Honeoye Falls-Lima Central School District...2016 Additions and Alterations Phase 2 Project...

29
Honeoye Falls - Lima Central School District 2016 Additions and Alterations Phase 2 Project Update November 2019

Transcript of Honeoye Falls-Lima Central School District...2016 Additions and Alterations Phase 2 Project...

Page 1: Honeoye Falls-Lima Central School District...2016 Additions and Alterations Phase 2 Project Status/Schedule Update Manor Intermediate •Construction in Rooms 302, 110, 108 and 106

Honeoye Falls-Lima Central School District

2016 Additions and Alterations Phase 2

Project Update

November 2019

Page 2: Honeoye Falls-Lima Central School District...2016 Additions and Alterations Phase 2 Project Status/Schedule Update Manor Intermediate •Construction in Rooms 302, 110, 108 and 106

2016 Additions and Alterations Phase 2

Referendum Value $29,986,084

Incidental Budget $ 4,632,681

Construction Contingency $ 1,564,311

Contracts Awarded $22,848,873

State Contract $ 940,219

Page 3: Honeoye Falls-Lima Central School District...2016 Additions and Alterations Phase 2 Project Status/Schedule Update Manor Intermediate •Construction in Rooms 302, 110, 108 and 106

Construction Contingency Budget Update

•Construction Contingency Budget $1,564,311

•Additional State Contract Purchases $ 176,223

•Approved Change Orders $ 432,812

•Remaining Construction Contingency $ 955,276

•Construction Project is 67% Complete

•Contingency Budget is 49% spent

•Contract allowance approved totals $0

•Project Team is following approximately $553,015 in pending issues

Page 4: Honeoye Falls-Lima Central School District...2016 Additions and Alterations Phase 2 Project Status/Schedule Update Manor Intermediate •Construction in Rooms 302, 110, 108 and 106

2016 Additions and Alterations Phase 2

Project Status/Schedule Update

Manor Intermediate

• Construction in Rooms 302, 110, 108

and 106 is nearly complete.

• Finishes are ongoing in the

Discovery Lab and the Art Room.

Transportation Building

• Concrete is being saw cut for the

foundations work and underslab

utilities.

Senior High School

• Construction continues in the Flex Space and

Conference Room on the 2nd Floor.

• The Art Room is scheduled to be completed

by December 13th.

• The Cafeteria underslab plumbing is roughed

in and the underslab electrical work is on

going.

• Showers are being roughed in the Girls Pool

Locker Room.

• The concrete sidewalks have been installed

in the Courtyard and continue to be installed

outside the Main Entrance.

Page 5: Honeoye Falls-Lima Central School District...2016 Additions and Alterations Phase 2 Project Status/Schedule Update Manor Intermediate •Construction in Rooms 302, 110, 108 and 106

2016 Additions and Alterations Phase 2

Project Status/Schedule Update

Lima Intermediate

• The elevator shaft is ready for the

elevator install to begin and

construction continues in room 206

and 210.

• The concrete steps have been

installed and the handrails are being

install.

Middle School

• The Projection Screen has been installed,

wired and the work for the proscenium is being

scheduled to be completed over Christmas

Break.

• The frame for the Alumni Hall of Fame screen

has been turned over to D’Agostino and shop

drawings are being prepared for review.

Page 6: Honeoye Falls-Lima Central School District...2016 Additions and Alterations Phase 2 Project Status/Schedule Update Manor Intermediate •Construction in Rooms 302, 110, 108 and 106

2016 Additions and Alterations Phase 2

What to expect in the upcoming Month

Manor Intermediate

• Construction will be completed in

rooms 302, 110, 108, 106, Discovery

Lab and The Art Room and these

room will be turned over to the District.

• The next set of rooms that will be

available for construction is being

worked out with Campus and the

District.

Senior High School

• The Art Room will be completed and

turned over to the District.

• Saw-cutting and under slab plumbing

and electrical work will be installed in the

Kitchen. Concrete will be installed, and

framing will continue.

Page 7: Honeoye Falls-Lima Central School District...2016 Additions and Alterations Phase 2 Project Status/Schedule Update Manor Intermediate •Construction in Rooms 302, 110, 108 and 106

2016 Additions and Alterations Phase 2

What to expect in the upcoming Month

Middle School

• The projection screen proscenium is

scheduled to be installed over

Christmas Break.

Lima Elementary

• Elevator work will continue along with

work in room 210, 206 and 116.

Page 8: Honeoye Falls-Lima Central School District...2016 Additions and Alterations Phase 2 Project Status/Schedule Update Manor Intermediate •Construction in Rooms 302, 110, 108 and 106

Honeoye Falls-Lima Central School District

2016 Additions and Alterations Phase 2

Progress Photos

Page 9: Honeoye Falls-Lima Central School District...2016 Additions and Alterations Phase 2 Project Status/Schedule Update Manor Intermediate •Construction in Rooms 302, 110, 108 and 106

Art Room 120 – High School

Page 10: Honeoye Falls-Lima Central School District...2016 Additions and Alterations Phase 2 Project Status/Schedule Update Manor Intermediate •Construction in Rooms 302, 110, 108 and 106

Art Room 120A – High School

Page 11: Honeoye Falls-Lima Central School District...2016 Additions and Alterations Phase 2 Project Status/Schedule Update Manor Intermediate •Construction in Rooms 302, 110, 108 and 106

Flex Space 201A– High School

Page 12: Honeoye Falls-Lima Central School District...2016 Additions and Alterations Phase 2 Project Status/Schedule Update Manor Intermediate •Construction in Rooms 302, 110, 108 and 106

Cafeteria – High School

Page 13: Honeoye Falls-Lima Central School District...2016 Additions and Alterations Phase 2 Project Status/Schedule Update Manor Intermediate •Construction in Rooms 302, 110, 108 and 106

Kitchen – High School

Page 14: Honeoye Falls-Lima Central School District...2016 Additions and Alterations Phase 2 Project Status/Schedule Update Manor Intermediate •Construction in Rooms 302, 110, 108 and 106

2nd Floor Addition (201A) – High SchoolGirls Pool Locker Room – High School

Page 15: Honeoye Falls-Lima Central School District...2016 Additions and Alterations Phase 2 Project Status/Schedule Update Manor Intermediate •Construction in Rooms 302, 110, 108 and 106

12/9/2019Girls Pool Locker Room – High School

Page 16: Honeoye Falls-Lima Central School District...2016 Additions and Alterations Phase 2 Project Status/Schedule Update Manor Intermediate •Construction in Rooms 302, 110, 108 and 106

12/9/2019Library Stairwell – High School

Page 17: Honeoye Falls-Lima Central School District...2016 Additions and Alterations Phase 2 Project Status/Schedule Update Manor Intermediate •Construction in Rooms 302, 110, 108 and 106

Courtyard – High School

Page 18: Honeoye Falls-Lima Central School District...2016 Additions and Alterations Phase 2 Project Status/Schedule Update Manor Intermediate •Construction in Rooms 302, 110, 108 and 106

Art Room – High School Art Room – Manor

Page 19: Honeoye Falls-Lima Central School District...2016 Additions and Alterations Phase 2 Project Status/Schedule Update Manor Intermediate •Construction in Rooms 302, 110, 108 and 106

Art Room – Manor

Page 20: Honeoye Falls-Lima Central School District...2016 Additions and Alterations Phase 2 Project Status/Schedule Update Manor Intermediate •Construction in Rooms 302, 110, 108 and 106

Discovery Lab – Manor

Page 21: Honeoye Falls-Lima Central School District...2016 Additions and Alterations Phase 2 Project Status/Schedule Update Manor Intermediate •Construction in Rooms 302, 110, 108 and 106

Discovery Lab - Manor

Page 22: Honeoye Falls-Lima Central School District...2016 Additions and Alterations Phase 2 Project Status/Schedule Update Manor Intermediate •Construction in Rooms 302, 110, 108 and 106

Faculty Lounge- Manor

Page 23: Honeoye Falls-Lima Central School District...2016 Additions and Alterations Phase 2 Project Status/Schedule Update Manor Intermediate •Construction in Rooms 302, 110, 108 and 106

Sensory Room – Manor

Page 24: Honeoye Falls-Lima Central School District...2016 Additions and Alterations Phase 2 Project Status/Schedule Update Manor Intermediate •Construction in Rooms 302, 110, 108 and 106

Work Room– Manor

Page 25: Honeoye Falls-Lima Central School District...2016 Additions and Alterations Phase 2 Project Status/Schedule Update Manor Intermediate •Construction in Rooms 302, 110, 108 and 106

SP. ED. Resource – Manor

Page 26: Honeoye Falls-Lima Central School District...2016 Additions and Alterations Phase 2 Project Status/Schedule Update Manor Intermediate •Construction in Rooms 302, 110, 108 and 106

Existing Bays - Transportation Center

Page 27: Honeoye Falls-Lima Central School District...2016 Additions and Alterations Phase 2 Project Status/Schedule Update Manor Intermediate •Construction in Rooms 302, 110, 108 and 106

Existing Bays – Transportation Center

Page 28: Honeoye Falls-Lima Central School District...2016 Additions and Alterations Phase 2 Project Status/Schedule Update Manor Intermediate •Construction in Rooms 302, 110, 108 and 106

12/9/2019Main Entrance Stairs – Lima

Page 29: Honeoye Falls-Lima Central School District...2016 Additions and Alterations Phase 2 Project Status/Schedule Update Manor Intermediate •Construction in Rooms 302, 110, 108 and 106

Honeoye Falls-Lima Central School

District

Questions?