Injector De-cabling Project
Project meeting # 7, 15.01.2016
S. EVRARD, EN-MEF, on behalf of the Injector De-cabling Project Team
Contents
• Planning• Booster follow-up• Booster: orphan cables• Booster: tests already carried out• SPS follow-up• Tour de table
Project time line RUN 2015 YETS 2015 RUN 2016 EYETS 2016 RUN 2017 YETS 2017 RUN 2018 LS2BOOSTER
Cable identification IDENTIFICATION IDENTIFICATION
Cable labelling LABELLING
Cable disconnection DISCONNECTION
Cable removal REMOVAL REMOVAL LIU cabling campaign
SPS
Cable identification IDENTIFICATION IDENTIFICATION
Cable labelling LABELLING
Cable disconnection DISCONNECTION
Cable removal BA5 REMOVAL BA5 REMOVAL BA3 REMOVAL
PS, TT2 & Linacs
Cable identification IDENTIFICATION IDENTIFICATION
Cable labelling LABELLING
Cable disconnection DISCONNECTION
Cable removal REMOVAL REMOVAL
Booster: YETS schedule
• 1 week for false-floor survey
• 1 week less for identification labelling and disconnection
• Work in 2 shifts (6.00-14.00 for de-cabling project & 14.00-22.00 for EN-EL activities)
• Intervention stage 1 in week 50,51/2015 : 07/12 18/12
• Intervention stage 2 in week 3,4/2016 : 18/01 29/01
x x x x x x o o o o o
o o o o o o o o o o o o o o o x x x x x x o o o o o o o o o o o o o
Technical Stop (weeks) From To rp rp rp rp rp rp rp rp rp rp x x x x x x x x x xPSB o o o o o o o o o o o o o o o x x x x x x
Consign/Deconsign machine elements 30.11.2015 01.02.2016Stop/Start water EN-CV 30.11.2015 29.01.2016Machine access 01.12.2015 29.01.2016Cable identification and disconnection 01.12.2105 18.12.2015Check of separate systems 04.01.2016 15.01.2016Disconnection for communication system 18.01.2016 29.01.2016Check communication of system 01.02.2016 12.02.2016
PROTONS
Q4
53
YETS 2015-201613 weeks beam to beam LHC
InjectorsLHC
DECEMBERNOVEMBER
2015
JANUARY49 50 51
Ions Run
2016Q1
MARCHFEBRUARY5 6 9 10 112 3 4 7 81524745 46 48
HW Test Cold CO & BCHW Tests
Cable identification and disconnection Check of separate systems
Disconnection for communication
system Check communicationsystem
Decabling HW testIMPACT YETS 2015-2016 IMPACT HARDWARE YETS 2015-2016
Protons LowIntensity
IMPACT YETS 2015-2016RP cooldownPROTONS
Protons to PSB02/03/2015
Beams to PS08/03/2015
SPS YETS 2015-2016
1 week False-floor survey7 weeks of access into the SPS: week 2 to 7: January 11th to Feb. 26th
No access allowed viaThe lift in ECA5!
NO Access into LSS5
NO Access into LSS5
ECA5
Access possible Access possible
SPS YETS 2015-2016 : access restriction
Booster Follow-up
• BE-BI Jean’s slides• BE-CO Emmanuel’s slides• TE-MPE• BE-ICS (ex-GS-ASE)• EN-EA (ex EN-MEF)• IT-CS
TE-MPE• from MPE side we have completed the identification, scotching and de-
connection of all cables mentioned in the list assigned to us. You will find in Sharepoint the updated information along with a comment in the ‘Comment’ field which I hope is self-explicit.
• As you will see we had issues with 2 cable groups to find the 2nd cable end (110818-110838 as the racks were removed and the cable must have been partially retracted/removed already and for cables 2700071-2700073 for which the information is not available from the initial listings.
• For us this normally completes the exercise for the PSB, please let us know if
there is anything else you would need from our side. As far as we can judge our operational systems are still working properly, final confirmation can however come only once the machines are started again (as many of the input channels are inactive during the shutdown).
BE-ICS (Former GS-ASE)EDMS 1518315 BOOSTER situation au 14.01.2016
Code couleurGesmar Cables a demanteler par EN/EL Repéré BE/ICS Non Repéré BE/ICSGesmar Cables a identifierGesmar Cables à demanteler par BE/ICSPapier Cablothèque papier. Identifié et à démanteler EN/ELPapier Cablothèque papier. Non Identifié
No. Cable No TYPE RE-FONCTION DU CABLE ORIGINE DESTINATION LON- Statut *actuel CABLE SEAU OUVRAGPosition Fonction.ELEMENT POSV POSH CONNECT CONVN OUVRAGPosition Fonction.ELEMENT POSV POSH CONNECT CONVN GUEUR Actuel
G 132061 0 NE48 YA.B BOOSTER PORTE D31360 PORTE D31 48BPFB 354 Y(MJ9-CCRBORNIER A2R-001 B 200G 132061 0 NE48 YA.B BOOSTER PORTE D31354 YMNR-AD2BORNIER MNR B 354 Y(MJ9-CCRBORNIER A2R-001 B 40 65G 132062 0 PJ2SB YA.P 48V D31/BOOSTER354 RACCORD B 354 YMNR-AP2AP2/3-4 MNR B 60 60G 132063 0 PH3SJ YA.P 220V / D31-BOOSTER354 RACCORD B 354 Y(MNR43 DEP 7 R-007 3PFBPM 60 61G 101661 0 CC75 YA.B VIDEO PORTE D.31354 Y(MR324-CCR 1B50PMA 360 YSIDA.360.D31 1B50PMA 300 300G 132061 0 NE48 YA.B BOOSTER PORTE D31360 PORTE D31 48BPFB 354 Y(MJ9-CCRBORNIER A2R-001 B 200G 132231 0 NE26 YA.B BOOSTER PORTE D38360 PORTE D38 28BPFB 354 Y(MJ9-CCRBORNIER B1R-001 B 200G 132231 0 NE26 YA.B BOOSTER PORTE D38354 YMNR-XD2BORNIER MNR B 354 Y(MJ9-CCRBORNIER B1R-001 B 40 62G 132232 0 PH2SB YA.P 48V D38/BOOSTER354 RACCORD B 354 YMNR-AP2AP2/5-6 MNR B 60 64G 132236 0 NE26 YA.B BOOSTER PORTE D39360 PORTE D39 28BPFB 354 Y(MJ9-CCRBORNIER B1R-001 B 200G 132236 0 NE26 YA.B BOOSTER PORTE D39354 YMNR-XD3BORNIER MNR B 354 Y(MJ9-CCRBORNIER B1R-001 B 40 62G 132237 0 PH2SB YA.P 48V D39/BOOSTER354 RACCORD B 354 YMNR-AP2AP2/7-8 MNR B 60 64G 132403 0 NE10 YA.B ACCES BOOSTER 354 YMNR-EI6 BORNIER MNR B 354 CJC01-CCRJONCTION 12BPFB 40 37G 132403 0 NE10 YA.B ACCES BOOSTER 354 CJC01-CCRJONCTION 12BPMB 350 CJ01-PSR JONCTIONLIG BTP JM1 340 340G 132403 0 NE10 YA.B ACCES BOOSTER 350 CJ01-PSR JONCTIONLIG BTP B 360 BTP.STP10BEAM STOPLIG TRAN 8BPFB 60 26G 132471 0 NE10 YA.B ACCES BOOSTER 354 YMNR-EI5 B8FE MNR B 360 BI.STP-FA JONCTIONLIG TRAN JM1 40 40G 132471 0 NE10 YA.B ACCES BOOSTER 354 YMNR-EI5 JONCTIONMNR J 360 BI.STP-FA BEAM STOPLIG TRAN 8BPFB 340 340G 132472 0 NE10 YA.B ACCES BOOSTER 354 YMNR-EI4 B8FE MNR B 360 BI.STP-SWJONCTIONLIG TRAN JM1 40 40G 132472 0 NE10 YA.B ACCES BOOSTER 354 YMNR-EI4 JONCTIONMNR J 360 BI.STP-SWBEAM STOPLIG TRAN 8BPFB 340 340G 2708199 NE12 EZ.B SIGNAUX SAFETY MPS BOOSTER361 EZD1.07 B 354 MNR BORNIER LE34P 132064 NE2 INTERCOM 354 SIJ4 Bornier 361 Porte D31 Booster BurndyP 132065 NE2 INTERCOM 354 SIJ4 Bornier 361 Porte D31 Booster BurndyP 132066 NE4 INTERCOM 354 SIJ4 Bornier 361 Porte D31 Booster Burndy
Public AddressG 2000101 NE48 CGPP LIAISON CCR-BOOSTER354 C(MR301-CCR 361 Y(BCER350G 2000102 PJ2SB CGPP HP ANNEAU BOOSTER361 Y(BCER350 360 HP.MPBO*PSBG 2000103 NE4 CGPP STATION D'ECOUTE361 Y(BCER350 360 ST-MPBO*PSBG 2000105 PJ2SB CGPP HP TT2 361 Y(BCER350 TT2 HP.TT2*TT2G 2000106 NE4 CGPP STATION D'ECOUTE361 Y(BCER350 TT2 ST-TT2*TT2G 2000107 PJ2SB CGPP HP TT70 361 Y(BCER350 TT70 HP.TT70*T70G 2000108 NE4 CGPP STATION D'ECOUTE361 Y(BCER350 TT70 ST-TT70*T70
2713725 2x0.15 SIGNAL SIRENE 361 Y(BCER350 361 R(LC-BCER
IT-CS and EN-EA
• IT-CS: • 25 câbles téléphoniques ont été identifiés, étiquetés et déconnectés et sont prêts pour enlèvement
• Difficulté de repérage car non liés à la machine ou aux racks DEC ad hoc + visite
• EN-EA: • 96 câbles interphones: la déconnexion débute lundi 25.01 pour une semaine. (démontage également de 3 racks + 30 boites de répartition)
Booster quality control: orphan cables1500 “orphan” cables have been identified in the Booster by F. Chapuis during LS1• 800 already in DEC’s + 700 still under investigation
DECs_cables EXCEL Booster_Gesmar_orphan_cables EXCELBooster_old_CABLO_orphan_cables EXCEL
Only 67 (10%) have been identified and treated.
What to do for the rest ?Consider them as obsolete ipso facto if not declared as spare by the equipment groups
Groupe DEC/NEWCâbles trouvés et déconnectés des
deux cotes
Câbles trouvés et déconnectés d'un
seul coteCâble non trouvés
Câbles connectés
Câbles Déjà retirés
Total Tests
IT-CS DEC 24 0 0 0 0 24 Pas nécessaire: démontage installation obsolèteNEW 0 0 0 0 0 0
BE-BI DEC 262 122 40 19 0 443En cours NEW 21 34 8 0 0 63
BE-CO DEC 363 197 308 2 0 870 En coursNEW 0 0 0 0 0 0
BE-RF DEC 53 46 23 0 0 122 ?NEW 25 13 0 0 0 38
EN-MEF DEC 0 0 96 0 0 96 Pas nécessaire: démontage installation obsolèteNEW 0 0 0 0 0 0
EN-STI DEC 22 26 0 0 0 48 OK terminé avec succès NEW 0 8 3 0 0 11
GS-ASE DEC 17 0 14 0 0 14 ?NEW 0 0 0 0 0 0
PH-LBD DEC 15 8 0 0 0 23 Pas nécessaire: démontage installation obsolète NEW 0 0 0 0 0 0
TE-ABT DEC 104 23 50 34 43 254 ?NEW 0 0 0 0 0 0
TE-EPC DEC 37 30 7 0 9 83 ?NEW 26 2 0 0 0 28
TE-MPEDEC 17 8 2 0 20 47 OK terminé avec succès
Nécessite retour faisceau NEW 0 0 0 0 0 0
TE-MSC DEC 113 12 0 0 0 125 ?NEW 0 0 0 0 0 0
TE-VSC DEC 28 72 0 0 0 100 ?NEW 2 2 1 0 0 5
1129 603 552 55 72 2370
Booster: tests already carried out
THANKS FOR YOUR ATTENTION !