

    4/55

  • 8/10/2019 Installation Reference

    5/55

    About This Document

    PurposeThis document provides the guidelines for the general installation operations for the installation

    personnel. This document also describes the relevant regulations that need to be observed for

    routing and bundling cables and using engineering labels.

    Related VersionsThe following table lists the product versions related to this document.

    Product Name Version

    OptiX RTN 605 1D/2D/1E/2E V100R005C00

    iManager U2000 V100R002C00

    Product Name Version

    OptiX RTN 605 1F/2F V100R003C00

    iManager U2000 V100R002C00

    Intended AudienceThe intended audiences of this document are hardware installation engineers.

    OrganizationThis document is organized as follows.

    OptiX RTN 605Installation Reference About This Document

    Issue 01 (2009-12-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    iii

  • 8/10/2019 Installation Reference

    6/55

    Chapter Content

    1 GeneralInstallationGuidelines

    Describes certain general operations of installing the OptiX RTN605 equipment.

    2 Regulations onRouting andBundling Cables

    Describes the regulations that need to be observed for routing and bundling cables.

    3 EngineeringLabels for IndoorCables

    Describes the regulations that need to be observed for using indoor engineering labels.

    4 EngineeringLabels for OutdoorIF Cables

    Describes the regulations that need to be observed for using outdoor engineering labels.

    Conventions

    Symbol Conventions

    The symbols that may be found in this document are defined as follows.

    Symbol Description

    Indicates a hazard with a high level of risk,which if not avoided, will result in death or serious injury.

    Indicates a hazard with a medium or low levelof risk, which if not avoided, could result inminor or moderate injury.

    Indicates a potentially hazardous situation,which if not avoided, could result inequipment damage, data loss, performance

    degradation, or unexpected results.

    Indicates a tip that may help you solve a problem or save time.

    Provides additional information to emphasizeor supplement important points of the maintext.

    General Conventions

    The general co nventions tha t may be found in this document are defined as follows.

    About This DocumentOptiX RTN 605

    Installation Reference

    iv Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    Issue 01 (2009-12-30)

  • 8/10/2019 Installation Reference

    7/55

    Convention Description

    Times New Roman Normal paragraphs are in Times New Roman.

    Boldface Names of files, directories, folders, and users are inboldface . For example, log in as user root .

    Italic Book titles are in italics .

    Courier New Examples of information displayed on the screen are inCourier New .

    GUI Conventions

    The GUI conventions that may be found in this document are defined as follows.

    Convention Description

    Boldface Buttons, menus, parameters, tabs, windows, and dialog titles are inboldface . For example, click OK .

    > Multi-level menus are in boldface and separated by the ">" signs. For example, choose File > Create > Folder .

    Mouse Operation

    The mouse operations that may be found in this document are defined as follows.

    Action Description

    Click Select and release the primary mouse button without moving the pointer.

    Double-click Press the primary mouse button twice continuously and quickly withoutmoving the pointer.

    Drag Press and hold the primary mouse button and move the pointer to a certain position.

    Update HistoryUpdates between document issues are cumulative. Therefore, the latest document issue containsall updates made in previous issues.

    Updates in Issue 01 (2009-12-30) Based on Product Version V100R005C00

    This document is the first release of the V100R005C00 version.

    OptiX RTN 605Installation Reference About This Document

    Issue 01 (2009-12-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    v

  • 8/10/2019 Installation Reference

    8/55

  • 8/10/2019 Installation Reference

    9/55

    Contents

    About This Docum ent...................................................................................................................iii

    1 General Installation Guidelines..............................................................................................1-11.1 Unpacking the Equipment...............................................................................................................................1-2

    1.1.1 Checking the Equipment........................................................................................................................1-21.1.2 Unpacking Crates...................................................................................................................................1-3

    1.1.3 Unpacking Cartons.................................................................................................................................1-6

    1.1.4 Unpacki ng Boards..................................................................................................................................1-7

    1.2 Terminati ng the IF Cable with Connectors.....................................................................................................1-8

    1.2.1 Terminating the Type-N Connectors......................................................................................................1-8

    1.2 .2 Terminating the TNC Connectors........................................................................................................1-11

    1.3 Testing th e Connectivity of the IF Cable......................................................................................................1-13

    1.4 Waterproofin g Outdoor Connectors..............................................................................................................1-14

    2 Regulations on Routing and Bundling Cables.....................................................................2-12.1 Regulations for Routing and Bundling the Indoor Cable................................................................................2-2

    2.1.1 Cabling...................................................................................................................................................2-2

    2.1.2 Bundling.................................................................................................................................................2-2

    2.1.3 Bun dling Fiber Jumpers.........................................................................................................................2-3

    2.2 Routing a nd Bundling the IF Cable.................................................................................................................2-4

    3 Engineering Labels for Indoor Cables...................................................................................3-13.1 Introduction to Labels.....................................................................................................................................3-2

    3.1.1 Labels for Power Cables........................................................................................................................3-2

    3.1.2 Labels f or Signal Cables........................................................................................................................3-33.2 Preparing Lab els..............................................................................................................................................3-3

    3.2.1 Printing Labels.......................................................................................................................................3-3

    3.2.2 Writing Labels........................................................................................................................................3-4

    3.3 Affixing Labels...............................................................................................................................................3-4

    3.3.1 Affixing a Label to a Power Cable.........................................................................................................3-5

    3.3 .2 Affixing a Label to a Signal Cable.........................................................................................................3-6

    3.4 Common Engineering Labels..........................................................................................................................3-7

    3.4.1 Engineering Labels for Cabinet Power Cables.......................................................................................3-8

    3.4.2 Engineering Labels for Optical Fibers...................................................................................................3-9

    3.4.3 Engineering Labels for Trunk Cables..................................................................................................3-11

    OptiX RTN 605Installation Reference Contents

    Issue 01 (2009-12-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    vii

  • 8/10/2019 Installation Reference

    10/55

    3.4.4 Engineering Labels for IF Jumpers......................................................................................................3-13

    3.4.5 Engineering Labels for Network Cables..............................................................................................3-14

    3.4.6 Engineering Labels for External Alarm Cables...................................................................................3-15

    4 Engineering Labels for Outdoor IF Cables...........................................................................4-14.1 Engineering Labels for IF Cables....................................................................................................................4-2

    4.2 Binding the Labels for IF Cables....................................................................................................................4-3

    ContentsOptiX RTN 605

    Installation Reference

    viii Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    Issue 01 (2009-12-30)

  • 8/10/2019 Installation Reference

    11/55

    Figures

    Figure 1-1 St raightening the tongue.....................................................................................................................1-4

    Figure 1-2 Re moving the cover ...........................................................................................................................1-5

    Figure 1-3 Re moving the surrounded wooden boards......................................................................................... 1-5

    Figure 1-4 Unpacking the carton..........................................................................................................................1-6

    Figure 1-5 Unpacking the boards.........................................................................................................................1-7

    Figure 1-6 St ripping back the cable sheath and the insulating layer....................................................................1-9

    Figure 1-7 Fi tting the lock nut and clamp 1.........................................................................................................1-9

    Figure 1-8 Fi tting clamp 2....................................................................................................................................1-9

    Figure 1-9 St ripping back the insulating layer...................................................................................................1-10

    Figure 1-10 Fitting the connector.......................................................................................................................1-10

    Figure 1-11 Fastening the connector..................................................................................................................1-10

    Figure 1-12 Stripping back the cable sheath and the insulating layer................................................................1-11

    Figure 1-13 Fitting the lock nut and clamp 1.....................................................................................................1-12

    Figure 1-14 Fitting clamp 2................................................................................................................................1-12Figure 1-15 Stripping back the insulating layer.................................................................................................1-12

    Figure 1-16 Fitting the connector.......................................................................................................................1-13

    Figure 1-17 Fastening the connector..................................................................................................................1-13

    Figure 1-18 Testing cable connectivity..............................................................................................................1-14

    Figure 1-19 Waterproof insulation tape.............................................................................................................1-15

    Figure 1-20 PVC tape.........................................................................................................................................1-15

    Figure 1-21 Wrapping a layer of PVC tape........................................................................................................1-16

    Figure 1-22 Wrapping three layers of waterproof insulation tape.....................................................................1-17

    Figure 1-23 Wrapping three layers of PVC tape over the waterproof insulation tape.......................................1-17

    Figure 1-24 A ppearance of waterproofed outdoor connector....................................................................... .....1-18

    Figure 2-1 Bu ndling cables.................................................................................................................................. 2-3

    Figure 3-1 La bel for power cables........................................................................................................................3-2

    Figure 3-2 La bel for signal cables........................................................................................................................3-3

    Figure 3-3 W riting direction of the label..............................................................................................................3-4

    Figure 3-4 A ppearance of labels affixed on power cables...................................................................................3-5

    Figure 3-5 Affixing labels to signal cables.......................................................................................................... 3-6

    Figure 3-6 Appearance of labels affixed on signal cables....................................................................................3-7

    Figure 3-7 Example of the label on a power cable...............................................................................................3-8

    Figure 3-8 Example of the label on a fiber that connects two pieces of equipment...........................................3-10

    OptiX RTN 605Installation Reference Figures

    Issue 01 (2009-12-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    ix

  • 8/10/2019 Installation Reference

    12/55

    Figure 3-9 Example of the label on a fiber that connects the equipment and the ODF.....................................3-10

    Figure 3-10 Example of the label on a trunk cable that connects two pieces of equipment..............................3-12

    Figure 3-11 Example of the label on a trunk cable that connects the equipment and the DDF.........................3-12

    Figure 3-12 Example of the label on an IF jumper............................................................................................3-13

    Figure 3-13 Example of the label on a network cable........................................................................................3-14

    Figure 3-14 Example of the label on an external alarm cable............................................................................3-15

    Figure 4-1 Example of the label on the IF cable..................................................................................................4-2

    Figure 4-2 Appearance of the label after it is bound with the IF cable................................................................4-3

    FiguresOptiX RTN 605

    Installation Reference

    x Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    Issue 01 (2009-12-30)

  • 8/10/2019 Installation Reference

    13/55

    Tables

    Table 3-1 Information on the label affixed to the power cable............................................................................ 3-8

    Table 3-2 Information on the label affixed to the fiber that connects two pieces of equipment..........................3-9

    Table 3-3 Information on the label affixed to the fiber that connects the equipment and the ODF.....................3-9

    Table 3-4 Information on the label affixed to the trunk cable that connects two pieces of equipment..............3-11

    Table 3-5 Information on the label affixed to the trunk cable that connects the equipment and the DDF........3-11

    Table 3-6 Information on the label affixed to the IF jumper..............................................................................3-13

    Table 3-7 Information on the label affixed to the network cable.......................................................................3-14

    Table 3-8 Information on the label affixed to the external alarm cable.............................................................3-15

    Table 4-1 Information on the label bound to the IF cable....................................................................................4-2

    OptiX RTN 605Installation Reference Tables

    Issue 01 (2009-12-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    xi

  • 8/10/2019 Installation Reference

    14/55

  • 8/10/2019 Installation Reference

    15/55

    1 General Installation GuidelinesAbout This Chapter

    This chapter describes in detail the general operations of installing the OptiX RTN equipment.

    1.1 Unpacking the EquipmentAfter the project starts, the project supervisor should unpack and inspect the equipment in the

    presence of the customer.

    1.2 Terminati ng the IF Cable with ConnectorsThe IF cables may be terminated with the type-N con nectors or TNC connectors.

    1.3 Testing th e Connectivity of the IF CableDuring the pr ocedures of routing or bundling cables, and installing connectors, the circuit in acable may be come open or broken. Hence, you need to test the connectivity of the cables after the preceding procedures are completed.

    1.4 Waterpro ofing Outdoor ConnectorsAll the outdo or IF cable connectors and the grounding clips must be completely waterproofed.

    OptiX RTN 605Installation Reference 1 General Installation Guidelines

    Issue 01 (2009-12-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    1-1

  • 8/10/2019 Installation Reference

    16/55

    1.1 Unpacking the EquipmentAfter the project starts, the project supervisor should unpack and inspect the equipment in the

    presence of the customer.

    In the case of a non-turnkey project, the customer and the project supervisor should be presentduring the unpacking process. If one party unpacks the equipment when the other party is not

    present, the party who performs the unpacking should take responsibility for any error.

    In the case of a turnkey project, the project supervisor and the order management engineer shallunpack, inspect and hand over the equipment, and sign to confirm the delivery. The proceduresfor unpacking and inspecting the equipment, and for reporting equipment problems are the sameas those for a non-turnkey project, except that the customer does not need to sign the relevantdocuments. After qualified initial acceptance, the equipment should be handed over to thecustomer.

    The following section describes how to unpack, inspect and hand over the equipment for a non-turnkey project.

    1.1.1 Checking the EquipmentCheck the packing list of the delivered equipment at the site. Before unpacking, the projectsupervisor should check the cargoes against the packing list in the presence of the customer.

    1.1.2 Unpacking CratesThis section describes how to unpack crates.

    1.1.3 Unpack ing CartonsThis section d escribes how to unpack the carton that packs boards and the procedure is providedas an exampl e.

    1.1.4 Unpack ing BoardsGenerally, th e boards are not delivered separately, and are installed in the chassis before delivery.If they are pla ced in a carton for shipment, they should be unpacked for inspection. The methodfor unpacking boards is different from the method for unpacking other articles. When you unpack

    boards, you s hould take antistatic mea sures.

    1.1.1 Checking the EquipmentCheck the packing list of the delivered equipment at the site. Before unpacking, the projectsupervisor sh ould check the cargoes against the packing list in the presence of the customer.

    Prerequisitel The equipment must be delivered to the site.l The project supervisor and the customer must be present at the site.

    Procedure

    Step 1 Print the packing list according to the electronic ship order.

    Step 2 Check if the number of packing boxes and the delivery destination correspond to the informationin the packing list.

    Step 3 Check the outer cover of the box. If you identify any of the following cases, stop unpackingimmediately.

    1 General Installation GuidelinesOptiX RTN 605

    Installation Reference

    1-2 Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    Issue 01 (2009-12-30)

  • 8/10/2019 Installation Reference

    17/55

    l The outer package is severely damaged.

    l There is water leakage on the outside packaging box.

    l There is rust or water on the equipment.

    Find the damage causes and report the situation to the local representative office of Huawei.

    CAUTION

    To protect the equipment and to determine the cause of the problems, place the unpackedequipment indoor in a proper storage area and take photos of the site storage environment, andthe rusted or corroded equipment/packing boxes/packaging materials. Keep these photos safelyand store the packing boxes and packaging materials.

    Step 4 Open the crates or cartons .NOTE

    It is recommended that you open another packing box only after you complete the inspection of the equipmentin a box.

    Step 5 Check if the equipment inside the packing box corresponds to the items listed in the packinglist.

    Check for the following items:l Check whether the number and type of articles correspond to the packing list.

    l Check whether the items and their inner packaging are damaged.

    l Check whether the cabinet, NM computer, and other equipment have all the required

    components. Check whether the components are damaged.

    Step 6 Place the items that have been inspected, according to their categories.

    ----End

    Postrequisite

    After the inspection, if no problem is found, both parties should sign the Packing List. Theequipment is then handed over to the customer.

    During the inspection, if some equipment is stated undelivered in the packing list, directly reportthe situation to the order management engineer of the local office of Huawei and sign the PackingList. If there are insufficient or excess supplies of the equipment, or if the equipment is foundto be damaged, both parties should sign the Unpacking Memo and the Packing List. The projectsupervisor has to fill in the Equipment Problem Report and send it to the order managementengineer of the local of fice of Hu awei. T he supervisor should also safely store the equipmentthat has a problem (including the outer and inner packages), for verification.

    1.1.2 Unpacking CratesThis section describes how to unpack crates.

    Prerequisitel The crate must not be wet or severely damaged.

    OptiX RTN 605Installation Reference 1 General Installation Guidelines

    Issue 01 (2009-12-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    1-3

  • 8/10/2019 Installation Reference

    18/55

    l The crate must be moved to the installation site.

    Tools, Equipment, and Materials

    Spanner

    Precautions

    CAUTION

    The crate should be positioned properly and should not be placed in an inverted manner.Otherwise, this can cause fatal damage to the equipment.

    CAUTION

    l When you transport or handle the equipment, spare parts, or components, make sure that theydo not collide with other objects, doors, walls, or shelves.

    l When you transport, handle, and install the equipment, do not handle the uncoated metalsurface of equipment parts or components with sweaty or dirty gloves.

    Procedure

    Step 1 Insert one end of the spanner into the hold of the tongue on the cover. Turn the spanner tostraighten the tongue.

    Figure 1-1 Straightening the tongue

    Spanner Tongue

    Woodenboard

    Steel edge

    Step 2 Refer to Step 1 to straighten all the tongues on the cover.

    Step 3 Remove the cover.

    1 General Installation GuidelinesOptiX RTN 605

    Installation Reference

    1-4 Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    Issue 01 (2009-12-30)

  • 8/10/2019 Installation Reference

    19/55

    Figure 1-2 Removing the cover

    Step 4 Straighten all the tongues that join the wooden boards around the crate, and remove the wooden boards.

    Figure 1-3 Removing the surrounded wooden boards

    OptiX RTN 605Installation Reference 1 General Installation Guidelines

    Issue 01 (2009-12-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    1-5

  • 8/10/2019 Installation Reference

    20/55

  • 8/10/2019 Installation Reference

    21/55

    1.1.4 Unpacking BoardsGenerally, the boards are not delivered separately, and are installed in the chassis before delivery.If they are placed in a carton for shipment, they should be unpacked for inspection. The method

    for unpacking boards is different from the method for unpacking other articles. When you unpack boards, you should take antistatic measures.

    Prerequisite

    The board package must not be damaged.

    Tools, Equipment, and Materials

    ESD gloves

    Precautions

    CAUTION

    l Electronic circuits and components are extremely sensitive to electrostatic discharge. Whenhandling circuit boards, make sure that you wear a securely grounded ESD wrist strap, andonly hold the edge of the boards during operation.

    l If the board has been moved from a cold and dry place to a warm and damp place, wait for a minimum of 30 minutes before unpacking. Otherwise, the moisture that condenses on the

    board surface can damage the components.l The boards are packed in a plastic bag and an ESD bag. Keep the bags properly. They can

    be used later for storing the boards or packing the damaged boards to be returned for repair.l Each ESD-preventive bag contains a small bag of desiccant, which should not be discarded.

    Procedure

    Step 1 Wear an ESD wrist strap.

    Step 2 Open the board box and take out the boards.

    Figure 1-5 Unpacking the boards

    ESD bagCard Card box

    Step 3 Check whether the board is physically damaged.

    OptiX RTN 605Installation Reference 1 General Installation Guidelines

    Issue 01 (2009-12-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    1-7

  • 8/10/2019 Installation Reference

    22/55

    Step 4 If no problem is detected during inspection, place the board back into the box and move the boxto the place specified by the customer.

    ----End

    Postrequisitel If you are going to install the board immediately after unpacking it, place the board on an

    antistatic surface to discharge the static electricity.

    l If you are going to install the board at a later time, pack the board using the original materialsand place them in a cool dry place without direct sunshine or strong electromagneticradiation.

    1.2 Terminating the IF Cable with ConnectorsThe IF cables may be terminated with the type-N connectors or TNC connectors.

    1.2.1 Terminating the Type-N ConnectorsBoth ends of the RG-8U or 1/2-inch IF cable need to be terminated with type-N connectors. AnIF jumper is required to connect the RG-8U or 1/2-inch IF cable to the IF board.

    1.2.2 Terminating the TNC ConnectorsOne end of the 5D IF cable needs to be terminated with a type-N connector and is connected tothe ODU or lightning arrester. The other end of the 5D IF cable needs to be terminated with aTNC connector and is connected directly to the IF cable .

    1.2.1 Terminating the Type-N ConnectorsBoth ends of the RG-8U or 1/2-inch IF cable need to be terminated with type-N connectors. AnIF jumper is required to connect the RG-8U or 1/2-inch IF cable to the IF board.

    Tools, Equipment, and Materialsl Wrench es

    l Electric knife

    l File

    l Installat ion parts and accessories of the type-N connector

    l IF cable

    Precautions

    This procedure is provided only as an example. Always follow the proper instructions packedwith the connector.

    Procedure

    Step 1 Use an electric knife to strip back the 16 mm cable sheath.

    1 General Installation GuidelinesOptiX RTN 605

    Installation Reference

    1-8 Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    Issue 01 (2009-12-30)

  • 8/10/2019 Installation Reference

    23/55

    Figure 1-6 Stripping back the cable sheath and the insulating layer

    CAUTION

    l During the operation, ensure that the core wire of the cable is not damaged.l If the length of the stripped sheath is more than 16 mm, cut the cable wire in Step 4 .

    Step 2 Fit the lock nut and clamp 1 on the cable.

    Figure 1-7 Fitting the lock nut and clamp 1

    Step 3 Fit clamp 2.

    1. Fold back the braided shield to cover clamp 1.

    2. Tidy the braided shield and use clamp 2 to bind the braided shield.

    3. Cut the redundant part of the shielding layer.

    Figure 1-8 Fitting clamp 2

    Step 4 Use the electric knife to strip back the dielectric insulating layer in front of clamp 2.During the operation, the exposed cable wire should be 6 mm long.

    OptiX RTN 605Installation Reference 1 General Installation Guidelines

    Issue 01 (2009-12-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    1-9

  • 8/10/2019 Installation Reference

    24/55

    Figure 1-9 Stripping back the insulating layer

    NOTE

    If the length of the stripped sheath in Step 1 is more than 16 mm, cut the cable wire to expose only a length of 6 mm.

    Step 5 Use a file to taper the edge of the core wire about 0.5 mm to make the top in an arc shape, andclean out the metal filings.

    Step 6 Fit the connector.

    Figure 1-10 Fitting the connector

    Step 7 Connect the connector and the lock nut. Use a wrench to tighten the connection.

    Use a wrench to rotate the lock nut and another wrench to position the body of the connector.The recommended torque is 152 Nm.

    Figure 1-11 Fastening the connector

    Keeping standing

    Rotating to tighten

    ----End

    1 General Installation GuidelinesOptiX RTN 605

    Installation Reference

    1-10 Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    Issue 01 (2009-12-30)

  • 8/10/2019 Installation Reference

    25/55

    Postrequisite

    After making the connectors, use the multimeter to check the cable circuit. Use the cables onlyafter you have ensured that there is no short circuit or open circuit in the cables.

    1.2.2 Terminating the TNC ConnectorsOne end of the 5D IF cable needs to be terminated with a type-N connector and is connected tothe ODU or lightning arrester. The other end of the 5D IF cable needs to be terminated with aTNC connector and is connected directly to the IF cable .

    Tools, Equipment, and Materialsl Wrenches

    l Electric knife

    l Filel Installation parts and accessories of the type-N connector

    l IF cable

    Precautions

    This procedure is provided only as an example. Always follow the proper instructions packedwith the connector.

    Procedure

    Step 1 Use an electric knife to strip back the 16 mm cable sheath.

    Figure 1-12 Stripping back the cable sheath and the insulating layer

    CAUTION

    l During the operation, ensure that the core wire of the cable is not damaged.

    l If the length of the stripped sheath is more than 16 mm, cut the cable wire in Step 4 .

    Step 2 Fit the lock nut and clamp 1 on the cable.

    OptiX RTN 605Installation Reference 1 General Installation Guidelines

    Issue 01 (2009-12-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    1-11

  • 8/10/2019 Installation Reference

    26/55

    Figure 1-13 Fitting the lock nut and clamp 1

    Step 3 Fit clamp 2.1. Fold back the braided shield to cover clamp 1.

    2. Tidy the braided shield and use clamp 2 to bind the braided shield.

    3. Cut the redundant part of the shielding layer.

    Figure 1-14 Fitting clamp 2

    Step 4 Use the electric knife to strip back the dielectric insulating layer in front of clamp 2.During the operation, the exposed cable wire should be 6 mm long.

    Figure 1-15 Stripping back the insulating layer

    NOTE

    If the length of the stripped sheath in Step 1 is more than 16 mm, cut the cable wire to expose only a length of 6 mm.

    Step 5 Use a file to taper the edge of the core wire about 0.5 mm to make the top in an arc shape, andclean out the metal filings.

    Step 6 Fit the connector.

    1 General Installation GuidelinesOptiX RTN 605

    Installation Reference

    1-12 Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    Issue 01 (2009-12-30)

  • 8/10/2019 Installation Reference

    27/55

  • 8/10/2019 Installation Reference

    28/55

    Prerequisite

    The connectors for the IF cables must be made.

    Tools, Equipment, and Materialsl Multimeter

    l Short-circuiting line

    Procedure

    Step 1 At one end of the IF cable, use a short-circuiting line to short-circuit the internal and externalconductors, and then use a multimeter to test the resistance. The resistance should be 0 ohms.

    Figure 1-18 Testing cable connectivity

    short-circuiting

    Step 2 Remove the short-circuiting line, and use a multimeter to test the resistance between the internalconductor and the external conductor.

    The resistance should be infinite.

    Step 3 Connect one end of the IF cable to the ODU, and connect the other end to the IDU.

    ----End

    1.4 Waterproofing Outdoor ConnectorsAll the outdoor IF cable connectors and the grounding clips must be completely waterproofed.

    Prerequisite

    The outdoor connector or the grounding clip must be installed.

    Tools, Equipment, and Materialsl Waterproof insulation tape

    1 General Installation GuidelinesOptiX RTN 605

    Installation Reference

    1-14 Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    Issue 01 (2009-12-30)

  • 8/10/2019 Installation Reference

    29/55

    Figure 1-19 Waterproof insulation tape

    l PVC tape

    Figure 1-20 PVC tape

    Precautions

    To facilitate the removal of tapes, first wrap a layer of PVC tape and then wrap the waterproof insulation tape over the first layer.

    Procedure

    Step 1 Clean the connector or the grounding clip.

    Step 2 Optional: Wrap a layer of PVC tape on the IF connector or the grounding clip.

    1. Stick one end of the tape to the IF cable 2 cm away from the connector or the groundingclip, The sticky side should face inwards.

    2. Stretch the tape until it is 3/4 as wide as its original size. Stretch the tape in this manner

    when performing the following steps.

    OptiX RTN 605Installation Reference 1 General Installation Guidelines

    Issue 01 (2009-12-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    1-15

  • 8/10/2019 Installation Reference

    30/55

    3. Wrap the cable spirally towards the connector or the grounding clip at a point that is 2 cmaway from the connector or the grounding clip to the other side. Make sure that theoverlapping area of the adjacent tape layers is 1/2 of the stretched width.

    Figure 1-21 Wrapping a layer of PVC tape

    Step 3 Wrap the waterproof insulation tape.

    If a layer of PVC tape has been applied, ensure that the waterproof insulation tape is wrappedover the PVC tape.

    1. Uncoil the waterproof insulation tape.

    2. Stick one end of the tape to the IF cable 2 to 5 cm away from the connector or the groundingclip. The sticky side should face inwards.

    3. Stretch the tape until it is 3/4-1/2 as wide as its original size. Stretch the tape in this manner when performing the following steps.

    4. Wrap the cable spirally towards the connector or the grounding clip at a point that is 2 to5 cm away from the connector or the grounding clip. Make sure that the overlapping areaof the adjacent tape layers is 1/2 of the stretched width.

    5. When the tape reaches a point that is 2 to 5 cm away from the connector or the groundingclip on the other side, reverse the wrapping direction so that the tape reaches the starting point.

    6. When the tape reaches the starting point, reverse the wrapping direction so that the tapereaches the other ending point, there are three layers of waterproof insulation tape.

    1 General Installation GuidelinesOptiX RTN 605

    Installation Reference

    1-16 Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    Issue 01 (2009-12-30)

  • 8/10/2019 Installation Reference

    31/55

    Figure 1-22 Wrapping three layers of waterproof insulation tape

    Step 4 After wrapping, squeeze the tape until it sticks to the cable. This ensures that there is no air between the layers of tape.

    Step 5 Similarly, wrap three layers of PVC tape over the waterproof insulation tape.During the wrapping, maintain the stretched length such that the width of the PVC tape is 3/4of the original size.

    Figure 1-23 Wrapping three layers of PVC tape over the waterproof insulation tape

    OptiX RTN 605Installation Reference 1 General Installation Guidelines

    Issue 01 (2009-12-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    1-17

  • 8/10/2019 Installation Reference

    32/55

    Step 6 After waterproof processing, use the outdoor bundling strap to bind the PVC tape tightly at the positions 1 cm away from the wrapping edges at both ends, to prevent aging and falling off of the PVC tape.

    ----End

    Result

    Figure 1-24 Appearance of waterproofed outdoor connector

    1 General Installation GuidelinesOptiX RTN 605

    Installation Reference

    1-18 Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    Issue 01 (2009-12-30)

  • 8/10/2019 Installation Reference

    33/55

    2 Regulations on Routing and Bundling Cables

    About This Chapter

    Routing and bundling cables according to the specified regulations is an important factor toensure reliable transmission of signals.

    2.1 Regulations for Routing and Bundling the Indoor CableIn actual situations, you must strictly observe the regulations when routing and bundling theindoor cable.

    2.2 Routing and Bundling the IF CableIn actual situ ations, you must strictly observe the regulations when routing and bundling the IFcable.

    OptiX RTN 605Installation Reference 2 Regulations on Routing and Bundling Cables

    Issue 01 (2009-12-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    2-1

  • 8/10/2019 Installation Reference

    34/55

    2.1 Regulations for Routing and Bundling the Indoor CableIn actual situations, you must strictly observe the regulations when routing and bundling theindoor cable.

    2.1.1 CablingWhen routing cables, ensure that signals are transmitted reliably, and also ensure that futuremaintenance is easy.

    2.1.2 BundlingCables must be tightly bundled. The bundled cables should be neatly arranged.

    2.1.3 Bundling Fiber JumpersUse a special binding strap to bundle fiber jumpers.

    2.1.1 Cabling When routing cables, ensure that signals are transmitted reliably, and also ensure that futuremaintenance is easy.

    The cabling requirements are as follows:

    l Signal cables should be routed separately from power cables, fiber jumpers, and jumpers.

    l The specifications and cross-sectional area of the cable, and the route and position for thecabling should be designed beforehand. All the cables should be arranged neatly.

    l Cable turns should be smooth. The bending radius of cable turns should be larger than 60mm, and the bending radius of fiber turns should be larger than 40 mm.

    l There should be no damage to the insulating layer of the conducting wire.l Cables that are routed along the wiring frame must be bundled.

    They should be bundled closely with appropriate tightness. The spacing between cable tiesshould be even.

    l Cables in troughs do not need to be bundled. They should be placed neatly and in a straightmanner without any crossover. The cables should not protrude from the trough. The cablesshould be bundled with cable ties at the inlets, outlets, and at the turns of the trough.

    l IDU cables should be routed along the left and the right to facilitate operations, and shouldnot cover the board indicators.

    In other words, the cables of the boards in the left slots should be routed to the left of thecabinet and those in the right slots should be routed to the right of the cabinet.

    l Leave enough slack when connecting cables to the IDU to facilitate insertion and removalof the boards and the fan box. If the IDU is equipped with a fan box, the cables of the IDUhave enough slack so that they can be routed away from the front of the fan box.

    2.1.2 Bundling Cables must be tightly bundled. The bundled cables should be neatly arranged.

    The bundling requirements are as follows:

    l Do not b ind the power cable with other types of cables.

    l The cab les should be bundled neatly.

    2 Regulations on Routing and Bundling CablesOptiX RTN 605

    Installation Reference

    2-2 Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    Issue 01 (2009-12-30)

  • 8/10/2019 Installation Reference

    35/55

    l Use cable ties of different specifications according to actual circumstances.

    l Do not connect two or more cable ties and use them as one to bundle cables in case thetightness is reduced.

    l After the cable ties are fixed, the extra part of the cable ties should be trimmed such thatno burrs exist.

    l The spacing between the cable ties should be even and should be three or four times thediameter of the bundle.

    l When making turns for bundled cables, ensure that the bending radius is as large as possibleso that the cable cores do not break.

    Figure 2-1 Bundling cables

    1

    2

    3

    3 4

    4

    3-4

    R

    1. No cable tie at turns 2. Cable tie 3. Burr 4. Trimmed : Correct bundling : Wrong bundling

    2.1.3 Bundling Fiber JumpersUse a special binding strap to bundle fiber jumpers.

    Observe the following requirements when bundling fiber jumpers:

    l Arrange fiber jumpers tidily into a bundle before bundling them.

    OptiX RTN 605Installation Reference 2 Regulations on Routing and Bundling Cables

    Issue 01 (2009-12-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    2-3

  • 8/10/2019 Installation Reference

    36/55

    l Ensure that the mat side, and not the hook side, of the binding strap is in contact with thefiber jumpers.

    l Bundle fiber jumpers with appropriate tightness. Do not bind them too tightly.

    l The spacing between two binding straps should not exceed 40 cm.

    l Do not bundle too many fiber jumpers together.

    In the case of the 2 mm fiber jumpers, a maximum of 100 pieces can be bound together. Inthe case of the 3 mm fiber jumpers, a maximum of 60 pieces can be bound together. If thereare a large number of fiber jumpers, bind them into several bundles.

    2.2 Routing and Bundling the IF CableIn actual situations, you must strictly observe the regulations when routing and bundling the IFcable.

    The routing requirements are as follows:l The IF cable should be routed from top downwards and should be bound at the time of

    routing.l The specifications and cross-sectional area of the cable, and the route and position for the

    cabling should be decided beforehand. The cable should be arranged neatly without anyoverlapping or crossover.

    l The IF cable should be curved for waterproof consideration under the ODU and beforeentering the IDU room.

    l The bending radius of the IF cable should be larger than 30 cm.

    The bundling requirements are as follows:

    l The IF cable routed along the wiring frame must be bundled. Whether to use binding tapesor cable clamps to fix the IF cable depends on the actual situations. It should be closely

    bundled with appropriate tightness. The spacing between the cable ties for outdoor use (thecable ties for outdoor use are in black) should be even.

    l The IF cable should be bound by using the cable ties for outdoor use every one meter.

    l The cable ties for outdoor use should face the same direction. There should be a slack of 3mm to 5 mm before cutting the cable ties.

    2 Regulations on Routing and Bundling CablesOptiX RTN 605

    Installation Reference

    2-4 Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    Issue 01 (2009-12-30)

  • 8/10/2019 Installation Reference

    37/55

    3 Engineering Labels for Indoor CablesAbout This Chapter

    Engineering labels for indoor cables should be filled and affixed based on this specification,unless the customer requires otherwise.

    3.1 Introducti on to LabelsThere are two types of engineering labels, labels for power cables and labels for signal cables.

    3.2 Preparing LabelsThe content o f the labels can be printed or writte n on the labels. It is recommended that the labels

    be printed for the sake of better readability and a proper layout.

    3.3 Affixing LabelsThe procedur e for affixing a labe l to a power cable is different from that for affixing a label toa signal cable .

    3.4 Common Engineering LabelsCommon eng ineering labels inclu de labels for the cabinet power cable, the optical fiber, thetrunk cable, t he IF jumper, the network cable, and the external alarm cable. For other unspecifiedlabels, handle them according to the on site requirements.

    OptiX RTN 605Installation Reference 3 Engineering Labels for Indoor Cables

    Issue 01 (2009-12-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    3-1

  • 8/10/2019 Installation Reference

    38/55

    3.1 Introduction to LabelsThere are two types of engineering labels, labels for power cables and labels for signal cables.

    3.1.1 Labels for Power CablesThe label for power cables is rectangular with round corners.

    3.1.2 Labels for Signal CablesThe label for signal cables is L-shaped with fixed dimensions.

    3.1.1 Labels for Power CablesThe label for power cables is rectangular with round corners.

    There is a dividing line on the label. In the upper left corner, there is a mark "TO:". The mark is used to identify the opposite end of the cable to which the label is affixed.

    The label is affixed to the identification plate on the cable tie that binds the cable.

    Figure 3-1 Label for power cables

    1.5

    0.6100

    26.2

    12.2

    0.6

    10

    11TO:

    25

    R1.0

    Cable tie

    Label

    Dividing line on the label

    Unit: mm

    3 Engineering Labels for Indoor CablesOptiX RTN 605

    Installation Reference

    3-2 Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    Issue 01 (2009-12-30)

  • 8/10/2019 Installation Reference

    39/55

    3.1.2 Labels for Signal CablesThe label for signal cables is L-shaped with fixed dimensions.

    The short dividing lines on the label specify the position of a cable more clearly. For example,there is one dotted line that helps in folding the label. In the lower right corner, there is a mark "TO:". The mark is used to identify the opposite end of the cable to which the label is affixed.

    Figure 3-2 Label for signal cables

    T O :

    84.07.5

    7.0

    5.5

    5.5

    11.0

    11.0

    37.0

    7.5

    7.0

    5.55.5

    1.5

    0.6

    1.0

    2.0

    Dividing line

    Dotted line

    10.0

    Dividing line

    Dotted line

    Unit: mm

    3.2 Preparing LabelsThe content of the labels can be printed or written on the labels. It is recommended that the labels

    be printed for the sake of better readability and a proper layout.

    3.2.1 Printing LabelsThe labels can be printed by using a laser printer and a label template.

    3.2.2 Writing LabelsUse the black oiliness markers that are delivered together with the equipment to write on thelabels.

    3.2.1 Printing LabelsThe labels can be printed by using a laser printer and a label template.

    OptiX RTN 605Installation Reference 3 Engineering Labels for Indoor Cables

    Issue 01 (2009-12-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    3-3

  • 8/10/2019 Installation Reference

    40/55

    The requirements are as follows:

    l Use a laser printer.

    l Use the label template.

    To download a template, do as follows: Download the template from http://support.huawei.com. The directory of the template

    is En gineering Service > Engineering Quality > Quality Standard and Template. Requ est for the template from the Huawei lo cal office.

    l When you modify the information on the template, do not modify the settings of centeredcharacters, direction, fonts, and others.

    l When there are too many characters to be filled in, zoom out the characters.

    l Before printing a label, try printing an ordinary blank paper (both sides should be blank) by covering it on the page of the label paper.

    l Feed in the labels one after another by hand. The label paper is made of a material differentfrom that of the ordinary blank paper.

    l If the warning "One or more margins are set outside the printable area of the page" appears before printing, click Ignore to continue the printing.

    3.2.2 Writing LabelsUse the black oiliness markers that are delivered together with the equipment to write on thelabels.

    The requirements for writing on the labels are as follows:

    l Use a black oiliness marker to write on a label.

    l The handwritten font should be similar to the standard typeface, so that it is clear and legible.

    l Write characters in proper size depending on the number of digits and letters.

    l The writing direction of the label is as shown in the following figure.

    Figure 3-3 Writing direction of the label

    T O :

    1 A01 2 A 06

    1 B 0 2 1 5 0 5

    3.3 Affixing LabelsThe procedure for affixing a label to a power cable is different from that for affixing a label toa signal cable.

    3.3.1 Affixing a Label to a Power Cable

    The label for the power cable is affixed to the identification plate on the cable tie that binds the power cable.

    3 Engineering Labels for Indoor CablesOptiX RTN 605

    Installation Reference

    3-4 Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    Issue 01 (2009-12-30)

  • 8/10/2019 Installation Reference

    41/55

    3.3.2 Affixing a Label to a Signal CableThe label for the signal cable is directly affixed to the signal cable.

    3.3.1 Affixing a Label to a Power CableThe label for the power cable is affixed to the identification plate on the cable tie that binds the

    power cable.

    Prerequisitel The power cable must be bundled.

    l The label content must be filled in.

    Procedure

    Step 1 Remove a label from the paper. Affix it to the rectangular flute on only one side of theidentification plate on the cable tie.

    Step 2 Determine the position of the cable tie.Generally, bind the cable tie 2 cm away from the connector. To avoid bending the cable or making the installation of other cables inconvenient, you can bind the cable tie to other places.

    Step 3 Use the cable tie to bind the cable.After the bundling, all the identification plates should face right or upwards and all the labelsshould face outwards.

    ----End

    Result

    Figure 3-4 Appearance of labels affixed on power cables

    TO:

    TO:

    B03 -48V2 B03 -48V2

    1-The identification plate is on topof the cable in horizontal cabling

    2-The identification plate is at the rightside of the cable in vertical cabling

    Cable

    Cable

    OptiX RTN 605Installation Reference 3 Engineering Labels for Indoor Cables

    Issue 01 (2009-12-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    3-5

  • 8/10/2019 Installation Reference

    42/55

  • 8/10/2019 Installation Reference

    43/55

    Result

    Figure 3-6 Appearance of labels affixed on signal cables

    T O :

    1

    A 0 1

    2

    A

    0 6

    TO:

    1 A01 2 A 06

    3.4 Common Eng ineering LabelsCommon eng ineering labels include labels for the cabinet power cable, the optical fiber, thetrunk cable, t he IF jumper, the network cable, and the external alarm cable. For other unspecifiedlabels, handle them according to the onsite requirements.

    3.4.1 Enginee ring Labels for Cabinet Power CablesThese labels are affixed to the power cable, the grounding cable (BGND), and the protectiongrounding ca ble (PGND) of a cabinet. Affix the labels to both en ds of the cable.

    3.4.2 Engineering Labels for Optical FibersThere are two types of labels for optical fibers. One type is used for the optical fiber that connectstwo pieces of equipment. The other type is used for the optical fiber that connects the equipmentand the ODF. The labels of both types of optical fibers should be affixed to both ends of a fiber.

    3.4.3 Engineering Labels for Trunk CablesThere are two types of labels for trunk cables. One type is used for the trunk cable that connectstwo pieces of equipment. The other type is used for the trunk cable that connects the equipment

    and the DDF. The labels of both types should be affixed to both ends of a trunk cable.3.4.4 Engineering Labels for IF JumpersThese labels are affixed to the IF jumpers that are connected to the IF boards. Affix the labelsto both ends of the jumpers.

    3.4.5 Engineering Labels for Network CablesThese labels are affixed to the Ethernet cables that are connected to the network ports of boards.Affix the labels to both ends of the cables.

    3.4.6 Engineering Labels for External Alarm CablesThese labels are affixed to the external alarm cable that connects the power distribution cabinet(the first cabinet of each row used for power distribution). Affix the label to the end of the cable

    on the side of the power distribution cabinet.

    OptiX RTN 605Installation Reference 3 Engineering Labels for Indoor Cables

    Issue 01 (2009-12-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    3-7

  • 8/10/2019 Installation Reference

    44/55

  • 8/10/2019 Installation Reference

    45/55

    3.4.2 Engineering Labels for Optical FibersThere are two types of labels for optical fibers. One type is used for the optical fiber that connectstwo pieces of equipment. The other type is used for the optical fiber that connects the equipment

    and the ODF. The labels of both types of optical fibers should be affixed to both ends of a fiber.

    Label Content

    Table 3-2 Information on the label affixed to the fiber that connects two pieces of equipment

    Content Parameter Meaning

    MN-B-C-D-R/T MN: cabinet number M: row number of a cabinet, from A to Z

    N: column number of a cabinet, from 01to 99

    B: subrack number Numbered from bottom upwards withtwo digits

    C: physical slot number Numbered with two digits

    D: optical port number Numbered from top downwards andfrom left to right with two digits

    R: optical receiving port

    T: optical transmitting port

    MN-B-C-D-R/T MN: cabinet number The abbreviations have the same

    meanings as given earlier. When thelocal equipment and the oppositeequipment are not in the same equipmentroom, MN can be the name of theequipment room.

    B: subrack number

    C: physical slot number

    D: optical port number

    R: optical receiving port

    T: optical transmitting port

    Table 3-3 Information on the label affixed to the fiber that connects the equipment and the ODF

    Content Parameter Meaning

    MN-B-C-D-R/T MN: cabinet number M: row number of a cabinet, from A to Z

    N: column number of a cabinet, from 01to 99

    B: subrack number Numbered from bottom upwards withtwo digits

    C: physical slot number Numbered with two digits

    D: optical port number Numbered from top downwards andfrom left to right with two digits

    OptiX RTN 605Installation Reference 3 Engineering Labels for Indoor Cables

    Issue 01 (2009-12-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    3-9

  • 8/10/2019 Installation Reference

    46/55

  • 8/10/2019 Installation Reference

    47/55

    3.4.3 Engineering Labels for Trunk CablesThere are two types of labels for trunk cables. One type is used for the trunk cable that connectstwo pieces of equipment. The other type is used for the trunk cable that connects the equipment

    and the DDF. The labels of both types should be affixed to both ends of a trunk cable.

    Label Content

    Table 3-4 Information on the label affixed to the trunk cable that connects two pieces of equipment

    Content Parameter Meaning

    MN-B-C-D-R/T

    MN: cabinet number M: row number of a cabinet, from A to Z

    N: column number of a cabinet, from 01 to 99

    B: subrack number Numbered from bottom upwards with two digits

    C: physical slot number Numbered with two digits

    D: cable number Numbered from top downwards and from left toright with two digits

    R: receiving port

    T: transmitting port

    MN-B-C-D-R/T

    MN: cabinet number The abbreviations have the same meaning asgiven earlier. When the local equipment and theopposite equipment are not in the same equipmentroom, MN can be the name of the equipmentroom.

    B: subrack number

    C: physical slot number

    D: cable number

    R: receiving port

    T: transmitting port

    Table 3-5 Information on the label affixed to the trunk cable that connects the equipment andthe DDF

    Content Parameter Meaning

    MN-B-C-D-R/T

    MN: cabinet number M: row number of a cabinet, from A to Z

    N: column number of a cabinet, from 01 to 99

    B: subrack number Numbered from bottom upwards with two digits

    C: physical slot number Numbered with two digits

    D: cable number Numbered from top downwards and from left toright with two digits

    OptiX RTN 605Installation Reference 3 Engineering Labels for Indoor Cables

    Issue 01 (2009-12-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    3-11

  • 8/10/2019 Installation Reference

    48/55

    Content Parameter Meaning

    R: receiving port

    T: transmitting port

    -

    DDF-MN-B-C-D/R/T

    MN: row number andcolumn number of the DDF

    M: row number of the DDF, from A to Z

    N: column number of the DDF, from 01 to 99

    B: row number of theterminal

    Numbered with two digits

    C: column number of theterminal

    -

    D: direction A or B

    R: receiving port

    T: transmitting port

    A: indicating that the DDF terminals areconnected to the optical transmission equipment

    B: indicating that the DDF terminals areconnected to the switching equipment

    Example

    Figure 3-10 Example of the label on a trunk cable that connects two pieces of equipment

    T O :

    G01 01 05 12 T

    D 0 2 0 1 0 1 0 1 R

    "G01-01-05-12-T" indicates that the local end of the trunk cable is connected to the transmittingterminal of trunk cable 12 in slot 05 of subrack 01 in the cabinet in row G and column 01 in theequipment room.

    "D02-01-01-01-R" indicates that the opposite end of the trunk cable is connected to the receivingterminal of trunk cable 01 in slot 01 of subrack 01 in the cabinet in row D and column 02 in theequipment room.

    Figure 3-11 Example of the label on a trunk cable that connects the equipment and the DDF

    T O :

    A01 03 01 01 R

    D D F G 0 1 0 1 0 1 A R

    "A01-03-01-01-R" indicates that the local end of the trunk cable is connected to the receiving

    terminal of trunk cable 01 in slot 01 of subrack 03 of the cabinet in row A and column 01 in theequipment room.

    3 Engineering Labels for Indoor CablesOptiX RTN 605

    Installation Reference

    3-12 Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    Issue 01 (2009-12-30)

  • 8/10/2019 Installation Reference

    49/55

  • 8/10/2019 Installation Reference

    50/55

    3.4.5 Engineering Labels for Network CablesThese labels are affixed to the Ethernet cables that are connected to the network ports of boards.Affix the labels to both ends of the cables.

    Label Content

    Table 3-7 Information on the label affixed to the network cable

    Content Parameter Meaning

    MN-B-C-D-R/T MN: cabinet number M: row number of a cabinet,from A to Z

    N: column number of acabinet, from 01 to 99

    B: subrack number Numbered from bottomupwards with two digits

    C: physical slot number Numbered with two digits

    D: network port number Numbered from topdownwards and from left toright

    MN-Z MN: cabinet number M: row number of a cabinet,from A to Z

    N: column number of acabinet, from 01 to 99

    Z: position number Depending on the onsiteinformation, provide thevalid position number of theequipment. If the cable isconnected to a router in acabinet, specify the cabinetnumber, the subrack number,and the network port number.If the cable is connected tothe network managementcomputer, specify the

    position of the computer.

    Example

    Figure 3-13 Example of the label on a network cable

    A01 03 10 05

    0 3 1 2 B 0 2 T O :

    3 Engineering Labels for Indoor CablesOptiX RTN 605

    Installation Reference

    3-14 Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    Issue 01 (2009-12-30)

  • 8/10/2019 Installation Reference

    51/55

    "A01-03-10-05" indicates that the local end of the network cable is connected to network port05 in slot 10 of subrack 03 in the cabinet in row A and column 01 in the equipment room.

    "B02-03-12" indicates that the opposite end of the network cable is connected to network port12 in subrack 03 in the cabinet in row B and column 02 in the equipment room. It is unnecessaryto specify the slot number.

    3.4.6 Engineering Labels for External Alarm CablesThese labels are affixed to the external alarm cable that connects the power distribution cabinet(the first cabinet of each row used for power distribution). Affix the label to the end of the cableon the side of the power distribution cabinet.

    Label Content

    Table 3-8 Information on the label affixed to the external alarm cable

    Content Parameter Meaning

    MN MN: cabinet number M: row number of a cabinet,from A to Z

    N: column number of acabinet, from 01 to 99

    Example

    Figure 3-14 Example of the label on an external alarm cable

    T O : A 0 1

    "A01" indicates that the alarm cable connects the power distribution cabinet and the cabinet inrow A and column 01 in the equipment room.

    OptiX RTN 605Installation Reference 3 Engineering Labels for Indoor Cables

    Issue 01 (2009-12-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    3-15

  • 8/10/2019 Installation Reference

    52/55

  • 8/10/2019 Installation Reference

    53/55

    4 Engineering Labels for Outdoor IF CablesAbout This Chapter

    Engineering labels for outdoor IF cables should be bound according to this specification, unlessthe customer requires otherwise.

    4.1 Engineering Labels for IF CablesThe engineering labels for IF cables are plastic tags and are bound by using cable ties. The labelcontent has been printed before delivery. Hence, there is no need to write or print the content onsite.

    4.2 Binding the Labels for IF CablesThe labels for IF cables should be bound with the IF cables by using the cable ties for outdoor use.

    OptiX RTN 605Installation Reference 4 Engineering Labels for Outdoor IF Cables

    Issue 01 (2009-12-30) Huawei Proprietary and ConfidentialCopyright Huawei Technologies Co., Ltd.

    4-1

  • 8/10/2019 Installation Reference

    54/55

  • 8/10/2019 Installation Reference

    55/55

    4.2 Binding the Labels for IF CablesThe labels for IF cables should be bound with the IF cables by using the cable ties for outdoor use.

    Prerequisitel The connectors for the IF cable must be prepared.

    Procedure

    Step 1 Determine the place where the label for the IF cable is to be bound.Generally, bind the label 20 cm away from the connector of the IF cable.

    Step 2 Use outdoor cable ties to bind the label with the IF cable.The label surface with letters should face outwards. All the cable ties should face the samedirection.

    ----End

    Result

    Figure 4-2 Appearance of the label after it is bound with the IF cable

    OptiX RTN 605Installation Reference 4 Engineering Labels for Outdoor IF Cables