CIFA STORY

• CIFA was founded in 1928 starting its business in the steel form works for tunnelling

• early 50ies CIFA started its production of batching plants with weighing bins

instead of volumetric system to measure sand and gravel

• 1958 first Italian truck-mixer manufactured by CIFA

• Late 60ies the first CIFA concrete pump appears• 1975 CIFA invents the mixer-boom pump, achieving an in discussed

leadership all over the world

• 1998 CIFA produces its largest boom pump 52 m vertical reach

• 38.000 truck-mixers manufactured and over than 3.670 batching plants all

over the world

Page 3: HCC Training Part 002

7/28/2019 HCC Training Part 002

http://slidepdf.com/reader/full/hcc-training-part-002 3/44

03/04/2013 

PRODUCTION LOCATION

G

Gerenzano 

Truck-mixer PumpTrailed concrete pump 

13.000 m2 open area

8.300 m2 covered surface 

Senago 

Formwork  3.200 m2 open area

4.600 m2 covered surface

Castiglione delle

Stiviere Truck-mixer

Batching plants 

100.000 m2 open area

12.000 m2 covered surface

Senago 

Headquarters 

Senago Truck mounted concrete boom pump

Spritz System 

30.500 m2 open area

17.200 m2 covered surface

Page 4: HCC Training Part 002

7/28/2019 HCC Training Part 002

http://slidepdf.com/reader/full/hcc-training-part-002 4/44

03/04/2013 

HIGHEST LEVEL OF QUALITY

CERTIFICATION ISO 9001

• CIFA means quality

• CIFA was able to be awared with this prestigious certification

for outstanding quality.

Page 5: HCC Training Part 002

7/28/2019 HCC Training Part 002

http://slidepdf.com/reader/full/hcc-training-part-002 5/44

03/04/2013 

PRODUCT RANGE OF CIFA 

Full line 

Page 6: HCC Training Part 002

7/28/2019 HCC Training Part 002

http://slidepdf.com/reader/full/hcc-training-part-002 6/44

03/04/2013 

Readymix Range 

• Horizontal batching plants

• Mixers for concrete plants• Horizontal concrete plants

• Vertical concrete plants

• Dust exhausting systems

• Recycling systems

• Cement silos

• Truck-mixers

• Truck-mixers pumps

Page 7: HCC Training Part 002

7/28/2019 HCC Training Part 002

http://slidepdf.com/reader/full/hcc-training-part-002 7/44

03/04/2013 

Pumping Range

• Truck-mounted concrete boom Pumps

• Portable concrete pumps

• Stationary placing booms

Page 8: HCC Training Part 002

7/28/2019 HCC Training Part 002

http://slidepdf.com/reader/full/hcc-training-part-002 8/44

03/04/2013 

Tunnelling Range 

• Sprayed concrete equipment

• Formwork for tunnels

• Prefabrication plants for tunnel segments

• Trainmix

• Concreting train system

Page 9: HCC Training Part 002

7/28/2019 HCC Training Part 002

http://slidepdf.com/reader/full/hcc-training-part-002 9/44

03/04/2013 

CIFA PRESENT POPULATION

Truck-mixers

Truck-mounted concrete boom pumps

and trailed concrete pumps

Truck-mixer pumps

Concrete and batching plants

Spritz System

Concrete tunnelling trains

Formwork for tunnels, dams,

 brake-water, bridges “countless“ 

38.000

4.970

3.120

3.670

440

125

Page 10: HCC Training Part 002

7/28/2019 HCC Training Part 002

http://slidepdf.com/reader/full/hcc-training-part-002 10/44

03/04/2013 

CIFA 2004 ACTIVITIES 

• CIFA Spritz System

• Concrete pump model K3/36

Only 36 m second hand Boom Pump

in INDIA purchased by HCC

Page 11: HCC Training Part 002

7/28/2019 HCC Training Part 002

http://slidepdf.com/reader/full/hcc-training-part-002 11/44

03/04/2013 

SELECTION OF PUMPS

Page 12: HCC Training Part 002

7/28/2019 HCC Training Part 002

http://slidepdf.com/reader/full/hcc-training-part-002 12/44

03/04/2013 

SELECTION OF PUMPS

CRITERIA FOR SELECTION OF CONCRETE PUMP

 Technical Identification Number

The construction industry demanded that concrete pumps

should be categorized so that the characteristics of performance can be

taken from the classification value. The data regarding the max. output

(m³/h) and the max. pumping pressure (bar) do not reveal to the user 

whether the equipment meets his requirements. It cannot be seen from

these data under what circumstances the max. output can be achieved .It is obvious that a concrete pump placing 50 m³ of concrete per hour 

over a horizontal distance of 400 m will need a stronger power unit than

a pump conveying this volume through the same, but only 100 m long

pipeline. The delivery output Q at a given power P depends on the

placing pressure p.

P = Q x p

This means that when choosing a concrete pump, the user should also

know the required power of the equipment in addition to the delivery

output and the pumping pressure.

Page 13: HCC Training Part 002

7/28/2019 HCC Training Part 002

http://slidepdf.com/reader/full/hcc-training-part-002 13/44

03/04/2013 

SELECTION OF PUMPS

The hydraulic output formula

“The required power is the product of delivery output and pumping

pressure” 

P = Q X p = Constant

Says that at a given power the delivery output of the concrete pump

decreases whenever the pumping pressure increases. The product of 

concrete delivery output in m³/h and concrete pumping pressure in bar  will be described as “TECHNICAL IDENTIFICATION NUMBER” TK.

TK = (m³/h X bar)

Based on this technical identification number, the required power of the

equipment (in kW) can be ascertained from the quotient of TK and 25:P (kW) = TK/25 = (m³/h X bar)/25

The constant value 25 contains total efficiency of 0.7 for the complete

system besides the conversion factors

1 W = 1 Nm/s : 1 bar = 10N/cm² 

Page 14: HCC Training Part 002

7/28/2019 HCC Training Part 002

http://slidepdf.com/reader/full/hcc-training-part-002 14/44

Page 15: HCC Training Part 002

7/28/2019 HCC Training Part 002

http://slidepdf.com/reader/full/hcc-training-part-002 15/44

03/04/2013 

• CIFA Spritz System

Page 16: HCC Training Part 002

7/28/2019 HCC Training Part 002

http://slidepdf.com/reader/full/hcc-training-part-002 16/44

03/04/2013 

• CIFA Spritz System

Page 17: HCC Training Part 002

7/28/2019 HCC Training Part 002

http://slidepdf.com/reader/full/hcc-training-part-002 17/44

03/04/2013 

Page 18: HCC Training Part 002

7/28/2019 HCC Training Part 002

http://slidepdf.com/reader/full/hcc-training-part-002 18/44

03/04/2013 

Page 19: HCC Training Part 002

7/28/2019 HCC Training Part 002

http://slidepdf.com/reader/full/hcc-training-part-002 19/44

03/04/2013 

Page 20: HCC Training Part 002

7/28/2019 HCC Training Part 002

http://slidepdf.com/reader/full/hcc-training-part-002 20/44

03/04/2013 

Page 21: HCC Training Part 002

7/28/2019 HCC Training Part 002

http://slidepdf.com/reader/full/hcc-training-part-002 21/44

03/04/2013 

Page 22: HCC Training Part 002

7/28/2019 HCC Training Part 002

http://slidepdf.com/reader/full/hcc-training-part-002 22/44

03/04/2013 

Page 23: HCC Training Part 002

7/28/2019 HCC Training Part 002

http://slidepdf.com/reader/full/hcc-training-part-002 23/44

03/04/2013 

CIFA 2004 ACTIVITIES 

Page 24: HCC Training Part 002

7/28/2019 HCC Training Part 002

http://slidepdf.com/reader/full/hcc-training-part-002 24/44

03/04/2013 

CIFA 2004 ACTIVITIES 

Page 25: HCC Training Part 002

7/28/2019 HCC Training Part 002

http://slidepdf.com/reader/full/hcc-training-part-002 25/44

03/04/2013 

CIFA 2004 ACTIVITIES 

Page 26: HCC Training Part 002

7/28/2019 HCC Training Part 002

http://slidepdf.com/reader/full/hcc-training-part-002 26/44

03/04/2013 

CIFA 2004 ACTIVITIES 

Page 27: HCC Training Part 002

7/28/2019 HCC Training Part 002

http://slidepdf.com/reader/full/hcc-training-part-002 27/44

03/04/2013 

CIFA 2004 ACTIVITIES 

Page 28: HCC Training Part 002

7/28/2019 HCC Training Part 002

http://slidepdf.com/reader/full/hcc-training-part-002 28/44

03/04/2013 

Page 29: HCC Training Part 002

7/28/2019 HCC Training Part 002

http://slidepdf.com/reader/full/hcc-training-part-002 29/44

03/04/2013 

Page 30: HCC Training Part 002

7/28/2019 HCC Training Part 002

http://slidepdf.com/reader/full/hcc-training-part-002 30/44

03/04/2013 

DON’TS 

Page 31: HCC Training Part 002

7/28/2019 HCC Training Part 002

http://slidepdf.com/reader/full/hcc-training-part-002 31/44

03/04/2013 

Page 32: HCC Training Part 002

7/28/2019 HCC Training Part 002

http://slidepdf.com/reader/full/hcc-training-part-002 32/44

03/04/2013 

Page 33: HCC Training Part 002

7/28/2019 HCC Training Part 002

http://slidepdf.com/reader/full/hcc-training-part-002 33/44

03/04/2013 

Page 34: HCC Training Part 002

7/28/2019 HCC Training Part 002

http://slidepdf.com/reader/full/hcc-training-part-002 34/44

03/04/2013 

Page 35: HCC Training Part 002

7/28/2019 HCC Training Part 002

http://slidepdf.com/reader/full/hcc-training-part-002 35/44

03/04/2013 

Page 36: HCC Training Part 002

7/28/2019 HCC Training Part 002

http://slidepdf.com/reader/full/hcc-training-part-002 36/44

03/04/2013 

Page 37: HCC Training Part 002

7/28/2019 HCC Training Part 002

http://slidepdf.com/reader/full/hcc-training-part-002 37/44

03/04/2013 

Page 38: HCC Training Part 002

7/28/2019 HCC Training Part 002

http://slidepdf.com/reader/full/hcc-training-part-002 38/44

03/04/2013 

Page 39: HCC Training Part 002

7/28/2019 HCC Training Part 002

http://slidepdf.com/reader/full/hcc-training-part-002 39/44

03/04/2013 

CIFA 2004 ACTIVITIES 

Page 40: HCC Training Part 002

7/28/2019 HCC Training Part 002

http://slidepdf.com/reader/full/hcc-training-part-002 40/44

03/04/2013 

CIFA 2004 ACTIVITIES 

• MK 24.4 Z

Transit Mixer, Boom Pump

and Concrete Pump together 

in one machine. CIFA is a

world leader in this category.

• MK 28.4 Z

Page 41: HCC Training Part 002

7/28/2019 HCC Training Part 002

http://slidepdf.com/reader/full/hcc-training-part-002 41/44

03/04/2013 

CIFA 2004 ACTIVITIES 

Page 42: HCC Training Part 002

7/28/2019 HCC Training Part 002

http://slidepdf.com/reader/full/hcc-training-part-002 42/44

03/04/2013 

CIFA News 

Transit Mixer of Light Weight 9 Cubic

Meter Capacity 

• SL9

Page 43: HCC Training Part 002

7/28/2019 HCC Training Part 002

http://slidepdf.com/reader/full/hcc-training-part-002 43/44

03/04/2013 

CIFA 2004 ACTIVITIES 

Page 44: HCC Training Part 002

7/28/2019 HCC Training Part 002

http://slidepdf.com/reader/full/hcc-training-part-002 44/44

CIFA WORLD EXPANSION 

1999 Established CIFA USA Inc.

The company is responsible for the sale and service in the

United States

2000 Signed the agreement for the manufacturing of truck-mixersand trailer-pumps in India with Greaves Cotton Limited

2001 Agreement to establish an industrial joint-venture for the

production of machines in Mexico