Improving project performance presentation
-
Upload
glen-alleman -
Category
Documents
-
view
571 -
download
1
description
Transcript of Improving project performance presentation
![Page 1: Improving project performance presentation](https://reader035.fdocuments.in/reader035/viewer/2022062319/55783a08d8b42a1f5b8b49f6/html5/thumbnails/1.jpg)
February 26 – March 1, 2012 ♦ Phoenix, Arizona
Improving DOE Project Performance Using the DOD Integrated Master Plan 12481
Glen B. Alleman and Michael R. Nosbisch, Project Time & Cost
![Page 2: Improving project performance presentation](https://reader035.fdocuments.in/reader035/viewer/2022062319/55783a08d8b42a1f5b8b49f6/html5/thumbnails/2.jpg)
Five Immutable Principles of Successful Project Management• What does Done look like?• How do we get to Done?• Do we have enough time, money, and
resources to reach Done?• What impediment will we encounter along
the way to Done?• How can we measure progress to Done?
2
![Page 3: Improving project performance presentation](https://reader035.fdocuments.in/reader035/viewer/2022062319/55783a08d8b42a1f5b8b49f6/html5/thumbnails/3.jpg)
Past performance is less than stellar
• GAO–07–336 Major Construction Projects Need a Consistent Approach for Assessing Technology Readiness to Avoid Cost Increases and Delays [4]
• GAO–09–406 Contract and Project Management Concerns at NNSA and Office of EM [5]
• GAO–08–1081 Nuclear Waste: Action Needed to Improve Accountability and Management of DOE’s Major Cleanup Projects [6]
3
![Page 4: Improving project performance presentation](https://reader035.fdocuments.in/reader035/viewer/2022062319/55783a08d8b42a1f5b8b49f6/html5/thumbnails/4.jpg)
The Solution Was In Hand in 2003
• Bob Card’s memo proposed the use of the Integrated Master Plan
• §6.5.1 of this memo called out measures needed to answer the critical question:
How long are we willing to wait before we find out we are late?
4
![Page 5: Improving project performance presentation](https://reader035.fdocuments.in/reader035/viewer/2022062319/55783a08d8b42a1f5b8b49f6/html5/thumbnails/5.jpg)
The Department of Defense Guidance
• Step by step guidance for constructing and using the Integrated Master Plan (IMP)
• DoD applies the IMP to major acquisitions that involve multiple Integrated Product Teams (IPTs) with high risk and high reward outcomes
5
![Page 6: Improving project performance presentation](https://reader035.fdocuments.in/reader035/viewer/2022062319/55783a08d8b42a1f5b8b49f6/html5/thumbnails/6.jpg)
What is an IMP?
• A contractually binding strategy for the successful completion of the program
• The IMP describes the logical progression of the program through accomplishments and their criteria– Measured through increasing maturity of
deliverables as they progress through a disciplined systems engineering process• These deliverables have units of measure
meaningful to the decision makers6
![Page 7: Improving project performance presentation](https://reader035.fdocuments.in/reader035/viewer/2022062319/55783a08d8b42a1f5b8b49f6/html5/thumbnails/7.jpg)
What Does The IMP Tell Us?
• What does DONE look like?– Outcomes rather than effort
• How do we get to DONE?– Tangible evidence of progress toward a
capability or an outcome• What are the units of measure of progress
to DONE?– Technical Performance Measures (TPMs)– Significant Accomplishments
7
![Page 8: Improving project performance presentation](https://reader035.fdocuments.in/reader035/viewer/2022062319/55783a08d8b42a1f5b8b49f6/html5/thumbnails/8.jpg)
What Does the IMP Look Like?
• Program Events– Periodic assessments of the program’s maturity
through reviews or physical demonstration• Initial Production Completed (IPC)
• Significant Accomplishments– Exit Criteria for Program Events
• Version 1 Kit Production and Delivery Completed
• Accomplishment Criteria– Entry/exit criteria needed to produce the Significant
Accomplishments• Version 1 Assembly/Integration/Test Completed
8
![Page 9: Improving project performance presentation](https://reader035.fdocuments.in/reader035/viewer/2022062319/55783a08d8b42a1f5b8b49f6/html5/thumbnails/9.jpg)
Work activities performed to produce the deliverables that fulfill the requirements that enable the capabilities
Specified result, substantiating a Milestone or Event, that indicates maturity or progress for each product or process
Definitive measures substantiating the Accomplishment maturity level. Completion of specific work that ensures closure of a specified Accomplishment
Major program milestones or assessment events that substantiate system maturity (initial, progress, or final). These milestones or assessment events deliver the specific capabilities for the system on planned dates.
IMS
IMPDescribes how thecapabilities will bedelivered andhow thesecapabilities willbe recognized
Supplemental Schedules
Work Packages and Tasks
Criteria
Accomplishment
EventsMilestones
The Topology of the IMP/IMS• The IMP dictates the strategy for success• The IMS describes how to reach this success
9
![Page 10: Improving project performance presentation](https://reader035.fdocuments.in/reader035/viewer/2022062319/55783a08d8b42a1f5b8b49f6/html5/thumbnails/10.jpg)
Program EventsDefine the availabilityof a Capability at a point in time.
AccomplishmentsRepresent requirements that enable Capabilities.
Criteria Represent Work Packages that deliver the Requirements.
Work Package
WorkPackage
Work Package
Work Package
Work Package
Work Package
Work Package
Work package
The structure of a Integrated Master Plan
The outcome of each Work Package is a tangible measureable item, service, or product. Technical Performance Measures (TPM) define the needed Measure of Performance (MoP).
The TPM and MoP are the basis for fulfilling the Measure of Effectiveness (MoE) for the customer.
The Accomplishments define the capabilities needed to fulfill the Mission Needs for the specific point in time of the project. • The maturity of these capabilities increase as the project
progresses from left to right.
![Page 11: Improving project performance presentation](https://reader035.fdocuments.in/reader035/viewer/2022062319/55783a08d8b42a1f5b8b49f6/html5/thumbnails/11.jpg)
The Traceable Flow of Information about increasing maturity
![Page 12: Improving project performance presentation](https://reader035.fdocuments.in/reader035/viewer/2022062319/55783a08d8b42a1f5b8b49f6/html5/thumbnails/12.jpg)
12
![Page 13: Improving project performance presentation](https://reader035.fdocuments.in/reader035/viewer/2022062319/55783a08d8b42a1f5b8b49f6/html5/thumbnails/13.jpg)
Program Events
Statement of Work
CWBS
Significant Accomplishments
Accomplishment Criteria
CDRLs and Deliverables
Tasks Contained in Work Packages
Measures the progress to plan using Physical & Complete at the Accomplishment Criteria (AC) and CWBS level
DefinesAligned Aligned
AlignedAligned
Aligned
Completed SA’s are entry criteria for Program Events
Completed Work Packages are exit criteria for Tasks
Describes increasing product maturity as 0/100 or EVMS SD guidance
Documents the product maturity that is aligned with SOW and CWBS
Work necessary to mature products grouped by CWBS
Work structure aligned to
SOW
Relationships between the IMP Parts
![Page 14: Improving project performance presentation](https://reader035.fdocuments.in/reader035/viewer/2022062319/55783a08d8b42a1f5b8b49f6/html5/thumbnails/14.jpg)
Putting the IMP to Work?
• Start with the WBS, SOW, SOO• Define incremental measures of increasing
maturity of the deliverables– Technical performance measures– Retirement of risk– Alternative strategies through assessment of
increasing maturity
14
![Page 15: Improving project performance presentation](https://reader035.fdocuments.in/reader035/viewer/2022062319/55783a08d8b42a1f5b8b49f6/html5/thumbnails/15.jpg)
The IMP within an IMS
15