ID Task Task Name Duration Start Finish % Complete Exam ...

15
ID Task Mode Task Name Duration Start Finish % Complete Exam Result Predecessors 1 1 Revision By Knowledge Area 33 days? Sat 25/07/20 Tue 08/09/20 76% 2 1.1 Project Integration Management 1 day? Sat 25/07/20 Sat 25/07/20 100% 3 1.1.1 Develop Project Charter 1 day? Sat 25/07/20 Sat 25/07/20 100% 4 1.1.2 Develop Project Management Plan 1 day? Sat 25/07/20 Sat 25/07/20 100% 5 1.1.3 Direct & Manage Project Work 1 day? Sat 25/07/20 Sat 25/07/20 100% 6 1.1.4 Monitor & Control Project Work 1 day? Sat 25/07/20 Sat 25/07/20 100% 7 1.1.5 Close Project or Phase 1 day? Sat 25/07/20 Sat 25/07/20 100% 8 1.1.6 Complete PrepCast 20 Q's 1 day? Sat 25/07/20 Sat 25/07/20 100% 85% 9 1.1.7 Complete Andy Crowe Quiz 1 day? Sat 25/07/20 Sat 25/07/20 100% 80% 10 11 1.2 Project Scope Management 2 days Mon 27/07/20 Tue 28/07/20 100% 2 12 1.2.1 Plan Scope Management 2 days Mon 27/07/20 Tue 28/07/20 100% 13 1.2.2 Collect Requirements 2 days Mon 27/07/20 Tue 28/07/20 100% 14 1.2.3 Define Scope 2 days Mon 27/07/20 Tue 28/07/20 100% 15 1.2.4 Create WBS 2 days Mon 27/07/20 Tue 28/07/20 100% 16 1.2.5 Validate Scope 2 days Mon 27/07/20 Tue 28/07/20 100% 17 1.2.6 Control Scope 2 days Mon 27/07/20 Tue 28/07/20 100% 18 1.2.7 Complete PrepCast 20 Q's 2 days Mon 27/07/20 Tue 28/07/20 100% 75% 19 1.2.8 Complete Andy Crowe Quiz 2 days Mon 27/07/20 Tue 28/07/20 100% 84% 20 21 1.3 Project Schedule Management 2 days Wed 29/07/20 Thu 30/07/20 100% 11 T F Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Late Baseline Baseline Milestone Baseline Summary Progress Manual Progress Slippage Page 1 Project: Revision-Project-Plan Date: Fri 14/08/20

Transcript of ID Task Task Name Duration Start Finish % Complete Exam ...

ID Task

Mode

Task Name Duration Start Finish % Complete Exam Result Predecessors

1 1 Revision By Knowledge Area 33 days? Sat 25/07/20 Tue 08/09/20 76%

2 1.1 Project Integration Management 1 day? Sat 25/07/20 Sat 25/07/20 100%

3 1.1.1 Develop Project Charter 1 day? Sat 25/07/20 Sat 25/07/20 100%

4 1.1.2 Develop Project Management Plan 1 day? Sat 25/07/20 Sat 25/07/20 100%

5 1.1.3 Direct & Manage Project Work 1 day? Sat 25/07/20 Sat 25/07/20 100%

6 1.1.4 Monitor & Control Project Work 1 day? Sat 25/07/20 Sat 25/07/20 100%

7 1.1.5 Close Project or Phase 1 day? Sat 25/07/20 Sat 25/07/20 100%

8 1.1.6 Complete PrepCast 20 Q's 1 day? Sat 25/07/20 Sat 25/07/20 100% 85%

9 1.1.7 Complete Andy Crowe Quiz 1 day? Sat 25/07/20 Sat 25/07/20 100% 80%

10

11 1.2 Project Scope Management 2 days Mon 27/07/20 Tue 28/07/20 100% 2

12 1.2.1 Plan Scope Management 2 days Mon 27/07/20 Tue 28/07/20 100%

13 1.2.2 Collect Requirements 2 days Mon 27/07/20 Tue 28/07/20 100%

14 1.2.3 Define Scope 2 days Mon 27/07/20 Tue 28/07/20 100%

15 1.2.4 Create WBS 2 days Mon 27/07/20 Tue 28/07/20 100%

16 1.2.5 Validate Scope 2 days Mon 27/07/20 Tue 28/07/20 100%

17 1.2.6 Control Scope 2 days Mon 27/07/20 Tue 28/07/20 100%

18 1.2.7 Complete PrepCast 20 Q's 2 days Mon 27/07/20 Tue 28/07/20 100% 75%

19 1.2.8 Complete Andy Crowe Quiz 2 days Mon 27/07/20 Tue 28/07/20 100% 84%

20

21 1.3 Project Schedule Management 2 days Wed 29/07/20 Thu 30/07/20 100% 11

T F S

20 Jul '20

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Late

Baseline

Baseline Milestone

Baseline Summary

Progress

Manual Progress

Slippage

Page 1

Project: Revision-Project-Plan

Date: Fri 14/08/20

ID Task

Mode

Task Name Duration Start Finish % Complete Exam Result Predecessors

22 1.3.1 Plan Schedule Management 2 days Wed 29/07/20 Thu 30/07/20 100%

23 1.3.2 Define Activities 2 days Wed 29/07/20 Thu 30/07/20 100%

24 1.3.3 Sequence Activities 2 days Wed 29/07/20 Thu 30/07/20 100%

25 1.3.4 Estimate Activity Durations 2 days Wed 29/07/20 Thu 30/07/20 100%

26 1.3.5 Develop Schedule 2 days Wed 29/07/20 Thu 30/07/20 100%

27 1.3.6 Control Schedule 2 days Wed 29/07/20 Thu 30/07/20 100%

28 1.3.7 Complete PrepCast 20 Q's 2 days Wed 29/07/20 Thu 30/07/20 100% 75%

29 1.3.8 Complete Andy Crowe Quiz 2 days Wed 29/07/20 Thu 30/07/20 100% 85%

30

31 1.4 Project Cost Management 3 days? Fri 31/07/20 Tue 04/08/20 100% 21

32 1.4.1 Plan Cost Management 3 days? Fri 31/07/20 Tue 04/08/20 100%

33 1.4.2 Estimate Costs 3 days? Fri 31/07/20 Tue 04/08/20 100%

34 1.4.3 Determine Budget 3 days? Fri 31/07/20 Tue 04/08/20 100%

35 1.4.4 Control Costs 3 days? Fri 31/07/20 Tue 04/08/20 100%

36 1.4.5 Complete PrepCast 20 Q's 3 days? Fri 31/07/20 Tue 04/08/20 100% 73%

37 1.4.6 Complete Andy Crowe Quiz 3 days? Fri 31/07/20 Tue 04/08/20 100% 70%

38

39 1.5 Project Quality Management 2 days Wed 05/08/20 Thu 06/08/20 100% 31

40 1.5.1 Plan Quality Management 2 days Wed 05/08/20 Thu 06/08/20 100%

41 1.5.2 Manage Quality 2 days Wed 05/08/20 Thu 06/08/20 100%

42 1.5.3 Control Quality 2 days Wed 05/08/20 Thu 06/08/20 100%

T F S

20 Jul '20

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Late

Baseline

Baseline Milestone

Baseline Summary

Progress

Manual Progress

Slippage

Page 2

Project: Revision-Project-Plan

Date: Fri 14/08/20

ID Task

Mode

Task Name Duration Start Finish % Complete Exam Result Predecessors

43 1.5.4 Complete PrepCast 20 Q's 2 days Wed 05/08/20 Thu 06/08/20 100% 80%

44 1.5.5 Complete Andy Crowe Quiz 2 days Wed 05/08/20 Thu 06/08/20 100% 68%

45

46 1.6 Project Resource Management 2 days Fri 07/08/20 Mon 10/08/20 100% 39

47 1.6.1 Plan Resource Management 2 days Fri 07/08/20 Mon 10/08/20 100%

48 1.6.2 Estimate Activity Resources 2 days Fri 07/08/20 Mon 10/08/20 100%

49 1.6.3 Acquire Resources 2 days Fri 07/08/20 Mon 10/08/20 100%

50 1.6.4 Develop Team 2 days Fri 07/08/20 Mon 10/08/20 100%

51 1.6.5 Manage Team 2 days Fri 07/08/20 Mon 10/08/20 100%

52 1.6.6 Control Resources 2 days Fri 07/08/20 Mon 10/08/20 100%

53 1.6.7 Complete PrepCast 20 Q's 2 days Fri 07/08/20 Mon 10/08/20 100% 70%

54 1.6.8 Complete Andy Crowe Quiz 2 days Fri 07/08/20 Mon 10/08/20 100% 100%

55

56 1.7 Project Communications Management 1 day? Tue 11/08/20 Tue 11/08/20 100% 46

57 1.7.1 Plan Communications Management 1 day? Tue 11/08/20 Tue 11/08/20 100%

58 1.7.2 Manage Communications 1 day? Tue 11/08/20 Tue 11/08/20 100%

59 1.7.3 Monitor Communications 1 day? Tue 11/08/20 Tue 11/08/20 100%

60 1.7.4 Complete PrepCast 20 Q's 1 day Tue 11/08/20 Tue 11/08/20 100% 65%

61 1.7.5 Complete Andy Crowe Quiz 1 day Tue 11/08/20 Tue 11/08/20 100% 80%

62

63 1.8 Project Risk Management 2 days? Wed 12/08/20 Thu 13/08/20 100% 56

T F S

20 Jul '20

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Late

Baseline

Baseline Milestone

Baseline Summary

Progress

Manual Progress

Slippage

Page 3

Project: Revision-Project-Plan

Date: Fri 14/08/20

ID Task

Mode

Task Name Duration Start Finish % Complete Exam Result Predecessors

64 1.8.1 Plan Risk Management 2 days? Wed 12/08/20 Thu 13/08/20 100%

65 1.8.2 Identify Risks 2 days? Wed 12/08/20 Thu 13/08/20 100%

66 1.8.3 Perform Qualitative Risk Analysis 2 days? Wed 12/08/20 Thu 13/08/20 100%

67 1.8.4 Perform Quantative Risk Analysis 2 days? Wed 12/08/20 Thu 13/08/20 100%

68 1.8.5 Plan Risk Responses 2 days? Wed 12/08/20 Thu 13/08/20 100%

69 1.8.6 Implement Risk Responses 2 days? Wed 12/08/20 Thu 13/08/20 100%

70 1.8.7 Monitor Risks 2 days? Wed 12/08/20 Thu 13/08/20 100%

71 1.8.8 Complete PrepCast 20 Q's 2 days? Wed 12/08/20 Thu 13/08/20 100% 70%

72 1.8.9 Complete Andy Crowe Quiz 2 days? Wed 12/08/20 Thu 13/08/20 100% 76%

73

74 1.9 Project Procurement Management 1 day? Fri 14/08/20 Fri 14/08/20 0% 63

75 1.9.1 Plan Procurement Management 1 day? Fri 14/08/20 Fri 14/08/20 0%

76 1.9.2 Conduct Procurements 1 day? Fri 14/08/20 Fri 14/08/20 0%

77 1.9.3 Control Procurements 1 day? Fri 14/08/20 Fri 14/08/20 0%

78 1.9.4 Complete PrepCast 20 Q's 1 day Fri 14/08/20 Fri 14/08/20 0%

79 1.9.5 Complete Andy Crowe Quiz 1 day Fri 14/08/20 Fri 14/08/20 0%

80

81 1.10 Project Stakeholder Management 3 days Mon 17/08/20 Wed 19/08/20 0% 74

82 1.10.1 Identify Stakeholders 3 days Mon 17/08/20 Wed 19/08/20 0%

83 1.10.2 Plan Stakeholder Engagement 3 days Mon 17/08/20 Wed 19/08/20 0%

84 1.10.3 Manage Stakeholder Enagagement 3 days Mon 17/08/20 Wed 19/08/20 0%

T F S

20 Jul '20

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Late

Baseline

Baseline Milestone

Baseline Summary

Progress

Manual Progress

Slippage

Page 4

Project: Revision-Project-Plan

Date: Fri 14/08/20

ID Task

Mode

Task Name Duration Start Finish % Complete Exam Result Predecessors

85 1.10.4 Monitor Stakeholder Enagagement 3 days Mon 17/08/20 Wed 19/08/20 0%

86 1.10.5 Complete PrepCast 20 Q's 3 days Mon 17/08/20 Wed 19/08/20 0%

87 1.10.6 Complete Andy Crowe Quiz 3 days Mon 17/08/20 Wed 19/08/20 0%

88

89 1.11 Exams 14 days Thu 20/08/20 Tue 08/09/20 0% 81

90 1.11.1 Exam 1 1 day Thu 20/08/20 Thu 20/08/20 0%

91 1.11.2 Revise Weaknesses 1 day Fri 21/08/20 Fri 21/08/20 0% 90

92 1.11.3 Exam 2 1 day Tue 25/08/20 Tue 25/08/20 0% 91FS+1 day

93 1.11.4 Revise Weaknesses 1 day Wed 26/08/20 Wed 26/08/20 0% 92

94 1.11.5 Exam 3 1 day Fri 28/08/20 Fri 28/08/20 0% 93FS+1 day

95 1.11.6 Revise Weaknesses 1 day Mon 31/08/20 Mon 31/08/20 0% 94

96 1.11.7 Exam 4 1 day Wed 02/09/20 Wed 02/09/20 0% 95FS+1 day

97 1.11.8 Revise Weaknesses 1 day Thu 03/09/20 Thu 03/09/20 0% 96

98 1.11.9 Exam 5 1 day Mon 07/09/20 Mon 07/09/20 0% 97FS+1 day

99 1.11.10 Revise Weaknesses 1 day Tue 08/09/20 Tue 08/09/20 0% 98

100

101 1.12 Exam Ready 0 days Tue 08/09/20 Tue 08/09/20 0% 89

T F S

20 Jul '20

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Late

Baseline

Baseline Milestone

Baseline Summary

Progress

Manual Progress

Slippage

Page 5

Project: Revision-Project-Plan

Date: Fri 14/08/20

S S M T W T F S S M T W T F S S M T W T F S S M T

20 Jul '20 27 Jul '20 03 Aug '20 10 Aug '20 17 Aug '20

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Late

Baseline

Baseline Milestone

Baseline Summary

Progress

Manual Progress

Slippage

Page 6

Project: Revision-Project-Plan

Date: Fri 14/08/20

S S M T W T F S S M T W T F S S M T W T F S S M T

20 Jul '20 27 Jul '20 03 Aug '20 10 Aug '20 17 Aug '20

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Late

Baseline

Baseline Milestone

Baseline Summary

Progress

Manual Progress

Slippage

Page 7

Project: Revision-Project-Plan

Date: Fri 14/08/20

S S M T W T F S S M T W T F S S M T W T F S S M T

20 Jul '20 27 Jul '20 03 Aug '20 10 Aug '20 17 Aug '20

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Late

Baseline

Baseline Milestone

Baseline Summary

Progress

Manual Progress

Slippage

Page 8

Project: Revision-Project-Plan

Date: Fri 14/08/20

S S M T W T F S S M T W T F S S M T W T F S S M T

20 Jul '20 27 Jul '20 03 Aug '20 10 Aug '20 17 Aug '20

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Late

Baseline

Baseline Milestone

Baseline Summary

Progress

Manual Progress

Slippage

Page 9

Project: Revision-Project-Plan

Date: Fri 14/08/20

08/09

S S M T W T F S S M T W T F S S M T W T F S S M T

20 Jul '20 27 Jul '20 03 Aug '20 10 Aug '20 17 Aug '20

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Late

Baseline

Baseline Milestone

Baseline Summary

Progress

Manual Progress

Slippage

Page 10

Project: Revision-Project-Plan

Date: Fri 14/08/20

T W T F S S M T W T F S S M T W T F S S M T W T F

17 Aug '20 24 Aug '20 31 Aug '20 07 Sep '20

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Late

Baseline

Baseline Milestone

Baseline Summary

Progress

Manual Progress

Slippage

Page 11

Project: Revision-Project-Plan

Date: Fri 14/08/20

T W T F S S M T W T F S S M T W T F S S M T W T F

17 Aug '20 24 Aug '20 31 Aug '20 07 Sep '20

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Late

Baseline

Baseline Milestone

Baseline Summary

Progress

Manual Progress

Slippage

Page 12

Project: Revision-Project-Plan

Date: Fri 14/08/20

T W T F S S M T W T F S S M T W T F S S M T W T F

17 Aug '20 24 Aug '20 31 Aug '20 07 Sep '20

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Late

Baseline

Baseline Milestone

Baseline Summary

Progress

Manual Progress

Slippage

Page 13

Project: Revision-Project-Plan

Date: Fri 14/08/20

T W T F S S M T W T F S S M T W T F S S M T W T F

17 Aug '20 24 Aug '20 31 Aug '20 07 Sep '20

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Late

Baseline

Baseline Milestone

Baseline Summary

Progress

Manual Progress

Slippage

Page 14

Project: Revision-Project-Plan

Date: Fri 14/08/20

08/09

T W T F S S M T W T F S S M T W T F S S M T W T F

17 Aug '20 24 Aug '20 31 Aug '20 07 Sep '20

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Late

Baseline

Baseline Milestone

Baseline Summary

Progress

Manual Progress

Slippage

Page 15

Project: Revision-Project-Plan

Date: Fri 14/08/20