Industrial Floor Joint

24
FOCUS ON INDUSTRIAL FLOOR JOINTS

Transcript of Industrial Floor Joint

Page 1: Industrial Floor Joint

FOCUS ON

INDUSTRIALFLOOR JOINTS

Page 2: Industrial Floor Joint

OUTLINE OF CONTENT

I. THE IMPORTANCE OF INDUSTRIAL

FLOOR JOINTS

II. FLOOR DESIGN DETERMINES JOINT DESIGN

III. JOINT DESIGN PRINCIPLES

IV. BASIC JOINT TYPES AND DESIGN

V. SLAB SHRINKAGE

VI. PROVIDING FOR SLAB SHRINKAGE

VII. JOINT FILLING

VIII. POST-FILLING

IX. THE FIRST YEAR

X. SUMMARY

Copyright 2005 Metzger/McGuire, Inc. All Rights Reserved by Steve Metzger Metzger/McGuire

M E T Z G E R / M C G U I R E800-223-MM80

www.metzgermcguire.comP.O. BOX 2217 CONCORD, NEW HAMPSHIRE 03302FAX: 603.224.6020 • E-MAIL: [email protected]

Additional copies of this article are available at no charge upon request.

FOCUS ONFOCUS ON

INDUSTRIALINDUSTRIALFLOOR JOINTSFLOOR JOINTS

Page 3: Industrial Floor Joint

I. THE IMPORTANCE OF INDUSTRIAL FLOOR JOINTSThe primary function of an industrialconcrete floor is to act as a work surfacefor the manufacture, storage and/ormovement of raw materials or finishedgoods. It goes without saying that thebest work surface is one that provides asmooth, hard and interruption-free plat-form for the facility operations. Unfor-tunately, concrete floors must havejoints, and joints are interruptions in anotherwise continuous surface. Eachjoint is a potential impact point for hardwheeled traffic.

FORWARDIn a recent survey of facility professionals we asked the participants to identifytheir most “significant” concrete floor problem.

An astounding 92% responded with the answer "deteriorated joints.”

Joint deterioration has been a problem ever since the first hand-pushed cart wasrolled across a concrete floor. It became a noticeable problem when pallet jacksand similar equipment was introduced. Now, with today's large and sophisticatedmaterial handling vehicles so common, joint deterioration is reaching crisis pro-portions, especially in the warehousing and distribution industries. To a largedegree the material handling industry sets the criteria that we in the concretefloor industry must meet.

Here are some actual comments we received back from our survey...

"My wheel replacement costs are double our company average. HQ is on my back even though I tell them I've got the worst floor of all our DC's."

"My vehicles are designed for high speed use, but I can't use them at high speeds because my joints are so badly deteriorated."

"I couldn't get any budget money for floor repairs until a load tipped and the driver got hurt. Now I get $4,600 each year for floor repairs. It's not nearly enough, but it's more than I had."

"I've been pushing for a transfer to our newer DC. I'm tired of having my chances for a promotion limited because our floor is in such lousy shape, and HQ blames our low productivity on my lack of ability.”

The goal of this article is to help you avoid joint deterioration problems in thefuture by gaining a better understanding of joints in industrial floors on groundand the critical design and construction issues involved in providing a floor jointsystem that will prove as durable as the floor itself.

Page 4: Industrial Floor Joint

II. FLOOR DESIGN DETERMINES JOINT DESIGNThere is no such thing as a “standard floordesign.” Every floor, and the joints in thatfloor, must suit the intended facility use.

Typical floor design consideration include;

1. Facility FunctionDistribution centers with constant traf-fic flow have different needs than a manu-facturing plant with less frequent trafficbut using steel wheeled carts. The floorsin so-called discount retail stores (HomeDepot, Sam's Club, etc.) have an aestheticas well as a functional factor to considersince they are also showrooms.

There is no “standard floor design” because eachindustrial floor has a variety of demands placedupon it depending on material handling vehicletypes, load weights, frequency of traffic, etc.

I. THE IMPORTANCE OF INDUSTRIAL FLOOR JOINTSWhen a material handling vehicle runs across an interruption-free floor, it can operate atits designed optimum speed and thus achieve its intended productivity rate. But when afloor has deteriorated joints, several negative effects occur;

1. Vehicle operators slow down asthey approach the joints toavoids jolts.

2. The vehicle wheels get chewedup and must be replaced, re-sulting in vehicle downtime,maintenance, personnel timeand expense, and wheel re-placement costs.

3. When defects are severe, theresults can be lower back dis-tress claims by drivers, thedanger of load tipping, etc.

4. As traffic continues to cross thejoints, the defects grow widerand deeper, and eventually willrequire expensive, time con-suming repairs.

When we in the concrete industry design or construct an industrial floor, we must al-ways be cognizant that joints are part of the floor surface, and that every joint poses apotential long term problem for the facility owner or tenant. We must therefore makesure that every joint will stand up to the operations planned for the facility.

Deteriorated joints create an interruption in the conti-nuity of the floor surface, leading to operational slow-downs and increased vehicle maintenance costs.

Page 5: Industrial Floor Joint

II. FLOOR DESIGN DETERMINES JOINT DESIGN

2. EnvironmentFacilities may be temperature controlled (heat, AC, fans) or reflect outside temper-atures,be refrigerated (coolers, freezers), etc. In each case joints will act differently and requiredifferent design considerations.

3. VehiclesFacility vehicles may have 12" (30 cm) diameter cush-ioned tires or 4" (10 cm) diameter solid wheels with a thincoating. Facilities might use hand-pushed pallet jacks,traditional forklifts or high-bay stacker-pickers. Vehicle+ load weights can go to tens of thousands of pounds.Additionally, some vehicles may require floor flatness cri-teria that exceeds which can be achieved using conven-tional floor placement and finishing methods.

4. OperationsSome facilities operate one shift/day and 5 days/weekwhile others run 24/7. Facilities with more intense sched-ules not only place greater demands on floor and jointdurability, but also have almost no time available for therepair or maintenance of joints.

5. Owner ExpectationsSome owners want a first class floor that will last for years,while others may have a shorter time horizon in mind.Some will pay for a premium floor, while others insist ona bare-bones floor with a budget to match. Some ownersmay want the number of joints held to a minimum, yetothers have no objections to more joints as long as theydon’t deteriorate.

6. Site ConditionsThe condition of the land the floor is placed on can have major design implications. Siteswith swampy conditions or expansive soils may need a different design than floors onmore stable grades.

7. Mix DesignConcrete mix design can vary due to many factors including local practices, local aggre-gate availability, etc. Joint spacing and design must take these factors into account.

When all these factors are considered it is possible one or more of the following floordesign criteria may be most appropriate;

a. Conventional floor; reinforced or non-reinforcedb. Shrinkage compensating concretec. Flat, superflatd. Post-tensioned

Once the floor type has been selected, the jointing system must be tailored to matchboth the floor design and facility function.

High rack lifts place higherdemands on floor joints due totheir smaller, harder wheelsand increased point loads.

Page 6: Industrial Floor Joint

III. JOINT DESIGN PRINCIPLESAlthough we talk about floors as if they were one entity, they are not. When speakingabout floors it is critical that we recognize that each floor is composed of numeroussmaller floor segments, both connected and separated by joints.

A 100,000 sq. ft. (9,290 sq. meters)building with 15'x15' (5mx5m) jointspacing will have approximately 400panel segments. Proper joint designmust provide the means for all thesefloor segments to function in unisonas though they were one floor as traf-fic flows across the floor, while alsoallowing each slab to expand or con-tract independently when necessary.

The guiding objectives in joint design must always be to provide joints that will recreatethe pre-jointing continuity of the floor surface, and do so in a manner that will make thejoints as durable as the floor itself. To achieve these goals joints must have the followingcharacteristics;

1. Joints should be “narrow” Joints should always be as narrow as possible to minimize their overall expo-

sure to hard wheels. A 1/4" (6.5mm) wide joint has twice the exposure to wheelimpact as a 1/8" (3 mm) joint. This width difference can be critical when jointsare subjected to 4" diameter, solid wheel traffic. Early entry saws have allowedfor standard joint widths to be narrower than was possible with wet cut saws.

2. Joints must be “plumb” (vertical) Joints that are not perpendicular to the floor surface plane will have an over-

hang on one side. This overhang can readily be broken off by traffic loads.

3. Joints must have “load-transfer” For all the smaller floor segments to act in unison under load they must be

“connected,” so individual panels do not deflect under load. This load transfer isgenerally accomplished with the use of dowels or through “aggregate interlock,”though aggregate interlock is not normally sufficient as slabs contract and jointsopen wider than originally sawn.

4. Joints must be “protectable” Joints must be created in a way that allows a subsequent joint filler to protect

joint edges from wheel inflicted damage. For a filler to properly protect a joint,the joint needs to have 90˚ vertical walls (i.e. not “tooled”) and certain minimumwidth and depth dimensions may be necessary.

A typical industrial floor is not “one” slab, but rather aseries of slabs both connected and separated by joints.

Page 7: Industrial Floor Joint

IV. BASIC JOINT TYPES AND DESIGNThere are four basic joint types onemight find in industrial concrete floors;

1. Construction Joints

2. Contraction Joints

3. Isolation Joints

4. Expansion Joints

1. Construction JointsFloors are placed in sections called “pours.”The junction where a new pour meets a pre-viously placed pour is called a constructionjoint, or a formed joint. Construction jointsfor most industrial slabs are generally “butt”joints that extend straight down the full slabdepth. “Keyed” joints are seldom used any-more because they add to forming costs whileyielding no substantial benefit. Left-in-placemetal screed keys should never be used.Experience has shown that the cantileveredlip often breaks off under heavy traffic, cre-ating extensive damage.

Future ACI documents will recommend thatconstruction joints be saw cut 1" (25 mm)after the concrete has hardened and a crackdevelops. This saw cut creates a reservoir fora joint filler, reveals any inherent weaknessin the formed joint edge due to lack of densi-fication, and makes all joints look the same.The use of a 1/8” (3 mm) radius edging toolon the first pour creates a guideline for thesaw to follow.

In some cases construction joints are “armored.” Armoring is achieved by the use of asteel bar, a steel angle, or a structural epoxy resin. Armored joints are recommendedwhen vehicles are extremely heavy, or when the joints are expected to widen substan-tially. Typical applications of armored joints include joints in shrinkage compensationconcrete, at the ends of long strip pours (i.e. post-tensioned slabs), at joints betweenadjacent rooms, etc.

Construction joints should be saw cut to 1” deep.

I I

ISOLATIONJOINTS

CONSTRUCTIONJOINTS

CONTRACTIONJOINTS

Page 8: Industrial Floor Joint

There are two basic methods of saw cuttingcontraction joints–the conventional “wetcut,” and the “early entry” dry cut. The wetcut saw can be used only after the slab hashardened sufficiently to support the saw'sweight, perhaps 6-16 hrs. The early entrysaw is generally used within a few hoursafter finishing. Wet cutting must provide acut one-quarter of the slab depth. Earlyentry cuts require less depth because theyinduce the plane of weakness before shrink-age stresses are significant. Joints in steelfiber reinforced floors are usually cut to one-third of slab depth.

The benefits of the early-entry saw systemsare that they reduce the potential for ran-dom slab cracking, and that they leave moreconcrete beneath the cut, thereby increas-ing the chances of obtaining effective ag-gregate interlock. The possible negativeswith early-entry saws are that they cancause micro-fracturing of the edge if theblade is dull, wobbles or if it dislodges ag-gregate instead of cutting through it. Theseproblems are due more often to contractorerror and neglect than with the saws them-selves. Some in the industry use the early-entry saw initially, then re-saw later with aconventional saw. The saw laitance left onthe adjacent surface should be removedbefore it hardens.

3. Isolation JointsIsolation joints are placed where the slabmeets a vertical surface such as a wall. Theirfunction is to separate building components.Isolation joints are also used to separateslabs from column pads.

4. Expansion JointsExpansion joints (EJ's) are rarely found in floors anymore.

Traditional “wet cut” saws require sufficient slabcure to support the saw’s weight.

“Early Entry” saws allow for joint cutting to beperformed within hours of slab placement, reduc-ing the potential of random cracking and allow-ing for a shallower joint depth to induce crackingbelow the joint.

Saw cut contraction (control) joints are designedto control where cracking occurs in the slab.

IV. BASIC JOINT TYPES AND DESIGN (continued)

2. Contraction JointsAlso known as “control joints,” contraction joints are created by saw cutting at intervalsbetween the construction joints. The function of contraction joints is to reduce the po-tential for random cracking within the slab panels caused by the linear shrinkage of thepanel as slab moisture evaporates. The sawn joint creates a weakened plane in theconcrete, inducing the expected shrinkage crack to develop below the cut. In effect, acontraction joint is a guided crack that remains unseen.

Page 9: Industrial Floor Joint

V. SLAB SHRINKAGEAt the heart of all floor design and joint design is the fact that all concrete shrinks. Aconcrete slab is never larger than it is on the day it is placed. From day one forward, thelinear dimension of each slab panel gets shorter as the excess water in the concreteevaporates. Shrinkage results in joints becoming wider, which means greater exposureto hard wheel traffic. It can also result in the loss of connectivity (load-transfer) betweenslab panels, allowing each panel to function independently rather than in unison withadjacent panels.

When designing a floor, a good rule of thumb is to assume that a 20' long (6 m) panel willshrink about 1/8" (3 mm). This means that with 20' joint spacing, each joint that isinitially 1/8" (3 mm) wide will eventually open to 1/4" (6 mm).

A second rule of thumb to remember is the rate of shrinkage. It is generally accepted that30% of the expected shrinkage takes place in the first 30 days after the pour. Another50-60% takes place over the next 11 months, bringing the one year total to 80-90% ofexpected shrinkage. The balance takes years or decades. Since most industrial projectstake less than a year to build, it can be assumed that the floor will still be shrinking afterthe owner takes occupancy. This slow shrinkage rate is the cause of many owner-con-tractor misunderstandings and conflicts.

Portland Cement Association (PCA) Shrinkage Chart

If you were to survey a conventionally poured floor with 20' (6 m) joint spacing 7 daysafter placement, you would likely find that the joints are still at their original width. Ifyou ran a forklift over the slab you would find that all slab panels are working together asone slab due to concrete-to-concrete friction at construction joints, and aggregate inter-lock beneath the saw cut contraction joints. But if you run that same forklift after a 30-60 day slab cure, you would find the joints to be 1/16" to 1/8" (1-3 mm) wider. Youmight also find each panel acting alone. This is because slab shrinkage has caused aloss of connectivity between the panels, and the floor will prove to be unsatisfactory formost industrial operations.

100

80

60

40

20

00 3 6 9 12 15 18 21

AGE, MONTHS*

% O

F U

LTIM

ATE

SH

RIN

KA

GE

2" SLAB

4"

6"

8"

10"

12"

* Drying in Laboratory Air from PCA Dev. Dept. Bulletin 103

Page 10: Industrial Floor Joint

V. SLAB SHRINKAGE (continued)Another adverse result of slab shrinkage is “slab edge curl.” Slabs dry from the top downbecause slab moisture is lost via evaporation into the air. While the top of the slab isdrying and shrinking at a significant rate, the bottom is hardly shrinking. This unevendrying can cause the top of the slab to “curl” up at panel ends, much like what you willsee in a dried up river bed.

Curl can cause the slab endsto lift up off the grade, leav-ing it cantilevered. Whentraffic loads are imposedupon a curled slab end, theslab can deflect, causing thepanel to “rock” as trafficpasses.

Heavy loads can cause theslab end to crack, evenbreak-off. When a panel de-flects, the joint edge of theadjacent panel remainshigh, exposing it to impactby vehicle wheels. The resultis severe edge spalling.

When we design a floor, andfloor joints, we must alwayslook beyond the early stagesand design for what the slabwill look like 3 months, 6months and 12 months af-terward.

Potential Crack

Slab edge curl can occur when the top of the slab drys at a signifi-cantly faster rate than the slab bottom. A curled edge creates animpact point at the joint, and left untreated will likely spall undermaterial handling vehicle traffic (below).

Severe slab edge curl can cause the panel edge to actually lift offthe grade, creating a void beneath the panel edge. Heavy loadscrossing the cantilevered panel edge may cause the panel to crackor completely break off.

Page 11: Industrial Floor Joint

VI. PROVIDING FOR SLAB SHRINKAGEThe effects of slab shrinkage and slab edge curl are directly related to slab thickness andthe designed joint grid spacing and layout. Most grid layouts are related to columnspacing. For example, a conventional 6" thick slab with 40' (12 m) column spacing mayhave the interim contraction joints cut at either mid-point or one-third points. Mid-pointspacing of 20' (6 m) will likely see joints eventually open 100%, 1/8" to 1/4" (3 mm to 6mm). One-third point spacing (13-4"/4 m) will see joints open proportionately less. Ei-ther amount of opening will cause a lack of connectivity between panels and betweenpours. A major problem is that we can't predict whether the shrinkage-related openingwill manifest itself at construction joints only, contraction joints only, or both. We alsocan't be certain that all joints that open willopen equally. The designer must bear thesevariables in mind when designing the floor.

With non-doweled construction joints, load-transfer is lost as soon as joints open. Withcontraction joints, it is generally acceptedthat load-transfer from aggregate interlockstarts to be compromised when the crackbeneath the joint exceeds 0.035 in. (0.9 mm).The only sure way to achieve load-transferat construction joints is through the use ofdowel devices. For contraction joints, effec-tive load-transfer may require dowels, or re-inforcement extended through joints. A re-duction in joint spacing to reduce the amounteach joint opens may suffice, but cannot al-ways be relied upon.

It can safely be said that all joint edges suf-fer curl. It's only when curl is significantenough to interfere with material handlingvehicle operations that it poses a problem.The degree of curl can be minimized in themix design (less water, less cement, largeraggregate, etc.). The effects of curl can beminimized by with tighter joint spacing.Shorter panel spacing reduces the shrink-age stresses across the top of the slab. Dow-els can also help minimize the adverse ef-fects of curl by providing load-transfer frompanel to panel, thus reducing how much thepanels can move vertically.

Deflection

After shrinkage occurs, non-doweled constructionjoints provide no load transfer from one slab panelto the next, which may result in slab panels de-flecting, leaving uneven elevations at the joint.

Adequate loadtransfer may beachieved at con-traction joints ifjoint spacing isreduced to keepthe shrinkagecrack below thesaw cut at0.035” (0.9 mm)or less in width,but the effective-ness can vary.

In theory, all joint edges likely suffer from somedegree of curl. Whether the curl is significant ornot is determined by whether it interferes withthe material handling operations and leads tojoint edge deterioration.

Page 12: Industrial Floor Joint

VI. PROVIDING FOR SLAB SHRINKAGE (continued)The three most common types of dowel systemsare the round (smooth) dowels, the square (smooth)dowels, and the “plate” dowel. One of these sys-tems should always be used at construction jointswhen heavy loads and/or frequent traffic is ex-pected. With all three types, one side must be al-lowed to slide smoothly to allow for joint movement.This can be achieved by greasing one half of thedowel, or proving a sleeve that isolates the dowelfrom the concrete.

The size and spacing of dowels should be deter-mined by the designer, based on expected loads,etc. It is critical that dowels be set at the properdepth, and at a 90 degree angle from the joint.Dowels placed too low will not provide adequateload-transfer. Dowels placed too high, or at otherthan a 90 degree angle, will result in slab damageas the slab moves laterally or vertically. The bestlocation for dowels is at mid-depth of the slab.

The “plate” dowel offers load-transfer capabilitiescomparable to the round and square dowels, whileeliminating their potential for horizontal restraint.Such restraint can occur when one panel is shrink-ing at a different rate than the adjacent panel dueto an age difference.

Contraction joints may also require load-transferdevices, especially when loads are very heavy orjoints are widely spaced.

When round orsquare dowels areused at contractionjoints, placementdirectly under thesubsequent joint iscritical.

In some cases a designer may use “tie bars” in-stead of smooth dowels. Tie bars are “deformed”steel bars that ensure contraction joints will openlittle, if at all. The negative side of using tie bars isthat all of the accumulated shrinkage can take placeat construction joints, or panels can suffer ran-dom cracking.

Round (Smooth) Dowels

Square (Smooth) Dowels

Plate Dowel

It’s critical that dowels be set at the properdepth and at a 90˚ angle from the joint toavoid slab damage.

Page 13: Industrial Floor Joint

VI. PROVIDING FOR SLAB SHRINKAGE (continued)Some designers or owners may prefer to have the fewest amount of joints possible. Theirobjectives may be to reduce future joint maintenance, avoid objectionable curl or achievehigher flatness readings required for some sophisticated material handling vehicles.

The most common means of reducing jointsinclude heavy reinforcing, steel fiber rein-forcing, using shrinkage-compensating con-crete and post-tensioning. With each of thesethe trade-off often is greater opening at con-struction joints. Such joints should be “ar-mored” with steel angles or steel bars. Thebar is preferable because greater densifica-tion of the concrete at the joint is possible.

Armoring joint edges with a structural epoxy nosing is another option, although thesejoints are more expensive to create. They may also prove less durable since they aretotally reliant upon the epoxy-to-concrete bond.

Joints in freezer and cooler room floors bear special attention. All joints open due tonormal concrete shrinkage, but joints in freezers and coolers open even wider due tothermal shrinkage of the slab. It is not uncommon in a freezer to see 1/8" (3mm) widesaw cuts open to 3/8" (10mm) or more. This additional width is a significant problemwhen vehicles have small diameter wheels.

Joint spacing and layout are a critical element in minimizing the adverse effects createdby shrinkage. Panels should always be kept as square as possible. Rectangular panelstend to develop random cracks about halfway in their long dimension due to enequalshrinkage stresses. Additionally, joints at the ends of the panel’s long dimension willopen wider than those at the end of the panel’s shorter dimension.

Construction joints tend to haveweaker edges than contractionjoints due to less concrete densifi-cation. This condition can be mini-mized by running the trowel up tothe formed edge instead of trowel-ing by hand. The best practice isto create a jointing layout wherethe construction joints are exposedto minimal traffic. For example,provide a joint layout where con-struction joints are located withinthe racking system.

Proper curing adds strength to thejoint edges. When wet curing agood practice is to temporarily filljoints with wet sand.

BAR ANGLE

Concrete underangle is lesscompacted.

ARMORED JOINTS

RA

CK

ING

RA

CK

ING

Construction Joints

Contraction(Control) Joints

Careful attention should be paid to the layout of the jointswithin a facility floor plan. Construction joints are the mostvulnerable to deterioration and should be placed within rack-ing as often as possible to minimize exposure to traffic.

Page 14: Industrial Floor Joint

VI. PROVIDING FOR SLAB SHRINKAGE (continued) Here are some of the most common causes of joint problems for owners, not necessarily in order of frequency or severity;

1. Saw cuts made too early or too late 2. Early-entry cuts made with worn “skid plates” or blades 3. Joints spaced too widely 4. Lack of dowels (no load-transfer) 5. Dowels improperly positioned 6. Excessive curl due to joint spacing, poor mix design, etc. 7. Rocking slabs due to curl and/or lack of load-transfer 8. Inadequate densification at construction joint edges 9. Lack of adequate curing at joint edges10. Failure to armor joints where appropriate11. Joints that open too wide (numerous causes)12. Reliance on aggregate interlock for load-transfer13. Not minimizing number of joints exposed to traffic14. Failure to fill joints15. Improper filling of joints (wrong material, inadequate filler depth, inadequate cleaning of joint before filling, concave filler profile, etc.).

One of our industry's problems is our failure to educate facility owners about floors andfloor joints. We should be telling owners in advance that their floor is still shrinking evenas he moves in, and that his joints are still widening. We need to tell him that his jointswill be narrower in the summer, and wider in the winter due to thermal expansion andcontraction. This means he may have slabs that “rock” in the winter but not the sum-mer. And we need to tell him that joint edges will “spall” (deteriorate) unless they areproperly filled and maintained.

Improper filling of joints (in this case inadequate filler depth) is just oneof many common causes of joint problems an owner may face, but it isone of the most easily preventable.

Page 15: Industrial Floor Joint

VII. JOINT FILLINGAs previously stated, the best floor is one that offers a con-tinuous surface upon which operations can run at opti-mum efficiency. Joint filling is the key to achieving thatgoal. The primary function of joint filling is to restore thesurface continuity we destroyed by creating joints. Jointfilling also protects joint edges from damage caused byhard wheel impact and heavy load pressure.

Note we use the term joint “filling,” not joint “sealing.” The terms “sealing” and “sealant”imply we are trying to prevent something from going into the joint, like moisture or air.With floor joints subject to hard wheel traffic we are “filling” the joint, replacing theconcrete that was removed. For this reason floor joint filling should always be specifiedin the Concrete (03300) Section. A cross-reference in the Caulking & Sealant (07900)Section is wise since most joint filling is performed by sealant contractors. There are nofederal or ASTM specifications for floor joint fillers as there are for sealants. The onlyacceptable use of sealants in an industrial floor is in joints not subject to traffic (isolationjoints at walls, column pads, under racks, etc.).

Joint filling is a “system” consisting of the proper filler, installed at the optimum time,using the proper installation techniques.

There is no “ideal” joint filler. Anideal filler would be one that is softenough to expand as the jointopens due to shrinkage, yet hardenough to support hard wheeledtraffic without deflecting. Giventhese conflicting properties, boththe American Concrete Institute(ACI) and the Portland Cement As-sociation (PCA) guidelines call forfillers to be “semi-rigid.” Semi-rigidfillers are compromise fillers. Theyare stiff enough to support traffic,but have low-range adhesive andtensile strengths so they will sepa-rate adhesively or cohesively whenjoints open. More specifically, ACIand PCA call for the filler hardnessto be a minimum of Shore A80.This is comparable to the hardnessof a hard rubber.

Most filler manufacturers have in-creased their Shore hardness overthe years (to A85-95) in responseto the use of smaller diameter,harder wheels by the material han-dling industry.

Wheel

Good abrasionresistance

Absence ofstructural weldpermits separa-tion if stressoccurs

Full-depth designeliminates possibledislodgment.Seating of filler onbottom of jointsadds to impactand loadedvehicle resistance

Rigidity to protect edges

Resiliency to absorb impact

No primer required

Full-depth pour makesinstallation simple

If movement occurs,separation will prob-ably take place ononly one side of joint

While there is no truly “ideal” industrial floor joint filler,semi-rigid fillers focus on the joint edge protection needs ofa floor through sufficient rigidity to support loads whileavoiding slab restraint through lower adhesive and tensileproperties.

The Concept of a Semi-Rigid Industrial Floor Joint Filler

Page 16: Industrial Floor Joint

VII. JOINT FILLING (continued)The two common types of semi-rigid fillers available are epoxies and polyureas. Both aretwo-component materials, and must be 100% solids (no solvents) to meet ACI and PCAcriteria. They must also be pour-grade to achieve the filling depth recommended. Asidefrom their chemical composition, the biggest difference between epoxies and polyureasis their cure time. Epoxies typically take 4-8 hours to attain an initial set time, whilepolyureas usually have an initial set in one hour or less. A second difference is theirability to cure in cold temperatures. The cure rate of epoxies is slowed by colder tempera-tures, while most polyureas are not as temperature-sensitive. Epoxies should be usedonly in temperatures above 35 degrees F. Many polyureas can be used in sub-zerotemperatures. Always verify acceptable installation and service temperature ranges withthe joint filler manufacturer.

In general, semi-rigid epoxies andpolyureas have comparable adhesive ca-pabilities, lateral (side-to-side) expansioncapabilities, and durability in service.High adhesion strength is not a desirablecharacteristic because it can lead to tear-ing off concrete edges. As to expansion,do not expect epoxies or polyureas to ex-pand more than 5-15% before separat-ing adhesively or cohesively. Don't bemislead by a filler's “elongation” claims.Joints “expand,” not elongate. Polyureastend to be more sensitive to moisture inthe joint. In some cases joint dampnesscan cause polyureas to bubble or foamduring their cure. Epoxies generally arenot moisture sensitive.

The timing of the filler installation is critical. Since joints are continually widening as theslab shrinks, it is advisable to defer the filling as long as possible. By waiting the jointsget continually closer to their eventual final width. ACI and PCA both recommend defer-ring the filling until the slab is 60-90 days old, longer if possible. It is ideal to wait untilthe facility is temperature controlled, since both heat and AC help the slab stabilize indimension.

In the case of coolers and freezers, fillingshould not take place until the room hasreached its ultimate operating tempera-ture, and been stabilized at that tempera-ture. For coolers the recommended pe-riod is 48 hours minimum; longer is bet-ter. For sub-zero freezers, a 14 day wait-ing period is advised.

Elongation vs. Lateral Expansion

Elongation

Lateral Expansion

Often a filler’s elongation property is equated withits ability to open with a joint as shrinkage contrac-tion occurs. But joints expand, they don’t elongate.Don’t be mislead into thinking that a filler’s elon-gation property equates to its lateral exponsion ca-pability. The two are not the same.

The timing of the filler’s installation is critical. Fill-ing joints too early after slab placement (or beforetemperature draw down and stabilization in freezer/cooler rooms) can result in filler adhesion loss andseparation from the joint walls, potentially leavingthe joint edges exposed to impact and deterioration.

Page 17: Industrial Floor Joint

VII. JOINT FILLING (continued)Good joint preparation (cleaning) is vital to adurable filler installation. The filler must bonddirectly to clean, bare concrete if it is to beeffective. The only satisfactory means of clean-ing a joint is to re-saw it, ensuring the bladehits both inner walls in a consistent manner.The sawing must remove all dirt, saw laitanceand any curing or sealer films deposited. It isadvisable to run the blade along one wall, thenreverse directions and clean the other wall.Cleaning should always extend to the full depthof the saw cut, or 2" (50 mm) in constructionjoints if they are not saw cut. The joint clean-ing saw should be a dry-cut type, preferablyvacuum equipped.

Semi-rigid fillers are typically formulated withlow-range adhesive strength to minimize thechances of restraining slab movement duringshrinkage. The intention is to have the fillerseparate adhesively (or internally) as the jointwidens.

To compensate for low adhesion, fillers must be installed fulldepth in saw cuts. By filling full depth the bottom of the cutprovides support for the filler when loads are imposed. Com-pressible backer rod should never be used at the base of sawcut joints because it negates the solid support provided bythe cut bottom. If it is necessary to “choke off” the bottom ofa saw cut to prevent material loss, dry bagged silica sandmay be used in accordance with the filler manufacturer's data.

Bottom-bearing support is an-other reason why ACI and PCArecommend that constructionjoints be saw cut. If constructionjoints are not sawn, and thuslack a supportive filler base, thefiller should be installed at least2" (50 mm) deep. The additionalfiller-to-concrete bond helps holdthe filler in place as loads areimposed.

Joint preparation (cleaning) is critical in en-suring long term filler durability. The use ofdry-cut type, vacuum equipped saws to cleanjoints is the preferred method of preparation.

CONTRACTION JOINT

1/4” MaxSilica Sand

THRU-SLABCONSTRUCTION JOINT

2”

Backer Rodor

Silica Sand

SAW CUTCONSTRUCTION JOINT

1”

Backer Rodor

Silica Sand

Page 18: Industrial Floor Joint

VII. JOINT FILLING (continued)The only correct finished profile for asemi-rigid filler is “flush with the floorsurface.” A flush filler profile facilitatesthe smooth flow of hard wheeled trafficacross the floor without impact. The onlyway to achieve a flush profile with a pour-grade filler is to overfill (crown), then ra-zor-off the overfill after the material hascured into a solid.

Most epoxy manufacturers recommend using a two-pass method of installation, withperhaps 30-90 minutes between passes. This allows the first pass to reveal any gapsbelow that could result in a concave profile. Polyureas are often dispensed in one pass,filling from the bottom-up to avoid air entrapment. Consult each manufacturer's data.Epoxies generally razor off flush. Polyureas tend to have a very slight concaveness afterrazoring. This is due to their rubbery nature, which pulls as the razor cuts through.

If an epoxy cures concave, the recommended cor-rection procedure is to saw cut the filler down 1/2"(13 mm) and refill in a crowned profile. Sincepolyureas cannot be sawn, the only recourse is toapply a “cap bead” after cleaning and/or roughen-ing the surface. Cap beads may prove less durabledue to their tiny mass and limited bond surface.

When epoxies and polyureas are overfilled,they generally leave a stain on the surfacesadjacent to the joints. This stain may be ob-jectionable to the facility owner. When stain-ing is not acceptable, the adjacent surfacesshould be treated with a film that preventsthe filler from contacting the concrete. Thereare proprietary stain preventing productsavailable from some filler manufacturers, orthe surface can be coated with a soap or waxthat is water-soluble for removal after razoring.

Due to their fairly rapid gel and set times, polyureas mustbe installed using a dual-component pump machine. Ep-oxies may be power-dispensed with pumps, or installedusing manual “bulk” caulking guns. Maintaining the cor-rect part A to part B ratio is critical with pump systems.Off-ratio materials may not cure.

FLUSH-NO IMPACT CONCAVE-IMPACT

CONCAVE FILLER REPAIR

1/2”

POLYUREAEPOXY

The use of a stain preventing film can reduceor eliminate slab surface staining from epoxy/polyurea filler overfill. Other stain preventionmethods include applying soap or wax.

Epoxy Stain

No Stain Where Film Was

Stain Preventing Film

Polyureas, due to their fast geltimes, require the use of dual-com-ponent pumps to install. Epoxiescan be dispensed manually throughbulk caulking guns or through adual-component pump as well.

Page 19: Industrial Floor Joint

STEEL ARMORED JOINT TREATMENT

Elastomeric Sealant1/2” Deep Initially

Semi-Rigid Filler2” Deep Later

Minor edge chipping is not unusual on newfloors to be filled. Chips wider than 1/16th”(2mm) should be “squared off” prior to filling.���������1/8” 3/16” 3/16”

Filler installed under an impervious coveringmay extrude or “hump” if slabs expand due toencapsulated moisture.

VII. JOINT FILLING (continued)Steel armored joints may be filled with a semi-rigid, or they may be “sealed” with an elasto-meric (polyurethane, etc.) sealant, depending onthe circumstances. If joints are armored becausethey are expected to open significantly, as withlarge pour segments, a sealant may be used ini-tially. The sealant is often removed and replacedwith a semi-rigid filler once the sealant fails,when the joint width exceeds 3/8" (10 mm), oronce the floor has stabilized in dimension.

If the joints are armored because of anticipated traffic loads and frequency, a semi-rigidshould be used from the start. Joints at the end of long strip pours (post-tensionedslabs, etc.) may exhibit dramatic movement over a long period of time, and multiple fillerinstallations should be expected. Armored joints should always be filled at least 2" (50mm) deep. Abrasion of the bond faces ofthe steel is recommended to give the fillerboth chemical and mechanical adhesion.

It is not unusual for joints to have edge chipsprior to the filler installation. These chips maybe the result of construction traffic, poor saw-ing techniques, etc. Minor edge chips may befilled as part of the filling installation. If thechips are more than 1/16" (2 mm) in width, itmay be wise to “square them off” prior to fillingso the filler flows into them and prevents themfrom further deterioration.

In recent years many filler installations have turned colors, often changing from gray toa yellowish tone. This color change has been traced to the UV rays emitted by variouslighting systems. While aesthetically objectionable, there is no indication that the fillersare adversely affected. Removal of the discolored surface will prove futile since the newlyexposed filler will also discolor.

When filling joints under an imperviouscovering like tile or hi-build coatings, oneshould be concerned about potential “fillerextrusion.” Covered floors typically have avapor retarder beneath the slab. This pre-vents the substantial moisture at the bot-tom of the slab from dissipating. When thefloor covering is applied, the moisture withinthe slab is encapsulated.

As the moisture in the slab equalizes, it is possible for the rising moisture to cause a re-expansion of the upper slab. This re-expansion can “extrude” the filler, causing a “hump”under the tile or coating. This phenomena does not happen on a consistent basis, and itcan happen anywhere regardless of geography or climate. The best means of preventingfiller extrusion is to fill earlier than normal, allowing for separation to occur before thecovering is applied.

Page 20: Industrial Floor Joint

VII. JOINT FILLING (continued)The cost of a “properly” performed semi-rigid filler installation for an ambient tempera-ture project will range from about $1.25 to $2.00 per lineal foot (labor + material). Thiscost will vary depending on joint depth and width, size of the project, work area access,presence of edge chipping, local labor rates, etc. Filling in cooler rooms will run a bithigher, and filling in freezer rooms can be double that for ambient areas due to reducedproductivity. While these costs may appear expensive, bear in mind that the overalllong-term durability of the floor often depends upon the quality of the joint protectionprovided. Also bear in mind that the repair of improperly filled joints can cost $3 to $10per lineal foot, not including the costs to the owner's operational productivity.

Based on findings by our staff, andmany floor experts, as many as 80-90%of all joint filler installations are likelydeficient. These deficiencies can be at-tributed to a number of reasons, themost common being intentional cheat-ing, sloppy workmanship, or the failureto understand the difference between“filling” and “sealing.”

The best way to avoid having deficien-cies is to prevent them. Specificationsshould be tightly drafted and compre-hensive. Bid prices substantially lowerthan those referenced above should bequestioned and realistic numbersshould be carried into the project for thejoint filling contract. Pre-slab meetingsshould be held discussing the joint fillerinstallation specifications and expecta-tions. Having a sample installation per-formed before the start of actual workis also strongly recommended. Fulldepth material filling can be verified bydrilling through the cured filler. If thedrill bit “plunges,” the depth is suspect.

An estimated 80-90% of joint filler installa-tions are performed improperly...

Full joint depth of the filler is easily verified bydrilling through the cured filler.

Page 21: Industrial Floor Joint

VIII. POST-FILLINGIf there is one “given” with concrete floors, it is that almost every joint will exhibit fillerseparation. This is obviously due to the continued shrinkage of concrete after the jointswere filled. The separation may be adhesive or cohesive. Polyureas generally will sepa-rate adhesively, and continually along one side of the joint. Epoxies generally separate ina “leap-frog” manner, with the adhesive separations jumping from side to side. Cohesiveseparation is not unknown for either product, but it is less common than adhesive.While filler separation may not be aesthetically pleasing, it does not in itself render theinstallation unacceptable or deficient.

Acceptability of a sepa-rated filler is generally de-termined by whether itcontinues to protect thejoint edges, and whetherthe smooth flow of vehicletraffic is affected. Thereare no specific industrystandards.

As a rule of thumb, most fillers will protect joint edges if the separation voids do notexceed credit card width, and if they remain held firmly in place. Once separation reachescredit card width, the condition should be regularly monitored. If the voids exceed creditcard width, corrective measures should be considered in order to prevent edge spalling.If the filler becomes “loose,” or if edge spalling starts to develop, corrective measuresshould be undertaken without further delay.

Corrective measures for separation are dif-ferent for semi-rigid epoxies and polyureas.With epoxies you can refill the separationvoids with a thin viscosity filler provided bysome manufacturers, or saw out the top 1/2"(13 mm) of the original filler and refill usingthe same filler. With polyureas you are lim-ited to filling in the separation voids becausethey generally cannot be sawn. When sawn,they either revert back to an uncured oily sub-stance, or shred like cotton candy and bindup the saw. These corrective limitationsshould be considered when specifying theoriginal filler. If either type of filler is loose, itshould be totally removed and replaced afterthe joints are properly cleaned.

Filler Separation

Adhesive

Cohesive

The need for correcting separation dependsupon the degree of separation and the vulner-ability of the joint edges. Separation shownon left is minor and may not warrant correc-tion. Separation on right should be corrected.

Page 22: Industrial Floor Joint

VIII. POST-FILLING (continued)Responsibility for correction of filler separation is frequently a source of conflict on projects.The applicator's defense is that he filled the joint that existed, and should not be heldresponsible for shrinkage of the concrete. The owner's position is that he paid to havethe joints filled and protected, and wants them traffic-ready and durable. Both argu-ments are valid. Project specifications should be clear on responsibility for separationcorrection, and the repair of any edge spalling that occurs due to separation. It shouldnot be part of a contractor's normal one year warranty because separation itself does notconstitute workmanship deficiency.

Some specifications ask thatthe bidder include in his pricea call-back after 6 months tocorrect separations. Otherspecs ask for a unit price “add”for correction. Still othersmake correction the responsi-bility of the facility owner. Allthese options offer negativeand positive aspects since no-body can predict the extent orseverity of correction.

The same conflict can arise when joint fillers become dis-tressed or loose due to “rocking slab” conditions. Rockingslabs are caused by curl. If slab panels deflect underload, the filler will be sheared off at its bond points. Rock-ing slabs can also result in severe joint edge deteriorationas hard wheels hit the adjacent panel edge. Correction ofthe filler at curled joints, and/or spalls, is wasted moneyunless the offending panels are “stabilized.”

The most common means of stabilizingslabs is to fill the voids beneath the pan-els with a grout or other supportive ma-terials. Certain polyurea fillers are nowbeing used for this process due to theirrapid set time, often allowing for the re-turn of full traffic within hours.

If the rocking is minimal, correction can sometimes beachieved by gravity-flowing a thin semi-rigid into the joint.If the penetration is substantial, the cured semi-rigid fillercan create enough friction against the joint walls to reduceor eliminate vertical deflection. Gravity-filling works best insawn contraction joints where it can fill the voids betweenthe irregular surfaces of the crack.

EPOEPOXYXY

OPTION #1OPTION #1

EPOEPOXY OPTION #2XY OPTION #2 POLPOLYUREAYUREA

SOLESOLE

OPTIONOPTION

Use knife or narrow or narrow tool toloosen debris. Blow/vacuum clean. Fill(overfill) voids with polyurea or epoxyand allow to set into solid. Razor offflush.

Saw cut out top 1/2” of epoxy.Blow/vacuum clean. Fill (overfill)channel with same epoxy or polyurea.Allow to set into solid and razor offflush.

Use knife or narrow or narrow tool toloosen debris. Blow/vacuum clean. Fill(overfill) voids with polyurea and allowto set into solid. Razor off flush.

Deflection

Rocking slabs can shear off filler

Filler Separation Correction Methods

Injection Holes Curled Slab Edge

POLYUREA OR GROUT

Semi-RigidFiller

Gravity-flowing thin semi-rigidinto joint can sometimes restoreload-transfer.

Page 23: Industrial Floor Joint

VIII. POST-FILLING (continued)In some cases filler distress and edgespalling may appear to be the result ofnormal slab shrinkage, when in fact theactual cause is improper filler installa-tion. One sign of poor installation iswhen the top of the filler has droppedbelow the floor surface. This usuallyturns out to be a case of the filler notbeing full depth. If the filler has brokenbond from both walls, even though theseparations are very thin, it could indi-cate that the joint was not properlycleaned and the filler was not adheredto the concrete.

It is the author's opinion that the repair of spalled joints should be initiated before theybegin to adversely affect facility operations (cause wheel or vehicle damage, etc.). But it isalso wise to defer the repairs until the slab shrinkage rate has significantly slowed, andthe joint dimension appears stable. The ideal time to perform repairs is in the wintermonths when joints will likely be at their widest point due to thermal considerations.

The repair procedure for spalled joint edges is dictated by the underlying cause of thedamage, and the width of the spall. The edges of saw cut joints can sometimes deterio-rate because of micro-fracturing resulting from a faulty sawing operation. Edges of con-struction joints may be spalling because they lacked adequate densification during trow-eling, were inherently weak due to inadequate curing, or the top surface of the slab isshowing signs of delamination.

For spalls with an overall width of up to 1/2"(13 mm), make a 1/2" to 1" (25 mm) deepsaw cut just beyond the outer point ofspalling, remove the concrete and filler be-tween the cuts, and refill with a semi-rigidfiller. For spalls 1/2" to 1" wide follow therecommendations of the filler manufacturer.Some epoxy manufacturers will recommendfield-modifying their semi-rigids with silicasand to increase its cured hardness. For spallswider than 1" (25 mm) it is usually recom-mended that the edge be rebuilt with a “struc-tural” epoxy grout. A saw cut can be madethrough the cured structural epoxy to recre-ate the joint, which is then filled with a semi-rigid. In some cases the best repair filler maybe a polyurea, whose fast-set properties willallow an earlier return of vehicle traffic. Theirnegative is that they cannot be ground orsanded. Other times an epoxy may be the bestchoice, since they offer longer working times,a more flush repair, and can be ground level.

If joint filler has dropped below the floor surface orwas not flush originally, joint edge spalling may occur.

1/2”-1”

StructuralRepair

Material

Spall 1/2” or Greater

Sand

Divider orSaw Cut

1/2”-1”Semi-Rigid

RepairMaterial

Spall 1/2” or Less

Page 24: Industrial Floor Joint

IX. THE FIRST YEARDuring the owner's first year of occupancy his focus is rightfully on his operations. Hemay not pay attention to joint deterioration that is related to ongoing concrete shrink-age. Even if he is aware of damage, he may not bring it to anyone's attention, assumingthat the contractor's warranty will cover all defects noted at the one year walk-through.This is a prescription for trouble and potential conflict, even legal actions.

By allowing a full year of deterioration to occur, minor edge chipping can evolve intomajor repair costs. It is strongly recommended that the owner and the GC arrange forinterim floor inspections to keep minor problems minor. Unless the project specificationsclearly identify who should bear the cost of post-occupancy corrections, the owner andGC may wish to negotiate the cost responsibility between themselves. The bottom line isthat joints should never be allowed to deteriorate because joints are a key to long-termfloor durability.

X. SUMMARYThe phrase "the devil is in the details" may well have first been coined by a concretecontractor. Despite our best design and construction intentions and practices, slabplacement is still a highly complex system that can be undermined by human error,timing problems, small details, even the weather. When all components are not in per-fect sync, the resulting problems often manifest themselves at the joints. Joints are alsoa “system” within the overall slab system. The highest quality floor finish will soon beforgotten if the joints deteriorate under the owner's material handling vehicle wheels. Itis the author's observation that of all the legal conflicts regarding floors, more than 50%are related to joint deterioration, often involving curl.

We must always remember that joints are an integral and vital part of the floor surface,perhaps even the most vulnerable part of a slab. We forget this at our own risk.

M E T Z G E R / M C G U I R E P.O. Box 2217 Concord, NH 03302Fax: 603-224-6020E-Mail: [email protected]

www.metzgermcguire.com800-223-MM80