Hampton Boulevard Traffic Shifts to New Underpass

1
VDOT Hampton Boulevard Grade Separation Project April 2015 Update Hampton Boulevard First Underpass Main Slab Pour (September 2014) Project Location: Hampton Boulevard between Maple Shade Avenue and B Avenue Project Update : All rail work was completed and is now in use. All concrete slabs, the special design retaining wall and the median for the underpass have been completed. Crews are currently constructing parapet walls, curbs and sidewalks for the underpass. Paving in the underpass started in February and phased traffic switches into the underpass should start after paving is complete. The traffic switches will occur in May and June and will include a closure to Greenbrier Avenue and at times, two lanes each direction on Hampton Boulevard itself. There will be electrical/street lighting, signal, signage, pavement marking, final drainage, and demolition of the temporary detour road to complete the project on its present schedule, in Summer of 2015. Project Overview: The Hampton Boulevard (Route 337) Grade Separation project is step two in the four step process of completing the Navy Triangle Improvements. * The four phases of the Navy Triangle Improvements include (i) Fleet Recreational Park (ii) Hampton Boulevard Grade Separation (iii) Intermodal Connector and (iv) Patriots Crossing. During this construction project, the existing at-grade conflict with the Norfolk Southern/Norfolk Portsmouth Beltline railroad and Hampton Boulevard (Route 337) will be removed. The current crossing creates significant delays for motorists and railway carriers on this heavily traveled thoroughfare. The railroad crossing conflict will be eradicated by depressing Hampton Boulevard below the existing railroad tracks thus eliminating the need to interrupt vehicular traffic for railway movement in to and out of the port terminals. The ½ mile improvement project will provide six lanes for through traffic and a 13-foot median for left turn lanes, as needed. The proposed roadway will also provide improved roadway lighting, signals, drainage, landscaping, bike lanes, curb/gutter and sidewalks. During construction, a temporary 6-lane detour roadway with adequate median for turn lanes was built to provide access into both Norfolk International Terminal and the US Navys Gate 6 while maintaining the same capacity as the existing Hampton Boulevard. Following construction of the permanent underpass, the temporary detour roadway will be demolished under this project. Total Project Costs : $105 Million (Six Year Improvement Program) (Project is Federally & State Funded. Norfolk Utilities contributed $117,000 for water betterment.) Schedule: Summer 2009 - Summer 2015

description

The underpass is the second phase of the Navy Triangle Improvement project that includes Fleet Recreational Park, the Intermodal Connector and Patriot’s Crossing.

Transcript of Hampton Boulevard Traffic Shifts to New Underpass

  • VDOT Hampton Boulevard Grade Separation ProjectApril 2015 Update

    Hampton Boulevard First Underpass Main Slab Pour (September 2014)

    Project Location: Hampton Boulevard between Maple Shade Avenue and B Avenue

    Project Update : All rail work was completed and is now in use. All concrete slabs, the special designretaining wall and the median for the underpass have been completed. Crews are currently constructingparapet walls, curbs and sidewalks for the underpass. Paving in the underpass started in February andphased traffic switches into the underpass should start after paving is complete. The traffic switches willoccur in May and June and will include a closure to Greenbrier Avenue and at times, two lanes eachdirection on Hampton Boulevard itself. There will be electrical/street lighting, signal, signage, pavementmarking, final drainage, and demolition of the temporary detour road to complete the project on itspresent schedule, in Summer of 2015.

    Project Overview: The Hampton Boulevard (Route 337) Grade Separation project is step two in thefour step process of completing the Navy Triangle Improvements. * The four phases of the NavyTriangle Improvements include (i) Fleet Recreational Park (ii) Hampton Boulevard Grade Separation (iii)Intermodal Connector and (iv) Patriots Crossing.

    During this construction project, the existing at-grade conflict with the Norfolk Southern/NorfolkPortsmouth Beltline railroad and Hampton Boulevard (Route 337) will be removed. The current crossingcreates significant delays for motorists and railway carriers on this heavily traveled thoroughfare. Therailroad crossing conflict will be eradicated by depressing Hampton Boulevard below the existing railroadtracks thus eliminating the need to interrupt vehicular traffic for railway movement in to and out of the portterminals.

    The mile improvement project will provide six lanes for through traffic and a 13-foot median for left turnlanes, as needed. The proposed roadway will also provide improved roadway lighting, signals, drainage,landscaping, bike lanes, curb/gutter and sidewalks.

    During construction, a temporary 6-lane detour roadway with adequate median for turn lanes was built toprovide access into both Norfolk International Terminal and the US Navys Gate 6 while maintaining thesame capacity as the existing Hampton Boulevard. Following construction of the permanent underpass,the temporary detour roadway will be demolished under this project.

    Total Project Costs : $105 Million (Six Year Improvement Program)(Project is Federally & State Funded. Norfolk Utilities contributed $117,000 for water betterment.)

    Schedule: Summer 2009 - Summer 2015