Implementation Schedule

1
CADANGAN KERJA-KERJA UBAHSUAI DAN NAIKTARAF 11 UNIT BANGUNAN RUMAH KEDAI 2-TINGKAT, LOT 20126 - LOT 20137, MUKIM 12, DAERAH SEBERANG PERAI UTARA, PULAU PINANG UNTUK DIJADIKAN POLITEKNIK METRrO TASEK GELUGOR IMPLEMENTATION SCHEDULE FOR CIVIL AND STRUCTURE CONSULTANCY SERVICES ITEM ACTIVITIES TIME DURATION (WEEKS) 1 2 3 4 5 6 7 8 9 ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### A PRE-CONSTRUCTION STAGE 1 Schematic Design Phase (Preliminary Stage) a) Analysis Project Brief b) Preparing Preliminary Conceptual Design c) Preparing and Submitting Relevant documentation for client's approval in principal d) Assisting on Preliminary Cost Estimate 2 Design Development Phase a) Developing Engineering Detailed Design (subject to final/confirmed dwg. from Architect) b) Submitting the same c/with necessary Documents to Relevant Authorities (Subject to Status of Building Submission) c) Updating Preliminary Cost Estimate 3 Contract Documentation Phase a) Preparing Tender Drawings With Regards to the work b) Assisting on Preparation of all Necessary Documents for Tender Exercise in Collaboration with Q.S. B CONSTRUCTION STAGE 1 Contract Implementation And Management Phase a) Preparing Contract Drawings b) Preparing Construction Drawings c) Conducting Inspection, Visit and Duties as per Agreement in regards to Construction Matter d) Supervision C POST - CONSTRUCTION STAGE 1 CPC 2 CCC PREPARED BY : FLOATING DUE TO DRAWINGS FINALISATION BY ARCHITECT FLOATING DUE TO SUBMISSION APPROVAL BY ARCHITECT FLOATING DUE TO TENDER, EVALUATION AND AWARDED PROCESS 1 2 3 1 2 3

description

Sample of implementation schedule for C&S works

Transcript of Implementation Schedule

Page 1: Implementation Schedule

CADANGAN KERJA-KERJA UBAHSUAI DAN NAIKTARAF 11 UNIT BANGUNAN RUMAH KEDAI 2-TINGKAT, LOT 20126 - LOT 20137,MUKIM 12, DAERAH SEBERANG PERAI UTARA, PULAU PINANG UNTUK DIJADIKAN POLITEKNIK METRrO TASEK GELUGOR

IMPLEMENTATION SCHEDULE FOR CIVIL AND STRUCTURE CONSULTANCY SERVICES

ITEM ACTIVITIESTIME DURATION (WEEKS)

1 2 3 4 5 6 7 8 9 ###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

A PRE-CONSTRUCTION STAGE

1 Schematic Design Phase(Preliminary Stage)

a) Analysis Project Briefb) Preparing Preliminary Conceptual Designc) Preparing and Submitting Relevant

documentation for client's approvalin principal

d) Assisting on Preliminary Cost Estimate

2 Design Development Phase

a) Developing Engineering Detailed Design(subject to final/confirmed dwg. from Architect)

b) Submitting the same c/with necessaryDocuments to Relevant Authorities(Subject to Status of Building Submission)

c) Updating Preliminary Cost Estimate

3 Contract Documentation Phase

a) Preparing Tender Drawings With Regards to the work

b) Assisting on Preparation of all NecessaryDocuments for Tender Exercise inCollaboration with Q.S.

B CONSTRUCTION STAGE

1 Contract Implementation And Management Phase

a) Preparing Contract Drawingsb) Preparing Construction Drawingsc) Conducting Inspection, Visit and Duties

as per Agreement in regards to Construction Matter

d) Supervision

C POST - CONSTRUCTION STAGE

1 CPC2 CCC

PREPARED BY :

FLOATING DUE TO DRAWINGS FINALISATION BY ARCHITECT

FLOATING DUE TO SUBMISSION APPROVAL BY ARCHITECT

FLOATING DUE TO TENDER, EVALUATION AND AWARDED PROCESS

1

2

3

1

2

3