Impacts of Quality Improvement Incentives on Automation
-
Upload
amany-hamdy -
Category
Documents
-
view
214 -
download
0
Transcript of Impacts of Quality Improvement Incentives on Automation
-
7/29/2019 Impacts of Quality Improvement Incentives on Automation
1/4
C I RC I RC I RC I R E DE DE DE D 20th International Conference on Electricity Distribution Prague, 8-11 June 2009Paper 0141
CIRED2009 Session 5 Paper No 0141
IMPACTS OF QUALITY IMPROVEMENT INCENTIVES ON AUTOMATION
INVESTMENTS IN THE FINNISH NEW REGULATION MODEL
Henry LGLAND Kimmo KAUHANIEMI Tapio HAKOLA Juha RINTAMKIUniversity of Vaasa Finland University of Vaasa Finland ABB - Finland Vaasan Shkverkko - [email protected] [email protected] [email protected]@vaasansahko
verkko.fi
ABSTRACT
During the second regulatory period of 2008-2011
incentives are included into the Finnish regulation model
which allows higher profits for the network owners for
properly allocated network investments leading to lower
operation and interruption costs. In this paper the
economical benefit and payback time of different
automation schemes in two typical Finnish rural medium
voltage (MV) distribution feeders are studied. The
electricity distribution reliability indices, total outage cost,
outage cost saving and payback time for different
automation schemes with different numbers and locations
of automated distribution substations were calculated.
INTRODUCTION
Finnish rural MV distribution feeders are usually protectedby the reclosers of the primary distribution substation only.Centrally located branching points of the feeders may beequipped with remote controlled switches to reduce faultlocating, isolation and restoration times. Using remotecontrolled circuit-breakers instead of switches also allowsfeeders to be sectionalised. Sectionalisation means dividinga feeder into sections in order to isolate faults and minimizethe section of the feeder circuit that is put out of service.Thus the cost of non-delivered energy (NDE) and auto-reclosing (AR) are reduced.
This integration of remote control and protection isachieved by using ABB's compact three-phase vacuum
recloser OVR-3, which is remotely controlled over aGeneral Packet Radio Service (GPRS) connection. Theearth-fault current is derived from the residual current of thethree phase-currents. A remote monitoring and control unittype REC 52_ is used for remote and local control of theline recloser and for protection, fault indication, conditionmonitoring and supervision of the downstream feedersection. According to the performed laboratory tests, anearth-fault protection sensitivity of 1.2 A primary value isachieved, which is of the same order as the sensitivity of thesubstation recloser earth-fault protection.
The new Finnish regulation model
According to the guidelines for the Finnish secondregulatory period of 2008-2011 the quality of the electricitydistribution influences the economy of distribution
companies in two ways. First, the regulation authority sets acompany-specific efficiency improvement obligation, whichconsists of a company-specific and a general improvementtarget. Second, the regulation authority calculates areasonable profit level for each distribution company, thusregulating the price setting of the companies. Thus
incentives are included into the Finnish regulation model,which allow higher profits for the network owners whoallocated network investments properly, leading to loweroperation and interruption costs.
The zone concept
Apart from sectionalisation the zone concept includesseveral other means of increasing the number of protectionzones within the distribution areas of a primary distributionsubstation. By increasing the primary distribution substationdensity with light 110 kV substations the effects ofinterruptions and voltage dips are restricted and themagnitude of the earth-fault currents is reduced. By
increasing the number of protection zones with switchingsubstations and line reclosers auto-reclosings are carried outdeeper in the network and the protection zones diminish.Creating new protection zones by using the 1000 Vdistribution system limits the influence of faults located onthe feeder laterals to the laterals. Enhancing feederautomation with fault location capability reduces faultduration. Increasing remote control of switches indistribution substation results in enhanced fault restoration.In this paper the economic benefit of integrated protectionand remote control is investigated in a case study
CASE STUDY
Two feeders in the distribution area of VaasanShkverkko, a distribution company on the Finnish westcoast, were chosen for the case study. Details of the studiedfeeders and the main calculation parameters are presented inTables 1-4. Electricity distribution reliability indices, totaloutage cost, outage cost saving and payback time fordifferent automation schemes with different number andlocation of automated distribution substations werecalculated. The results were calculated for feeders with noautomation, with current remote control facilities and withcurrent remote control facilities and possible future cost-effective sectionalisation schemes. The benefits of possiblefuture automation schemes were evaluated with regard tothe improvements of the distribution substation reliability
-
7/29/2019 Impacts of Quality Improvement Incentives on Automation
2/4
C I RC I RC I RC I R E DE DE DE D 20th International Conference on Electricity Distribution Prague, 8-11 June 2009Paper 0141
CIRED2009 Session 5 Paper No 0141
indices T-SAIFI and T-SAIDI and the payback time of theautomation investments, of which the most cost-effectivesolution was chosen for the pilot installation.
Table 1. Characteristics of the two feeders studiedcompared to average values for Finnish rural areadistribution feeders. Abbreviations: UGL= undergroundinglevel, DSS= distribution substation, NOP= normally openpoint.
Fee-der
WGWh
PMW
Lkm
UGL%
DSS/km
No.NOPs
F1F2Finland
12.59.4
1.41.1
54.568.631.6
7.86.64.0
0.840.931.0
35
Table 2. Forestry level and outage-related data compared toaverage Finnish rural area feeder values.Frequency 1/100 km, yearFee-
derForestry
HSAR DAR Sust. Interrupt.F1F2Finland
15 %20 %28 %
48.437.537.2
3.02.58.7
8.66.25.4
Table 3. Unit costs of NDE and AR [1].NDE
/ kW / kWhHSAR
/ kWDAR
/ kW1.19 11.9 0.59 1.19
Table 4. Used calculation parameters. Abbreviations:OHL= overhead line, UGC= underground cable, COC=coated overhead cable.
Property Component ValueFault frequency,1/100 km, year
OHLOHL, open fieldOHL, forestUGCCOCDSS
5.372.9410.01.762.00.88
Switching time, h manualremote
1.00.1
Repair time, h OHL, COCUGCDSS
3244
Zone design
Natural locations for line reclosers are downstream of loadcentres, at the interface between underground cables andoverhead lines, in the beginning of branches or laterals andat current remote control sites. According to the principle oflocation the studied feeders were divided in 4-5 zones(Figure 1), and then the characteristics of the zones were
calculated (Table 5). The automation schemes studied arepresented in Table 6.
Feeder F1
R3
R1R2R1C
RC1
RC2
A1429 kW
13 km19 DSS
A2
472 kW8 km16 DSS
B156 kW12 km10 DSS
110/ 20 kV
C377 kW19 km20 DSS
C2
145 kW9 km10 DSS
Feeder F2
B184 kW12 km11 DSS
A2133 kW14 km14 DSS
A1421 kW20 km23 DSS
C1
222 kW14 km16 DSS
RC1
RC3
R1
R3
R2RC4
RC2
110/ 20 kV
Figure 1. Circuit configuration, zone design andcharacteristics of feeders F1 and F2.
Table 5. Characteristics of the zones of the feeders.Length, kmFee-
derZo-ne
Fo-restry%
PkW OHL UGC COC
No.ofDSS
A1 10 428 9.9 3.8 19A2 30 472 8.2 0.3 16B 10 156 12.5 10
F1
C 10 377 19.6 0.2 20Sum 4 1434 50.2 4.3 65
A1 20 421 19.8 0.1 23A2 20 133 9.5 4.4 14B 25 184 12.4 11C1 20 222 11.8 2.1 16
F2
C2 20 145 6.6 1.9 10Sum 5 1104 60.1 4.5 4.0 74
Table 6. Applied automation schemes and symbols.Auto-
mation
Sym-
bol
Description
Remotecontrolledswitches
RC1
RC2
RC12
Remote controlled distributionsubstation RC1Remote controlled distributionsubstation RC2Remote controlled distributionsubstations RC1 and RC2
Remotecontrol-led linerecloser
R1R2R3R12
R1-3
Remote controlled line recloser R1Remote controlled line recloser R2Remote controlled line recloser R3Remote controlled line reclosersR1 and R2Remote controlled line reclosersR1, R2 and R3
Results
The chosen feeders for the study were among the worstperforming feeders of the distribution company partly
-
7/29/2019 Impacts of Quality Improvement Incentives on Automation
3/4
-
7/29/2019 Impacts of Quality Improvement Incentives on Automation
4/4
C I RC I RC I RC I R E DE DE DE D 20th International Conference on Electricity Distribution Prague, 8-11 June 2009Paper 0141
CIRED2009 Session 5 Paper No 0141
REFERENCES
[1] The Finnish Energy Market Authority (EMA), 2008,
Liite 1 Menetelmt shkn jakeluverkkotoiminnan tuotonmrittmiseksi 1.1.2008 alkavalla ja 31.12.2011pttyvll valvontajaksolla. (Methods for determining theprofit of electricity distribution for the second regulatoryperiod), 29-31, 63-64, available at:http://www.energiamarkkinavirasto.fi/files/liite1_770-873-425-2004.pdf, only in Finnish.
[2] Lakervi E, E.J. Holmes, 1996, Electricity distributionnetwork design, Second edition. Peter Peregrinius Ltd.,London, UK, 70-79.
APPENDIX: Equations used in calculations
Reliability indices
mpmpkSAIFIT i /= , where
impk = number of distribution substation
areas that are influenced by outage imp = total number of distribution substation
areas in the distribution area
= = =
n
i
x
jijij mphmpkSAIDIT 1 1 / , where
n = number of outagesx = number of different outage durationsrelated to a certain outage
ijmpk = number of distribution substation areas
in the areas where the outage duration was ijh
mp = total number of distribution substation
areas in the distribution area
mpmpkMAIFIT i/= , where
ijmpk = number of distribution substation areas
that are influenced by the momentaryinterruption imp = total number of distribution substation
areas in the distribution area
Cost, savings and payback time
The cost of NDE is calculated by means of the cost of thepower and energy not supplied NDEC [2]:
( ) ( )[ ] += jijijijjiNDE PttbtaC , where
i
= average outage rate( )ijj ta and ( )ijj tb are the per-unit cost values for
the power and energy not supplied to the loadpoint j when the outage time is
ijt (e.g./kW and
/kWh)
jP = average power not supplied
The cost of AR CAR is:
+= DiiDHiiHAR cPLcPLC , where
Hc = HSAR unit price
Dc = DAR unit priceH = HSAR frequency per unit length of line
D = DAR frequency per unit length of lineLi = line length of zone iPi = average power of zone i
The total outage cost INTC is:
ARNDEINT CCC +=
The economic benefit of an automation scheme i is:
( ) ( )[ ]iARARijji
CCCCB += 00, where
0jC is the cost of NDE for the basic feeder 0
without automation
ijC is the cost of NDE for the feeder with
automation scheme i
0ARC is the cost of AR for the basic feeder 0
without automation
iARC is the cost of AR for the feeder with
automation scheme i
The payback time iT with the remote controlled linerecloser scheme i is:
( )INTiINTii CCKT = 1/ , where
iK is the investment cost of recloser scheme i
1INTC is the total outage cost in year 2008
INTiC is the total outage cost with recloser
scheme i