03/04/2013
Not Only A Slogan
7/28/2019 HCC Training Part 002
http://slidepdf.com/reader/full/hcc-training-part-002 2/44
03/04/2013
CIFA STORY
• CIFA was founded in 1928 starting its business in the steel form works for tunnelling
• early 50ies CIFA started its production of batching plants with weighing bins
instead of volumetric system to measure sand and gravel
• 1958 first Italian truck-mixer manufactured by CIFA
• Late 60ies the first CIFA concrete pump appears• 1975 CIFA invents the mixer-boom pump, achieving an in discussed
leadership all over the world
• 1998 CIFA produces its largest boom pump 52 m vertical reach
• 38.000 truck-mixers manufactured and over than 3.670 batching plants all
over the world
7/28/2019 HCC Training Part 002
http://slidepdf.com/reader/full/hcc-training-part-002 3/44
03/04/2013
PRODUCTION LOCATION
G
Gerenzano
Truck-mixer PumpTrailed concrete pump
13.000 m2 open area
8.300 m2 covered surface
Senago
Formwork 3.200 m2 open area
4.600 m2 covered surface
Castiglione delle
Stiviere Truck-mixer
Batching plants
100.000 m2 open area
12.000 m2 covered surface
Senago
Headquarters
Senago Truck mounted concrete boom pump
Spritz System
30.500 m2 open area
17.200 m2 covered surface
7/28/2019 HCC Training Part 002
http://slidepdf.com/reader/full/hcc-training-part-002 4/44
03/04/2013
HIGHEST LEVEL OF QUALITY
CERTIFICATION ISO 9001
• CIFA means quality
• CIFA was able to be awared with this prestigious certification
for outstanding quality.
7/28/2019 HCC Training Part 002
http://slidepdf.com/reader/full/hcc-training-part-002 5/44
03/04/2013
PRODUCT RANGE OF CIFA
Full line
7/28/2019 HCC Training Part 002
http://slidepdf.com/reader/full/hcc-training-part-002 6/44
03/04/2013
Readymix Range
• Horizontal batching plants
• Mixers for concrete plants• Horizontal concrete plants
• Vertical concrete plants
• Dust exhausting systems
• Recycling systems
• Cement silos
• Truck-mixers
• Truck-mixers pumps
7/28/2019 HCC Training Part 002
http://slidepdf.com/reader/full/hcc-training-part-002 7/44
03/04/2013
Pumping Range
• Truck-mounted concrete boom Pumps
• Portable concrete pumps
• Stationary placing booms
7/28/2019 HCC Training Part 002
http://slidepdf.com/reader/full/hcc-training-part-002 8/44
03/04/2013
Tunnelling Range
• Sprayed concrete equipment
• Formwork for tunnels
• Prefabrication plants for tunnel segments
• Trainmix
• Concreting train system
7/28/2019 HCC Training Part 002
http://slidepdf.com/reader/full/hcc-training-part-002 9/44
03/04/2013
CIFA PRESENT POPULATION
Truck-mixers
Truck-mounted concrete boom pumps
and trailed concrete pumps
Truck-mixer pumps
Concrete and batching plants
Spritz System
Concrete tunnelling trains
Formwork for tunnels, dams,
brake-water, bridges “countless“
38.000
4.970
3.120
3.670
440
125
7/28/2019 HCC Training Part 002
http://slidepdf.com/reader/full/hcc-training-part-002 10/44
03/04/2013
CIFA 2004 ACTIVITIES
• CIFA Spritz System
• Concrete pump model K3/36
Only 36 m second hand Boom Pump
in INDIA purchased by HCC
7/28/2019 HCC Training Part 002
http://slidepdf.com/reader/full/hcc-training-part-002 11/44
03/04/2013
SELECTION OF PUMPS
7/28/2019 HCC Training Part 002
http://slidepdf.com/reader/full/hcc-training-part-002 12/44
03/04/2013
SELECTION OF PUMPS
CRITERIA FOR SELECTION OF CONCRETE PUMP
Technical Identification Number
The construction industry demanded that concrete pumps
should be categorized so that the characteristics of performance can be
taken from the classification value. The data regarding the max. output
(m³/h) and the max. pumping pressure (bar) do not reveal to the user
whether the equipment meets his requirements. It cannot be seen from
these data under what circumstances the max. output can be achieved .It is obvious that a concrete pump placing 50 m³ of concrete per hour
over a horizontal distance of 400 m will need a stronger power unit than
a pump conveying this volume through the same, but only 100 m long
pipeline. The delivery output Q at a given power P depends on the
placing pressure p.
P = Q x p
This means that when choosing a concrete pump, the user should also
know the required power of the equipment in addition to the delivery
output and the pumping pressure.
7/28/2019 HCC Training Part 002
http://slidepdf.com/reader/full/hcc-training-part-002 13/44
03/04/2013
SELECTION OF PUMPS
The hydraulic output formula
“The required power is the product of delivery output and pumping
pressure”
P = Q X p = Constant
Says that at a given power the delivery output of the concrete pump
decreases whenever the pumping pressure increases. The product of
concrete delivery output in m³/h and concrete pumping pressure in bar will be described as “TECHNICAL IDENTIFICATION NUMBER” TK.
TK = (m³/h X bar)
Based on this technical identification number, the required power of the
equipment (in kW) can be ascertained from the quotient of TK and 25:P (kW) = TK/25 = (m³/h X bar)/25
The constant value 25 contains total efficiency of 0.7 for the complete
system besides the conversion factors
1 W = 1 Nm/s : 1 bar = 10N/cm²
7/28/2019 HCC Training Part 002
http://slidepdf.com/reader/full/hcc-training-part-002 14/44
7/28/2019 HCC Training Part 002
http://slidepdf.com/reader/full/hcc-training-part-002 15/44
03/04/2013
• CIFA Spritz System
7/28/2019 HCC Training Part 002
http://slidepdf.com/reader/full/hcc-training-part-002 16/44
03/04/2013
• CIFA Spritz System
7/28/2019 HCC Training Part 002
http://slidepdf.com/reader/full/hcc-training-part-002 17/44
03/04/2013
7/28/2019 HCC Training Part 002
http://slidepdf.com/reader/full/hcc-training-part-002 18/44
03/04/2013
7/28/2019 HCC Training Part 002
http://slidepdf.com/reader/full/hcc-training-part-002 19/44
03/04/2013
7/28/2019 HCC Training Part 002
http://slidepdf.com/reader/full/hcc-training-part-002 20/44
03/04/2013
7/28/2019 HCC Training Part 002
http://slidepdf.com/reader/full/hcc-training-part-002 21/44
03/04/2013
7/28/2019 HCC Training Part 002
http://slidepdf.com/reader/full/hcc-training-part-002 22/44
03/04/2013
7/28/2019 HCC Training Part 002
http://slidepdf.com/reader/full/hcc-training-part-002 23/44
03/04/2013
CIFA 2004 ACTIVITIES
7/28/2019 HCC Training Part 002
http://slidepdf.com/reader/full/hcc-training-part-002 24/44
03/04/2013
CIFA 2004 ACTIVITIES
7/28/2019 HCC Training Part 002
http://slidepdf.com/reader/full/hcc-training-part-002 25/44
03/04/2013
CIFA 2004 ACTIVITIES
7/28/2019 HCC Training Part 002
http://slidepdf.com/reader/full/hcc-training-part-002 26/44
03/04/2013
CIFA 2004 ACTIVITIES
7/28/2019 HCC Training Part 002
http://slidepdf.com/reader/full/hcc-training-part-002 27/44
03/04/2013
CIFA 2004 ACTIVITIES
7/28/2019 HCC Training Part 002
http://slidepdf.com/reader/full/hcc-training-part-002 28/44
03/04/2013
7/28/2019 HCC Training Part 002
http://slidepdf.com/reader/full/hcc-training-part-002 29/44
03/04/2013
7/28/2019 HCC Training Part 002
http://slidepdf.com/reader/full/hcc-training-part-002 30/44
03/04/2013
DON’TS
7/28/2019 HCC Training Part 002
http://slidepdf.com/reader/full/hcc-training-part-002 31/44
03/04/2013
7/28/2019 HCC Training Part 002
http://slidepdf.com/reader/full/hcc-training-part-002 32/44
03/04/2013
7/28/2019 HCC Training Part 002
http://slidepdf.com/reader/full/hcc-training-part-002 33/44
03/04/2013
7/28/2019 HCC Training Part 002
http://slidepdf.com/reader/full/hcc-training-part-002 34/44
03/04/2013
7/28/2019 HCC Training Part 002
http://slidepdf.com/reader/full/hcc-training-part-002 35/44
03/04/2013
7/28/2019 HCC Training Part 002
http://slidepdf.com/reader/full/hcc-training-part-002 36/44
03/04/2013
7/28/2019 HCC Training Part 002
http://slidepdf.com/reader/full/hcc-training-part-002 37/44
03/04/2013
7/28/2019 HCC Training Part 002
http://slidepdf.com/reader/full/hcc-training-part-002 38/44
03/04/2013
7/28/2019 HCC Training Part 002
http://slidepdf.com/reader/full/hcc-training-part-002 39/44
03/04/2013
CIFA 2004 ACTIVITIES
7/28/2019 HCC Training Part 002
http://slidepdf.com/reader/full/hcc-training-part-002 40/44
03/04/2013
CIFA 2004 ACTIVITIES
• MK 24.4 Z
Transit Mixer, Boom Pump
and Concrete Pump together
in one machine. CIFA is a
world leader in this category.
• MK 28.4 Z
7/28/2019 HCC Training Part 002
http://slidepdf.com/reader/full/hcc-training-part-002 41/44
03/04/2013
CIFA 2004 ACTIVITIES
7/28/2019 HCC Training Part 002
http://slidepdf.com/reader/full/hcc-training-part-002 42/44
03/04/2013
CIFA News
Transit Mixer of Light Weight 9 Cubic
Meter Capacity
• SL9
7/28/2019 HCC Training Part 002
http://slidepdf.com/reader/full/hcc-training-part-002 43/44
03/04/2013
CIFA 2004 ACTIVITIES
7/28/2019 HCC Training Part 002
http://slidepdf.com/reader/full/hcc-training-part-002 44/44
CIFA WORLD EXPANSION
1999 Established CIFA USA Inc.
The company is responsible for the sale and service in the
United States
2000 Signed the agreement for the manufacturing of truck-mixersand trailer-pumps in India with Greaves Cotton Limited
2001 Agreement to establish an industrial joint-venture for the
production of machines in Mexico