Infrastructure, Regulators and Utilities in the World of RTOs and Electricity Markets

29
Infrastructure, Regulators and Utilities in the World of RTOs and Electricity Markets Steve Gaw, Commissioner, Missouri Public Service Commission President of the Organization of MISO States Springfield, Illinois November 30, 2006

description

Infrastructure, Regulators and Utilities in the World of RTOs and Electricity Markets. Steve Gaw, Commissioner, Missouri Public Service Commission President of the Organization of MISO States Springfield, Illinois November 30, 2006. - PowerPoint PPT Presentation

Transcript of Infrastructure, Regulators and Utilities in the World of RTOs and Electricity Markets

Page 1: Infrastructure, Regulators and Utilities in the World of RTOs and Electricity Markets

Infrastructure, Regulators and Utilities in the World of RTOs and Electricity Markets

Infrastructure, Regulators and Utilities in the World of RTOs and Electricity Markets

Steve Gaw, Commissioner,

Missouri Public Service CommissionPresident of the Organization of MISO States

Springfield, Illinois

November 30, 2006

Steve Gaw, Commissioner,

Missouri Public Service CommissionPresident of the Organization of MISO States

Springfield, Illinois

November 30, 2006

Page 2: Infrastructure, Regulators and Utilities in the World of RTOs and Electricity Markets

2

RTOs In The United States

Page 3: Infrastructure, Regulators and Utilities in the World of RTOs and Electricity Markets

3

Markets Operated by Regional Transmission Organizations (RTOs)

Markets Operated by Regional Transmission Organizations (RTOs)

A. Advertised Benefits

1. Transparency of Wholesale Electricity Prices

2. Transparency of Congestion Costs

3. Greater Independence in Transmission Planning

4. Greater efficiency in use of transmission grid and in dispatch of generation

5. Increased incentives to build needed infrastructure

6. Benefits to participants that exceed costs

A. Advertised Benefits

1. Transparency of Wholesale Electricity Prices

2. Transparency of Congestion Costs

3. Greater Independence in Transmission Planning

4. Greater efficiency in use of transmission grid and in dispatch of generation

5. Increased incentives to build needed infrastructure

6. Benefits to participants that exceed costs

Page 4: Infrastructure, Regulators and Utilities in the World of RTOs and Electricity Markets

4

Are the RTOs Delivering Progress as Promised?

Are the RTOs Delivering Progress as Promised?

Transparency….Transparency….

Page 5: Infrastructure, Regulators and Utilities in the World of RTOs and Electricity Markets

5

Have the RTOs Delivered?Transparency of Prices and CostsHave the RTOs Delivered?Transparency of Prices and Costs

Page 6: Infrastructure, Regulators and Utilities in the World of RTOs and Electricity Markets

6

Progress as Promised? Progress as Promised?

Page 7: Infrastructure, Regulators and Utilities in the World of RTOs and Electricity Markets

7

Progress as Promised?Progress as Promised?

WEST

CENTRAL

EAST

EastFE, NIPS, METC, ITC

CentralHE, CIN, SIGE, LGEE,

IPL, DEVI, IPRV, CWLD,AMRN, IP, CILC, CWLP,

SIPC, EEI

WestALTW, ALTE, WE, WPS, MGE, UPPC, XEL, MDU,MP, SMMPA, GRE, OTP

WEST

CENTRAL

EAST

EastFE, NIPS, METC, ITC

CentralHE, CIN, SIGE, LGEE,

IPL, DEVI, IPRV, CWLD,AMRN, IP, CILC, CWLP,

SIPC, EEI

WestALTW, ALTE, WE, WPS, MGE, UPPC, XEL, MDU,MP, SMMPA, GRE, OTP

Independence in Planning:Midwest Independent System Operators (MISO)Independence in Planning:Midwest Independent System Operators (MISO)

Page 8: Infrastructure, Regulators and Utilities in the World of RTOs and Electricity Markets

8

Progress as Promised?Progress as Promised?

Tensions exist between the particular interests of generator owners and improvements in the overall efficiency of the transmission grid.

An Independent, Regional Transmission Planning Process.

Provides an independent review of both needs and benefits by an entity that is not economically impacted by the transmission upgrade.Includes a stakeholder process that provides input on need and benefits.

Tensions exist between the particular interests of generator owners and improvements in the overall efficiency of the transmission grid.

An Independent, Regional Transmission Planning Process.

Provides an independent review of both needs and benefits by an entity that is not economically impacted by the transmission upgrade.Includes a stakeholder process that provides input on need and benefits.

Page 9: Infrastructure, Regulators and Utilities in the World of RTOs and Electricity Markets

9

Progress as Promised?Progress as Promised?

Efficiency of Dispatch Operation:

• Theoretically RTO Markets should cause the dispatch of most efficient units first.

• Sharing Resources

• The actual efficiencies in MISO compared to the theoretical benefits are currently being studied.

Efficiency of Dispatch Operation:

• Theoretically RTO Markets should cause the dispatch of most efficient units first.

• Sharing Resources

• The actual efficiencies in MISO compared to the theoretical benefits are currently being studied.

Page 10: Infrastructure, Regulators and Utilities in the World of RTOs and Electricity Markets

10

$74 - 109$74 - 109

$39 - 99$39 - 99 $172 - 326$172 - 326 $25$25

$147 - 301$147 - 301

Contingency Reserves Market

Contingency Reserves Market

Regulation Market

Regulation Market

GrossAnnual Benefits

GrossAnnual Benefits

AverageAnnual

Operating Costs*

AverageAnnual

Operating Costs*

NetAnnual Benefits

NetAnnual Benefits

$59-118

Footprint-wide Contingency

Reserve

Footprint-wide Contingency

Reserve

Estimated Annual Benefits:Estimated Annual Benefits:

NPV**NPV**

1,299%1,299% 583% 583%IRRIRR

$2,456$2,456$990$990

HighHighLowLow

Source: Midwest ISO April 3, 2006, FERC Compliance Filing* Recovery through existing Midwest ISO Schedule 17; includes amortization of startup costs calculated using $65 million estimated project cost; amortized over seven years at 5% ** NPV calculated over 10 years using 5% discount rate

Source: Midwest ISO April 3, 2006, FERC Compliance Filing* Recovery through existing Midwest ISO Schedule 17; includes amortization of startup costs calculated using $65 million estimated project cost; amortized over seven years at 5% ** NPV calculated over 10 years using 5% discount rate

$ in Millions$ in MillionsBenefits – Implementationof CRS, ASM

Benefits – Implementationof CRS, ASM

Consolidation of Control Areas and Creation of Ancillary Services MarketsConsolidation of Control Areas and Creation of Ancillary Services Markets

Page 11: Infrastructure, Regulators and Utilities in the World of RTOs and Electricity Markets

11

Progress as Promised?Progress as Promised?

• Incentives for new construction

– Financial signals are clearer now than prior to markets.

• Are Pricing Signals alone sufficient?

– Adoption of a Fair Cost Allocation Formula is critical to new transmission investment.

• Incentives for new construction

– Financial signals are clearer now than prior to markets.

• Are Pricing Signals alone sufficient?

– Adoption of a Fair Cost Allocation Formula is critical to new transmission investment.

Page 12: Infrastructure, Regulators and Utilities in the World of RTOs and Electricity Markets

12

Progress as Promised?Progress as Promised?

FERC Order 888 Policy established the entity requesting new or changed transmission service must pay for all upgrades required to grant that service (“Requestor Pays”)

A regional cost allocation methodology is needed that recognizes:

Transmission upgrades cannot be sized to exactly fit the request.Transmission customers other than the Requestor benefit from transmission upgrades needed to meet the request.

FERC Order 888 Policy established the entity requesting new or changed transmission service must pay for all upgrades required to grant that service (“Requestor Pays”)

A regional cost allocation methodology is needed that recognizes:

Transmission upgrades cannot be sized to exactly fit the request.Transmission customers other than the Requestor benefit from transmission upgrades needed to meet the request.

Page 13: Infrastructure, Regulators and Utilities in the World of RTOs and Electricity Markets

13

Cost Allocation Methodology Must Be:Cost Allocation Methodology Must Be:

• Fair

• Acceptable to transmission owners and investors

• Acceptable to federal and state regulators

• Create sufficient assurances that investment will be returned.

• Fair

• Acceptable to transmission owners and investors

• Acceptable to federal and state regulators

• Create sufficient assurances that investment will be returned.

Page 14: Infrastructure, Regulators and Utilities in the World of RTOs and Electricity Markets

14

Regional Transmission Planned by MISORegional Transmission Planned by MISOMISO Transmission Expansion Plans have:

identified over $4.3 billion of transmission projects,more than 390 transmission projects primarily for reliability purposes,approximately 5,123 miles of transmission line upgrades are projected through 2009 (4.6% of the approximately 112,000 miles of line existing throughout the MISO area),over $400 million of these projects were completed by the end of 2004, and for 2006, MISO has identified approximately 80 transmission projects. The top ten of those projects will cost approximately $135 million.

MISO Transmission Plans are steadily evolving and the third regional plan is due December 2006.

MISO Transmission Expansion Plans have:identified over $4.3 billion of transmission projects,more than 390 transmission projects primarily for reliability purposes,approximately 5,123 miles of transmission line upgrades are projected through 2009 (4.6% of the approximately 112,000 miles of line existing throughout the MISO area),over $400 million of these projects were completed by the end of 2004, and for 2006, MISO has identified approximately 80 transmission projects. The top ten of those projects will cost approximately $135 million.

MISO Transmission Plans are steadily evolving and the third regional plan is due December 2006.

Page 15: Infrastructure, Regulators and Utilities in the World of RTOs and Electricity Markets

15

Increasing Transmission Investments Observed, but is it Enough?

Planned New Transmission Investments in the Midwest

Increasing Transmission Investments Observed, but is it Enough?

Planned New Transmission Investments in the Midwest

$0

$500

$1,000

$1,500

$2,000

$2,500

$3,000

Mill

ion

s o

f D

olla

rs

2004 2005 2006 2007 2008 2009

MISO Treansmission Expansion Plan 05

Growing Need for Investment in Midwest Transmission

MISO Transmission Expansion Plan 05

MISO Transmission Expansion Plan 05 estimates.MISO Transmission Expansion Plan 05 estimates.

Page 16: Infrastructure, Regulators and Utilities in the World of RTOs and Electricity Markets

16

Transmission InvestmentTransmission Investment

A few weeks ago, in USA Today, an article on the ‘Power crunch’1 illustrated the “transmission lines that we have now are overloading.”2 “If we are to continue to have a strong economy and continue to meet America’s growing demand for electricity, we have got to take proactive measures to ensure our ability to deliver electricity is unimpeded.”3

Why does the Transmission Grid Need to Grow & Change? Reliability

Economic Growth Increase in use of power consuming technology Increasing reliance on market transactions for supply

A few weeks ago, in USA Today, an article on the ‘Power crunch’1 illustrated the “transmission lines that we have now are overloading.”2 “If we are to continue to have a strong economy and continue to meet America’s growing demand for electricity, we have got to take proactive measures to ensure our ability to deliver electricity is unimpeded.”3

Why does the Transmission Grid Need to Grow & Change? Reliability

Economic Growth Increase in use of power consuming technology Increasing reliance on market transactions for supply

11 ‘Power crunch could lead to lots more lines, Nov 10, 2006, Paul Davidson. ‘Power crunch could lead to lots more lines, Nov 10, 2006, Paul Davidson.22 John Smatlak, Dominion Vice President; John Smatlak, Dominion Vice President; 33 Kevin Kolevar, a director for the Energy Dept. Kevin Kolevar, a director for the Energy Dept.

11 ‘Power crunch could lead to lots more lines, Nov 10, 2006, Paul Davidson. ‘Power crunch could lead to lots more lines, Nov 10, 2006, Paul Davidson.22 John Smatlak, Dominion Vice President; John Smatlak, Dominion Vice President; 33 Kevin Kolevar, a director for the Energy Dept. Kevin Kolevar, a director for the Energy Dept.

Page 17: Infrastructure, Regulators and Utilities in the World of RTOs and Electricity Markets

17

Transmission InvestmentTransmission InvestmentDespite the importance of transmission to reliable and efficient

operations of the transmission grid, there has been insufficient investment in Transmission.

The following is a quote from the Notice of Proposed Rulemaking on “Promoting Transmission Investment through Pricing Reform” issued by the Federal Energy Regulatory Commission on November 17, 2005.

“Transmission investment declined in real dollar terms for 23 years, from 1975 to 1998, before increasing again, although investment for the most recent year available, 2003, is still below 1975 levels.[1] Over the same time period, electric load more than doubled, resulting in a significant decrease in transmission capacity relative to load in every North American Electric Reliability Council region.[2] Edison Electric Institute (EEI) estimates that capital spending must increase by 25 percent, from $4 billion annually to $5 billion annually, to assure system reliability and to accommodate wholesale electric markets, and that the 2.5 percent growth rate in transmission mileage since 1999 is insufficient to meet the expected 50 percent growth in consumer demand for electricity over the next two decades.[3]”

[1] EEI Survey of Transmission Investment: Historical and Planned Capital Expenditures (1999-2008) at 3 (2005).[2] Barriers to Transmission Investment, Presentation by Brendan Kirby (U.S. Department of Energy, Oak Ridge National

Laboratory), April 22, 2005 Technical Conference, Transmission Independence and Investment, Docket No. AD05-5-000 (April 22, 2005 Technical Conference).

[3] Energy Policy Act of 2005: Hearings before the House Subcommittee on Energy and Commerce, 109th Congress, First Sess. (2005) (Prepared statement of Thomas R. Kuhn, President of EEI).

Despite the importance of transmission to reliable and efficient operations of the transmission grid, there has been

insufficient investment in Transmission.

The following is a quote from the Notice of Proposed Rulemaking on “Promoting Transmission Investment through Pricing Reform” issued by the Federal Energy Regulatory Commission on November 17, 2005.

“Transmission investment declined in real dollar terms for 23 years, from 1975 to 1998, before increasing again, although investment for the most recent year available, 2003, is still below 1975 levels.[1] Over the same time period, electric load more than doubled, resulting in a significant decrease in transmission capacity relative to load in every North American Electric Reliability Council region.[2] Edison Electric Institute (EEI) estimates that capital spending must increase by 25 percent, from $4 billion annually to $5 billion annually, to assure system reliability and to accommodate wholesale electric markets, and that the 2.5 percent growth rate in transmission mileage since 1999 is insufficient to meet the expected 50 percent growth in consumer demand for electricity over the next two decades.[3]”

[1] EEI Survey of Transmission Investment: Historical and Planned Capital Expenditures (1999-2008) at 3 (2005).[2] Barriers to Transmission Investment, Presentation by Brendan Kirby (U.S. Department of Energy, Oak Ridge National

Laboratory), April 22, 2005 Technical Conference, Transmission Independence and Investment, Docket No. AD05-5-000 (April 22, 2005 Technical Conference).

[3] Energy Policy Act of 2005: Hearings before the House Subcommittee on Energy and Commerce, 109th Congress, First Sess. (2005) (Prepared statement of Thomas R. Kuhn, President of EEI).

Page 18: Infrastructure, Regulators and Utilities in the World of RTOs and Electricity Markets

18

Growth in LoadProjected loads show that load will exceed supply anywhere from 2011-2016, depending on how you define the region and whose study you’re looking at [sources: MISO, NERC].

Growth in LoadProjected loads show that load will exceed supply anywhere from 2011-2016, depending on how you define the region and whose study you’re looking at [sources: MISO, NERC].

CONTINUING GROWTH IN LOAD AND GENERATION:CONTINUING GROWTH IN LOAD AND GENERATION:

Page 19: Infrastructure, Regulators and Utilities in the World of RTOs and Electricity Markets

19EIA / Annual Energy Review 2005: Energy PerspectivesEIA / Annual Energy Review 2005: Energy Perspectives

Page 20: Infrastructure, Regulators and Utilities in the World of RTOs and Electricity Markets

20Source: US Department of Energy, Energy Information Administration

Coal

Gas

Nuclear

Renewables Oil

Trends in Electric Power Generation1980 - 2025

Source: US Department of Energy, Energy Information Administration

Coal

Gas

Nuclear

Renewables Oil

Trends in Electric Power Generation1980 - 2025

Importance of Transmission: Improvement and Expansion

Importance of Transmission: Improvement and Expansion

Page 21: Infrastructure, Regulators and Utilities in the World of RTOs and Electricity Markets

21

Page 22: Infrastructure, Regulators and Utilities in the World of RTOs and Electricity Markets

22

Page 23: Infrastructure, Regulators and Utilities in the World of RTOs and Electricity Markets

23

Page 24: Infrastructure, Regulators and Utilities in the World of RTOs and Electricity Markets

24

Transmission InvestmentTransmission Investment

• If the transmission system is challenged to function reliably how can we expect it to function optimally in a market based system?– Achieving the Theoretical Benefit of

Markets Depends on the Deliverability of Lower Cost Generation.

• If the transmission system is challenged to function reliably how can we expect it to function optimally in a market based system?– Achieving the Theoretical Benefit of

Markets Depends on the Deliverability of Lower Cost Generation.

Page 25: Infrastructure, Regulators and Utilities in the World of RTOs and Electricity Markets

25

Challenges to New Generation InfrastructureChallenges to New Generation Infrastructure

• Are market signals sufficient?

• Do capacity markets result in construction of new generation that timely and adequately matches load requirements?

• How should regulators and markets from vertically integrated and retail choice states work together to ensure such new generation is built?

• Are market signals sufficient?

• Do capacity markets result in construction of new generation that timely and adequately matches load requirements?

• How should regulators and markets from vertically integrated and retail choice states work together to ensure such new generation is built?

Page 26: Infrastructure, Regulators and Utilities in the World of RTOs and Electricity Markets

26

Increasing Role of Demand ResponseIncreasing Role of Demand Response

Demand Response and energy efficiencyefforts will have an impact on necessarygeneration and transmission.Demand response and energy efficiency efforts can:

Slow the increase in need for additional generation, and Reduce grid congestion.

Understanding how demand response fits into the equation for Modernization of the grid will be important.

Demand Response and energy efficiencyefforts will have an impact on necessarygeneration and transmission.Demand response and energy efficiency efforts can:

Slow the increase in need for additional generation, and Reduce grid congestion.

Understanding how demand response fits into the equation for Modernization of the grid will be important.

Page 27: Infrastructure, Regulators and Utilities in the World of RTOs and Electricity Markets

27

Increasing Role of Demand Response:Increasing Role of Demand Response:Utility DSM Program ExpendituresUtility DSM Program ExpendituresIncreasing Role of Demand Response:Increasing Role of Demand Response:Utility DSM Program ExpendituresUtility DSM Program Expenditures

0

3000

6000

9000

12000

15000

18000

21000

24000

27000

19891990

19911992

19931994

19951996

19971998

19992000

20012002

2003

Source: Energy Information Administration and EEI. Some utilities were spending money on DSM as early as 1976. National data is not available for expenditures from 1976-1988.

Source: Energy Information Administration and EEI. Some utilities were spending money on DSM as early as 1976. National data is not available for expenditures from 1976-1988.

1989-2003 (Million $)1989-2003 (Million $)1989-2003 (Million $)1989-2003 (Million $)

Page 28: Infrastructure, Regulators and Utilities in the World of RTOs and Electricity Markets

28

Increasing Role of Demand Response: Increasing Role of Demand Response: Energy SavingsEnergy Savings Increasing Role of Demand Response: Increasing Role of Demand Response: Energy SavingsEnergy Savings

0

100000

200000

300000

400000

500000

600000

700000

19891990

19911992

19931994

19951996

19971998

19992000

20012002

2003

Source: Energy Information Administration and EEISource: Energy Information Administration and EEI

Utility DSM ProgramsUtility DSM Programs1989-2003 (Million kWh)1989-2003 (Million kWh)Utility DSM ProgramsUtility DSM Programs

1989-2003 (Million kWh)1989-2003 (Million kWh)

Page 29: Infrastructure, Regulators and Utilities in the World of RTOs and Electricity Markets

Steve Gaw, CommissionerMissouri Public Service Commission andPresident of the Organization of MISO StatesE-mail: [email protected]

Steve Gaw, CommissionerMissouri Public Service Commission andPresident of the Organization of MISO StatesE-mail: [email protected]

THANK YOUTHANK YOU