Honeoye Elementary School The school encompasses K-12 in one building.
Honeoye Falls-Lima Central School District...2016 Additions and Alterations Phase 2 Project...
Transcript of Honeoye Falls-Lima Central School District...2016 Additions and Alterations Phase 2 Project...
Honeoye Falls-Lima Central School District
2016 Additions and Alterations Phase 2
Project Update
November 2019
2016 Additions and Alterations Phase 2
Referendum Value $29,986,084
Incidental Budget $ 4,632,681
Construction Contingency $ 1,564,311
Contracts Awarded $22,848,873
State Contract $ 940,219
Construction Contingency Budget Update
•Construction Contingency Budget $1,564,311
•Additional State Contract Purchases $ 176,223
•Approved Change Orders $ 432,812
•Remaining Construction Contingency $ 955,276
•Construction Project is 67% Complete
•Contingency Budget is 49% spent
•Contract allowance approved totals $0
•Project Team is following approximately $553,015 in pending issues
2016 Additions and Alterations Phase 2
Project Status/Schedule Update
Manor Intermediate
• Construction in Rooms 302, 110, 108
and 106 is nearly complete.
• Finishes are ongoing in the
Discovery Lab and the Art Room.
Transportation Building
• Concrete is being saw cut for the
foundations work and underslab
utilities.
Senior High School
• Construction continues in the Flex Space and
Conference Room on the 2nd Floor.
• The Art Room is scheduled to be completed
by December 13th.
• The Cafeteria underslab plumbing is roughed
in and the underslab electrical work is on
going.
• Showers are being roughed in the Girls Pool
Locker Room.
• The concrete sidewalks have been installed
in the Courtyard and continue to be installed
outside the Main Entrance.
2016 Additions and Alterations Phase 2
Project Status/Schedule Update
Lima Intermediate
• The elevator shaft is ready for the
elevator install to begin and
construction continues in room 206
and 210.
• The concrete steps have been
installed and the handrails are being
install.
Middle School
• The Projection Screen has been installed,
wired and the work for the proscenium is being
scheduled to be completed over Christmas
Break.
• The frame for the Alumni Hall of Fame screen
has been turned over to D’Agostino and shop
drawings are being prepared for review.
2016 Additions and Alterations Phase 2
What to expect in the upcoming Month
Manor Intermediate
• Construction will be completed in
rooms 302, 110, 108, 106, Discovery
Lab and The Art Room and these
room will be turned over to the District.
• The next set of rooms that will be
available for construction is being
worked out with Campus and the
District.
Senior High School
• The Art Room will be completed and
turned over to the District.
• Saw-cutting and under slab plumbing
and electrical work will be installed in the
Kitchen. Concrete will be installed, and
framing will continue.
2016 Additions and Alterations Phase 2
What to expect in the upcoming Month
Middle School
• The projection screen proscenium is
scheduled to be installed over
Christmas Break.
Lima Elementary
• Elevator work will continue along with
work in room 210, 206 and 116.
Honeoye Falls-Lima Central School District
2016 Additions and Alterations Phase 2
Progress Photos
Art Room 120 – High School
Art Room 120A – High School
Flex Space 201A– High School
Cafeteria – High School
Kitchen – High School
2nd Floor Addition (201A) – High SchoolGirls Pool Locker Room – High School
12/9/2019Girls Pool Locker Room – High School
12/9/2019Library Stairwell – High School
Courtyard – High School
Art Room – High School Art Room – Manor
Art Room – Manor
Discovery Lab – Manor
Discovery Lab - Manor
Faculty Lounge- Manor
Sensory Room – Manor
Work Room– Manor
SP. ED. Resource – Manor
Existing Bays - Transportation Center
Existing Bays – Transportation Center
12/9/2019Main Entrance Stairs – Lima