IEEE SCC21 1547 Overview NERC SPIDERWG 01072019 v3 … Planning...Minnesota Public Utilities...

26
Bulk System Opportunities from New Distributed Energy Resource Interconnection and Interoperability Standards IEEE Std 1547-2018 Clayton Stice, ERCOT Jens C. Boemer, EPRI (on behalf of SCC21) NERC SPIDER WG Meeting Austin, TX, Jan 8-9, 2019

Transcript of IEEE SCC21 1547 Overview NERC SPIDERWG 01072019 v3 … Planning...Minnesota Public Utilities...

Page 1: IEEE SCC21 1547 Overview NERC SPIDERWG 01072019 v3 … Planning...Minnesota Public Utilities Commission •Phase 1 (2017): Interconnection Process, Applications, Agreements •Phase

Bulk System Opportunities from New Distributed Energy Resource Interconnection and Interoperability Standards

IEEE Std 1547-2018

Clayton Stice, ERCOT

Jens C. Boemer, EPRI (on behalf of SCC21)

NERC SPIDER WG Meeting

Austin, TX, Jan 8-9, 2019

Page 2: IEEE SCC21 1547 Overview NERC SPIDERWG 01072019 v3 … Planning...Minnesota Public Utilities Commission •Phase 1 (2017): Interconnection Process, Applications, Agreements •Phase

Disclaimer and Acknowledgment

This presentation and discussion represents the authors’ views and are not the formal position, explanation or position of the IEEE or the IEEE Standards Association.

This slide deck has been peer-reviewed by IEEE Standard Coordination Committee 21 (SCC21) and IEEE P1547 Officers.

The presenters acknowledge the contributions of the IEEE Std 1547-2018 Working Group, Balloters and Officers.

Page 3: IEEE SCC21 1547 Overview NERC SPIDERWG 01072019 v3 … Planning...Minnesota Public Utilities Commission •Phase 1 (2017): Interconnection Process, Applications, Agreements •Phase

Overview on North American Standards

3

IEEE Std1547.1

IEEE Std1547

NERC1 / FERC2

Product & Installation Requirements

Grid Interconnection & Functional Requirements

UL 1741(Listing / Certification Test)

Communication Certification Requirements

IEEE P2030.5 DNP3 IEEE P1815

State/PUC Utility Laws (e.g. CA Rule 21)

Individual Utility Generator Connection Agreements

State Codes/Laws(selective adoption of NEC)

National Electric Code (voluntary)

Local Municipal Codes

Loca

lSta

teN

atio

nal

Sta

ndar

dsTe

sts

SunSpecIEC 61850(Standards have no inherent authority)

1 e.g., NERC PRC-024-02, 2 e.g., FERC Order No. 828

Approval rate of >90% among 380 balloters

IEEE 1547 is a voluntary industry standard – no inherent authority

Requires adoption by an Authority Governing Interconnection Requirements

– For example, a PUC, municipal or cooperative/ governing board

Page 4: IEEE SCC21 1547 Overview NERC SPIDERWG 01072019 v3 … Planning...Minnesota Public Utilities Commission •Phase 1 (2017): Interconnection Process, Applications, Agreements •Phase

Example Adoption of IEEE Std 1547-2018

ISO New England•Coordination between ISO-NE and the MA’s utilities in the Massachusetts Technical Standards Review Group•Reference to UL 1741 SA as a stopgap to verify DER ride-through capability in the interim•Harmonization of voltage & frequency trip settings with IEEE Std 1547-2018 ranges of allowable settings

PJM Interconnection•Two ad-hoc stakeholder workshops in 2018 for DER ride-through categories and trip settings (PJM website)•Initiation of formal stakeholder proceedings in 2019•Aiming at full adoption of IEEE Std 1547-2018 for jurisdictional DER by early 2020

Minnesota Public Utilities Commission•Phase 1 (2017): Interconnection Process, Applications, Agreements•Phase 2 (2018): Technical Requirements consistent with IEEE Std 1547-2018 (MN PUC website)•Coordination with regional reliability coordinator, e.g., MISO

MN

MA

Page 5: IEEE SCC21 1547 Overview NERC SPIDERWG 01072019 v3 … Planning...Minnesota Public Utilities Commission •Phase 1 (2017): Interconnection Process, Applications, Agreements •Phase

Definition of Distributed Energy Resource

In the context of IEEE 1547:

“A source of electric power that is not directly connected to a bulk power system.”

– Includes distributed generators.– Includes distributed energy storage technologies.– Does not include controllable loads used for demand response.– Does not include DER that is behind a transfer switch with <100msec– Exempts emergency/standby generators that are not intended to parallel with the

Grid from many requirements.

5

Page 6: IEEE SCC21 1547 Overview NERC SPIDERWG 01072019 v3 … Planning...Minnesota Public Utilities Commission •Phase 1 (2017): Interconnection Process, Applications, Agreements •Phase

• Shall NOT actively regulate voltage• Shall trip on abnormal voltage/frequency

Evolution of grid support functionsIEEE Std 1547-

2003

IEEE Std 1547a-2014

(Amendment 1)

• May actively regulate voltage• May ride through abnormal voltage or frequency• May provide frequency response

IEEE Std 1547-2018

• Shall be capable of actively regulating voltage• Shall ride through abnormal voltage/frequency• Shall be capable of frequency response

Source: NREL

Page 7: IEEE SCC21 1547 Overview NERC SPIDERWG 01072019 v3 … Planning...Minnesota Public Utilities Commission •Phase 1 (2017): Interconnection Process, Applications, Agreements •Phase

IEEE Std 1547-2003• Focused only on distribution system• Specifications for the “interconnection system”

sufficiently achieve the standard’s objective.• Meant as DER interconnection standard but

mainly used for equipment listing.• Limited to electrical requirements.

Important changes in focus and coverage

7

Area EPS

Interconnection System

Scope of IEEE 1547-2003

DER unit

IEEE Std 1547-2018• Focused on distribution and bulk system• Specifications encompass the whole DER• Equipment listing as well as plant-level

verification.• Includes both electrical as well as

interoperability/communications requirements.

Area EPS

Communication Interface

Power Interface

Scope of IEEE 1547-2018

DER

Source: EPRI

Page 8: IEEE SCC21 1547 Overview NERC SPIDERWG 01072019 v3 … Planning...Minnesota Public Utilities Commission •Phase 1 (2017): Interconnection Process, Applications, Agreements •Phase

Bulk System Opportunities

8

Standards for DER Listing/ Interconnection Standards State/ PUC/Utility RulesCertification CA HI/HECO

Function Set Advanced Functions Capability UL 1741 UL 1741(SA) IEEE 1547.1‐201?* IEEE 1547‐2003 IEEE 1547a‐2014 IEEE 1547‐

2018Rule 21 Rule 14H & UL 

SRDv1.12016 (Phases)All Adjustability in Ranges of Allowable Settings ∆ √ ‡

Monitoring & Control

Ramp Rate Control ∆ ‡ (P1) ‡Communication Interface ∆ ‡ ‡ (P2) ‡

Disable Permit Service (Remote Shut‐Off, Remote Disconnect/Reconnect) ∆ ‡ ‡ (P3) ‡

Limit Active Power ∆ ‡ ‡ (P3)Monitor Key DER Data ∆ ‡ ‡ (P3)

SchedulingSet Active Power [ ‡ (P3) ]

Scheduling Power Values and Models ‡ (P3)

ReactivePower&

VoltageSupport

Constant Power Factor √ ∆ ∆ √ √ ‡ ‡ (P1) XVoltage‐Reactive Power (Volt‐Var) ∆ ∆ X √ ‡ ‡ (P1) ‡

Autonomously Adjustable Voltage Reference ∆ ‡ !!! !!!Active Power‐Reactive Power (Watt‐Var) ∆ X ‡ ‡

Constant Reactive Power √ ∆ √ √ ‡Voltage‐Active Power (Volt‐Watt) ∆ ∆ X √ ‡ ‡ (P3) ‡

Dynamic Voltage Support during VRT √ [ ‡ (P3) ]Bulk SystemReliability

&FrequencySupport

Frequency Ride‐Through (FRT) ∆ ∆ ‡ ‡ (P1) ‡Rate‐of‐Change‐of‐Frequency Ride‐Through ∆ ‡ !!! !!!

Voltage Ride‐Through (VRT) ∆ ∆ ‡ ‡ (P1) ‡Voltage Phase Angle Jump Ride‐Through ∆ ‡ !!! !!!

Frequency‐Watt ∆ ∆ X √ ‡ ‡ (P3) ‡

Other Advanced DER Functions

Anti‐Islanding Detection and Trip ∆ ‡ ‡ (P1) ‡Transient Overvoltage ‡ ‡Remote Configurability ‡ ‡ (P2) ‡

Return to Service (Enter Service) ‡ ‡ (P1) ‡

Legend: X Prohibited, √ Allowed by Mutual Agreement, ‡ Capability Required, ∆ Test and Verifica on Defined Source: EPRI. Source: EPRI. Please contact EPRI for any[ … ] Subject to clarification of the technical requirements and use cases, !!! Important Gap suggested updates to this table.Source: EPRI

Page 9: IEEE SCC21 1547 Overview NERC SPIDERWG 01072019 v3 … Planning...Minnesota Public Utilities Commission •Phase 1 (2017): Interconnection Process, Applications, Agreements •Phase

Reference Point of Applicability (RPA)

RPA is where performance requirements apply

IEEE 1547 specifies RPA depending on three criteria:– Aggregate DER rating– Average load demand– Zero sequence continuity

Generally:– PoC (DER terminals) for small

and load-immersed DER– PCC for large exporting

installations

Page 10: IEEE SCC21 1547 Overview NERC SPIDERWG 01072019 v3 … Planning...Minnesota Public Utilities Commission •Phase 1 (2017): Interconnection Process, Applications, Agreements •Phase

Mandatory Communication Interface

10

Out of Scope

–In Scope  Local DER Interface

Other Interfaces (optional)1547 Interface (mandatory)

DER Site

Requirements in IEEE Std 1547-2018 are limited to the “Local DER (Communication) Interface”

Page 11: IEEE SCC21 1547 Overview NERC SPIDERWG 01072019 v3 … Planning...Minnesota Public Utilities Commission •Phase 1 (2017): Interconnection Process, Applications, Agreements •Phase

Telemetered Data – Nameplate Data – As-built characteristics of the DER, e.g.:

• Manufacturer/model/Active and reactive power rating, etc.– Monitoring Information – Measured values of:

• Active and reactive power, Voltage, etc.

Operational Control / Management information – Change of Permit Service logical to disabled and shut down– Limit active power output– Change control modes and settings, e.g. Volt/Var, Trip, etc.

Measurement and Control

11

Interoperability capabilities allow Area EPS Operator a great level of DER control if communication infrastructure is implemented

Page 12: IEEE SCC21 1547 Overview NERC SPIDERWG 01072019 v3 … Planning...Minnesota Public Utilities Commission •Phase 1 (2017): Interconnection Process, Applications, Agreements •Phase

Normal and abnormal operating performance categories

Category ACategory I

Category III

Category B

Category II

1 State Regulator, Area EPS or bulk system operator, etc.

Authorities Governing

Interconnection Requirements

(AGIRs)1

Impact Assessment• Technical conditions: type & capacity & future

penetration of DER, type of grid configuration, etc.• Non-technical issues: DER use case, impacts on

environment, emissions, and sustainability, etc.

DER Vendors

Market Analysis

• Costs• Market segment• Etc.

Settings (Utilization)• Ranges of allowable sttgs• Default parameters

Stakeholder Engagement• Distribution utilities.• Bulk system operators &

planners• Regional reliability

coordinator.• DER developers.• Others.

Assignment of Performance Categories

Ride-Through

VoltageRegulation

Page 13: IEEE SCC21 1547 Overview NERC SPIDERWG 01072019 v3 … Planning...Minnesota Public Utilities Commission •Phase 1 (2017): Interconnection Process, Applications, Agreements •Phase

Abnormal Performance Capability

13

Category Objective Foundation

IEssential bulk system needs and reasonably achievable by all current state-of-art DER technologies

German grid code for synchronous generator DER

II Full coordination with bulk power system needs

Based on NERC PRC-024, adjusted for distribution voltage differences (delayed voltage recovery)

III Ride-through designed for distribution support as well as bulk system

Based on California Rule 21 and Hawaii Rule 14H

Category II and III are sufficient for bulk system reliability.

Page 14: IEEE SCC21 1547 Overview NERC SPIDERWG 01072019 v3 … Planning...Minnesota Public Utilities Commission •Phase 1 (2017): Interconnection Process, Applications, Agreements •Phase

0.00

0.10

0.20

0.30

0.40

0.50

0.60

0.70

0.80

0.90

1.00

1.10

1.20

1.30

0.01 0.1 1 10 100 1000

Volta

ge (p

.u.)

Time (s)(cumulative time for ride‐through and clearing time for trip)

shall trip1.20 p.u.

13 s

1.10 p.u.

0.00 p.u.

0.88 p.u.

0.16 s

0.00 p.u.

0.50 p.u.

21 s

Continuous Operation Capability(subject to requirements of clause 5)

Mandatory OperationCapability

Permissive OperationCapability

shall trip

0.32 s 2 s

2 s

2

1 s1

2

1

may ride‐through or may trip

may ride‐throughor may trip

may ride‐throughor may trip

0.88 p.u.

0.45 p.u.   

0.65 p.u.

Permissive Operation Capability

0.16 s

mayride‐through

0.16 s

Legend

range of allowable settings

default value

shall trip zones

may ride‐through ormay trip zones

shall ride‐through zonesand operating regionsdescribing performance

NERCPRC‐024‐2

Balancing Bulk & Distribution Grid Needs

Bulk System Reliability• Long trip times• Ride‐through withoutmomentary cessation

• Reactive power support

T&D Coordination

Distribution Grid Safety• Short trip times• Ride‐through withmomentary cessation

• Voltage rise concerns• Protection coordination• Islanding concerns (line worker safety)Utility‐owned equipment may defeat DER ride‐through!

TENSION

Sou

rce:

EPR

I

Page 15: IEEE SCC21 1547 Overview NERC SPIDERWG 01072019 v3 … Planning...Minnesota Public Utilities Commission •Phase 1 (2017): Interconnection Process, Applications, Agreements •Phase

Further Information

http://sites.ieee.org/sagroups-scc21/standards/1547rev/– General– Scope– Purpose– Leadership Team– Sourcesdiscounted copies

– SCC21-Reviewed Slide Decks Available for Interested Lecturers

– Further Reading– Webinars

Please submit further reading suggestions via the web form!

Page 16: IEEE SCC21 1547 Overview NERC SPIDERWG 01072019 v3 … Planning...Minnesota Public Utilities Commission •Phase 1 (2017): Interconnection Process, Applications, Agreements •Phase

Contact Information

Clayton Stice

ERCOT

(512) 248-6806

[email protected]

Jens C. Boemer (SCC21 Secretary)

EPRI

(206) 471-1180

[email protected]

16

Page 17: IEEE SCC21 1547 Overview NERC SPIDERWG 01072019 v3 … Planning...Minnesota Public Utilities Commission •Phase 1 (2017): Interconnection Process, Applications, Agreements •Phase

Backup Slides

17

Page 18: IEEE SCC21 1547 Overview NERC SPIDERWG 01072019 v3 … Planning...Minnesota Public Utilities Commission •Phase 1 (2017): Interconnection Process, Applications, Agreements •Phase

List of eligible protocols

18

Page 19: IEEE SCC21 1547 Overview NERC SPIDERWG 01072019 v3 … Planning...Minnesota Public Utilities Commission •Phase 1 (2017): Interconnection Process, Applications, Agreements •Phase

Capability (versus Utilization, determined by settings)

IEEE 1547• Performance & Functional Capability Requirements

• Default settings• Ranges of allowable settings

Technical Capability(Ranges of technical settings)

Evaluated Capability(Ranges of evaluated settings)

Allowable Utilization(Ranges of allowable settings)

Actual Utilization(Specified settings)

Sou

rce:

EPR

I

Page 20: IEEE SCC21 1547 Overview NERC SPIDERWG 01072019 v3 … Planning...Minnesota Public Utilities Commission •Phase 1 (2017): Interconnection Process, Applications, Agreements •Phase

Trip – cessation of output without immediate return to service; not necessarily disconnection

Cease to energize – no active power delivery, limitations to reactive power exchange; Does not necessarily mean physical disconnection. Can be either a momentary cessation or a trip

Permissive operation – DER may either continue operation or may cease to energize, at its discretion

Mandatory operation – required active and reactive current exchange

Momentary cessation – cessation of energization for the duration of a disturbance with rapid recovery when voltage or frequency return to defined range

Return to service – re-entry of DER to service following a trip

Restore output – DER recovery to normal output following a disturbance that does not cause a trip.

Specific abnormal performance terminology

Page 21: IEEE SCC21 1547 Overview NERC SPIDERWG 01072019 v3 … Planning...Minnesota Public Utilities Commission •Phase 1 (2017): Interconnection Process, Applications, Agreements •Phase

Other ride-through requirements

Consecutive voltage disturbances, e.g.:– Voltage dips caused by multiple unsuccessful reclosing attempts on another circuit– Dynamic voltage swings in and out of normal range following bulk system fault– Repetitive faults

Rate-of-change of frequency (ROCOF)– Severe bulk grid dynamic events

Phase angle jumps, e.g.:– Unbalanced faults– Bulk system switching events (generator trip, line switching, etc.)

21

Page 22: IEEE SCC21 1547 Overview NERC SPIDERWG 01072019 v3 … Planning...Minnesota Public Utilities Commission •Phase 1 (2017): Interconnection Process, Applications, Agreements •Phase

Frequency response

Increasing penetration of unconventional generation is reducing system inertia which can degrade system frequency stability

Frequency droop (governor-like) response required of all DER– Active power output is modulated in response to frequency deviation– No mandate to maintain headroom to increase active power to provide

under-frequency response

Frequency response parameters:– Default droop 0.05 p.u. frequency for one p.u. active power change– Default deadband 36 mHz– Other parameter settings allowed as approved by the regional reliability coordinator

22

Page 23: IEEE SCC21 1547 Overview NERC SPIDERWG 01072019 v3 … Planning...Minnesota Public Utilities Commission •Phase 1 (2017): Interconnection Process, Applications, Agreements •Phase

Area of Concern beyond IEEE 1547

Utility-Owned recloser at DER connection point may terminate ride-through!

IEEE 1547 General remarks and limitations (per clause 1.4): “The … ranges of allowable settings for voltage and frequency trip settings specified in this standard for DER are not intended to limit the capabilities and settings of other equipment on the Area EPS.”

IEEE Std 1547-2018 recommends:

Area EPS protections conform to the voltage and frequency ride-through objectives of IEEE 1547 under normal circumstances (footnotes 80 and 99)

Settings outside the allowable range only to be used occasionally and selectively to accommodate worker safety or to protect distribution infrastructure while in an abnormal configuration, such as:– Circuit reconfiguration– Temporary loss of direct transfer trip

Coordinate special settings with regional reliability coordinator

Page 24: IEEE SCC21 1547 Overview NERC SPIDERWG 01072019 v3 … Planning...Minnesota Public Utilities Commission •Phase 1 (2017): Interconnection Process, Applications, Agreements •Phase

New SCC21 Website

http://sites.ieee.org/sagroups-scc21/

Page 25: IEEE SCC21 1547 Overview NERC SPIDERWG 01072019 v3 … Planning...Minnesota Public Utilities Commission •Phase 1 (2017): Interconnection Process, Applications, Agreements •Phase

Discounted Distribution of SCC21-Sponsored Standards to Qualifying Parties http://sites.ieee.org/sagroups-scc21/standards/discountedcopies/

Definition of qualifying parties:– Participants of SCC21-supported trainings for educational purposes

(1 copy per participant)– Governments / state regulatory authorities for policy making

(1 copy per entity)– Others at discretion of SCC21 Officers and P1547 Chair

(1 copy per person or entity)

Criteria for discretionary copies– Interested party has hardship acquiring a commercial copy of a SCC21-sponsored standard.– There is a public benefit associated with giving the interested party access to a discounted copy of the

standard.

Use the web form to request a discounted copy of a standard!

Page 26: IEEE SCC21 1547 Overview NERC SPIDERWG 01072019 v3 … Planning...Minnesota Public Utilities Commission •Phase 1 (2017): Interconnection Process, Applications, Agreements •Phase

SCC21 Outreach Procedure and Request Form for Standards Presentations http://sites.ieee.org/sagroups-scc21/resources/standardspresentations/

“Give and taken” approach:– SCC21 provides latest set of draft slides– Requesting party edits slides as they see fit– SCC21 Officers review the updated slides– Requesting party sends final slide deck and feedback received

Intellectual Property– SCC21 has executed a license agreement with IEEE– Need to specify copyrights on the slide decks produced– The parties maintain the ownership of their respective materials

Professional Development Hours (PDH) Form is available – need to check whether these are accredited or not

Use the web form to request a SCC21-reviwed slide deck!