HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14...

78
JAN? 2005 S. I Lic HERCULES Corrective Action Plan Revision 01 Hercules Incorporated 613 West 7th Street Hattiesburg, Mississippi 39401 FILE COPY Prepared for: Hercules Incorporated 1313 North Market Street Wilmington, Delaware 19894 Prepared kv. Groundwater & Envfronmental Services, Inc. 5961 Live Oak Parkway, Suite B Norcross, Georgia 30093 /% /- f S. Duncan, Senkfr Project Manager 20 January 2005

Transcript of HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14...

Page 1: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

JAN? 2005

S.I Lic

HERCULESCorrective Action Plan Revision 01

Hercules Incorporated613 West 7th Street

Hattiesburg, Mississippi 39401

FILE COPYPreparedfor:

Hercules Incorporated1313 North Market Street

Wilmington, Delaware 19894

Prepared kv.Groundwater & Envfronmental Services, Inc.

5961 Live Oak Parkway, Suite BNorcross, Georgia 30093

/% /-f S. Duncan,

Senkfr Project Manager

20 January 2005

Page 2: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

TABLE OF CONTENTS

1.0 INTRODUCTION1

1.1 OBJECTIVES/RATIONALE 1

1.2 FACILITYSETTINGAND OVERVIEW 2

1.3 PURPOSE AND SCOPE 3

2.0 CONCEPTUAL DESIGN 4

2.1 SLUDGE PITS 4

2.2 LANDFILL4

2.3 GROUNDWATER 4

2.4 GREEN’S CREEK 4

3.0 SYSTEM COMPONENTS 5

3.1 SLUDGE PITS 5

3.2 LANDFILL5

3.3 GROUNDWATER 6

3.4 GREEN’S CREEK 7

4.0 SCHEDULE8

4.1 DEED RESTRICTIONS 8

4.2 GRO UND WA TER AND SURFA CE WA TER MONITORING 8

5.0 REMEDIAL GOALS 9

6.0 OPERATION AND MONITORING PLAN 10

7.0 PERFORMANCE MONITORING PLAN 11

GES i HERCULES - 01/20/2005

Page 3: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

8.0 COMPLIANCE MONITORING PLAN

8.1 SLUDGE PITS

8.2 LANDFILL

8.3 GROUNDWATER

8.4 GREEN’S CREEK

9.0 CONTINGENCY PLAN

9.1 SLUDGE PITS

9.2 LANDFILL

9.3 GROUNDWATER

9.4 GREEN’S CREEK

10.0 QUALITYASSURANCE PROJECTPLAN

11.0 HEALTHAND SAFETYPLAN

LIST OF FIGURES

1 Site Location Map

2 Site Map

LIST OF TABLES

1 Analytical Requirements by Area

2 Groundwater Monitoring Schedule

3 Screening Criteria and Reporting Limits

LIST OF APPENDICES

A

B

Dioxathion Sampling and Analysis Protocol

Health and Safety Plan

14

15

16

17

12

12

12

12

12

14

14

14

()

GES 11 HERCULES - Y1/2O/2OO5

Page 4: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

1.0 INTRODUCTION

On behalf of Hercules Incorporated (Hercules), Groundwater and EnviromnentalServices, Inc. (GES) has prepared this Corrective Action Plan (CAP) for theHercules facility located at 613 West 7th Street in Hattiesburg, Mississippi. A SiteLocation Map is included as Figure 1.

This CAP has been prepared in response to the Mississippi Department ofEnvironmental Quality (MDEQ) request in a letter dated 12 August 2004. The 12August 2004 MDEQ letter and subsequent GES response letter dated 28September 2004 provided further clarification on the 16 July 2004 RemedialAction Evaluation (RAE) and the implications on the preparation of this CAP.GES has incorporated the intent of these communications in this CAP.

1.1 BACKGROUND

As presented in the referenced RAE prepared by Eco-Systems, Inc. (EcoSystems), the following provides a background summary of site investigationsconducted at the facility.

Site investigations at the Hercules facility in Hattiesburg Mississippi, which wereconducted between April 1999 and November 2003, are discussed in the InterimGroundwater Monitoring Report (Eco-Systems, January 2003), the Hercules SiteInvestigation Report (Eco-Systems, April 2003), and the Supplemental SiteInvestigation Report (Eco-Systems, November 2004). The findings of the siteinvestigations include the following:

• Detection of volatile organic compounds (VOCs) in groundwater atconcentrations above Target Remediation Goals (TRGs) in the Landfilland Groundwater areas of the site;

• Delineation of the lateral limits of the Landfill based on geophysicalinvestigation;

• Presence of VOCs and Dioxathion at concentrations less than TRGs insurface water and sediment samples collected from Green’s Creek, and;

• Presence of VOCs arid Dioxathion in one of three groundwater monitoringwells located hydraulically downgradient of the sludge pits. It should benoted that Dioxathion has not been detected above the TRGs in this area.

Site investigations indicated that neither VOCs nor Dioxathion, are migrating viagroundwater or surface water onto off-site properties. Some of the VOCsdetected in Green’s Creek were detected in samples collected from the location

GES 1 HERCULES —1/20/2004

Page 5: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

where Green’s Creek enters the property, which indicates that, at least, some ofthe VOCs are due to upstream, off-site, sources.

1.2 FACILITY SETTING AND OVER VIEW

As presented in the RAE prepared by Eco-Systems, the following presents thefacility settings and overview.

The Hercules facility is located on approximately 200 acres of land north of WestSeventh Street in Hattiesburg, Forest County, Mississippi. More specifically, theSite is located in Sections 4 and 5, Township 4 North, Range 13 West, just northof Hattiesburg, Mississippi (Figure 1). The facility has been in operation since1923. The facility is bordered to the north by Highway 42 and beyond which isIllinois-Central & Gulf Railroad, along with various residential and commercialproperties. The southern property boundary is bordered by 7th Avenue; and byRoseland Park cemetery and Zeon Chemical Corporation to the south-southwest.Across from these locations are residential areas. The eastern and westernboundaries are bordered by sparsely populated residential and commercial areas.

QThe facility’s historical operations consisted of wood grinding, shredding,extraction, fractionation, refining, distillation, and processing of rosin from pinetree stumps. Historically, over 250 products were produced from the above-referenced operations and included: modified resins, polyamides, ketene dimmer,crude tall oil wax emulsions, and Delnav, an agricultural miticide. Structures atthe facility include offices, a laboratory, a powerhouse, production buildings, awastewater treatment plant, settling ponds, a landfill, and central loading andpackaging areas.

Previous investigations at the Hercules facility have centered on efforts todetermine whether the miticide, Dioxathion, was present in site soil andgroundwater. The work has included soil, groundwater, surface water, and streamsediment sampling and analysis. The work has also included geophysicalinvestigation to delineate the limits of the landfill and to investigate the potentialfor buried metal in a location identified by the MDEQ. The results of previousinvestigations are discussed in reports, which have been submitted to the MDEQ:

1. Site Inspection Report, B&V Waste Science and Technology Corp., April,1993.

2. Work Plan for Well Installation, Bonner Analytical Testing Company;June, 1997.

C 3. Installation, Sampling, and Analysis Report, Bonner Analytical Testing$ Company; December, 1997.

GES 2 HERCULES -1/20/2004

Page 6: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

4. Quarterly Monitor Well Sampling Event Reports, Bonner AnalyticalTesting Company; June, 1998 through October, 1998.

5. Site Investigation Work Plan, Eco-Systems, Inc., February 1999.6. Interim Groundwater Monitoring Report, Eco-Systems, Inc. January 2003.7: Site Investigation Report, Eco-Systems, Inc. April 2003.8. Work Plan for Supplemental Site Investigation, Eco-Systems, Inc. June

2003.9. Supplemental Site Investigation Report, Eco-Systems, Inc. November

2003.10. Remedial Action Evaluation, Eco-Systems, Inc. July 2004.

The information discussed in the listed documents indicates that sources, sourcearea concentrations, and vertical and horizontal extent of groundwater containingconstituents of concern have been defined sufficiently for corrective actionplanning purposes. The existing data does not indicate that the site poses asignificant threat to human health and the environment in its current use as achemical production facility. However, if changes in land use occur or additionalinformation is obtained, the current risk scenario for the site could also change.

1.3 PURPOSE AND SCOPE

The purpose of this CAP is to present the regarding the reflected remedial optionfor each of the four areas of the site included in the RAE. The scope of this CAPis presented in the following sections:

• Section 2.0 presents the completed design per area;• Section 3.0 presents the components per area;• Section 4.0 presents the schedule for each component;• Section 5.0 presents the Remedial Goals;• Section 6.0 presents the Operation & Monitoring Plan for the fencing;• Section 7.0 presents the Performance Monitoring Plan for MNA;• Section 8.0 presents the Compliance Monitoring Plan for each area;• Section 9.0 presents the Contingency Plan for each area;• Section 10.0 presents Quality Assurance Project Plan considerations per

area, and;• Section 11.0 presents Health and Safety Plan considerations.

GES 3 HERCULES —1/20/2004

Page 7: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

2.0 CONCEPTUAL DESIGN

The conceptual design of this CAP is comprised of Monitored NaturalAttenuation (MNA) and institutional controls consisting of fencing and deedrestrictions. There is limited historical groundwater quality data available foreach of the areas included in this CAP. As such, it is necessary to collect acomprehensive round of groundwater samples for the period of one (1)-year priorto defining the MNA parameters to be analyzed and the wells to be sampled forMNA parameters. This will ensure that a MNA program is designed to beeffective and cost-efficient. The specific conceptual design of each of the areas isincluded below.

2.1 SLUDGE PITS

For the sludge pits, this CAP presents MNA combined with a deed restriction torestrict future land use of the sludge pits and nearby surrounding areas and themaintenance of the existing chain-link fence surrounding the facility to limitcurrent and future exposure to the Sludge Pits.

The MNA element of this design will provide monitoring to ensure thatcontaminated groundwater does not migrate at unacceptable levels from thesludge pits thereby eliminating or reducing risk to human health and theenvironment. Limiting current and future exposure to the Sludge Pits willeliminate or reduce risk to human health and the environment by preventing usageof the site for any purpose other than industrial.

2.2 LANDFILL

For the landfill, this CAP presents MNA combined with a deed restriction torestrict future land use in the landfill area.

The MNA element of this design will provide monitoring to ensure thatcontaminated groundwater does not migrate at unacceptable levels from thelandfill thereby eliminating or reducing risk to human health and the environment.Limiting current and future exposure to the landfill area will eliminate or reducerisk to human health and the environment by preventing usage of the site for anypurpose other than industrial.

GES 4 HERCULES —1/20/2004

Page 8: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

2.3 GROUNDWATER

For Groundwater, this CAP presents MNA combined with deed restrictions torestrict future land use in the area of groundwater containing VOCs in excess ofthe TRGs.

The MNA element of this design will provide monitoring to ensure thatcontaminated groundwater does not migrate from the site at unacceptable levelsthereby eliminating or reducing risk to human health and the environment.Limiting current and future exposure to the Groundwater area will eliminate orreduce risk to human health and the environment by preventing usage of the sitefor any purpose other than industrial.

2.4 GREEN’S CREEK

For Green’s Creek, this CAP presents MNA combined with a deed restriction torestrict future land use of Green’s Creek and the maintenance of the existing chainlink fence surrounding the facility to limit current and future exposure to Green’sCreek.

The A element of this design will provide monitonng to ensure thatcontaminated water does not migrate at unacceptable levels from Green’s Creekthereby eliminating or reducing risk to human health and the environment.Limiting current and future exposure to Green’s Creek will eliminate or reducerisk to human health and the environment by preventing usage of the site for anypurpose other than industrial.

GES 5 HERCULES —1/20/2004

Page 9: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

3.0 SYSTEM COMPONENTS

The primary components of this CAP consist of groundwater and surface watermonitoring networks, deed restrictions and fencing. All work will be completedin accordance with the Environmental Investigations Standard OperatingProcedures and Quality Assurance Manual (EISOPQAM) dated November 2001.Specifically, groundwater sampling via low-flow/low-stress purging and surfacewater sampling techniques will be completed in accordance with the methodsdescribed in the Work Plan Supplemental Site Investigation Report (Eco-Systems,June 2003) which was submitted to and approved by MDEQ. The locations ofgroundwater and surface water monitoring locations are presented on Figure 2.The analytical requirements by area are presented on Table 1. The specificcomponents of each area are described below.

3.1 SLUDGE PITS

The components of this CAP for the Sludge Pits consist of the following:

• Deed amendment to restrict land use to commercial/industrial andeliminate potential future residential land use;

• Maintenance of an existing chain-link fence around the facility and;

• Collection of groundwater samples from an existing monitoring wellnetwork consisting of MW-2, MW-3, MW-4, MW-b and MW-il. Thesamples will be analyzed for VOCs via USEPA SW846-8260 andDioxathion (cis- and trans-) and Dioxenethion via the DioxathionSampling and Analysis Protocol (Appendix A). This method is acombination of USEPA SW846-3 510/8321 using HPLC-PDA analyses.

3.2 LANDFILL

The system components of this CAP for the Landfill consist of the following:

• Deed amendment to restrict land use to commercial/industrial andeliminate potential future residential land use, and;

• Collection and analysis of groundwater samples from a monitoring wellnetwork consisting of existing wells MW-5 and MW-6 and proposed wells

GES 6 HERCULES —1/20/2004

Page 10: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

C) MW-12, MW-13 and MW-14. The samples will be analyzed for VOCsvia USEPA SW846-8260.

Proposed monitoring wells MW-12, MW-13 and MW-14 will be installedas permanent two-inch diameter wells as follows:

o Soil borings will be installed via; Hollow Stem Auger (HSA)drilling rig;

o Permanent wells will be installed in the soil borings to bracket theobserved water table with a 10-foot screened interval; which willbe constructed to monitor the same water-bearing zone asmonitoring wells MW-5 and MW-6.

o The estimated total depths of these monitoring wells is 20-feetbelow ground surface.

3.3 GROUNDWATER

(: The components of this CAP for Groundwater consist of the following:

• Deed amendment to restrict land use to commercial/industrial andeliminate potential future residential land use, and;

• Collection of groundwater samples from a monitoring well networkconsisting of existing monitoring wells MW-7, MW-8 and MW-9,proposed monitoring wells MW-15, MW-16 and MW-17 and proposedcompliance wells MW-18 and MW-19. It should be noted that anadditional well is proposed, for a total of three proposed new wells, so thatpermanent wells are installed at both locations of water samples collectedfrom GP-2 and GP-4. The samples will be analyzed for VOCs via USEPASW846-8260 and the Dioxathion Sampling and Analysis Protocol(Appendix A). This method is a combination of USEPA SW846-3510/8321 using RPLC-PDA analyses.

• Proposed monitoring wells MW-15 through MW-19 will be installed aspermanent two-inch diameter wells as follows:

o Soil borings will be installed via; Hollow Stem Auger (HSA)drilling rig;

o Permanent wells will be installed in the soil borings to bracket theobserved water table with a 10-foot screen interval; which will be

GE5 7 HERCULES —1/20/2004

Page 11: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

constructed to monitor the same water-bearing zone as monitoringwells MW-7, MW-8 and MW-9.

o The estimated total depths of those monitoring wells is 20-feetbelow ground surface.

3.4 GREEN’S CREEK

The components of this CAP for Green’s Creek consist of the following:

• Deed amendment to restrict land use to commerciallindustrial andeliminate potential future land use;

• Maintenance of an existing chain-link fence around the facility, and;

• Collection and analysis of surface water samples from a surface watermonitoring network consisting of CM-00 through CM-05. The sampleswill be analyzed for VOCs via USEPA SW846-8260 and .the DioxathionSampling and Analysis Protocol (Appendix A). This method is acombination of USEPA SW846-35 10/832 1 using RPLC-PDA analyses.

GES 8 HERCULES —1/20/2004

Page 12: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

4.0 SCHEDULE

C)

The CAP presented herein will be initiated upon approval by MDEQ. Agroundwater monitoring schedule is presented as Table 2. An implementationschedule and duration of implementation for each component is described below.

4.1 DEED RESTRICTIONS

Deed restrictions for each of the four areas will be initiated within 30-daysfollowing the date in which the first round of groundwater sampling results aresubmitted to MDEQ. It is currently envisioned that the necessary documentationof the deed restrictions will be provided in the first annual CAP ImplementationReport.

4.2 GRO UND WA TER AND SURFA CE WA TER MONITORING

Implementation of groundwater and surface water monitoring well beimplemented within 90-days following MDEQ’s approval of this CAP. Themonitoring will be completed on a quarterly basis for the period of two years.Quarterly sampling reports will be submitted within 45-days after the conclusionof each field sampling event. The quarterly reports will be inclusive of laboratoryanalytical reports, analytical summary and screening tables, andconclusions/recommendations regarding any necessary action during the nextquarterly monitoring period. At the conclusion of eight (8) quarterly monitoringevents, an evaluation of the need for further monitoring and a schedule for suchmonitoring will be proposed to MDEQ at that time.

GES 9 HERCULES —1/20/2004

Page 13: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

5.0 REMEDIAL GOALS

The overall remedial goals (RGs) of this CAP are to restrict future land use viadeed restrictions, limit current and future potential exposure via fencing anddocument long-term natural attenuation of groundwater constituents via MNA.The following presents the rationale for determining when the remedial goalshave been achieved.

The RG of restricting future land use will be considered complete once the deedrestrictions are complete and the supporting documentation has been provided toMDEQ.

The RG of limiting current potential exposure considered complete since existingfencing is protective of exposure to the Sludge Pits and Green’s Creek. For theRG of limiting potential future exposure an inspection and maintenance will beimplemented to ensure the integrity of the fencing.

The RG of documenting long-term natural attenuation of groundwaterconstituents will be considered complete once a sufficient amount of MNA datahas been compiled and evaluated to support the that groundwater constituents aredecreasing over time and the extent of the groundwater plume(s) are reducing inareal extent over time.

GES 10 HERCULES —1/20/2004

Page 14: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

6.0 OPERA TIONAND MONITORING PLAN

(j

The only component of this CAP that requires an Operation and Monitoring(O&M) requirement is inspection of fencing. Annual inspection and maintenancewill be implemented to limit future potential exposure to these areas.Documentation of the annual inspection and maintenance will be included inAnnual Monitoring Reports. Barring any unforeseen circumstances, anynecessary repairs to the fencing will be completed within 90-days following anyobservance.

GES 11 HERCULES —1/20/2004

Page 15: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

7.0 PERFORMANCE MONITORING PLAN

The CAP component that requires a Performance Monitoring Plan is MNA.MNA will be evaluated based on groundwater constituent concentrations andareal distribution of groundwater plume(s) over time.

Implementation of this Performance Monitoring Plan will be documented inquarterly monitoring reports that will be submitted to MDEQ within 45-daysfollowing the completion of each monitoring event (see Section 4.2). In addition,annual monitoring reports will be submitted to document the quarterly activitiesconducted during that year and will provide all data generated to date.

The annual monitoring reports will contain copies of the analytical reports, chain-of-custody forms, and a discussion of the data evaluation. Liquid-level datacollected during groundwater sampling will be used to determine groundwaterelevations and flow direction. The groundwater analytical data will be tabulatedand screened against the MDEQ TRGs. Groundwater potentiometric and qualitymaps will be prepared for the main constituents detected in excess of theirrespective TRGs to facilitate an evaluation of groundwater plume areal extentover time. Groundwater constituent trend charts will be prepared to facilitate anevaluation of groundwater constituent concentrations over time.

GES 12 HERCULES —1/20/2004

Page 16: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

8.0 COMPLIANCE MONITORING PLAN

During the implementation of this CAP, compliance monitoring for the MNAcomponent will be conducted in each of these areas. The compliance monitoringis required to ensure that contingent actions are undertaken if a certain “trigger” ismet. This “trigger” is identified as a detection of a contaminant at a concentrationin excess of the MDEQ TRG concentrations in a downgradient well for three (3)consecutive sampling events.

Exceedance of this “trigger” could indicate the potential that groundwatercontamination may be expanding or migrating from restricted use areas. As such,monitoring wells MW-6, MW-7, MW-9, MW-13 and MW-16 will also beconsidered during compliance monitoring evaluations in addition to thedowngradient monitoring wells identified in the following subsections.

8.1 SLUDGE PITS

Compliance monitoring in the Sludge Pits area will consist of evaluating theanalytical data generated from downgradient monitonng wells MW-4, MW-band MW-il. The data generated from these monitoring wells will provide anevaluation of groundwater quality emanating from the Sludge Pits area andtowards Green’s Creek.

• 8.2 LANDFILL

Compliance monitoring in the landfill area will consist of evaluating theanalytical data generated from downgradient monitoring wells MW-5, MW-12and MW-i4. The data generated from these monitoring wells will provide anevaluation of groundwater quality emanating from the landfill area and towardsGreen’s Creek.

8.3 GROUNDWATER

Compliance monitoring in the Groundwater area will consist of evaluating theanalytical data generated from downgradient monitoring wells MW- 14 (landfillwell) and MW- 15. The data generated from these wells will provide an

O evaluation of groundwater quality emanating from the Groundwater area andtowards Green’s Creek.

GES 13 HERCULES —1/20/2004

Page 17: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

8.4 GREEN’S CREEK

Compliance monitoring for Green’s Creek will consist of evaluating the analyticaldata in downgradient surface water sampling locations CM-03, CM-04 and CM-05. The data generated from those surface water monitoring locations willprovide an evaluation of surface water in the creek on-site and quality of surfacewater leaving the property. The data from these points will be compared to theupgradient monitoring points CM-OO, CM-O1 and CM-02.

GES 14 HERCULES —1/20/2004

Page 18: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

9.0 CONTINGENCY PLAN

The following Contingency Plan has been prepared and will be enacted should thespecific “trigger” condition identified in Section 8.0 is met. The overallcontingency plan approach is that if MDEQ or Hercules suspects that a “trigger”condition has been met, a meeting will be held between both parties (and/orrepresentatives) to facilitate an objective evaluation of the situation including; thedata, the potential risk to human health and the environment, current technologies,prior to initiation of any of the specified contingency actions identified below. Aspecific plan for each area is described below.

9.1 SLUDGE PITS

Contingent measures will be necessary if it is determined that a “trigger”condition has been met in monitoring wells MW-4, MW- 10 and MW-il. A“trigger” condition in these wells could indicate that a release of constituents fromthe Sludge Pits area may have occurred. If deemed necessary, the contingent planfor the Sludge Pits area consists of installation of the cap as detailed in the RAE.

Upon approval of this CAP, Hercules will purchase financial assurance in theamount of $758K to cover the costs of installing a cap on the Sludge Pits shouldthe contingent measure become necessary. The financial assurance will nameMDEQ as a beneficiary should Hercules become unable to cover the potentialfinancial responsibility of this measure.

9.2 LANDFILL

Contingent measures may be necessary if it is determined that a “trigger”condition has been met in monitoring wells MW-5, MW-12 and MW-14. A“trigger” condition in these wells could indicate that a release of constituents fromthe landfill area may have occurred. Pending an evaluation of the circumstancesregarding a “trigger” condition, the contingent plan for the landfill area couldconsist of either in-situ chemical oxidation (ISCO) or the horizontal containmentplan as detailed in the RAE.

9.3 GROUNDWATER

Contingent measures will be necessary if it is determined that a “trigger”condition has been met in monitoring wells MW-5, MW-12 and MW-14. A

GES 15 HERCULES —1/20/2004

Page 19: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

“trigger” condition in these wells could indicate that a significant source ofgroundwater constituents is present in the Groundwater area. If deemednecessary, the contingent plan for the Groundwater consists of ISCO as detailedin the RAE.

Upon approval of this CAP, Hercules will purchase financial assurance in theamount of $669K to cover the costs of implementing ISCO in the Groundwaterarea should the contingent measure become necessary. The financial assurancewill name MDEQ as a beneficiary should Hercules become unable to cover thepotential financial responsibility of this measure.

9.4 GREEN’S CREEK

Contingent measures will be necessary if it is determined that a “trigger”condition has been met in downgradient surface water monitoring points CM-03,CM-04 and CM-05. However, the concentrations in CM-03, CM-04 and CM-05will be compared to the constituents observed in upgradient surface water pointsCM-OO, CM-Ol and CM-2 prior to concluding that a “trigger” condition has beenmet. A sustained significant increase in constituent concentrations in thedowngradient surface water monitoring points would indicate that a release ofconstituents from the Sludge Pits area may have occurred. If deemed necessary,the contingent plan for Green’s Creek will consist of addressing the Sludge Pitsarea as detailed in Section 9.1.

As previously discussed, upon approval of this CAP, Hercules will purchasefinancial assurance in the amount of $758K to cover the costs of installing a capon the Sludge Pits should the contingent measure become necessary. Thefinancial assurance will name MDEQ as a beneficiary should Hercules becomeunable to cover the potential financial responsibility of this measure.

GES 16 HERCULES —1/20/2004

Page 20: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

10.0 QUALITYASSURANCE PROJECT PLAN

The following Quality Assurance Project Plan (QAPP) considerations have beenprepared for the MNA component of this CAP. Specifically, these considerationshave been made to assure the quality of the analytical data to be generated issufficient to be used to evaluate groundwater quality trends and ensure thatimplementation of the CAP is protective of human health and the environment.All work will be completed in accordance with the Quality Provisions of SW846QAIQC Protocol and EPA Region IV EISOPQA dated November 2001.

The following field sampling QAPP considerations will be followed:

• Blind Field Duplicate samples will be collected at the rate of 1 per 10samples;

• Equipment field rinsate samples will be collected at the rate of 1 per fieldday per non-disposable equipment used;

• Trip blank samples will be analyzed at the rate of 1 per cooler containingsamples for VOC analysis.

The results of these samples will be tabulated and included in the AnnualMonitoring Reports.

The Data Quality Objectives (DQOs) for the groundwater data generated duringimplementation of this CAP will be the TRGs. The groundwater analyticalparameter list is provided as Table 3. This table also presents the TRGs and therespective laboratory analytical reporting limits. For those compounds where thescreening criteria are lower than the report limit (RL), the method detection limit(MDL) will be used. If detections are made between the RL and the MDL, theresulting detection will be j-flagged indicating that the detection is estimated. Itshould be noted, that this table also presents (in bold) the compounds with MDLsthat exceed the TRGs.

GES 17 HERCULES —1/20/2004

Page 21: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

11.0 HEALTHAND SAFETY PLAN

A Health & Safety Plan (HASP), consistent with the requirements of OSHA1910.120 Hazardous Waste Operations (Hazwoper) that has been prepared andfollowed by Eco-Systems, Inc. is included as Appendix B. The consultant(s)chosen to implement the CAP will be required to submit their own HASP toHercules and MDEQ prior to the implementation of the CAP. In addition, allfield personnel and subcontractors will be required to attend a HerculesIncorporated site-specific health and safety training meeting prior tocommencement of field activities.

GES 18 HERCULES —1/20/2004

Page 22: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

0

0

Page 23: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated
Page 24: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

SOURCE: USGS 7.5 MINUTE SERIESTOPOGRAPHIC QUADRANGLE 1982HATflESBURG. MISSISSIPPICONTOUR INTERVAL = 10’

I

-

I

DRAFrED BY:WAW. SiTE LOCATION MAP(N.J.)

HERCULES INCORPORATED613 WEST 7th STREET

HATTIESBURG, MISSISSIPPI

Groundwater & Environmental Services, Inc.5961 UVE OAK PKW’, SUItE B, NORCROSS, GEORGIA 3009

CHECKED BY:

IAT. 031” 20’ 24.78” NLONG. 089” 18’ 28.22” W

(PPPROXIMATE SITE COORDINATES)

NORTH

SCALE IN FEET DATE FIGURE

1 2000 10—29—04 1QUADRANGLE LOCA11ON

Page 25: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

r

©

saq

i

Page 26: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

Tables

Page 27: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

I’

0)

0

L00)

0

C.00)0.0

0

C,

0

C)0

CC

0

.00-B0

— x APPROXIMATE PROPERfl’ BOUNDARY

INTERMITTENT DRAINAGE DITCH

MONITORING WELL

MONITORING WELL—LANDFILL

MONITORING WELL—GROUNDWATER

MONITORING WELL—SLUDGE PITS

SAMPLE LOCATION—GREEN’S CREEKPROPOSED MONITORING WELL—GROUNDWATERPROPOSED MONITORING WELL—LANDFILL

- V.

S

&

&

S

$

LEGEND

RIDmAVcoMMERcL

ZEON CHEMILCORPORATION

TE:

E MAP PREPARED FROM ECO SYSTEMS INC DRAWINGTED MARCH 5, 2003.

D BY:LW. SITE MAPCi.)

HERCULES INCORPORATED613 WEST 7th STREET

HATTIESBIJEG, MISSISSIPPI

ED BY:

ED BY

Groundwater & Environmental Services, Inc.5961 LIVE OAK PKWY, SUITE B, NORCROSS, GEORGIA 3009

SCAI± IN I±hI(APPRoXIMATE)

450

DATE FIGURE

11—5—04 2

Page 28: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

Tab

le1

Ana

lytic

alR

equi

rem

ents

byA

rea

Her

cule

sIn

corp

orat

edF

acil

ity

Hat

tiesb

urg,

Mis

siss

ppi

Are

aA

naly

tica

lR

equi

rem

ents

Ana

lyti

cal

Met

hod

Slud

gePi

ts(1

)A

ppen

dix

IXV

olat

ileO

rgan

icC

ompo

unds

(1)

SW

846-

8260

(2)

Dio

xath

ion

(cis

-an

dtr

ans-

),D

ioxe

neth

ion

(2)

SW

846-

3510

/832

1,H

PLC

anal

ysis

Lan

dfill

(1)

App

endi

xIX

Vol

atil

eO

rgan

icC

ompo

unds

(1)

SW

846-

8260

Gro

undw

ater

(1)

App

endi

xIX

Vol

atil

eO

rgan

icC

ompo

unds

(1)

SW

846-

8260

(2)

Dio

xath

ion

(cis

-an

dtr

ans)

,D

ioxe

neth

ion

(2)

SW84

6-35

10/8

321,

HPL

Can

alys

is

Gre

ens

Cre

ek(1

)A

ppen

dix

IXV

olat

ileO

rgan

icC

ompo

unds

(1)

SW

846-

8260

(2)

Dio

xath

ion

(cis

-an

dtr

ans-

),D

ioxe

neth

ion

(2)

SW84

6-35

10/8

321,

HP

LC

anal

ysis

GE

S-

1/20

/200

5Pa

ge1

of1

HE

RC

UL

ES

-HA

TT

IES

BU

RG

,M

S

Page 29: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

Table 2

Groundwater Monitoring Schedule

Hercules Incorporated Facility

Hattiesburg, Mississippi

. SampleMonitoring Location Initial Monitoring ScheduleClassification

Liquid LevelsPiezometersTP-3 Groundwater Elevation QuarterlyTP-4 Groundwater Elevation QuarterlyTP-5 Groundwater Elevation QuarterlyTP-6 Groundwater Elevation Quarterly

P-7 Groundwater Elevation QuarterlyP-I I Groundwater Elevation Quarterly

Monitoring WellsMW-2 Groundwater Elevation QuarterlyMW-3 Groundwater Elevation QuarterlyMW-4 Groundwater Elevation QuarterlyMW-5 Groundwater Elevation QuarterlyMW-6 Groundwater Elevation QuarterlyMW-7 Groundwater Elevation QuarterlyMW-8 Groundwater Elevation QuarterlyMW-9 Groundwater Elevation QuarterlyMW-i 0 Groundwater Elevation QuarterlyMW-il Groundwater Elevation QuarterlyMW-12 Groundwater Elevation QuarterlyMW-13 Groundwater Elevation QuarterlyMW-l4 Groundwater Elevation QuarterlyMW- 15 Groundwater Elevation Quarterly1W- 16 Groundwater Elevation QuarterlyvIW-17 Groundwater Elevation Quarterly

MW- 18 Groundwater Elevation QuarterlyMW-19 Groundwater Elevation QuarterlyGree&s Creek Staff GaugesSG-l Groundwater Elevation QuarterlySG-2 Groundwater Elevation QuarterlySG-3 Groundwater Elevation QuarterlySG-4 Groundwater Elevation Quarterly

GES - 1/20/200 5 Page 1 of 2 HERCULES-HATTIESBURG, MS

Page 30: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

Table 2Groundwater Monitoring Schedule

Hercules Incorporated FacilityHattiesburg, Mississippi

. SampleMonitoring Location Initial Monitoring ScheduleClassification

Groundwater SamplingSludge PitsMW-2 Upgradient Well QuarterlyMW-3 Upgradient Well QuarterlyMW-4 Downgradient Well QuarterlyMW-i 0 Downgradient Well QuarterlyMW-Il Downgradient Well QuarterlyLandfillMW-5 Downgradient Well QuarterlyMW-6 Upgradient Well QuarterlyMW-12 P Upgradient Well QuarterlyMW-I 3 P Upgradient Well QuarterlyMW-14 P Downgradient Well QuarterlyGroundwaterMW-7 Upgradient Well QuarterlyMW-8 Downgradient Well QuarterlyMW-9 Upgradient Well QuarterlyMW-15 P Downgradient Well QuarterlyMW-I 6 P Downgradient Well QuarterlyMW-17 PMW-i 8 P Point of Compliance Well QuarterlyMW-19 P Point of Compliance Well QuarterlyGreen’s CreekCM-00 Upgradient Surface Water QuarterlyCM-Ol Upgradient Surface Water QuarterlyCM-02 Upgradient Surface Water QuarterlyCM-03 Downgradient Surface Water QuarterlyCM-04 Downgradient Surface Water QuarterlyCM-05 Downgradient Surface Water Quarterly

Notes:No Analytical Data Available

P - Proposed Monitoring WellInitial Monitoring Schedule proposed for the first 2 years of CAP implementation

GES - 1/20/2005 Page 2 of 2 HERCULES-HATrIESBURG, MS

Page 31: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

Table 3Screening Criteria and

Reporting LimitsHercules Incorporated Facility

Hattiesburg, Mississippi

Sample ID MDEQ TRGs Reporting Limit1Appendix IX Volatile Organic Compounds (VOCs) Method SW8260B (ugfL)Acetone 601 25Acetonitrile 125 40Acrolein (Propenal) 00416 10I.crylonitrile

- 0.0367 5.7Bennene 5 1.0Bromodichloromethane 0.168 0.14

rontoform 8.48 1.0Promomethane (Methyl bromide) 8.52 1.02-Butanone (Methyl ethyl ketone) 1,910 10Carbon dinsilfide 1,040 1.0Carbon tetrachloride 5 1.0Chlorobenzene 100 1.0Chloroethane 3.64 1.0Chloroform 0.155 0.37Chloromethane (Methyl Chloride) 1.43 1.0

bloroprene (1,3 Butadiene) 0.00696 1.0‘-Chioroprene (Allylchloridc) 1.43 1.0flibromochloromethane 0.126 0.51,2-Dibromo-3-chloropropane 0.2 0.47l,2-Dibromoethaoe (EDB) 0.0500 0.39

ibrornomethane (Methylcue bromide) 60.8 1.0trana-1,4—Dichloro-2-butene - 0.00135 0.78Pichlorodifluoromethane 348 1.01,1 Dichloroethane 798 1.01,2 Dichloroethane 5 1.01,lDichloroethene 7 1.0tie-’ 70 1.0

e 100 1.01.2 Dichloropropane 5 1.0is-1,3-Dicbloropropene 0.0842 1.0

Pans-1.3-Dichloropropene 0.0842 1.0Ethylbeozene 700 1.0Ethyl rnethacrylate 548 1.02-Hexanone 1,460 10,domethane (Methyl iodide) 1.0

Jtobutanol (Isobutyl alcohol) 40Methacrylonitrile 1.84 20Methylene chloride (Dichlorometbanc) 5 5Methyl methacrylate 1,420 1.0“-Methyl-Z-pentanooe 139 10Pentachloroethane 5Propionitrile

— 20Styrene 100 1.01,l,1,2-Tetrachlorethane 0.406 0.261 ,1,2,2-Tetrachlorethane 0.0527 0.18Teimchloroethene 5 1.0Toluene 1,000 1.0l,l,1-Trichloroethane 200 1.01,1,2-Tcichloroethane 5 1.0“riclaloroethene 5 1.0Trichlorofluoromethane 1,290 1.01,2,3-Tricbloropropane 0.00423 0.61Vinyl acetate 412 2.0‘linyl chloride 2 1.0Xylenes, total 10,000 2.0Additional Parameters Method SW846 3518C (ugfL)Dioxenethioo

-‘ 0.400Pioxathion (cis) 54.8 0.400Dioxathion (traas) 54.1 0.400

Notes:

= not available or not applicableScreening Criteria MDEQ, Final Regulations Governing Browrasfield Voluntary Cleanup andRedevelopment in Mississippi (amended 26 Ptb 2002), Appendix A, Tier 1 Target Remedial Goal‘For compounds where Reporting Limit> Screening Criteria, the Method Detection Limit is usedbold method detection limit exceeds screening criteria

GES - 1/20/2005 Page 1 oft HERCULES - HATfIESBURG, MS

Page 32: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

CC

vqpuadd

Page 33: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

Appendix A

Dioxathion Sampling and Analysis Protocol

Page 34: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

SAMPLING AND ANALYSIS PROTOCOL FOR THEDETERMINATION OF DIOXATHION IN WATER

Recent results of analyses of well water samples from the Hercules Incorporated plant inHattiesburg, Mississippi, have exhibited a wide range in the levels of dioxathion reported.Discussions among representatives from the analytical laboratories demonstrated that the samplesanalyzed to date were not true split samples and that the analytical methods were applieddifferently. In order to minimize the effects from different water samples and from inconsistentapplication of the analytical methods, the following protocol has been assembled by agreementbetween Hercules Incorporated and the Mississippi State Chemical Laboratory. This protocolwill be used in a study to determine the proper sampling and analysis methods to be used for allfuture water monitoring programs at the Hattiesburg plant.

1.) SAMPLE COLLECTION

Water samples will be withdrawn from the well using a Teflon bailer. The contents ofthe bailer will be placed into a large glass or Teflon container (one gallon, or more, in size). Thecontainer should have a Teflon-lined screw cap. Successive bailers of water will be removedfrom the well and placed into the container until there is enough water to supply split samples toeach laboratory participating in the study. The contents of the large container will then be mixedthoroughly. After the composited water sample in the large container has been mixed, equalamounts of water will be poured into each sample jar. The sample jars should have Teflon-linedscrew caps. This procedure will be repeated for each well.

Each analytical batch of a given matrix (up to 20 samples) will require the analysis of amethod blank, Laboratory Control Standard (LCS), Matrix Spiked sample (MS) and Matrix SpikeDuplicate (MSD). Alternately , a duplicated sample maybe substituted for the (MSD). The MSand the MSD are counted as part of the analytical batch (aka Sample Delivery Group) which maybe held open for up to seven (7) days.

Water samples collected from Wells #1, #4 and #5 will be submitted in duplicateto each laboratory. That is, two separate sample jars from Well #1, Well #4 and Well #5will be filled and sent to each laboratory for analysis.

NOTE: The sample collected for the MS/MSD will require six (6) one-liter samples.

2.) EXTRACTION OF SAMPLES

All samples will be extracted with methylene chloride following the detailsdescribed in the latest revision of U.S. EPA SW-846 Method 3510 C. The solvent shouldbe exchanged into hexane, and all extracts will be adjusted to a final volume of tenmilliliters (10 mL) before analysis.

8/21)2002

Page 35: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

3.) CLEANUP OF EXTRACTS

In order to minimize interferences in the determination of dioxathion, sampleextracts that appear to contain interferences will be cleaned up using the latest revision ofU.S. EPA SW-846 Method 3620, Florisil Cleanup. The volume of eluting solventnecessary for quantitative recovery of dioxathion from the Florisil column will bedetermined in each laboratory using the dioxathion and dioxenethiol reference standardssupplied for calibration of the GC methods.

4.) SULFUR CLEANUP

If there is significant interference from sulfur compounds, the extracts may becleaned up according to U.S. EPA SW-846 Method 3660, copper option.

5.) ANALYSIS OF EXTRACTS

Previous work performed by Bonner Analytical and Testing (BATCO) hasrevealed that trans dioxathion undergoes thermal degradation in the Gas Chromatographcolumn therefore the protocol is changed to a lower temperature analytical method. ForAll sample extracts will be analyzed by High Performance Liquid Chromatography(HPLC) ) using a Photo Diode Array (PDA), operated in . U.S. EPA SW-846 Method8321 A will be used as general guidance for HPLC methodology.. A five-pointcalibration curve will be used to calculate the results of analyses. The lowest point on thecalibration curve should be equal to, or slightly higher than, the limit of detection of theGC-PDA system. The highest point on the calibration curve should be the end of thelinear portion of the PDA response profile. All laboratories will follow the QAIQCcriteria described in the analytical method. Those results will be stored at each laboratoryfor review at a later date, if necessary.

InstrumentationHPLC — Hewlett Packard Model 10980 Series II Liquid Chromatographwith Diode Array DetectorFluoresence Detector Hewlett Packard Series 1100 HPLC Column:Supelco Discovery Cl8, 250 mm X 4.6mm ID, 5 jim Particle Size.

Method ParametersMobile Phase : Isocratic, 30% Deionized water and 70 % AcetoneFlow: 1.2 mIs/mmInjection Volume: 25 jiLsRun Time: 20 MinutesOven Temperature 35 CDetector WavelengthsDiode Array: Excitation at 200, 210 and 270 nmsFluorescence: Excitation at 250 nms, Emission at 410 nms

Surrogate/Internal Standards: A surrogate will be chosen that does not coelute with anydioxathion isomer. Internal standards may or may not be used.

8/21/2002

Page 36: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

6.) CONFIRMATION OF ANALYSES

The preferred method for qualitative and quantitative confirmation of dioxathionand dioxenethiol is Liquid Chromatography/Mass Spectra analysis (LC/MS), howeverthe present time Bonner Analytical and Testing does not own an LC/MS instrument.Therefore, for qualitative and quantitative confirmation of the dioxathion results, allsample extracts will be analyzed by Bonner Analytical and Testing using gaschromatography-mass spectrometry (GC-MS) using the latest revision of U.S. EPA SW-846 Method 8270, or an equivalent mass spectrometry system that is deemed appropriateto give equivalent results. A five-point calibration curve will be used to calculate theresults of analyses. The lowest point on the calibration curve should be equal to, orslightly higher than, the limit of detection of the GC-MS system. The highest point on thecalibration curve should be the end of the linear portion of the MS detector responseprofile. All laboratories will follow the QAJQC criteria described in the analyticalmethod. Those results will be stored at each laboratory for review at a later date, ifnecessary. If significant differences are observed between Bonner Analytical & Testing’ sresults and Mississippi States University Chemical Laboratory’results, BATCO will sendthe extracts of these samples to a third party laboratory to investigate the reasons forthese differences.

GC column: 30-meter X 0.25-mm (or 0.32-mm) DB-5 fused silica capillarycolumn, as specified in Paragraph 4.1.2 in U.S. EPA SW-846 Method 8270.

GC oven and injector conditions: As specified in Paragraph 7.3 in SW-846 Method 8270.

The specifications given in Method 8270, Section 4.0, “APPARATUS ANDMATERIALS,” and Section 5.0, “REAGENTS,” will be followed. The guidance inSection 7.0, “PROCEDURE” will be used to perform the GC separations and GC/MSidentification and quantitation. Specific criteria for peak identification are given inSection 7.6 of the method. The characteristic ions, both primary and secondary ions,listed in Table 1 of the method will be used. For cis and trans dioxathion anddioxenthiol, the primary ion is m/z 97 with secondary ions at m!z 125, 270, and 153.Instrument tuning criteria are given in Table 3 of the method. For the Internal Standard,chrysene-d12is recommended because it meets the retention time criteria set forth inSection 7.3.2.

7.) GENERAL COMMENTS

a.) All samples will be extracted and analyzed within the normal holding times fororganophosphorus compounds.

b.) The dioxathion standard to be used by all laboratories will be supplied by theHercules Incorporated.

8/21/2002

Page 37: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

c.) Water samples spiked with cis or trans dioxathion or dioxenethiol will beprepared by the Mississippi State Department of Environmental Quality(MSDEQ) personnel and distributed to each laboratory for inclusion in this study.

d.) Within three weeks of receipt of samples, all results of analyses and allconfirmatory results will be reported to MSDEQ, who will collate them anddistribute the results to the participating laboratories.

e.) A meeting will be held to review the results of analyses and to decide the nextstep in the implementation of the analytical methods to be used in monitoringwell water samples from the Hercules Incorporated Hattiesburg plant.

f) After its approval of this sampling and analysis protocol, MSDEQ will determinethe time frame for the completion of all sampling and analysis activities and willset the date and time of the review meeting.

g.) Only results greater than or equal to the Limit of Quantitation will be reported.The numerical sum of the cis and trans isomers of dioxathion will be reported asdioxathion. Dioxenethiol will be reported as separate compound.

8/21/2002

Page 38: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

C0

axjp

uad

d

Page 39: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

Appendix B

Health and Safety Plan

Page 40: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

HEALTH AN]) SAFETY PLANREMEDIAL 11NVESTIGATIONS

HERCULES, INC.FIATTTESBURG, MTSSISSIPPI

3Prepared for:

EERCULES, INC.HATTIESBURG, MISSISSIPPI

MAY 2004

Prepared by:

Eco-Systems, Inc.Consultants, Engineers, and Scientists

ESI

Page 41: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

Hercules, Inc. ESIHealth and Safety Plan

TABLE OF CONTENTS

1.0 PROJECT IDENTIFICATION 12.0 INTRODUCTION 1

2.1 PuRPosE 12.2 SiTE DESCRPTTON OF INVESTIGATIVE AREAS I2.4 PREvious CRAcTERIzATION WoRK 12.5 KEY PERsOI’mTEL 2

2 1 Eco-Sys’tems Project Manager 2.2.5.2 Eco-Systems Health and Safety Officer 22.. 5.3 Eco-Systems Site Safety Officer 3

3.0 WORK PLAN 44.0 HAZARI) ASSESSMENT 4

4.1 BIOLoGIcAL HAZARDS 44.2 HEAr STREss HAZARDS 443 PHYsIcAL HAZARDS 44,4 CHEMICAL HAZARDS 4

5.0 GENERAl HEALTH MN]) SAFETY REQUIREMENTS 55.1 W0RKZ0NES 55.2 SAFETY EQUIPMENT REQUIRED 65.3 DECONTAMINATION PROCEDURES 7

5.3.1 Equipment Decontamination 75.3.2 Personnel Decontamination 7

5.4 MEDICAL. ExAIvm’4ATI0N 85.5 CoMPLIANcE AGREEMENT 85.6 PRoJEcT MANAGER N0TrFIcATI0N 85.7 PROJEcTSAFEn’Loci 95.8 PROmBITI0Ns 95.9 SITESAFETYMEETING 9

6.0 LA.BORATORY CONSIDERATIONS 9

7M PERSONAL PROTECTIVE EQUIPMENT 97.1 HEADPP0TECTI0N 97.2 EYE PROTEcTIoN 107.3 SKmJPR0TEcTI0N 107.4 FooTwEAR 107.5 REsPIIToRY PROTECTION 107.6 HEAFUNG PRoTEcTIoN 11

8.0 AIR QUALITY MONITORING 118.1 AIRQUAL.rrYSURVEY 118.2 PERsoNNEL. ExPosuRE M0NIT0IUNG 11

Page I

Page 42: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

Hercules, Inc.Health and Safety Pla,z ESI c

Heat Stress Casualty Prevention PlanSafety Guidelines for DrillingsMaterial Safety Data SheetsSite Safety Meeting Report FormHealth and Safety Incident Report FormEmergency Services/Phone Numbers and Route to the Hospital

9.0 EMERGENCIES/ACCIDENTS 12

10.0 PERSONNEL ASSIGNMENTS 1210.1 PRoJEcT PERSONNEL 1210.2 PRoJEcT SAFETY PERSONNEL 12

11.0 SAFETY PLAN APPROVALS 13

12.0 SAFETY PLAN COMPLIANCE AGREEMENT 14

FIGURES

Figure 1 Hospital Route

APPENDICES

Appendix AAppendix BAppendix CAppendixDAppendix EAppendix F

Page ii

Page 43: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

Hercules, I,zc.Health and Safeiy Plaii

1.0 PROJECT IDENTIFICATION

Client:Project:Project Manager:Proj ect Number:Date of Plan:Estimated Dates of Work:Expiration Date:

2.0 INTRODUCTION

Hercules, Inc.Remedial InvestigationCharles ConeyBER241 005/24J04May—June 2004December 2004

This Health and Safety Plan (HSP) establishes guidelines and requirements for the safety of fieldpersonnel during the conduct ofthe field activities associated with the referenced project. Thespecific activities addressed by this plan are defined in Section 3.0. All employees of Eco

Systems, Inc (Eco-Systems) and their subcontractor, Singley Environmental Services, Inc. ofColumbia, Mississippi, involved in this project are required to abide by the provisions of thisplan. They are required to read this plan and sign the attached Compliance Agreement.

The health and safety guidelines and requirements presented are based on a review of availableinformation and an evaluation of potential hazards. This plan outlines the health and safetyprocedures and equipment required for activities at this site to minimize the potential forexposures of field personneL This plan may be modified by the Project Manager with theapproval of the Health and Safety Officer in response to additional information obtainedregarding the potential hazards to field investigative personnel.

2.1 PuruosE

Hercules, Inc. contracted with Eco-Systems in to investigate areas of environmental concern atHercules, Inc facility located in Hattiesburg, Mississippi. The objective of this investigation willbe to collect and analyze soil samples for geotechnical parameters.

2.2 SITE DEscRIPTIoN OF INVESTIGATIVE AREAS

The investigative area will encompass the entire site of the Hercules facility. The site includesopen areas, production areas, wooded areas, and small stream.

2.4 PREVIOuS CHARAcTERIzATIoN WoRK

Several site investigations have previously been performed. One investigation was performed byEPA contractor, and covered hazardous substance scans of hazardous substances in surface soilsand stream sediments.. A later investigation installed monitoring wells and sampled groundwater.

ESI

Page 1

Page 44: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

Hercules, Inc. E IHealth and Safety Plan

2.5 Kir PERsoNNEL

2.5.1 Eco-Systenis Project Manager

For this project, the Fcc-Systems Project Manager has the following responsibilities:

• To see that the project is performed in a manner consistent with the Fcc-Systems Healthand Safety Program

• To have an approved Health and Safety Plan prepared and properly implemented for thisproject.

• To provide the Eco-Systerns Health and Safety Officer with project information related tohealth and safety matters and development of the Health and Safety Plan.,

• To implement the Health and Safety Plan.

• To insure compliance with the Health and Safety Plan by Eco-Systems and contractorpersonnel.

• To coordinate with the Eco-Systems Health and Safety Officer on health and safetymatters.

The Fcc-Systems Project Manager has the authority to take the following actions:

• To determine matters relating to schedule, cost, and personnel assignments on hazardouswaste management projects.

• To temporarily suspend field activities, if the health and sa±ty of personnel areendangered, pending further consideration by the Health and Safety Officer.

• To temporarily suspend an individual from field activities for infractions of the Healthand Safety Plan, pending further consideration by the Health and Safety Officer.

2.5.2 Eco-Systems Health and Safety Officer

The Fcc-Systems Health and Safety Officer has the following responsibilities:

• To interface with the Eco-Systems Project Manager as may be required in matters ofhealth and safrty

• To develop a Health and Safety Plan for the project.

Page 2

Page 45: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

Hercules, Inc. ESIHealth anti Safety Plan

• To appoint or approve a Eco-Systems Site Safety Officer to assist in implementing theHealth and Safety Plan.

• To monitor compliance with the approved Health and Safety Plan.

• To assist the Eco-Systerns Project Manager in seeing that proper health and safetyeqnipment is available for the project

• To approve personnel to work on this site with regard to medical examinations and healthand safety training.

The Eco-Systems Health and Safety Officer has the authority to take the following actions:

• To suspend work or otherwise limit exposures to personnel, if a Health and Safety Planappears to be unsuitable or inadequate.

• To direct personnel to change work practices, if they are deemed to be hazardous tohealth and safety of personneL

• To remove personnel from the project, if their actions or condition endangers their healthand safety or the health and safety of co-workers..

2.5.3 Eco-Systeins Site Safety Officer

Eco-Systems Site Safety Officer: Charles Coney (To be designated pnor to commencementof work)

The Eco-Systems Site Safety Officer has the following responsibilities:

• To direct health and safety activities onsite.

• To report safety-related incidents or accidents to the Eco-Systems Project Manager orHealth and Safety Officer, and the Hercules, Inc. Facility Supervisor.

• To assist the Eco-Systems Project Manager in all aspects of implementing the Health andSafety Plan.

• To maintain health and safety equipment onsite, as specified in the Health and SafetyPlan.

• To perform health and safety activities onsite, as specified in the Health and Safety Plan,and report results to the Eco-Systems Project Manager and Health and Safety Officer.

Page 3

Page 46: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

Hercules, Inc. ESIHealth and Safety Pie,,

3.0 WORKPLAN

A separate work plan has been prepared for this project which details the investigative samplingmethods and procedures.

4.0 HAZARD ASSESSMENT

4.1 BIoLoGIcAL HAZARDS

If clearing has not been conducted or if biological hazards develop during work activities,practical guidelines for prevention of exposure to pests should be implemented.

4.2 HEAT STREss HAZARDS

If heat stress becomes a concern, the heat stress casualty prevention plan attached as Appendix Ashall be implemented.

4.3 PnsicAL HAzARDs

There is a risk of physical injury resulting from misuse of the drilling equipment at the site. Useof steel toe and shank boots will be required when using or in the vicinity of heavy equipment.Personnel should be cognizant of the fact that when protective equipment such as respirators,gloves, and protecdve clothing are worn while using heavy equipment, visibility, hearing, andmanual dexterity are impaired. Safety guidelines for drilling operations are attached as AppendixB.

Noise hazards may also be presented from drilling operations. Personnel exposed to noise levelsin excess of permissible noise exposures as defined by 29 CFR 2910.95 shall be protected.Where feasible, administrative or engineering controls shall be utilized. If control measures arenot effective or until controls are implemented, personnel shall wear approved personalprotective equipment in the form of ear plugs or muffs.

Personnel who are exposed to a time weighted average of greater than 85dBA shall be required toparticipate in a hearing conservation program as defined by 29 CFR 1910.95..

4.4 CHEMICAL HAZARDS

Specific chemical hazards associated with this site include: Dioxatbion and isopropyl alcohol.Chemical safety data sheets for these chemicals are attached as Appendix C. The primary routeof exposure for these chemicals is: dermal (skin) with the secondary routes being (ingestion andpossible inhalation, although not expected due to the low vapor pressure of these compounds andcontaminated dust). As a result of these potential exposures, a modified Level D personalprotective equipment (PPE) will be required during subsurface and sample handling activities. Apotential upgrade to Level C PPE (respiratory protection) will be required if air monitoring action

Page 4

Page 47: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

Hercules, Inc. ESIHealth and Safety Plan

levels are exceeded. Specific PPE ensembles associated with the various site activities are listedin Section 5.2. Air monitoring action levels are listed in Table 8.1 Air monitoring exposurelimits axe listed in Table 4.1 below.

TABLE 4.1EXPOSURE LIMiTS FOR POTENTIAL CONTAMINANTS

AT THE PROPOSED WORK SITES

TLV PEL STEL IDLFI SkinContammant 3 3 3 3(mg/rn) (mg/rn) (mg/rn) (mg/rn) Hazard

Dioxathion ND ND ND ND

ND = No DataCA Potential Human Carcinogen (No IDLH level established)

Note: TLV — 0.2mg/rn3 (skin) (ACGIH 199 1-1992)Insoluble in Water

5.0 GENERAL HEALTH AN]) SAFETY REQUIREMENTS

Si WORIC ZoNEs

During activities conducted in modified Level D PPE, the setup of work zones as defined by Ti.S. EPA will not be required. Although, management of this project shall be conducted in amanner which will restrict access to the job site by unauthorized personnel. If Level D actionlevels establish in Table 8.1 are exceeded resulting in an upgrade to Level C PPE, work zones asdescribed in the following paragraphs shall be implemented.

To minimize the movement of contaminants from the site to uncontaminated areas, three workzones will be set up during activities conducted under Level C PPE. The three work zones willinclude the following:

Zone 1: Exclusion ZoneZone 2: Contamination Reduction ZoneZone 3: Support Zone

The exclusion zone is the zone where contamination does or could occur. The exclusion zonewill be defmed initially by a 20 x 20-foot area around the drill rig. Air monitoring andobservation by the site safety officer will determine the extent of the zones. All persons enteringthis zone must wear at a minimum the level of protection set forth in Section 5.2 (Level C PPE).

• Between the exclusion zone and support zone is the personnel contamination reduction zone(CRZ) which provides a transition zone between the contaminated and clean areas of the site.

0Page 5

Page 48: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

Hercules, Inc. ESIHealth and Safely Plan

This zone will be located directly outside of the exclusion zone and will be defined as a 10-footzone directly outside the exclusion zone.

The support zone will be an uncontaminated area from which operations will be directed. it isessential that contamination from the site be kept out of this area. Included in this area will be astorage area for decontaminated clothing, additional personal protective equipment, etc.

5.2 SAFETY EQUIPMENT REQUIRED

The following personal protective equipment will be required for personnel engaged in fieldactivities at the site:

Mobilization - Level D Protection

• Boots, steel toe and shank

• Hardhat

• Safety glasses with side shields

Subsurface and Sample Handling Activities/Decontamination Procedures - Modified Level DProtection

• Coveralls, chemical resistant; polycoated tyvek

• Gloves (outer), chemical-resistant, nitrile rubber

• Gloves (inner), chemical-resistant, latex.

• Boots, chemical-resistant, steel toe and shank (or bootie covers)

• Hard hat (with faceshield if splash hazard exists)

a Safety glasses with side shields

• Ear plugs or ear muffs (during drilling operations)

Level C Protection

• Half-face air purifying respirator withvapor/dustlflimes/mists/HEPA filter carthdges

• Coveralls, chemical-resistant; policoated tyvek

combination organic

Page 6

Page 49: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

Hercules, Inc.EsIHealth and Safety Plan

• Gloves (outer), chemical-resistant; nitrile rubber

• Gloves (inner), chemical-resistant; latex

• Boots, chemical-resistant; steel-toe and shaulc (or bootie covers)

• Hard hat (with face shield if splash hazard exists)

• Safety glasses with side shields

• Ear plugs or ear muffs (during drilling operations)

When work is conducted over the pond, all sampling personnel shall also wear a coastguardapproved life jacket and life line

5.3 DEC0NTMVIINATION PRocEDu1us

5.3.1 Equipment Decontamination

All equipment used to collect soil and water samples will be decontaminated by the followingprocedure:

1. Washing in a detergent solution (Liquinox)

2. Triple rinsing with clean deionized water

3. Airdrying

4. Wrap in aluminum foil

Decontamination of equipment shall be conducted in Modified Level D PPE as listed in Section5,2.

In the case of the shallow soil borings, decontamination between sampling intervals will beperformed to preclude vertical cross-contamination between sample intervals. An alternative todecontamination of equipment within the same boring (between sample intervals) will be toutilize new augers, stems, etc, for each sampling interval, thereby requiring decontaminationbetween boring locations only.

5.3.2 Personnel Decontamination

Decontamination of personnel will be performed at a designated location at the perimeter of thework area. Decontamination will consist primarily of soap and water washings and water rinseof exterior protective gear to remove contaminants, followed by doffing of the gear.

Page7

Page 50: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

Hercules, Inc. ESIHealth aizd Safety Plait

Coveralls should be removed by turning the clothing inside out. A general sequence of doffingprocedures is outlined below. The extent of washing required, or modifications to the sequence,may be specified as appropriate.

Steps in decontamination will be as follows:

• Wash and rinse outer protective coverall

• Wash work gloves and boots

• Remove outer protective clothing

• Rinse respirator

• Wash hands and face

Contaminated disposable PPE and all decontamination fluids shall be containerized onsite forsubsequent disposal by the direction of the Hercules, Inc.

5.4 MEDICAL ExAMINATIoN

Before commencing any of the field or laboratory activities defined in Section 3.0, all EcoSystems personnel must talce an annual Eco-Systems-approved medical examination as part ofEco-Systems’ medical surveillance program.

5.5 Co1IPLIANcE AGREEMENT

The Eco-Systems Project Manager and Health and Safety Officer shall hold meetings with allEco-Systems field personnel before work commences. During the meeting, all personnel shall beprovided with a copy of this safety plan; the plan shall be reviewed and discussed and questionsanswered. Signed Compliance Agreement Forms shall be collected by the Eco-Systems ProjectManager and filed by the Health and Safety Officer. individuals refusing to sign the form will notbe allowed to work on the site

5.6 PRoJEcT MANAGER NOTIFICATIONV

All Eco-Systems field personnel must inform the Eco-Systems Project Manager or his/herdesignated representative before entering the site At least two members of the field crew mustbe on site whenever work is performed. Personnel must be in visual contact with each other orcarry two-way radios at all times.

If any drums or other previously unidentified potential hazards are discovered during any fieldwork, immediately notify the Eco-Systems Project Manager for further instructions.

V PageS

Page 51: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

Hercules, Inc. ESIHealth and Safety Plan

5.7 PROJECT SAFETY LOG

A prqject safety log will be used to record the names, entry and exit dates and times of all Eco

Systems and subcontractor personnel and of project site visitors; accidents, injuries, and

illnesses; incidence of safety infractions by field personnel; air quality and personal exposure

monitoring data; and other information related to safety matters All accidents, illnesses or other

incidences shall be reported immediately to the Eco-Systems Project Manager, and the Eco

Systems’ Health and Safety Officer and subsequently documented for filing on the Incident

Report Form attached as Appendix E.

5.8 PR0mBITI0Ns

• Smoking, eating, drinking, chewing gum or tobacco, storing food or food containers

shall not be permitted on the work site. Good personal hygiene should be practiced

by field personnel to avoid ingestion of contaminants or spread of contaminated

materials.• Iguition of flammable liquids within, on, or through improvised heating devices or

space heaters.• Approach or entry into areas or spaces where toxic or explosive concentrations of

gases or dust may exist without proper equipment available to enable safe entry.

• Conduct of onsite operations without offsite backup personnel.

5.9 SITE SAFETY MEETING

Each day prior to commencement of work, a safety meeting will be held by the Eco-Systems Site

Safety Officer to review and plan the specific health and safety aspects of scheduled work for the

day.

6.0 LABORATORY CONSIDERATIONS

The laboratory director must be informed of any contaminant levels in the samples that would

require special handling procedures to prevent risk to the health and safety of laboratory

personnel.

7.0 PERSONAL PROTECTIVE EQfflPMENT

This section outlines the general usage guidelines for personal protective equipment

7.1 HEAD PRoTECTIoN

Hard hats must be worn by all personnel working onsite

Page 9

Page 52: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

Hercules, Inc. ES.1Health and Safety Plan

7.2 EYE PROTECTION

Safety glasses with side shields or goggles must be worn by all personnel performing activitieswhere potential for eye or face exposure exists due to splash, dust, or vapor, etc. An eyewashstation will be set up by the Site Safety Officer prior to commencing field activities and shouldbe placed so that it could be used quickly in an emergency.

7.3 SKiN PRoTECTIoN

Chemical resistant gloves and coveralls shall be worn by all personnel during subsurface andsample handling activities. These will be disposed of in a designated salable drum afier each useor when they become worn or punctured.

7.4 Foorwiru

Chemically resistant boots with steel toes and shanks will be worn by field personnel engaged inthe field activities at the site. Chemical resistant booties can be substituted for chemical resistantboots, although worlc boots to be covered must always maintain steel toes and shanks.

7.5 RESPIRAToRY PRoTEcTioN

For respiratory protection against possible volatile organics, half-face air purifying respirators(APR) will be required if Level 0 air monitoring action levels are exceeded. Specific cariridgesto be utilized with the APRs will be combination organic vapor/dust/fume/mistJHEPA filtercartridges All personnel must be properly fit-tested for the specific brand and size respirator tobe used. A respirator which has not been successfully fit-tested cannot be used by an individualon the project. To ensure a proper fit, no facial hair will be allowed that will interfere with maskoperation. The Site Safety Officer will determine if facial hair represents such an interference.Air purifring respirators will only be used if the following conditions are met:

• The oxygen content of the air is greater than 19.5 percent.

• Concentrations of air contaminants are known and monitored,

• The contaminants of concern all have good warning properties (i.e., odor threshold belowPEL value).

• The protection factor is adequate and PELs are not exceeded.

• If concentrations of air contaminants exceed IDLH value, personnel must immediatelyevacuate.

• Cartridges are changed daily or whenever breakthrough occurs, whichever occurs first.

Page 10

Page 53: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

Hercules, Inc. ESIHealth and Safety Plan

• Each person has been fit-tested for the specific brand and size of respirator used.

• The respirator is MSHA- and NIOSH-approved.

7.6 HEARING PRoTEcTIoN

Ear plugs or ear niuffs shall be worn by all personnel in the vicinity of drilling operations toreduce their exposure to noise.

8.0 AIR QUALITY MONITORING

The primary goal of onsite air quality monitoring will be compliance with the specifiedcontaminant action levels.. The secondary goal will be documentation of personal exposures asrequired by OSHA 1910.120.

8.1 AIR QUALITY SURVEY

During field activities at the site, an air quality survey will be performed utilizing an HNuphotoionization detector (PID), OVA Flame ionizing detector (FJD), or equivalent instrument tocharacterize volatile organic concentrations onsite. Standard operating procedures for theseinstruments must be followed.

8.2 PERsoNNEL ExPosuRE MoNIToRING

The OSHA. regulations for Hazardous Waste Workers (1910J20) states in Section (h) that,“Those closest to the source of contaminant generation shall receive personal air monitoringsufficient to characterize employee exposure.”

Table 8-1Mr Monitoring Action Levvels for Level C and D Work

Contaminant Instrument* Reading Action TakenVolatile Organics HNU, OVA <2 ppm Continue work in

Modified EquivalentLevel D

>2 ppm Upgrade to Level Cand expand workzones

> 5 ppm Evacuate Area‘ Sustained readings above background which shall not be exceeded within worker

breathing zones or exclusion zones.

Page H

Page 54: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

Hercules, Inc.ESIHealth and Safrty Flazi

9.0 EMERGENCIES/ACCIDENTS

Illnesses, injuries and accidents occurring onsite must be attended to immediately in thefollowing manner:

• Remove the injured or exposed persons(s) from immediate danger.

• Render first aid if necessary. Decontaminate affected personnel, if necessary,

• Call ambulance for transport to local hospital. This procedure should be followed eventif there is no apparent serious injury Emergency numbers are listed on the next page.

• Evacuate other personnel onsite to a safe place until the engineer (assisted by the SiteSafety Officer) determines that it is safe for work to resume.

• Report the accident to the Health and Safety Officer immediately.

• Develop procedures, in accordance with the Health and Safety Officer, Site SafetyOfficer, and Engineer to prevent a recurrence.

In the event that an emergency sit evacuation should be necessary for any reason, the Site SafetyOfficer will render an alarm using a horn and all personnel shall leave the site. The assemblypoint will be designated in the field. Personnel will not return to the site until an all-clear hasbeen received from the Site Safety Officer.

10.0 PERSONNEL ASSIGNMENTS

10.1 PROJECT PERSONNEL

Eco-Systems personnel authorized to work on this project and enter the site are:

Proj ect Manager Charles ConeySite Safety Officer* Charles ConeyField Investigation/Site Manager Charles ConeyHydrogeologic Review Charles ConeyTechnician Christopher TerrellDrill Crew Singley Environmental Services, Inc.To be completed prior to commencement of work.

10.2 PROJEcT SAFETY PERsoNNEL

Personnel responsible for implementing this safety plan are the Eco-Systems Project Manger andSite Safety Officer.

Page 12

Page 55: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

Hercules, Inc.Health and Safety Plan

11.0 SAFETY PLAN APPROVALS

ESI :y:

ecager

Health and Safety Officer’/

Date

Date

Project Name:Project Number:

Remedial InvestigationHER241 00

Page 13

Page 56: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

Hercules, Inc.Health and Safety Plan

12.0 SAFETY PLAN COMPLIANCE AGREEMENT

ESI

(print name) have received a copy of theSafety Plan for the Remedial Investigation of the

__________________________________

Site in

___________________________________

(Eco-Systems Prpject No.

________________).

I have readthe plan, understand it, and agree to comply with all of its provisions. I understand that I couldbe prohibited from working on the project for violating any of the safety requirements specifiedin the plan.

Signed:

I,

(Signature) (Date)

Finn:

Page ]4

Page 57: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

Hercules, Inc.Health and Safety Plan

FIGURES

ESI ®

Page 58: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

C

0 C 0 ‘H

4•1

-

—.

_r—

:li

t

I;

—1

In..

““!U

.-.

.L:-

--•‘

H-

.•_.l-

.1—

——

r

••

Page 59: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

Flu,;ESI

APPEIX A

HEAT STRESS CASUALTY PREVENTION PLAN

Page 60: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

ESI ()APPENDIX A

BEAT-STRESS CASUALTY PREVENTION PLAN

Due to the increase in ambient temperatures and the effects of protective outer wear decreasingbody ventilation, there exists an increase in the potential for injury, specifically, heat casualties. Sitepersonnel will be instructed in the identification of a heat-stress victim, the first aid treatment proceduresfor the victim and the prevention of beat stress casualties.

Identification and Treatment

I) Heat Exhaustion

L1.l) Symptoms: Usually begins with muscular weakness, dizziness, nausea, andstaggering gait. Vomiting is frequent. The bowels may move involuntarily. The victim is very pale, hisskin is clammy, and be may perspire profusely. The pulse is weak and fast, his breathing is shallow,. Hemay faint unless he lies down. This may pass, but sometimes it remains and death could occur

1 .1.2) First Aid: Immediately remove the victim to the Personnel DecontaminationReduction Zone in a shady or cool area with good air circulation. Remove all protective outer wear. Call aphysician Treat the victim for shock. (Make him lie down, raise his feet 6 - 12 inches and keep bins warmbut loosen all clothing.) If the victim is conscious, it may be helpful to give him sips of a salt water solution(1 teaspoon of salt to 1 glass of water) Transport victim to a medical facility as soon as possible..

1.2) Heat Stroke

1.2.1) Symptoms: This is the most serious of heat casualties due to the fact that thebody excessively overheats. Body temperatures often are between 107o - I lOoF First there is often painin the head, dizziness, nausea, oppression, and the skin is dry, red and hot Unconsciousness followsquickly and death is imminent if exposure continues. The attack will usually occur suddenly

1.2.2) First Aid: Immediately evacuate the victim to a cool and shady area in thePersonnel Decontamination Reduction Zone. Remove all protective outer wear and all personal clothingLay him on his back with the head and shoulders slightly elevated. It is imperative that the bodyterriperature be lowered immediately. This can be accomplished by applying cold wet towels, ice bags, etc.,to the head. Sponge off the bare skin with cool water or rubbing alcohol, if available, or even place him iiia tub of cool water. The main objective is to cool him without chilling him. Give no stimulants. Transportthe victim to a medical facility as soon as possible

2 Prevention of Heat Stress

2.1) One of the major causes of heat casualties is the depletion of body fluids. Plenty offluids should be available on the site. Personnel should replace water and salts loss when perspiring. Saltscan be replaced by either a O 1 percent salt solution, more heavily salted foods, or commercial mixes suchas Gatorade. The commercial mixes are advised for personnel on low sodium diets.

2.2) A work schedule should be established so that the majority of the work day will beduring the morning hours of the day before ambient air temperature levels reach their highs.

2.3) A work/rest guideline will be implemented for personnel required to wear Level C orhigher level of protection. This guideline is as follows:

Page 61: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

ESIAmbient Temperatures Maximum Wearing Tj

Above 90°F 1/2 hour80o - 90°F 1 hour70o-80°F 2hours60o-70°F 3 hours

A sufficient period will be allowed for personnel to cool down.’ This may require shifts ofworkers during operations

3 Heat-Stress Monitoring

For monitoring the body’s recuperative ability to excess beat, one or more of the followingtechniques should be used-’a a screening mechanism,, Monitoring of personnel wearing protective clothingshould commence when the ambient temperature is 70 degrees Fahrenheit or above. Frequency ofmonitoring should increase as the ambient temperature increases or if slow recovery rates are indicatethWhen temperatures exceed 80 degree Fahrenheit, workers must be monitored for heat stess after everywork period.

• Heart rate should be measured by the radial pulse for 30 seconds as early as possible in the restingperiod. The heart rate at the beginning of the rest period should not exceed 110 beats per minuteIf the heart rate is higher, the next work period should be shortened by one third (33 percent),while the length of the rest period stays the same. if the pulse rate is 100 beats per minute at thebeginning of the next rest period, the following work cycle should be shortened by one third.

• Body temperature should be measured orally with a clinical thermometer as early as possible inthe resting period. Oral temperature at the beginning of the rest period should not exceed 99.6degree Fahrenheit If it does, the next work period should be shortened by one third (33 percent),while the length of the rest period stays the same. However, if the oral temperature exceeds 99 6degrees Fahrenheit at the beginning of the next period, the following work cycle should be furthershortened by 33 percent Oral temperature should be measured again at the end of the rest periodto make sure that it has dropped below 99 degree Fahrenheit Do not permit a worker to wear asemipermeable or impermeable garment if his/her oral temperature exceeds 100.6 degreeFahrenheit.

• Body water loss due to sweating should be measured by weighing the worker in the morning andin the evening. The clothing worn should be similar at both weigh-ins; preferably the workershould be nude. The scale should be accurate to plus or minus 1/4 pouncL Body water loss shouldnor exceed 1.5 percent of the total body weight. If it does, workers should be instructed toincrease their daily intake of fluids by the weight loss

Ideally, body fluids should be maintained at a consistent level during the work day This requiresreplacement of salt lost when perspiring.

Good hygienic standards must be maintained by frequent change of clothing and daily showering.Clothing should be permitted to dry during rest periods Persons who notice skin problems shouldimmediately consult medical personnel.

Page 62: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

Hercules, Inc. EHealth and Safety Plan

APPENDIX B

SAFETY GUIDELINES FOR D1ULLINGS

Page 63: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

ESI C)APPENDIX B

SAFETY GUIDELINES FOR DRILLING

Drill rig maintenance and safety is the responsibility of the drill rig operator. The following isprovided as a general guideline for safe drilling practices on site.

B.I Off-Road Movement of Drill Rigs

The following safety guidelines relate to off-road movement:

Before moving a drill rig, first walk the route of travel, inspecting for depressions, slumps,gulleys, ruts and similar obstacles,.

• Always check the brakes of a drill rig carrier before traveling, particularly on rough, uneven orbilly ground

o Discharge aU passengers before moving a drill rig on rough or hilly terrain..

• Engage the front axle (for 4 x 4, 6 x 6, etc., vehicles or carriers) when traveling off highway onhilly terrain

o Use caution when traveling side-hill, Conservatively evaluate side-bill capability of drill rigs,because the arbitrary addition of drilling tools may raise the center of mass. When possible, traveldirectly uphill or downhill.

o Attempt to cross obstacles such as small logs and small erosion channel or ditches squarely, not atan angle.

• Use the assistance of someone on the ground as a guide when lateral or overhead clearance isclose.

• After the drill ri has been moved to a new drilling site, set all brakes and/or locks When gradesare steep, block the wheels.

Never travel off-road with the mast of the drill rig in the raised or partially raised position.

• Tie down loads on the drill rig and support trucks during transport.

B2 Overhead and Buried Utilities

The use of a drill rig near electrical power lines and other utilities requires that special precautionsbe taken by both supervisors and members of the exploration crew. Electricity can shock, burn and causedeath. Overhead and buried utilities should be located, noted and emphasized on all boring location plansand boring assignment sheets. Before raising the drill rig toast on a site in the vicinity of power lines, walkcompletely around the drill rig. Determine what the minimum distance from any point on the drill rig to thenearest power line will be when the msst is raised and/or being raised. Do not raise the mast or operate thedrill rig if this distance is less than 20-feet. Keep in mind that both hoist lines and overhead power linescan be moved toward each other by the wind

Page 64: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

ESIBJ Clearing the Work Area

Prior to drilling, adequate site cleaning and leveling should be performed to accommodate the drill rig andsupplies and provide a safe working area Drilling should not commence when tree limbs, unstable groundor site obstructions cause unsafe tool handling conditions. In coordination with the drilling crew, the SiteSafety Officer will review the precautions taken to ensure that the drill rig is leveled and stabilized

B.4 Housekeeping On and Around the Drill Rig

The first requirement for safe field operations is that the drilling crew safety supervisor understand andflulfills the responsibility for maintenance and ‘housekeeping” on and around the drill rig Generalhousekeeping should include the following:

• Suitable storage—locations should be provided for all tools, materials and supplies so that they canbe conveniently and safely handled without hitting or falling on a member of the drill crew or avisitor.

• Avoid storing or transporting tools, materials or supplies within or on the mast of the drill rig.

• Pipe, drill rods, bits casing, augers and similar drilling tools should be orderly stacked on racks orsills to prevent spreading, rolling or sliding.

o Penetration or other driving hammers should be placed at a safe location on the ground or securedto prevent movement when not in use

o Work areas, platforms, walkways, scaffolding and other accessways should be kept free ofmaterials, obstructions and substances such as ice, excess grease or oil that could cause a surfaceto become slick or otherwise hazardous.

o Keep all controls, control linkages, warning and operation lights and lenses free of oil, creaseand/or ice

• Do not store gasoline in any portable container other than a non-sparking, red container with aflame arrester in the fill spout and having the work “gasoline” easily visible

B.5 Safe Use of Hand Tools

There are many hand tools which can be used on or around a drill rig. “Use the tool for itsintended purpose” is the most important rule. The following are a few specific and some generalsuggestions which apply to safe use of several hand tools that are often used on and around drill rigs:

• When a tool becomes damaged, either repair it before using it again or get rid of it.

• When using a hammer, any kind of hammer for any purpose, wear safety glasses and require allothers near you to wear safety glasses

• When using a chisel, any kind of chisel, for any purpose, wear safety glasses and require all othersaround you to wear safety glasses.

• Keen all tools cleaned and stored when not in use

o Replace hook and heel jaws when they become visibly worn

Page 65: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

ESI ()When loosening a sting of drilling pipe on the ttround or on a drilling platform, position yourbands so that your fsrgers will not be smashed between the wrench handle and the ground or theplatform, should the wrench slip or the pipe joint suddenly release.

H.6 Safe Use of Wire Line Hoists, Wire Rope, and Hoisting Hardware

The use of wire line hoists, wire rope and hoisting hardware should be as stipulated by theAmerican Iron and Steel Institute’s Wire Rope Users Manual and should include the following precautiois:

o All wire ropes and fittings should be visually inspected during use and thoroughly inspected atleast once a week for abrasion, broken wires, wear, reduction in rope diameter, reduction in wirediameter, fatigue, corrosion, damage from heat, improper weaving, jamming, crushing, birdcaging, kinicing, core protrusion and damage to lifting hardware and any other feature that wouldlead to failure —=Wire ropes should be replaced when inspection indicates excessive damageaccording to the wire rope users manual

• If a ball-bearing type hoisting swivel is used to hoist drill rods, swivel bearings should beinspected and lubricated daily to assure that the swivel freely rotates under load.

If a rod slipping device is used to hoist drill rods, do not drill through or rotate drill rods throughthe slipping device, do not hoist more than 1 foot (O3m) of the drill rod column above the top ofthe mast, do not hoist a rod column with loose tool joints and do nor make up, tighten or loosentool joints while the rod column is being supported by a slipping device If drill rods should slipback into the borehole, do not attempt to brake the fall of the rods with your hands.

o Most sheaves on drill rigs are stationary with a single part line.. The number of parts of lineshould not ever be increased without first consulting with the manufacturer of the drill rig.. Wireropes must be properly matched with each sheave.

o The following procedures and precautions must be understood and implemented for safe use ofwire rnpes and rigging hardware.

o Use tool handling hoists only for vertical lifting of tools (except when angle hole drilling). Do notuse tool handling hoists to pull on objects away from the drill rig: however drills may be movedusing the main hoist as the wire rope is spooled through proper sheaves according to themanufacturer’s recorrunendations.

• When stuck tools or similar loads cannot be raised with a hoist, disconnect the hoist line andconnect the stuck tools directly to the feed mechanism of the drill. Do not use hydraulic levelingjacks for added pull to the hoist line or the feed mechanism of the drill.

o When attempting to pull out a mired down vehicle or drill rig carrier, only use a winch on thefront or rear of the vehicle or drill rig carrier and stay as far as possible away from the wire rope.Do not attempt to use tool hoists to tow a mired vehicle or drill rig carrier

• Minimize shock loading of a wire rope, apply loads smoothly and steadily.

• Protect wire rope from sharp corners or edges

• Replace faulty guides and rollers

o Replace worn sheaves or worn sheave bearings

Replace damaged safety latches on safety hooks before using

Page 66: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

ESI ()• Know the safe working load of the equipment and tackle being used and never exceed tb_is limit.

• Clutches and brakes of hoists should be periodically inspected and tested,

• Know and do not exceed the rated capacity of hooks, rings, links, swivels, shackles and otherlifting aid&

• Always wear gloves when handling wire ropes.

• Do not guide wire ropes on hoist drums with your bands.

• Following the installation of a new wire rope, first lift a light load to allow the wire rope to adjust.

• Never carry out any hoisting operations when the weather conditions are such that hazards topersonnel, the public or property are created.

• Never leave a load suspended in the air when the hoist is unattended_

• Keep your hands away from hoists, wire rope, hoisting hooks, sheaves and pinch points as slack isbeing taken up and when the load is being hoisted.

Never hoist the load over the head, body or feet of any personnel

B.7 Safe Use of Augers

The following general procedures should be used when advancing a boring with continuous flightor holIowstem augers:

Prepare to start an auger boring with the drill rig level, the clutch or hydraulic rotation controldisengaaed, the transmission in low gear and the engine running at low RPM..

• The operator and tool handler should establish a system of responsibility for the series of variousactivities required for auger drilling, such as connecting and disconnecting auger sections, andinserting and removing the auger fork The operator must assure that the tool handler is wellaway from the auger column and that the auger fork is removed before starting rotation.

• Only use the rnanufacmrers recommended method of securing the auger to the power coupling.Do not touch the coupling or the auger with your hands, a wrench or any other tools duringrotation

• Whenever possible, use tool hoists to handle auger sections

• Never place hands or fingers under the bottom of an auger section when hoisting the auger overthe top of the auger section in the ground or other hard surfaces such as the drill rig platform.

• Never allow feet to get under the auger section that is being hoisted.

• When rotating augers, stay clear of the rotating auger and other rotating components of the drillrig. Never reach behind or around a rotating auger for any reason whatever.

o Never use your hands or feet to move cuttings away from the auger

Page 67: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

ESI®• Augers should be cleaned Ofli when the drill rig is in neuta! and the augers are stopped from

rotating

B.8 Safety During Rotary and Core Drilling

Rotary drilling tools should be safety checked prior to drilling arid should include the following:

• Water swivels and hoisting plugs should be lubricated and checked for frozen bearings beforeuse

• Drill rod chuck jaws should be checked periodically and replaced when necessary.

• The capacities of hoists and sheaves should be checked against the anticipated weight of the drillrod suing plus other expected hoisting loads. All cables should be inspected daily.

Special precautions should be taken for safe rotary or core drilling which involves chucking, jointbreak, hoisting and lowering of drill rods. These special precautions include:

• Drill rods should not be braked during lowering into the hold with drill rod chuck jaws

• Drill rods should not be held or lowered into the hole with pipe wrenches,

• If a string of drill rods are accidentally or inadvertently released into the hole, do not attempt tograb the falling rods with your hands or a wrench.

• In the event of a plugged bit or other circulation blockage, the high pressure in the piping andhose between the pump and the obstruction should be relieved before breaking the first tool joint

• When drill rods are hoisted from the hole, they should be cleaned for safe handling with a rubberor other suitable rod wiper. Do not use your hands to clean drilling fluids from drill rods

• If work must progress over a portable drilling fluid (mud) pit, do not attempt to stand on narrowsides or cross members. The mud pit should be equipped with rough surface, fitted cover panelsof adequate strength to hold drill rig personnel

• Drill rods should not be lified and leaned unsecured against the mast. Either provide some methodof securing the upper ends of the drill rod sections for safe vertical storage or lay the rods down.

o All hydraulic lines should be periodically inspected for integrity and replaced as needed.

B9 Start Tip

All drill rig personnel and visitors should be instructed to “stand clear” of the drill rig immediatelyprior to and during starting of an engine. Make sure all gear boxes are in neutral, all hoist levers aredisengaged, all hydraulic levers are in the correct nonacruating positions and the cathead rope is not on thecathead before starting a drill rig engine.

Bill Safety During Drilling Operations

Safety requires the attention and cooperation of every worker and site visitor. The followingconsiderations should be observed during drilling operations:

• Do not drive the drill rig from hole to hole with the mast irs the raised position.

Page 68: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

€1

ESI C!)• Before raising the mast look up to check for overhead obstructions.

• Before raising the mast, all drill rig personnel and visitors (with exception of the operator) shouldbe cleared from the areas immediately to the rear and the sides of the mast. All drill rig personneland visitors should be informed that the mast is being raised prior to raising it.

• Before the mast of a drill rig is raised and drilling is commenced, the drill rig must be first leveledand stabilized with leveling jacks and/or solid cribbing. The drill rig should be releveled if itsettles after initial set up.. Lower the mast only when leveling jacks are down and do not raise theleveling jack pads until the mast is lowered completely.

• Before starting drilling operations, secure and/or lock the mast if required according to the drillmanufacturer’s recommendations.

• The operator of a drill rig should only operate a drill rig from the position of the controls. Theoperator should shut down the drill engine before leaving the vicinity of the drilL

• Do not consume alcoholic beverages or other depressants or chemical stimulants prior to startingwork on a drill rig or while on the job.

• Watch for slippery ground when mounting or dismounting from the platform.

• All unattended boreholes must be adequately covered or other wise protected to prevent drill rigpersonnel, site visitors or animals from stepping or falling into the hole. AU open boreholesshould be covered, protected or backfilled adequately arid according to local or state regulationson completion of the drilling project

• “Horsing around” within the vicinity of the drill rig and tool and supply storage areas should neverbe allowed, even when the drill rig is shut down

o Be careful when lifting heavy objects.

• Before lifting a relatively heavy object, approach the object by bending at the laiees, keeping yourback vertical and umiarched while obtaining a firm footing. Grasp the object firmly with bothhands and stand slowly and squarely while keeping your back vertical and unarched. In otherwords. perform the lifting with the muscles in your legs. not with the muscles in your lower back.

• Drilling operations should be terminated during an elecincal storm.

Page 69: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

Hercules, Inc.Health and Safety Plan

ESI y

APPENDIX C

MATERIAL SAFETY DATA SHEETS

Page 70: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

international Chemical Safety Cards (WHO/IPC...

International Chemical Safety Cards

Page I o12

DIOXATHION (ISOMER MIXTURE) rcsc: 0883

DIUXAFHIUNS.S-(l,4-Dioxane-2,3-diyl) O,O,OO.totraethyl his (phosphorodithinate

C12H2606P2S4

Molecular mass: 456.5CAS # 78-34-2ThCS # TE3350000ICSC# 0883IN#3018

EC 015-063-00-X

ACUTE AZARDS/PREVENTION FIRST AID!

EXPOSURESYMPTOMS FIRE FIGWrING

,omousubie. Liquta torrnulseions iUopen lames. osm, powoer, carton otoxiac,ositaining organic solvents stay be

larrtntable. Gives-fFireitating or toxicurnes (or gases) in a fire.ins explosion oazsrd will aepena on Insolveot used irs the fot-muladon.

TIULI HYI.zlb.NblAVUIL) - NALLLASbSCUNSULI .EXPOSURE 30°OSURE OF ADOLESCENTS AND )OCTOR!HILDRENt

.onvutsions. urzzsneos. Laoourna entliatton, local esnaust, or oreatnttsg eesn air, rest. Reter tor meoscsl8HA.LATlO scathing. Nausea. Unconsciousness. rotection ttendonc

fomiting. Pupillary constriction, muscleramp. excessive salivation.

i4Ah da .‘usOH±lD! (runner 5CC rotective gloves. Protective clotning. ietrsove contaminasea domes RinseSKIN lhalationi nil then wash skin with water and snapRefer for medical attention.ldiurreo vIsion, ace snicid, or eye protection ‘lb test rinse wits plenty or waler marEYES

ombination with breathing protection everal minutes (remove contact lensesfeasily possible), then take to a doctor.

,

oaommna cramps. Diarrnaea )o not eat, SlinK, or smoo outing worK. 005.1cc vomiting çtJNL’o INLaboured breathing. Nausea. ONSCIOUS PERSONS!) Rest. ReferINGESTION .lnconsciossneos. Vomiting. Pupillary or medical attention:on,nuiction. muscle cramps. excessivealivation.

SPlLLAGDlSPU STORAGE PACGG & LA.ELLIiiGLollect leaking asia spttles tiquma it camaoie separates trorn rood and iseosturts, strong )d not ans’port with tooa acid [eeesrsmtis.:onsainers as far as possible AbsoPa mrtatning xidanis. strong bases Dry Keep in a - symbolliquid in sand or inert absorbent and :entove to bell-ventilated room R: 26/27/28ale place. Do NOT wash away into sewer S: 1-13-2845Cextia personal protection: complete Drolective UN Hazard Class: 6.1lothing including self-contained breathing UN Packing Group: IIipparatus).—_ b,IM?ORiA.iT INFORMA lION UN BALii CSC- 0883 — Prcpa’su ,n sue con,rxi oicoopcnuan oc,wecn cc nccn,ac,ccai Prognansucon Lnc0000, 5arcr Sc arc Ccmnun,cn si u,c Sampan

‘ c,sd= C lP CEc 995

international Chemical Safety Cards

MP0R

roan,,crJ., ROL’TESOTSTATE; EXPOSURE:APPEARANCE The substance canVISCOUS b absorbed intoBROWN LIQUID the body by

inhalation of itsPH’ISTCAL aerosol, throughDANGERS: the skin,by

ingestion.

CHEMICAL INHALATIONDANGERS: RISK:

The substance A harmfuldecomposes on contamination ofheatttig and on the air will not orbuming producing will only verytoxic fi.irriea slowly be reachedincluding on evaporation ofhosphoross this substance at

oxides arid sulfur 20°C on sprayingsxidcs. HydrolyaedDy alktslieo Not EFFECTS OF

DIOXATHION (ISOMER MIXTTJRE)-- ICSC: 0883

http:Ilsiri. uvm.eduJmsds/m’corda 0883 html4127199

Page 71: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

international Chemical Safety Cards (WHO/IPC..Page 2 of 2

Rstable on cosines SHORT-TERM

A with iron and tin. EXPOSURE:The substance

T OCCTJPAT!ONALmay tause effectsEXPOSURE on the nervousLIMiTS (OELs): system, resultingTLV: ppm; 0.2 in convulsions.ma/rn5 (skin) respiratory failure(ACGIH Cholinesrerase1991-1992) rnhibimr

Exposure at highlevel may result indeath Medicalobservatjon isindicated

EFFECTS OFLONG-TERMOR REPEATEDEXPOSURECholinenteraseinhibitor;cumulative effectis possible: seeacutehazartlslsymptorns.

delong point: Solubinsy in-2OC water: NonePHYSICALRelative densityPROPERTIES(wattr I): 12Gat26C

—-

i his substance may Os nalzroous toENVIRONMENTALthe environment; special attentionDATAhosid be given to crustacean and fish.NUIES

iepeuutng on ume ucgrcc 55 cspssurc, pencaic rnecitcat exsrrsnauon is mnotcasea. ._ .-- not oecsame masiteot untit0 minutes to 2 hosr Specific beatteent is necessary in ease of poisoning wish this substance; the appropriate means with insta-uctiorts must bevailnble. Carrier solvents used itt csmrnsercial formulations may changs physical and toxicological properties. Do NOT take working clsthe horns)eltsav. Deltic and Hercules 52S are trade names.Transport Emergency Card: TEC (R)-61 (144

ABDI l’IONAL INFORMAl IONLCSC: OS DIOXATHJON (ISOI4ER MIXTURE)z tPcs. CEC. 1991

Netsner inc t..bL or the 1lC nor any person acting on senate us toe CEL or erie IFCS ta responstole tar fits use wince might SeIMPORTANT frnade of this information. Tnis card contains the collective views of the IPCS Peer Review Comnersinee and may not reflect inLEGA.I_ NOTICE: all cases all the detailed requirements included in national legislatisn on the subject. The user should verify compliascs of shecards with the relevant legislation in the country of use.

hrtp:/Isiri.uvm edu/msdsJmcsrds/file/O883..hn-nI 4/27/99

Page 72: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

Health aiu1 Safety Plan ESI (V)

APPENDIX D

SITE SkFETY MEETING REPORT FORM

Page 73: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

ESI()

SITE SAFETY MEETING REPORT FORM

Project Number and Name: Location:Date and Time:

_____________________

Activity:

_________________________________

Site Manager: Site Health and Safety

________________________

Officer:

_______________

EMERGENCY INFORMATION:

Hospital: Location:

_________________________

Phone:

______________

Fire Department: Location:

_________________________

Phone:

______________

Police Location:

_________________________

Phone:

______________

Ambulance: Location:

___________________________

Phone:

ITEMS DISCUSSED:

ATTENDEES:

Name (Printed) Signature Date

Page 74: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

Health and Safety Plan ESI ()

APPENDIX E

HEALTH AND SAFETY INCIDENT REPORT FORM

Page 75: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

ECOSYSTEMS, iNCHEALTH AND SAYEfl INCIDENT REPORT

Project Number

_____________Date/Time

of Incident___________________________Project Name Project Location______________________________DESCPIPTION OF THE TNCIDENT. Describe below, what happened and possiblecause. Identify individuals involved, witnesses, and their affiliations Describe emergencyand/or corrective action that was taken.

Name of Person Making Report:____________________________________________

NOTh: This report must b sent to Eco”Sysrems HSO ASAP’Reviewed by:____________________________________________________________

Reviewed by:_______________________________________________________

De

Ecu Systems, Inc.

Distribution:EcoSystems Management______________Project Manager_________________________Site Manager___________________________Site I-ISO

Page 76: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

ECOSYSTEMS, INCHEALTH AND SAFETY ]NCmENT REI’ORT

Project Number____________ Date/Time of Incident___________________________Project Name

_________________Project

Location_____________________________

DESCR.TION OF ThE rNCENT. Describe below, what happened and possiblecause. Identi’ individuals involved, witnesses, and their affihiations Describe emergencyandlor corrective action that was taken.

I

Name of Person Making Report:_________________________________

NOTE: This report must be sent to Eco Systems HSO .4SLP’

Reviewed by:_______________________________________

-j

Reviewed by:_____________________________________

EcoSystems, Inc.

Distribution:Eco- Systems Management____________Project Manager________________________Site Manager

_________________________

Site HSO

Page 77: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

() Hercules, Inc.Health and Safety Plan ESI

APPENDIX 1’

ETsIERGENCy SERVJCES[pflo NUMBERS AN]) ROIJTE TO THE HOSPITAL

Page 78: HERCULES I Lic S. Corrective Action Plan Revision 01 JAN ... · 15 16 17 12 12 12 12 12 14 14 14 GES 11 HERCULES-Y1/2O/2OO5. ... Environmental Quality (MDEQ) request in a letter dated

ESI ()EMERGENCY SERVICES/PHONE Nul’mERS AND ROUTE TO THE HOSPITAL

PROJECT: HERCULES, INC.LOCATION: HATTIESBURG, MISSISSIPPIPROJECT NO.: HER24IOO

The directions to the hospital are as follows:

1 From Hercules main gate on 7th Street, go left (eastward) approximately 1/8 mile to MainStreet and turn nght.

2. Go approximatly L2 miles to the coiner of Hall Ave and Main Street.

3. Methodist Hospital is located on the southwest corner.

The list of emergency services must either be posted on-site or carried by all field personneL

Emergency Service Location Telephone

Emergency Number Hattiesburg, Mississippi 911

Fire Department Hattiesburg, Mississippi 601/545-4691

Police Department Hattiesburg Police Dept. 601/544-7900

Ambulance Hattiesburg 601/

Hospital Methodist Hospital 601/

Wesley Medical Center Hattiesburg 601/268-8000

Poison Control Center UMC - Jackson, Miss. 601/354-7660

Rankin Medical CenterEco-Systems Physician. . 601/825-2811Brandon, Mississippi