1 Integrated Corridor Management (ICM) I I - - 880 Integrated Corridor Management: 880 Integrated Corridor Management: Building on Existing Planning Efforts Building on Existing Planning Efforts Presentation to Presentation to Arterial Operations Committee Arterial Operations Committee July 13, 2010 July 13, 2010

Transcript of I-880 Integrated Corridor Management...2010/07/13  · ACCMA, AC Transit, & BART (March 2008) 10...

Page 1: I-880 Integrated Corridor Management...2010/07/13  · ACCMA, AC Transit, & BART (March 2008) 10 Identified ICM Strategies (Past Efforts) • Information Sharing/Distribution-511 Traveler

1

Integrated Corridor Management (ICM)

II--880 Integrated Corridor Management:880 Integrated Corridor Management:Building on Existing Planning EffortsBuilding on Existing Planning Efforts

Presentation to Presentation to

Arterial Operations CommitteeArterial Operations Committee

July 13, 2010July 13, 2010

Page 2: I-880 Integrated Corridor Management...2010/07/13  · ACCMA, AC Transit, & BART (March 2008) 10 Identified ICM Strategies (Past Efforts) • Information Sharing/Distribution-511 Traveler

2

Integrated Corridor Management (ICM)

Background: What is ICM?Background: What is ICM?

Page 3: I-880 Integrated Corridor Management...2010/07/13  · ACCMA, AC Transit, & BART (March 2008) 10 Identified ICM Strategies (Past Efforts) • Information Sharing/Distribution-511 Traveler

3

TodayToday’’s Corridors: Independent Systemss Corridors: Independent Systems

• Efforts to date to “reduce congestion” have focused on optimization of individual systems

• There have been significant investments in ITS

• There are tremendous opportunities to integrate operations to manage total corridor capacity

Arterial Signal

Systems

Freeway

Systems

Bus

Systems

Rail

Systems

Page 4: I-880 Integrated Corridor Management...2010/07/13  · ACCMA, AC Transit, & BART (March 2008) 10 Identified ICM Strategies (Past Efforts) • Information Sharing/Distribution-511 Traveler

4

Schematic of an Integrated CorridorSchematic of an Integrated Corridor

Local Jurisdiction 2 – Traffic Signal System

Local Jurisdiction 1 – Traffic Signal System

Bus Company – AVL system

State DOT – Freeway Management System

Regional Rail Agency – Train Management System

P

Local Jurisdiction 2 – Traffic Signal System

Local Jurisdiction 1 – Traffic Signal System

Bus Company – AVL system

State DOT – Freeway Management System

Regional Rail Agency – Train Management System

P

Page 5: I-880 Integrated Corridor Management...2010/07/13  · ACCMA, AC Transit, & BART (March 2008) 10 Identified ICM Strategies (Past Efforts) • Information Sharing/Distribution-511 Traveler

5

Integrated Corridor Management (ICM)

The IThe I--880 Corridor880 Corridor

Page 6: I-880 Integrated Corridor Management...2010/07/13  · ACCMA, AC Transit, & BART (March 2008) 10 Identified ICM Strategies (Past Efforts) • Information Sharing/Distribution-511 Traveler

6

Corridor LimitsCorridor Limits

southern limit TBD by SCVTA (potentially I-280)

Page 7: I-880 Integrated Corridor Management...2010/07/13  · ACCMA, AC Transit, & BART (March 2008) 10 Identified ICM Strategies (Past Efforts) • Information Sharing/Distribution-511 Traveler

7

II--880 ICM Vision880 ICM Vision

I-880 ICM will help the existing highway,

arterial, and transit (rail, ferry, and bus)

elements along the corridor, operated by

separate agencies, to function as an

integrated transportation network,

enhancing safety, efficiency,

mobility and transportation choicesfor all travelers under all conditions.

Page 8: I-880 Integrated Corridor Management...2010/07/13  · ACCMA, AC Transit, & BART (March 2008) 10 Identified ICM Strategies (Past Efforts) • Information Sharing/Distribution-511 Traveler

8

Regional and Local PartnershipsRegional and Local Partnerships

Congestion Mitigation & Air

Quality Program

CTC &

Local Alternative Transportation

Improvement Program

Page 9: I-880 Integrated Corridor Management...2010/07/13  · ACCMA, AC Transit, & BART (March 2008) 10 Identified ICM Strategies (Past Efforts) • Information Sharing/Distribution-511 Traveler

9

Existing Plans and ReportsExisting Plans and Reports

• Corridor System Management Plan (CSMP) for I-880, Caltrans (June 2010)

• Central Alameda County Local Alternative Transportation Improvement Program (Central LATIP) – Final Project Initiation Document, ACCMA (November 2009)

• State Route 84 Historic Parkway Local Alternative Transportation Improvement Program (SR-84 LATIP) – Final Project Initiation Document, ACTA (October 2009)

• I-880 Integrated Corridor Management Final Concept of Operation[s] (ICM ConOps), Caltrans, MTC, ACCMA, AC Transit, & BART (March 2008)

• I-880 Integrated Corridor Management (ICM) Final System Requirements, Caltrans, MTC, ACCMA, AC Transit, & BART (March 2008)

Page 10: I-880 Integrated Corridor Management...2010/07/13  · ACCMA, AC Transit, & BART (March 2008) 10 Identified ICM Strategies (Past Efforts) • Information Sharing/Distribution-511 Traveler

10

Identified ICM Strategies Identified ICM Strategies (Past Efforts)(Past Efforts)

• Information Sharing/Distribution

-511 Traveler Information

• Improve Operational Efficiency of Network

Junctions and Interfaces

-Adaptive Ramp Metering & BRT

• Accommodate/Promote Cross-Network Route and

Modal Shifts

-Interagency Coordination & Information Sharing

• Manage Capacity Using Real-Time Traffic

Information

-Park and Ride Facilities

Page 11: I-880 Integrated Corridor Management...2010/07/13  · ACCMA, AC Transit, & BART (March 2008) 10 Identified ICM Strategies (Past Efforts) • Information Sharing/Distribution-511 Traveler

11

Integrated Corridor Management (ICM)

Where do we go from here?Where do we go from here?

Page 12: I-880 Integrated Corridor Management...2010/07/13  · ACCMA, AC Transit, & BART (March 2008) 10 Identified ICM Strategies (Past Efforts) • Information Sharing/Distribution-511 Traveler

12

Integrated Corridor Management (ICM)

Coordinated DeploymentCoordinated Deployment

of ICM Strategiesof ICM Strategies

Where do we go from here?Where do we go from here?

Page 13: I-880 Integrated Corridor Management...2010/07/13  · ACCMA, AC Transit, & BART (March 2008) 10 Identified ICM Strategies (Past Efforts) • Information Sharing/Distribution-511 Traveler

13

Integrated Corridor Management (ICM)

Coordinated DeploymentCoordinated Deployment

of ICM Strategiesof ICM Strategies

Where do we go from here?Where do we go from here?

Current Current

RFPRFP

Page 14: I-880 Integrated Corridor Management...2010/07/13  · ACCMA, AC Transit, & BART (March 2008) 10 Identified ICM Strategies (Past Efforts) • Information Sharing/Distribution-511 Traveler

14

RFP Approach: RFP Approach: Segment CentricSegment Centric

Central Ala. (LATIP)

Davis to SR-92

Southern Ala. (LATIP)

SR-92 to Dixon Ld.

Northern Alameda

I-580/I-80 to Davis

Santa Clara

Dixon Ld. to [TBD]

(to I-280, ~10 miles)

Coordinated

Deployment

Page 15: I-880 Integrated Corridor Management...2010/07/13  · ACCMA, AC Transit, & BART (March 2008) 10 Identified ICM Strategies (Past Efforts) • Information Sharing/Distribution-511 Traveler

15

RFP Desired OutcomesRFP Desired Outcomes

Local Local

ObjectivesObjectivesSystem System

EfficiencyEfficiency

SafetySafety

Coordinated

Deployment

Page 16: I-880 Integrated Corridor Management...2010/07/13  · ACCMA, AC Transit, & BART (March 2008) 10 Identified ICM Strategies (Past Efforts) • Information Sharing/Distribution-511 Traveler

16

RFP Scope of WorkRFP Scope of Work

1. Corridor-Wide Process:ICM Strategy Selection &

Systems Engineering Documentation

(requirements before construction)

2. Northern Ala. Segment:Construction of Trailblazer Signs +

Other Incident Management Strategies

Coordinated

Deployment

Phase

Phase

(MTC funded)

(pending MTC

funding appr.)

Page 17: I-880 Integrated Corridor Management...2010/07/13  · ACCMA, AC Transit, & BART (March 2008) 10 Identified ICM Strategies (Past Efforts) • Information Sharing/Distribution-511 Traveler

17

RFP Scope of Work: RFP Scope of Work: Phase 1Phase 1(MTC funded)(MTC funded)

I. Coordinate among stakeholders

II. Develop sustainable strategies for the Corridor

III. Prepare systems engineering documentation

Coordinated

Deployment

Page 18: I-880 Integrated Corridor Management...2010/07/13  · ACCMA, AC Transit, & BART (March 2008) 10 Identified ICM Strategies (Past Efforts) • Information Sharing/Distribution-511 Traveler

18

I. Stakeholder CoordinationI. Stakeholder CoordinationCoordinated

Deployment

Page 19: I-880 Integrated Corridor Management...2010/07/13  · ACCMA, AC Transit, & BART (March 2008) 10 Identified ICM Strategies (Past Efforts) • Information Sharing/Distribution-511 Traveler

19

II. Strategy SelectionII. Strategy Selection

Segment Segment

ApproachApproach

Single Strategy Single Strategy

oror

Suite of Suite of

Strategies?Strategies?

Temporal Classification

• Incident Management

• Peak Hour/Recurrent Traffic Mgmt(e.g., corridor-wide adaptive ramp metering)

User-group Classification

• Managers & Operators (e.g., detection, surveillance)

Freeway, Arterial, Transit

• Travelers (e.g., traveler information systems)

Motorists, Transit Riders, Pedestrians, Freight

• The Community / Environment

Residents, Businesses

Coordinated

Deployment

Page 20: I-880 Integrated Corridor Management...2010/07/13  · ACCMA, AC Transit, & BART (March 2008) 10 Identified ICM Strategies (Past Efforts) • Information Sharing/Distribution-511 Traveler

20

II. Strategy Selection (cont.): For ArterialsII. Strategy Selection (cont.): For Arterials

Signal Timing Coordination• Demand responsive (traffic responsive, adaptive, etc.)

• Red light running detection-signal coordination

• Preemption (TSP, EVP, etc.)

Dynamic Facility Management• Smart parking (CMS with park-and-ride availability, reservation, etc.)

• Bus lanes with intermittent priority (BLIPs)

Traveler Information• Advanced decision support (online traffic/transit information)

• En route decision support (CMS on fwy approach, trailblazer signs)

Coordinated

Deployment

Page 21: I-880 Integrated Corridor Management...2010/07/13  · ACCMA, AC Transit, & BART (March 2008) 10 Identified ICM Strategies (Past Efforts) • Information Sharing/Distribution-511 Traveler

21

III. Systems Engineering DocumentationIII. Systems Engineering Documentation

• Project Study Report

• Expanded Concept of Operations

• Systems Engineering Management Plan

• Implementation Plan

• Other documents required for deployment

Coordinated

Deployment

Page 22: I-880 Integrated Corridor Management...2010/07/13  · ACCMA, AC Transit, & BART (March 2008) 10 Identified ICM Strategies (Past Efforts) • Information Sharing/Distribution-511 Traveler

22

RFP Approach: RFP Approach: Segment CentricSegment Centric

Central Ala. (LATIP)

Davis to SR-92

Southern Ala. (LATIP)

SR-92 to Dixon Ld.

Northern Alameda

I-580/I-80 to Davis

Santa Clara

Dixon Ld. to [TBD]

Coordinated

Deployment

Page 23: I-880 Integrated Corridor Management...2010/07/13  · ACCMA, AC Transit, & BART (March 2008) 10 Identified ICM Strategies (Past Efforts) • Information Sharing/Distribution-511 Traveler

23

RFP Scope of Work: RFP Scope of Work: Phase 2Phase 2Funding dependent on cost estimates and MTC budget approvalFunding dependent on cost estimates and MTC budget approvalCoordinated

Deployment

• Focus on Northern Ala. Segment

• Construction of trailblazer signs

+ other strategies for incident/traffic mgmt

• Scope includes:

– PSR, ConOps, SEMP

– Environmental reviews

– Permits

– Detailed designs

– Construction

TURN LEFT

TO I-880

trailblazer sign

(not to scale)

Page 24: I-880 Integrated Corridor Management...2010/07/13  · ACCMA, AC Transit, & BART (March 2008) 10 Identified ICM Strategies (Past Efforts) • Information Sharing/Distribution-511 Traveler

24

Subsequent WorkSubsequent Work

• Central Alameda Segment

Expected Timeline*: Construction in 2012

Funding: Dependent on avail. and approval of LATIP

• Southern Alameda Segment

Funding and Timeline: TBD

• Santa Clara Segment

Funding and Timeline: TBD

Coordinated

Deployment

Page 25: I-880 Integrated Corridor Management...2010/07/13  · ACCMA, AC Transit, & BART (March 2008) 10 Identified ICM Strategies (Past Efforts) • Information Sharing/Distribution-511 Traveler

25

RFP Procurement ScheduleRFP Procurement Schedule

Summer 2010Stakeholder Review of Draft RFP

Winter 2010Begin Contract

Winter 2010MTC Commission Approval

Summer/Fall 2010Release RFP

Coordinated

Deployment

Page 26: I-880 Integrated Corridor Management...2010/07/13  · ACCMA, AC Transit, & BART (March 2008) 10 Identified ICM Strategies (Past Efforts) • Information Sharing/Distribution-511 Traveler

26

RFP MilestonesRFP Milestones

Mid-Year 2011Complete feasibility studies

Start Phase 2

Winter 2011Complete Phase 1, part of Phase 2*

Fall/Winter 2011Complete PSR, ConOps, SEMP

Winter 2010Start Phase 1

* Excludes the following Phase 2 work:

environmental reviews, construction documentation, actual construction

Coordinated

Deployment

Page 27: I-880 Integrated Corridor Management...2010/07/13  · ACCMA, AC Transit, & BART (March 2008) 10 Identified ICM Strategies (Past Efforts) • Information Sharing/Distribution-511 Traveler

27

II--880 Corridor Stakeholder Survey880 Corridor Stakeholder SurveyCoordinated

Deployment

Page 28: I-880 Integrated Corridor Management...2010/07/13  · ACCMA, AC Transit, & BART (March 2008) 10 Identified ICM Strategies (Past Efforts) • Information Sharing/Distribution-511 Traveler

28

QuestionsQuestions

Stella SoStella So

I-880 ICM Project Manager

[email protected]

(510) 817-5724

Coordinated