ID Task Task Name Duration Start Finish ...

58
ID Task Mode Task Name Duration Start Finish Pred Resource Names 1 Ingagane 275 kV Plan 2 Remove droppers on CB, CT and remove cables. 4 days Mon 22/04/04 Thu 22/04/07 275 kV trfr 4 3 Remove old CB,CT an 5 days Fri 22/04/08 Thu 22/04/14 2 275 kV trfr 4 4 Modify Foundations C 31 days Fri 22/04/15 Fri 22/05/27 3 275 kV trfr 4 5 Install new Steel work 15 days Mon 22/05/3 Fri 22/06/17 4 275 kV trfr 4 6 Test Equipment and b 14 days Mon 22/06/2 Thu 22/07/07 5 275 kV trfr 4 7 Remove droppers on 4 days Fri 22/07/08 Wed 22/07/1 6 275 kV Danskraal 8 Remove old CT,CVT,L 5 days Thu 22/07/14 Wed 22/07/2 7 275 kV Danskraal 9 Modify Foundations C 31 days Thu 22/07/21 Thu 22/09/01 8 275 kV Danskraal 10 Install new Steel work 35 days Fri 22/09/02 Thu 22/10/20 9 275 kV Danskraal 11 Test Equipment and b 14 days Fri 22/10/21 Wed 22/11/0 10 275 kV Danskraal 12 Remove droppers on 4 days Thu 22/11/10 Tue 22/11/15 11 275 kV Bloukrans 13 Remove old CT,CVT,L 5 days Wed 22/11/1 Tue 22/11/22 12 275 kV Bloukrans 14 Modify Foundations C 31 days Wed 22/11/2 Wed 23/01/0 13 275 kV Bloukrans 15 Install new Steel work 35 days Thu 23/01/05 Wed 23/02/2 14 275 kV Bloukrans 16 Test Equipment and b 14 days Thu 23/02/23 Tue 23/03/14 15 275 kV Bloukrans 17 Remove droppers on 4 days Wed 23/03/1 Mon 23/03/2 16 275 kV Bloedrivier 18 Remove all equipmen 5 days Tue 23/03/21 Mon 23/03/2 17 275 kV Bloedrivier 19 Modify Foundations 31 days Tue 23/03/28 Tue 23/05/09 18 275 kV Bloedrivier 20 Install new Steel work 35 days Wed 23/05/1 Tue 23/06/27 19 275 kV Bloedrivier 21 Test Equipment and b 14 days Wed 23/06/2 Mon 23/07/1 20 275 kV Bloedrivier 22 Remove droppers on 4 days Tue 23/07/18 Fri 23/07/21 21 275 kV Bloedrivier 23 Remove all equipmen 5 days Mon 23/07/2 Fri 23/07/28 22 275 kV Bloedrivier W T F S S M T W T F S S M T W T F '20 Nov 22 '20 Nov 29 Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Manual Progress Page 1 Project: Ingagane 275 kV plan 8 O Date: Tue 21/10/12

Transcript of ID Task Task Name Duration Start Finish ...

Page 1: ID Task Task Name Duration Start Finish ...

ID Task Mode

Task Name Duration Start Finish PredecessorsResource Names

1 Ingagane 275 kV Plan2 Remove droppers on

CB, CT and remove cables.

4 days Mon 22/04/04

Thu 22/04/07

275 kV trfr 4

3 Remove old CB,CT and steel work5 days Fri 22/04/08 Thu 22/04/142 275 kV trfr 4

4 Modify Foundations CB,CT31 days Fri 22/04/15 Fri 22/05/27 3 275 kV trfr 4

5 Install new Steel work and new CB, CT and droppers and cables15 days Mon 22/05/30Fri 22/06/17 4 275 kV trfr 4

6 Test Equipment and bay and Commission bay14 days Mon 22/06/20Thu 22/07/075 275 kV trfr 4

7 Remove droppers on CT, CVT,LT,SA and remove cables.4 days Fri 22/07/08 Wed 22/07/136 275 kV Danskraal 1

8 Remove old CT,CVT,LT and SA and steel work5 days Thu 22/07/14Wed 22/07/207 275 kV Danskraal 1

9 Modify Foundations CT, CVT,LT and SA31 days Thu 22/07/21Thu 22/09/018 275 kV Danskraal 1

10 Install new Steel work and new CT,CVT,LT and Saand new droppers and cables35 days Fri 22/09/02 Thu 22/10/209 275 kV Danskraal 1

11 Test Equipment and bay and Commission bay14 days Fri 22/10/21 Wed 22/11/0910 275 kV Danskraal 1

12 Remove droppers on CT, CVT,LT,SA and remove cables.4 days Thu 22/11/10Tue 22/11/1511 275 kV Bloukrans 1

13 Remove old CT,CVT,LT and SA and steel work5 days Wed 22/11/16Tue 22/11/2212 275 kV Bloukrans 1

14 Modify Foundations CT, CVT,LT and SA31 days Wed 22/11/23Wed 23/01/0413 275 kV Bloukrans 1

15 Install new Steel work and new CT,CVT,LT and Saand new droppers and cables. Include final adjustments on isolators35 days Thu 23/01/05Wed 23/02/2214 275 kV Bloukrans 1

16 Test Equipment and bay and Commission bay14 days Thu 23/02/23Tue 23/03/1415 275 kV Bloukrans 1

17 Remove droppers on entire bay and remove all cables.4 days Wed 23/03/15Mon 23/03/2016 275 kV Bloedrivier 4

18 Remove all equipment and steel work except Line isolator earth switch5 days Tue 23/03/21Mon 23/03/2717 275 kV Bloedrivier 4

19 Modify Foundations 31 days Tue 23/03/28Tue 23/05/0918 275 kV Bloedrivier 4

20 Install new Steel work and new equipment except line isolaotor earth switch and all droppers and all cables. Include final adjustments on isolators35 days Wed 23/05/10Tue 23/06/2719 275 kV Bloedrivier 4

21 Test Equipment and bay and Commission bay14 days Wed 23/06/28Mon 23/07/1720 275 kV Bloedrivier 4

22 Remove droppers on entire bay and remove all cables.4 days Tue 23/07/18Fri 23/07/21 21 275 kV Bloedrivier 5

23 Remove all equipment and steel work5 days Mon 23/07/24Fri 23/07/28 22 275 kV Bloedrivier 5

W T F S S M T W T F S S M T W T F'20 Nov 15 '20 Nov 22 '20 Nov 29

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Manual Progress

Page 1

Project: Ingagane 275 kV plan 8 ODate: Tue 21/10/12

Page 2: ID Task Task Name Duration Start Finish ...

ID Task Mode

Task Name Duration Start Finish PredecessorsResource Names

24 Modify Foundations 31 days Mon 23/07/31Mon 23/09/1123 275 kV Bloedrivier 5

25 Install new Steel work and new equipment and all droppers and all cables. Include final adjustments on isolators35 days Tue 23/09/12Mon 23/10/3024 275 kV Bloedrivier 5

26 Test Equipment and bay and Commission bay14 days Tue 23/10/31Fri 23/11/17 25 275 kV Bloedrivier 5

27 Remove droppers on isolators and remove cables.4 days Mon 23/11/20Thu 23/11/2326 275 kV bypass

28 Remove old isolator and steel work5 days Fri 23/11/24 Thu 23/11/3027 275 kV bypass

29 Modify Foundations for isolator and build new foundations for new 88 kV CT's31 days Fri 23/12/01 Fri 24/01/12 28 275 kV bypass

30 Install new Steel work and new isolators and CT and droppers and cables15 days Mon 24/01/15Fri 24/02/02 29 275 kV bypass

31 Test Equipment and bay and Commission bay14 days Mon 24/02/05Thu 24/02/2230 275 kV bypass

W T F S S M T W T F S S M T W T F'20 Nov 15 '20 Nov 22 '20 Nov 29

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Manual Progress

Page 2

Project: Ingagane 275 kV plan 8 ODate: Tue 21/10/12

Page 3: ID Task Task Name Duration Start Finish ...

F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S'20 Nov 29 '20 Dec 06 '20 Dec 13 '20 Dec 20 '20 Dec 27 '21 Jan 03 '21 Jan 10

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Manual Progress

Page 3

Project: Ingagane 275 kV plan 8 ODate: Tue 21/10/12

Page 4: ID Task Task Name Duration Start Finish ...

F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S'20 Nov 29 '20 Dec 06 '20 Dec 13 '20 Dec 20 '20 Dec 27 '21 Jan 03 '21 Jan 10

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Manual Progress

Page 4

Project: Ingagane 275 kV plan 8 ODate: Tue 21/10/12

Page 5: ID Task Task Name Duration Start Finish ...

S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S'21 Jan 10 '21 Jan 17 '21 Jan 24 '21 Jan 31 '21 Feb 07 '21 Feb 14 '21 Feb 21

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Manual Progress

Page 5

Project: Ingagane 275 kV plan 8 ODate: Tue 21/10/12

Page 6: ID Task Task Name Duration Start Finish ...

S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S'21 Jan 10 '21 Jan 17 '21 Jan 24 '21 Jan 31 '21 Feb 07 '21 Feb 14 '21 Feb 21

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Manual Progress

Page 6

Project: Ingagane 275 kV plan 8 ODate: Tue 21/10/12

Page 7: ID Task Task Name Duration Start Finish ...

S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M'21 Feb 28 '21 Mar 07 '21 Mar 14 '21 Mar 21 '21 Mar 28 '21 Apr 04 '21 Apr 11

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Manual Progress

Page 7

Project: Ingagane 275 kV plan 8 ODate: Tue 21/10/12

Page 8: ID Task Task Name Duration Start Finish ...

S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M'21 Feb 28 '21 Mar 07 '21 Mar 14 '21 Mar 21 '21 Mar 28 '21 Apr 04 '21 Apr 11

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Manual Progress

Page 8

Project: Ingagane 275 kV plan 8 ODate: Tue 21/10/12

Page 9: ID Task Task Name Duration Start Finish ...

M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T'21 Apr 11 '21 Apr 18 '21 Apr 25 '21 May 02 '21 May 09 '21 May 16 '21 May 23

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Manual Progress

Page 9

Project: Ingagane 275 kV plan 8 ODate: Tue 21/10/12

Page 10: ID Task Task Name Duration Start Finish ...

M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T'21 Apr 11 '21 Apr 18 '21 Apr 25 '21 May 02 '21 May 09 '21 May 16 '21 May 23

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Manual Progress

Page 10

Project: Ingagane 275 kV plan 8 ODate: Tue 21/10/12

Page 11: ID Task Task Name Duration Start Finish ...

T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W'21 May 23 '21 May 30 '21 Jun 06 '21 Jun 13 '21 Jun 20 '21 Jun 27 '21 Jul 04

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Manual Progress

Page 11

Project: Ingagane 275 kV plan 8 ODate: Tue 21/10/12

Page 12: ID Task Task Name Duration Start Finish ...

T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W'21 May 23 '21 May 30 '21 Jun 06 '21 Jun 13 '21 Jun 20 '21 Jun 27 '21 Jul 04

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Manual Progress

Page 12

Project: Ingagane 275 kV plan 8 ODate: Tue 21/10/12

Page 13: ID Task Task Name Duration Start Finish ...

W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T'21 Jul 04 '21 Jul 11 '21 Jul 18 '21 Jul 25 '21 Aug 01 '21 Aug 08 '21 Aug 15

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Manual Progress

Page 13

Project: Ingagane 275 kV plan 8 ODate: Tue 21/10/12

Page 14: ID Task Task Name Duration Start Finish ...

W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T'21 Jul 04 '21 Jul 11 '21 Jul 18 '21 Jul 25 '21 Aug 01 '21 Aug 08 '21 Aug 15

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Manual Progress

Page 14

Project: Ingagane 275 kV plan 8 ODate: Tue 21/10/12

Page 15: ID Task Task Name Duration Start Finish ...

T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F'21 Aug 15 '21 Aug 22 '21 Aug 29 '21 Sep 05 '21 Sep 12 '21 Sep 19 '21 Sep 26

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Manual Progress

Page 15

Project: Ingagane 275 kV plan 8 ODate: Tue 21/10/12

Page 16: ID Task Task Name Duration Start Finish ...

T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F'21 Aug 15 '21 Aug 22 '21 Aug 29 '21 Sep 05 '21 Sep 12 '21 Sep 19 '21 Sep 26

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Manual Progress

Page 16

Project: Ingagane 275 kV plan 8 ODate: Tue 21/10/12

Page 17: ID Task Task Name Duration Start Finish ...

F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S'21 Sep 26 '21 Oct 03 '21 Oct 10 '21 Oct 17 '21 Oct 24 '21 Oct 31 '21 Nov 07

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Manual Progress

Page 17

Project: Ingagane 275 kV plan 8 ODate: Tue 21/10/12

Page 18: ID Task Task Name Duration Start Finish ...

F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S'21 Sep 26 '21 Oct 03 '21 Oct 10 '21 Oct 17 '21 Oct 24 '21 Oct 31 '21 Nov 07

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Manual Progress

Page 18

Project: Ingagane 275 kV plan 8 ODate: Tue 21/10/12

Page 19: ID Task Task Name Duration Start Finish ...

S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S'21 Nov 07 '21 Nov 14 '21 Nov 21 '21 Nov 28 '21 Dec 05 '21 Dec 12 '21 Dec 19

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Manual Progress

Page 19

Project: Ingagane 275 kV plan 8 ODate: Tue 21/10/12

Page 20: ID Task Task Name Duration Start Finish ...

S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S'21 Nov 07 '21 Nov 14 '21 Nov 21 '21 Nov 28 '21 Dec 05 '21 Dec 12 '21 Dec 19

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Manual Progress

Page 20

Project: Ingagane 275 kV plan 8 ODate: Tue 21/10/12

Page 21: ID Task Task Name Duration Start Finish ...

S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M'21 Dec 26 '22 Jan 02 '22 Jan 09 '22 Jan 16 '22 Jan 23 '22 Jan 30 '22 Feb 06

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Manual Progress

Page 21

Project: Ingagane 275 kV plan 8 ODate: Tue 21/10/12

Page 22: ID Task Task Name Duration Start Finish ...

S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M'21 Dec 26 '22 Jan 02 '22 Jan 09 '22 Jan 16 '22 Jan 23 '22 Jan 30 '22 Feb 06

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Manual Progress

Page 22

Project: Ingagane 275 kV plan 8 ODate: Tue 21/10/12

Page 23: ID Task Task Name Duration Start Finish ...

275 kV trfr 4

275 kV trfr 4

275 kV trfr 4

M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T'22 Feb 06 '22 Feb 13 '22 Feb 20 '22 Feb 27 '22 Mar 06 '22 Mar 13 '22 Mar 20

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Manual Progress

Page 23

Project: Ingagane 275 kV plan 8 ODate: Tue 21/10/12

Page 24: ID Task Task Name Duration Start Finish ...

M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T'22 Feb 06 '22 Feb 13 '22 Feb 20 '22 Feb 27 '22 Mar 06 '22 Mar 13 '22 Mar 20

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Manual Progress

Page 24

Project: Ingagane 275 kV plan 8 ODate: Tue 21/10/12

Page 25: ID Task Task Name Duration Start Finish ...

275 kV trfr 4

275 kV trfr 4

275 kV trfr 4

275 kV trfr 4

T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W'22 Mar 20 '22 Mar 27 '22 Apr 03 '22 Apr 10 '22 Apr 17 '22 Apr 24 '22 May 01

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Manual Progress

Page 25

Project: Ingagane 275 kV plan 8 ODate: Tue 21/10/12

Page 26: ID Task Task Name Duration Start Finish ...

T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W'22 Mar 20 '22 Mar 27 '22 Apr 03 '22 Apr 10 '22 Apr 17 '22 Apr 24 '22 May 01

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Manual Progress

Page 26

Project: Ingagane 275 kV plan 8 ODate: Tue 21/10/12

Page 27: ID Task Task Name Duration Start Finish ...

275 kV trfr 4

275 kV trfr 4

275 kV trfr 4

275 kV trfr 4

275 kV trfr 4

275 kV Danskraal 1

275 kV Danskraal 1

275 kV Danskraal 1

W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T'22 May 01 '22 May 08 '22 May 15 '22 May 22 '22 May 29 '22 Jun 05 '22 Jun 12

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Manual Progress

Page 27

Project: Ingagane 275 kV plan 8 ODate: Tue 21/10/12

Page 28: ID Task Task Name Duration Start Finish ...

W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T'22 May 01 '22 May 08 '22 May 15 '22 May 22 '22 May 29 '22 Jun 05 '22 Jun 12

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Manual Progress

Page 28

Project: Ingagane 275 kV plan 8 ODate: Tue 21/10/12

Page 29: ID Task Task Name Duration Start Finish ...

275 kV trfr 4

275 kV trfr 4

275 kV trfr 4

275 kV Danskraal 1

275 kV Danskraal 1

275 kV Danskraal 1

275 kV Danskraal 1

T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F'22 Jun 12 '22 Jun 19 '22 Jun 26 '22 Jul 03 '22 Jul 10 '22 Jul 17 '22 Jul 24

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Manual Progress

Page 29

Project: Ingagane 275 kV plan 8 ODate: Tue 21/10/12

Page 30: ID Task Task Name Duration Start Finish ...

T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F'22 Jun 12 '22 Jun 19 '22 Jun 26 '22 Jul 03 '22 Jul 10 '22 Jul 17 '22 Jul 24

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Manual Progress

Page 30

Project: Ingagane 275 kV plan 8 ODate: Tue 21/10/12

Page 31: ID Task Task Name Duration Start Finish ...

275 kV trfr 4

275 kV trfr 4

275 kV Danskraal 1

275 kV Danskraal 1

275 kV Danskraal 1

275 kV Danskraal 1

275 kV Danskraal 1

F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S'22 Jul 24 '22 Jul 31 '22 Aug 07 '22 Aug 14 '22 Aug 21 '22 Aug 28 '22 Sep 04

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Manual Progress

Page 31

Project: Ingagane 275 kV plan 8 ODate: Tue 21/10/12

Page 32: ID Task Task Name Duration Start Finish ...

F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S'22 Jul 24 '22 Jul 31 '22 Aug 07 '22 Aug 14 '22 Aug 21 '22 Aug 28 '22 Sep 04

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Manual Progress

Page 32

Project: Ingagane 275 kV plan 8 ODate: Tue 21/10/12

Page 33: ID Task Task Name Duration Start Finish ...

275 kV Danskraal 1

275 kV Danskraal 1

275 kV Danskraal 1

275 kV Bloukrans 1

275 kV Bloukrans 1

275 kV Bloukrans 1

S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S'22 Sep 04 '22 Sep 11 '22 Sep 18 '22 Sep 25 '22 Oct 02 '22 Oct 09 '22 Oct 16

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Manual Progress

Page 33

Project: Ingagane 275 kV plan 8 ODate: Tue 21/10/12

Page 34: ID Task Task Name Duration Start Finish ...

S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S'22 Sep 04 '22 Sep 11 '22 Sep 18 '22 Sep 25 '22 Oct 02 '22 Oct 09 '22 Oct 16

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Manual Progress

Page 34

Project: Ingagane 275 kV plan 8 ODate: Tue 21/10/12

Page 35: ID Task Task Name Duration Start Finish ...

275 kV Danskraal 1

275 kV Danskraal 1

275 kV Bloukrans 1

275 kV Bloukrans 1

275 kV Bloukrans 1

275 kV Bloukrans 1

S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M'22 Oct 23 '22 Oct 30 '22 Nov 06 '22 Nov 13 '22 Nov 20 '22 Nov 27 '22 Dec 04

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Manual Progress

Page 35

Project: Ingagane 275 kV plan 8 ODate: Tue 21/10/12

Page 36: ID Task Task Name Duration Start Finish ...

S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M'22 Oct 23 '22 Oct 30 '22 Nov 06 '22 Nov 13 '22 Nov 20 '22 Nov 27 '22 Dec 04

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Manual Progress

Page 36

Project: Ingagane 275 kV plan 8 ODate: Tue 21/10/12

Page 37: ID Task Task Name Duration Start Finish ...

275 kV Danskraal 1

275 kV Bloukrans 1

275 kV Bloukrans 1

275 kV Bloukrans 1

275 kV Bloukrans 1

275 kV Bloukrans 1

M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T'22 Dec 04 '22 Dec 11 '22 Dec 18 '22 Dec 25 '23 Jan 01 '23 Jan 08 '23 Jan 15

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Manual Progress

Page 37

Project: Ingagane 275 kV plan 8 ODate: Tue 21/10/12

Page 38: ID Task Task Name Duration Start Finish ...

M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T'22 Dec 04 '22 Dec 11 '22 Dec 18 '22 Dec 25 '23 Jan 01 '23 Jan 08 '23 Jan 15

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Manual Progress

Page 38

Project: Ingagane 275 kV plan 8 ODate: Tue 21/10/12

Page 39: ID Task Task Name Duration Start Finish ...

275 kV Bloukrans 1

275 kV Bloukrans 1

275 kV Bloukrans 1

275 kV Bloedrivier 4

275 kV Bloedrivier 4

275 kV Bloedrivier 4

T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W'23 Jan 15 '23 Jan 22 '23 Jan 29 '23 Feb 05 '23 Feb 12 '23 Feb 19 '23 Feb 26

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Manual Progress

Page 39

Project: Ingagane 275 kV plan 8 ODate: Tue 21/10/12

Page 40: ID Task Task Name Duration Start Finish ...

T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W'23 Jan 15 '23 Jan 22 '23 Jan 29 '23 Feb 05 '23 Feb 12 '23 Feb 19 '23 Feb 26

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Manual Progress

Page 40

Project: Ingagane 275 kV plan 8 ODate: Tue 21/10/12

Page 41: ID Task Task Name Duration Start Finish ...

275 kV Bloukrans 1

275 kV Bloukrans 1

275 kV Bloedrivier 4

275 kV Bloedrivier 4

275 kV Bloedrivier 4

275 kV Bloedrivier 4

W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T'23 Feb 26 '23 Mar 05 '23 Mar 12 '23 Mar 19 '23 Mar 26 '23 Apr 02 '23 Apr 09

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Manual Progress

Page 41

Project: Ingagane 275 kV plan 8 ODate: Tue 21/10/12

Page 42: ID Task Task Name Duration Start Finish ...

W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T'23 Feb 26 '23 Mar 05 '23 Mar 12 '23 Mar 19 '23 Mar 26 '23 Apr 02 '23 Apr 09

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Manual Progress

Page 42

Project: Ingagane 275 kV plan 8 ODate: Tue 21/10/12

Page 43: ID Task Task Name Duration Start Finish ...

275 kV Bloukrans 1

275 kV Bloedrivier 4

275 kV Bloedrivier 4

275 kV Bloedrivier 4

275 kV Bloedrivier 4

275 kV Bloedrivier 4

T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F'23 Apr 09 '23 Apr 16 '23 Apr 23 '23 Apr 30 '23 May 07 '23 May 14 '23 May 21

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Manual Progress

Page 43

Project: Ingagane 275 kV plan 8 ODate: Tue 21/10/12

Page 44: ID Task Task Name Duration Start Finish ...

T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F'23 Apr 09 '23 Apr 16 '23 Apr 23 '23 Apr 30 '23 May 07 '23 May 14 '23 May 21

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Manual Progress

Page 44

Project: Ingagane 275 kV plan 8 ODate: Tue 21/10/12

Page 45: ID Task Task Name Duration Start Finish ...

275 kV Bloedrivier 4

275 kV Bloedrivier 4

275 kV Bloedrivier 4

275 kV Bloedrivier 5

275 kV Bloedrivier 5

F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S'23 May 21 '23 May 28 '23 Jun 04 '23 Jun 11 '23 Jun 18 '23 Jun 25 '23 Jul 02

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Manual Progress

Page 45

Project: Ingagane 275 kV plan 8 ODate: Tue 21/10/12

Page 46: ID Task Task Name Duration Start Finish ...

275 kV Bloedrivier 5F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S

'23 May 21 '23 May 28 '23 Jun 04 '23 Jun 11 '23 Jun 18 '23 Jun 25 '23 Jul 02

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Manual Progress

Page 46

Project: Ingagane 275 kV plan 8 ODate: Tue 21/10/12

Page 47: ID Task Task Name Duration Start Finish ...

275 kV Bloedrivier 4

275 kV Bloedrivier 4

275 kV Bloedrivier 5

275 kV Bloedrivier 5

S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S'23 Jul 02 '23 Jul 09 '23 Jul 16 '23 Jul 23 '23 Jul 30 '23 Aug 06 '23 Aug 13

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Manual Progress

Page 47

Project: Ingagane 275 kV plan 8 ODate: Tue 21/10/12

Page 48: ID Task Task Name Duration Start Finish ...

275 kV Bloedrivier 5

275 kV Bloedrivier 5

S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S'23 Jul 02 '23 Jul 09 '23 Jul 16 '23 Jul 23 '23 Jul 30 '23 Aug 06 '23 Aug 13

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Manual Progress

Page 48

Project: Ingagane 275 kV plan 8 ODate: Tue 21/10/12

Page 49: ID Task Task Name Duration Start Finish ...

275 kV Bloedrivier 4

275 kV Bloedrivier 5

275 kV Bloedrivier 5

S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M'23 Aug 20 '23 Aug 27 '23 Sep 03 '23 Sep 10 '23 Sep 17 '23 Sep 24 '23 Oct 01

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Manual Progress

Page 49

Project: Ingagane 275 kV plan 8 ODate: Tue 21/10/12

Page 50: ID Task Task Name Duration Start Finish ...

275 kV Bloedrivier 5

275 kV Bloedrivier 5

275 kV Bloedrivier 5

S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M'23 Aug 20 '23 Aug 27 '23 Sep 03 '23 Sep 10 '23 Sep 17 '23 Sep 24 '23 Oct 01

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Manual Progress

Page 50

Project: Ingagane 275 kV plan 8 ODate: Tue 21/10/12

Page 51: ID Task Task Name Duration Start Finish ...

M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T'23 Oct 01 '23 Oct 08 '23 Oct 15 '23 Oct 22 '23 Oct 29 '23 Nov 05 '23 Nov 12

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Manual Progress

Page 51

Project: Ingagane 275 kV plan 8 ODate: Tue 21/10/12

Page 52: ID Task Task Name Duration Start Finish ...

275 kV Bloedrivier 5

275 kV Bloedrivier 5

275 kV Bloedrivier 5

275 kV bypass

275 kV bypass

275 kV bypass

M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T'23 Oct 01 '23 Oct 08 '23 Oct 15 '23 Oct 22 '23 Oct 29 '23 Nov 05 '23 Nov 12

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Manual Progress

Page 52

Project: Ingagane 275 kV plan 8 ODate: Tue 21/10/12

Page 53: ID Task Task Name Duration Start Finish ...

T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W'23 Nov 12 '23 Nov 19 '23 Nov 26 '23 Dec 03 '23 Dec 10 '23 Dec 17 '23 Dec 24

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Manual Progress

Page 53

Project: Ingagane 275 kV plan 8 ODate: Tue 21/10/12

Page 54: ID Task Task Name Duration Start Finish ...

275 kV Bloedrivier 5

275 kV Bloedrivier 5

275 kV bypass

275 kV bypass

275 kV bypass

275 kV bypass

275 kV bypass

T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W'23 Nov 12 '23 Nov 19 '23 Nov 26 '23 Dec 03 '23 Dec 10 '23 Dec 17 '23 Dec 24

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Manual Progress

Page 54

Project: Ingagane 275 kV plan 8 ODate: Tue 21/10/12

Page 55: ID Task Task Name Duration Start Finish ...

W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T'23 Dec 24 '23 Dec 31 '24 Jan 07 '24 Jan 14 '24 Jan 21 '24 Jan 28 '24 Feb 04

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Manual Progress

Page 55

Project: Ingagane 275 kV plan 8 ODate: Tue 21/10/12

Page 56: ID Task Task Name Duration Start Finish ...

275 kV Bloedrivier 5

275 kV bypass

275 kV bypass

275 kV bypass

275 kV bypass

275 kV bypass

W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T'23 Dec 24 '23 Dec 31 '24 Jan 07 '24 Jan 14 '24 Jan 21 '24 Jan 28 '24 Feb 04

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Manual Progress

Page 56

Project: Ingagane 275 kV plan 8 ODate: Tue 21/10/12

Page 57: ID Task Task Name Duration Start Finish ...

T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F'24 Feb 04 '24 Feb 11 '24 Feb 18 '24 Feb 25 '24 Mar 03 '24 Mar 10 '24 Mar 17

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Manual Progress

Page 57

Project: Ingagane 275 kV plan 8 ODate: Tue 21/10/12

Page 58: ID Task Task Name Duration Start Finish ...

275 kV bypass

275 kV bypass

275 kV bypass

T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F'24 Feb 04 '24 Feb 11 '24 Feb 18 '24 Feb 25 '24 Mar 03 '24 Mar 10 '24 Mar 17

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Manual Progress

Page 58

Project: Ingagane 275 kV plan 8 ODate: Tue 21/10/12