The Project for the Improvement of Water Supply, Sewerage and Drainage System in Yangon City Vol IV Water Supply System Feasibility Study, Appendix H-1 H RESULT OF SOIL INVESTIGATION GEOLOGY OF YANGON AREA The geology of Yangon area was classified into the following geological units: (a) Quaternary deposits - 4. Upper Delta Alluvium, Pleistocene and Recent - 3. Lower Delta Alluvium, Pleistocene (b) Tertiary deposits - 2. Irrawaddian Series, Pliocene - 1. Pegu Series, Oligocene-Miocene The regional geological study has been made in an area which includes ridges and deltaic lands lying south of the Bago Yoma. This area is in a north-south trending synclinal basin containing a thick Tertiary - Quaternary deposits. The Tertiary deposits are strongly folded into narrow en-echelon anticlinal folds such as the ridge, which is trending south towards the Gulf of Martaban. The rocks of the Tertiary age contain well-consolidated marine sandstone and shales of the Pegu Group and semi-consolidated, continental deltaic and marginal marine (?) deposits of the Irrawaddy Formation. The synclinal valley west of the Yangon anticlinal ridge is filled with unconsolidated water laid deposit of Quaternary age. These form a wedge shaped alluvial accumulation ranging in thickness from a few meter near the ridge about 60 to 90 meter in the valley. These sediments include clays, silts, sands and predominantly fine to coarse gravels. The Boreholes Location Points with the geological Map of Yangon area is presented as following. Source: Myint Lwin Thein et al., 1972 The Boreholes Location Points with the Geological Map of Yangon Area Bahan BH1 Dagon BH1 Botataung BH1 North Dagon BH1 South Dagon BH1 East Dagon BH1~5 Bago River Right Bank BH1 Bago River Left Bank BH1

Transcript of H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT...

Page 1: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

The Project for the Improvement of Water Supply, Sewerage and Drainage System in Yangon City Vol IV Water Supply System Feasibility Study, Appendix

H-1

H RESULT OF SOIL INVESTIGATION GEOLOGY OF YANGON AREA

The geology of Yangon area was classified into the following geological units: (a) Quaternary deposits

- 4. Upper Delta Alluvium, Pleistocene and Recent - 3. Lower Delta Alluvium, Pleistocene

(b) Tertiary deposits - 2. Irrawaddian Series, Pliocene - 1. Pegu Series, Oligocene-Miocene

The regional geological study has been made in an area which includes ridges and deltaic lands lying south of the Bago Yoma. This area is in a north-south trending synclinal basin containing a thick Tertiary - Quaternary deposits.

The Tertiary deposits are strongly folded into narrow en-echelon anticlinal folds such as the ridge, which is trending south towards the Gulf of Martaban.

The rocks of the Tertiary age contain well-consolidated marine sandstone and shales of the Pegu Group and semi-consolidated, continental deltaic and marginal marine (?) deposits of the Irrawaddy Formation. The synclinal valley west of the Yangon anticlinal ridge is filled with unconsolidated water laid deposit of Quaternary age. These form a wedge shaped alluvial accumulation ranging in thickness from a few meter near the ridge about 60 to 90 meter in the valley. These sediments include clays, silts, sands and predominantly fine to coarse gravels.

The Boreholes Location Points with the geological Map of Yangon area is presented as following.

Source: Myint Lwin Thein et al., 1972 The Boreholes Location Points with the Geological Map of Yangon Area

●Bahan BH‐1 

●Dagon BH‐1 

●Botataung BH‐1 

●North Dagon BH‐1 

●South Dagon BH‐1 

●   

East Dagon BH‐1~5 

Bago River Right Bank BH‐1 

● ● 

Bago River Left Bank BH‐1 

Page 2: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

2

3.0 LOCATION OF THE PROJECT SITE

The proposed site of The Improvement Of Water supply is situated near San Chuan Restaurant, Bahan Township, Yangon Division. The location of project site is shown in Fig. (1) .

Fig. (1) Location Map of the Project Area

4.0 METHODS OF INVESTIGATION

Wash boring method up to the depth of 30m and sampling program of 1m up to depth of 30m intervals were specified. Borehole sounding test or Standard Penetration Test was performed in accordance with ASTM-D1586 standard. Bore logging and visual soil classification were made. The ground water table was measured and recorded. The soil profile and its corresponding SPT-N values are graphically presented in this report. It is compiled with the lab test result on the disturbed but representative samples.

5.0 GEOLOGY OF YANGON AREA

The geology of Yangon area was classified into the following geological units: (a) Quaternary deposits

- 4. Upper Delta Alluvium, Pleistocene and Recent

- 3. Lower Delta Alluvium, Pleistocene

(b) Tertiary deposits

- 2. Irrawaddian Series, Pliocene

- 1. Pegu Series, Oligocene-Miocene

H-2

Bahan BH-1 for Kokine Service Reservoir

Page 3: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

1ProjectLocation : Bahan TownshipCoordinatesElevation (m) : 37.63 m

Very Soft

3.00

6.00

9.00

35.63

34.63

33.63

32.63

Hard

Density of Cohesionless Soils

1.71

0.90

2.34

2.52

2.14

1.37

UD

1.84Gray and yellowish brown, very firm, Silty CLAY

( 5.5 m ~ 6.5 m ).

30.63

29.63

28.639

8

7

18

12

>50

8 - 15

15 - 30

Very Loose

Loose Sand

10 - 30

<4 Soft 4 - 10

<2

2 - 4

4 - 8 Medium Medium Dense

>30

10

Strength of Consistency of Cohesive Soils

Gray, firm, Silty CLAY ( 6.5 m ~ 7.5 m ).

Firm

Very Firm

Type of Sample

Gray, Silty CLAY ( 7.5 m ~ 10.0 m ).

27.63

UD

5.3647

Disturbed Sample (Split spoon)

Rock Sample

Undisturbed Sample

1

Soil Description

36.63

Reddish brown, firm to very firm, Clayey SILT with lateritic soil

( 0.0 m ~ 3.5 m ).

Reddish brown, very firm, Clayey SILT with lateric soil

( 3.5 m ~ 5.5 m ).

31.636

2

3

4

5

SOILINVERSTIGATIONLOG

19

10

26

28

: The Improvement Of Water Supply

: N-1860987.90,E-197174.6

SPT (N-Value)

of 3: 1: 30 m

Sheet

: 7.95 m: Than Maung

Field Bearing capacity calculated

from SPT value (Ton/ft2)

30 - 50 Dense

21

Very Dense

: Automatic: 23 . 3 . 2013: 25 . 3 . 2013: Phyo Ko Ko Oo: Wai Phyo Aung

Type of HammerBoring StartedBoring CompletedLogged byChecked by

Hole NoTotal Depth (m)Water Level (m)Driller

H-3

Page 4: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

2ProjectLocation : Bahan TownshipCoordinatesElevation (m) : 37.626 m

20.00

18.00

15.00

12.00

39

: Phyo Ko Ko OoChecked by : Wai Phyo Aung

SOILINVERSTIGATIONLOG

11 26.63

12 25.63

14 23.63

Boring Completed : 25 . 3 . 2013: N-1860987.90,E-197174.6 Logged by

: The Improvement Of Water Supply

Soil Description

: 30 m

Sheet of 3: 1

Very Soft <4 Very LooseUndisturbed Sample 2 - 4 Soft 4 - 10 Loose Sand

Rock Sample 15 - 30 Very Firm >50 Very Dense

13 24.63

Yellowish brown, medium dense to dense, Silty SAND with a little amount of Clay

( 10.0 m ~ 20.0 m ).

Yellowish brown, medium dense to dense, Silty SAND with a little amount of Clay

( 10.0 m ~ 20.0 m ).

Boring Started : 23 . 3 . 2013 Hole No

Dense

4.32

4.08

15 22.63 3.72

3.60

17

4.68

Total Depth (m)Water Level (m)Driller

3.84

2.76

3.36

: Than Maung

4.68

Type of Hammer : Automatic

4.4419 18.63

20.63

36

32

31

30

Field Bearing capacity calculated

from SPT value (Ton/ft2)

SPT (N-Value)

: 7.95 m

16 21.63

18 19.63

Disturbed Sample (Split spoon) 4 - 8 Medium 10 - 30 Medium Dense8 - 15 Firm 30 - 50

20 17.63Type of Sample Strength of Consistency of Cohesive Soils Density of Cohesionless Soils

<2

23

28

34

37

39

H-4

Page 5: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

3ProjectLocation : Bahan TownshipCoordinatesElevation (m) : 37.626 m

4.80

Reddish brown,dense, Silty SAND with a little amount of Clay

( 20.0 m ~ 22.5 m ).

23

Yellowish brown,very dense, Silty SAND ( 22.5 m ~ 30.0 m ).

>50

>50 >5

: 7.95 m: Than Maung

Sheet of 3: 1

40

Type of Hammer : Automatic: The Improvement Of Water Supply Boring Started : 23 . 3 . 2013

38

22 15.63

27 10.63 >527.00

24.00

14.63 >50

24 13.63 >5

25 12.63 >5

>50

26 11.63

8.63 >5

30 7.63 >5

>50

>5030.00

28 9.63 >5>50

8 - 15 Firm 30 - 50 DenseRock Sample 15 - 30 Very Firm >50 Very Dense

21.00 4.56

: Wai Phyo Aung

Disturbed Sample (Split spoon) 4 - 8 Medium 10 - 30 Medium Dense

Type of Sample Strength of Consistency of Cohesive Soils Density of Cohesionless Soils<2 Very Soft <4 Very Loose

Undisturbed Sample 2 - 4 Soft 4 - 10 Loose Sand

29

>5

Soil DescriptionSPT

(N-Value)

: 30 m

SOILINVERSTIGATIONLOG

Hole NoBoring Completed : 25 . 3 . 2013 Total Depth (m)

: N-1860987.90,E-197174.6

Field Bearing capacity calculated

from SPT value (Ton/ft2)

21 16.63

Logged by : Phyo Ko Ko Oo Water Level (m)Checked by

>50

Driller

H-5

Page 6: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

Fr To ( % ) ( % ) ( % ) ( % ) ( % ) ( % ) ( % ) ( % ) g/cm3 g/cm3 kg/cm2 ( ° ) kg/cm2 kg/cm2

1 1.00 1.45 2.56 0.00 46.20 33.91 16.50 17.41 19.7 2.03 1.69 0.30 11.00 0.41

2 3.00 3.45 2.56 0.00 41.84 41.45 21.46 19.99 24.00 2.00 1.61 0.42 14.00 0.53

3 6.00 6.45 2.51 0.00 14.40 35.89 19.38 16.51 18.7 1.94 1.63 0.32 8.00 0.38

4 7.00 7.45 2.48 0.00 2.60 45.88 26.07 19.81 29.17 1.96 1.52 0.31 5.00 0.44

5 8.00 9.00 2.50 0.00 4.68 40.51 22.00 18.51 30.50 1.89 1.45 0.35 5.00 0.36 0.83 2.60 0.27

6 9.00 10.00 2.52 0.00 7.54 41.31 23.48 17.83 31.70 1.88 1.43 0.32 6.00 0.34 0.86 2.20 0.26

Gray colour, very firm ,SiltyCLAY with alittle amount of sand . 85.60

97.40

Gravel Sand

SOIL TEST RESULTSProject : The Improvement of Water Supply Project

Location : Bahan , Yangon Borehole No

Date : 24-4-2013

Reddish Brown colour, very firm ,Clayey Silt and sand (Lateriticsoil) .

Clay

53.80

Reddish Brown colour, SiltyCLAY with trace amount of Sand .

92.46

Silt

Reddish Brown colour, very firm ,Clayey Silt and sand (Lateriticsoil) .

58.16

Gray colour, Silty CLAY withtrace amount of Sand . 95.32

Gray colour, firm ,Silty CLAY withtrace amount of Sand .

Consolidation Test

Initi

al V

oid

R

atio

( e

)

Pre-

cons

olid

atio

n Pr

essu

re (

Com

pres

sion

In

dex

( Cc

)

TriaxialCompression

Test

(L.L) (P.L) ( P. I )Description of Soil

: BH-1

Moi

stur

e co

nten

t

Bul

k de

nsity

Dry

den

sity

U C

S T

est

CSr; N

o,

Dep

th (

m )

Spec

ific

grav

ity Grain Size Analysis Atterberg Limit

H-6

Page 7: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

Fr To ( % ) ( % ) ( % ) ( % ) ( % ) ( % ) ( % ) ( % ) g/cm3 g/cm3 kg/cm2 ( ° ) kg/cm2 kg/cm2

7 11.00 11.45 2.59 0.00 75.90 NL NP NI 15.72 2.02 1.75 0.33 11.00 0.34

8 13.00 13.45 2.57 0.00 68.30 NL NP NI 20.00 1.99 1.66 0.14 9.00 0.25

9 18.00 18.45 2.60 0.00 70.60 NL NP NI 23.50 1.89 1.52 0.28 10.00 0.35

10 22.00 22.45 2.60 0.00 71.40 NL NP NI 21.00 1.91 1.57 0.38 13.00 0.40

11 26.00 26.45 2.62 0.00 75.70 NL NP NI 19.00 2.02 1.70 0.30 15.00 0.36

12 28.00 28.45 2.65 0.00 80.20 NL NP NI 17.00 2.03 1.72 0.27 14.00 0.34

Borehole No

SOIL TEST RESULTSProject : The Improvement 0f Water Supply Project : 24-4-2013Date

Sr; N

o,

Dep

th (

m )

Description of Soil

Spec

ific

grav

ity Grain Size Analysis

Location : Bahan , Yangon : BH-1

Consolidation Test

Gravel Sand Silt Clay (L.L) (P.L) ( P. I )

Initi

al V

oid

R

atio

( e

)

Pre-

cons

olid

atio

n Pr

essu

re (

Pc

Com

pres

sion

In

dex

( Cc

)

C

TriaxialCompression

Test

U C

S T

est

Atterberg Limit

Moi

stur

e co

nten

t

Bul

k de

nsity

Dry

den

sity

Yellowish Brown colour,dense,Silty SAND with alittle amount of Clay

28.60

Yellowish Brown colour, very dense,Silty SAND with alittle amount of Clay

24.30

Yellowish Brown colour, very dense,Silty SAND with alittle amount of Clay

19.80

Yellowish Brown colour,dense,Silty SAND with alittle amount of Clay

24.10

Yellowish Brown colour, medium dense,Silty SAND with alittle amount of Clay

31.70

Yellowish Brown colour,dense,Silty SAND with alittle amount of Clay

29.40

H-7

Page 8: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

: The Improvement of Water Supply Project

Soil Test Results For Triaxial Permeability Test

7.15x10-9

To 9.00

9.00

10.00

TP

SPECIMEN DEPTH ( M )

: Bahan ,Yangon

From 8.00

Date:7.5.2013

Premeability Permeability at 20 c m/s

TP

9.00x10-10

Triaxial Cofficient of

SAMPLE TYPE :

BORING NO : BH-1

: UD

Project

Location

H-8

Page 9: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

2

3.0 LOCATION OF THE PROJECT SITE

The proposed site of The Improvement Of Water supply is situated near Mahawizaya pagoda, Dagon Township, Yangon Division. The location of project site is shown in Fig. (1) .

Fig. (1) Location Map of the Project Area

4.0 METHODS OF INVESTIGATION

Wash boring method up to the depth of 25m and sampling program of 1m up to depth of 25m intervals were specified. Borehole sounding test or Standard Penetration Test was performed in accordance with ASTM-D1586 standard. Bore logging and visual soil classification were made. The ground water table was measured and recorded. The soil profile and its corresponding SPT-N values are graphically presented in this report. It is compiled with the lab test result on the disturbed but representative samples.

5.0 GEOLOGY OF YANGON AREA

The geology of Yangon area was classified into the following geological units:

(a) Quaternary deposits

- 4. Upper Delta Alluvium, Pleistocene and Recent

- 3. Lower Delta Alluvium, Pleistocene

(b) Tertiary deposits

- 2. Irrawaddian Series, Pliocene

- 1. Pago Series, Oligocene-Miocene

H-9

Dagon BH-1 for Central Service Reservoir

Page 10: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

1ProjectLocation : Dagon TownshipCoordinatesElevation (m) : 37.39 m

0 10 20 30 40 50

30 - 50

10 - 30

>50

Dense

Medium Dense

Very Dense

8 - 15

15 - 30

Firm

Very FirmHard

Medium

>30

4 - 8

29.39

32.39

31.39

Light gray to reddish brown, mediumdense, Silty SAND and lateritic soil

( 3.5 m ~ 4.5 m ).

Reddish brown, Silty SANDwith some lateric soil

( 4.5 m ~ 7.0 m ).

30.39

5

7

1.08

0.99

0.90

1.08

UD

6

Loose Sand

Gray to light gray, dense to very dense,Silty SAND with some lateric soil

( 7.0 m ~ 10.0 m ). 9

Very Soft

8 >50

>50

>50

<4

>5

>5

>5

Disturbed Sample (Split spoon)

Rock Sample

Undisturbed Sample Soft

<2

2 - 4

1

Soil Description

Gra

phic

Log

Elev

atio

n

(m)

Dep

th (m

)36.39

:The Improvement Of Water Supply Boring Completed : 27 . 3 . 2013

SOILINVERSTIGATIONLOG

Reddish brown, mediumdense, Clayey SAND withsome silt and lateritic soil

( 0.0 m ~ 3.5 m ).35.39

34.39

33.39

2

3

4

: N-1858540.52,E-196868.55

Cas

ing

(m)

SPT(N-Value)

of 3: 1: 25.5 m

Sheet

: 6.1 m: Than Maung

Field Bearing capacity calculated

from SPT value(Ton/ft2)Ty

pe o

f sa

mpl

e

Type of Hammer : AutomaticBoring Started : 25 . 3 . 2013 Hole No

Total Depth (m)Logged by : Phyo Ko Ko Oo Water Level (m)Checked by : Wai Phyo Aung Driller

>50

27.39

UD

9.00

>5

28.39

Very Loose

Type of Sample

10

Strength of Consistency of Cohesive Soils Density of Cohesionless Soils

4 - 10

12

11

10

12

3.00

6.00

H-10

Page 11: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

2ProjectLocation : Dagon TownshipCoordinatesElevation (m) : 37.39 m

0 10 20 30 40 50

>5

>5

Type

of

sam

ple Field Bearing

capacity calculated from SPT value

(Ton/ft2)Cas

ing

(m)

SOILINVERSTIGATIONLOG

14

>5

12 >5

SPT(N-Value)

Sheet of 3

: 25.5 m: 6.1 m: Than Maung

: 1

Light gray, very dense,Silty SAND

( 10.0 m ~ 15.5 m ).

Dark gray, very dense,Silty SAND and gravels

( 15.5 m ~ 20.0 m ).

Soil Description

Gra

phic

Log

Dep

th (m

)

Elev

atio

n

(m)

>5020 >5

>50

>50

>50

>50

15 >5

11

12.00

15.00

18.00

19

17 >5

>5

>50

>50

>50

<4 Very LooseUndisturbed Sample 2 - 4 Soft 4 - 10 Loose Sand

Density of Cohesionless Soils

Medium Dense8 - 15 Firm 30 - 50 Dense

Rock Sample 15 - 30 Very Firm >50 Very Dense

Disturbed Sample (Split spoon) 4 - 8 Medium

Type of Sample Strength of Consistency of Cohesive Soils

<2

18

Checked by : Wai Phyo Aung Driller

Type of Hammer : Automatic

>5

>50

>50

>5

13

16

Boring Started : 25 . 3 . 2013 Hole NoBoring Completed : 27 . 3 . 2013 Total Depth (m)Logged by : Phyo Ko Ko Oo Water Level (m): N-1858540.52,E-196868.55

26.39

25.39

24.39

23.39

22.39

21.39

20.39

19.39

18.39

17.39 20.00

:The Improvement Of Water Supply

10 - 30

Very Soft

H-11

Page 12: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

3ProjectLocation : Dagon TownshipCoordinatesElevation (m) : 37.39 m

0 10 20 30 40 50

Gray, very dense, Silty SAND( 20.0 m ~ 25.5 m ).

Sheet of 3: 1:The Improvement Of Water Supply Boring Started : 25 . 3 . 2013 Hole No

SOILINVERSTIGATIONLOGType of Hammer : Automatic

: 25.5 m: 6.1 m: Than Maung

Soil Description

Gra

phic

Log

Dep

th (m

)

Elev

atio

n

(m)

Cas

ing

(m)

SPT(N-Value)

Type

of

sam

ple Field Bearing

capacity calculated from SPT value

(Ton/ft2)

Boring Completed : 27 . 3 . 2013 Total Depth (m)Logged by : Phyo Ko Ko Oo Water Level (m)Checked by

>5

22 15.39 >5

>50

>50

10 - 30 Medium Dense8 - 15 Firm 30 - 50 Dense

Rock Sample 15 - 30 Very Firm >50 Very Dense

Disturbed Sample (Split spoon) 4 - 8 Medium

Density of Cohesionless Soils

27

28

4 - 10 Loose Sand

29

30

Very Soft <4 Very LooseUndisturbed Sample 2 - 4 Soft

<2Type of Sample Strength of Consistency of Cohesive Soils

25 12.39

24 13.39 24.00

26

23 14.39 >5

: Wai Phyo Aung Driller

21 16.39 21.00

>5

>5

>50

>50

>50

: N-1858540.52,E-196868.55

H-12

Page 13: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

Fr To ( % ) ( % ) ( % ) ( % ) ( % ) ( % ) ( % ) ( % ) g/cm3 g/cm3 kg/cm2 ( ° ) kg/cm2 kg/cm2

1 2.00 2.45 2.54 8.50 60.40 NL NP NI 14.72 1.97 1.71 0.16 20.00 0.21

2 3.00 3.45 2.58 7.00 64.40 NL NP NI 16.50 1.90 1.60 0.18 16.00 0.25

3 5.00 6.00 2.60 3.50 71.40 NL NP NI 13.16 2.03 1.70 0.30 10.00 0.32 0.560 1.40 0.1

4 6.00 7.00 2.60 3.00 73.80 NL NP NI 12.60 2.02 1.74 0.28 11.00 0.36 0.526 1.30 0.1

5 8.00 8.45 2.55 0.00 72.90 25.88 15.83 10.05 18.11 1.85 1.56 0.35 21.00 0.36

6 10.00 10.45 2.64 0.00 80.20 NL NP NI 11.94 2.20 1.97 0.38 26.00 0.33

Reddish brown colour, Silty SAND with some Clay with trace amount of Gravels.

25.10

23.20

Gravel Sand

SOIL TEST RESULTSProject : The Improvement of Water Supply Project

Location : Dagon , Yangon Borehole No

Date : 28-4-2013

Reddish brown colour,medium dense,Clayey SAND with some Silt and trace amount of Gravels.

Clay

31.10

Light gray colour,very dense, SiltySAND with alittle amount of Clay. 19.80

Silt

Reddish brown colour,medium dense,Clayey SAND with some Silt and trace amount of Gravels.

28.60

Light gray colour,dense, SiltySAND with Clay. 27.10

Reddish brown colour, Silty SANDwith some Clay with trace amount of Gravels.

Consolidation Test

Initi

al V

oid

R

atio

( e

)

Pre-

cons

olid

atio

n Pr

essu

re (

Pc)

Com

pres

sion

In

dex

( Cc

)

TriaxialCompression

Test

(L.L) (P.L) ( P. I )Description of Soil

: BH-1

Moi

stur

e co

nten

t

Bul

k de

nsity

Dry

den

sity

U C

S T

est

CSr; N

o,

Dep

th (

m )

Spec

ific

grav

ity Grain Size Analysis Atterberg Limit

H-13

Page 14: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

Fr To ( % ) ( % ) ( % ) ( % ) ( % ) ( % ) ( % ) ( % ) g/cm3 g/cm3 kg/cm2 ( ° ) kg/cm2 kg/cm2

7 12.00 12.45 2.60 0.00 82.60 NL NP NI 15.49 1.97 1.68 0.19 24.00 0.20

8 14.00 14.45 2.64 0.00 85.45 NL NP NI 11.17 1.99 1.71 0.22 25.00 0.25

9 16.00 16.45 2.65 1.30 89.00 NL NP NI 11.44 2.01 1.70 0.20 28.00 0.21

10 18.00 18.45 2.65 1.00 90.20 NL NP NI 10.35 1.96 1.62 0.18 29.00 0.23

11 20.00 20.45 2.70 1.40 94.00 NL NP NI 12.67 2.23 1.98 0.16 30.00 0.19

12 22.00 22.45 2.56 0.00 67.30 NL NP NI 11.11 1.78 1.60 0.21 26.00 0.22

Borehole No

SOIL TEST RESULTSProject : The Improvement 0f Water Supply Project : 28-4-2013Date

Sr; N

o,

Dep

th (

m )

Description of Soil

Spec

ific

grav

ity Grain Size Analysis

Location : Dagon , Yangon : BH-1

Consolidation Test

Gravel Sand Silt Clay (L.L) (P.L) ( P. I )

Initi

al V

oid

R

atio

( e

)

Pre-

cons

olid

atio

n Pr

essu

re (

Pc )

Com

pres

sion

In

dex

( Cc

)

C

TriaxialCompression

Test

U C

S T

est

Atterberg Limit

Moi

stur

e co

nten

t

Bul

k de

nsity

Dry

den

sity

Dark gray colour,very dense, SiltySAND with trace amount of Gravels.

8.80

Dark gray colour,very dense, SiltySAND with trace amount of Gravels.

4.60

Gray colour,very dense , SiltySAND with some Clay. 32.70

Light gray colour,very dense, SiltySAND with alittle amount of Clay. 17.40

Light gray colour,very dense, SiltySAND with alittle amount of Clay. 14.55

Dark gray colour,very dense, SiltySAND with trace amount of Gravels.

9.70

H-14

Page 15: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

: The Improvement of Water Supply Project

Soil Test Results For Triaxial Permeability Test

5.2 x10-9

To 6.00

6.00

7.00

TP

UD UD

SPECIMEN DEPTH ( M )

: Dagon ,Yangon

From 5.00

Date: 28.4.2013

Premeability Permeability at 20 c m/s

TP

5.4 x10-9

Triaxial Cofficient of

SAMPLE TYPE :

BORING NO : BH-1

Project

Location

:

H-15

Page 16: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

2

3.0 LOCATION OF THE PROJECT SITE

The proposed site of The Improvement Of Water supply is situated Botataung Township, Yangon Division. The location of project site is shown in Fig. (1) .

Fig. (1) Location Map of the Project Area

4.0 METHODS OF INVESTIGATION

Wash boring method up to the depth of 35m and sampling program of 1m up to depth of 35m intervals were specified. Borehole sounding test or Standard Penetration Test was performed in accordance with ASTM-D1586 standard. Bore logging and visual soil classification were made. The ground water table was measured and recorded. The soil profile and its corresponding SPT-N values are graphically presented in this report. It is compiled with the lab test result on the disturbed but representative samples.

5.0 GEOLOGY OF YANGON AREA

The geology of Yangon area was classified into the following geological units:

(a) Quaternary deposits

- 4. Upper Delta Alluvium, Pleistocene and Recent

- 3. Lower Delta Alluvium, Pleistocene

(b) Tertiary deposits

- 2. Irrawaddian Series, Pliocene

- 1. Pegu Series, Oligocene-Miocene

H-16

Botataung BH-1 for Existing WWTP

Page 17: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

1ProjectLocation : Botataung TownshipCoordinates : N-1855515.95,E-200826.3Elevation (m) : 4.56 m

1.44

Type of Hammer : Automatic:The Improvement Of Water Supply Boring Started : 20 . 3 . 2013 Hole No

Boring Completed : 23 . 3 . 2013 Total Depth (m)Logged by : Phyo Ko Ko Oo Water Level (m)Checked by : Wai Phyo Aung Driller

Density of Cohesionless Soils

4 - 10

<2

2 - 4

10 - 30

>50

12

8 - 15

15 - 3030 - 50

-5.44

Loose Sand

DenseFirm

Very Firm

Hard

Medium

>30

Medium Dense

Very Dense

0.27

UD

UD

UD

0.20

-4.44 9.00

0.34

0.68

1.36

3.00

1

Brown, loose, Silty SAND and a little amount of gravels

( 0.0 m ~ 1.5 m ).

2

3

6.00

-2.44

-3.44

9 12

Very Soft

8

7

6 2

3

6

5

Very Loose

Type of Sample

Dark gray, very soft to soft, Silty CLAY ( 6.0 m ~ 7.5 m ).

Disturbed Sample (Split spoon)

Rock Sample

Undisturbed Sample<4

Soft

Soil Description

Gray, medium firm to firm, Sandy CLAY with some silt

(7.5 m ~ 10.0 m ).

3.56

4 - 8

4

10

Strength of Consistency of Cohesive Soils

3

8

Dark gray, soft, Silty CLAY ( 1.5 m ~ 6.0 m ).

2.56

1.56

0.56

-0.44

-1.44

SPT (N-Value)

of 4: 1: 35.5 m

Sheet

: 2.45 m: Than Maung

Field Bearing capacity calculated

from SPT value (Ton/ft2)

0.72

SOILINVERSTIGATIONLOG

H-17

Page 18: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

2ProjectLocation : Botataung TownshipCoordinates : N-1855515.95,E-200826.3Elevation (m) : 4.56 m

12.00

1.44

1.32

1.08

15

Water Level (m)Checked by : Wai Phyo Aung Driller

SOILINVERSTIGATIONLOG

Soil DescriptionSPT

(N-Value)

Sheet of 4: 1

Field Bearing capacity calculated

from SPT value (Ton/ft2)

Boring Started : 20 . 3 . 2013 Hole NoBoring Completed : 23 . 3 . 2013 Total Depth (m)Logged by : Phyo Ko Ko Oo

Type of Hammer : Automatic:The Improvement Of Water Supply

0.96

14 -9.44

: 35.5 m: 2.45 m: Than Maung

0.847

12 -7.44 0.72

8

6

9

-10.44 1.089

1.5613

18.00

15.00

20 -15.44 2.1618

11

14

Strength of Consistency of Cohesive Soils Density of Cohesionless Soils

17 -12.44 12

18

1.68

20.00

<2 Very Soft <4 Very LooseUndisturbed Sample 2 - 4 Soft 4 - 10 Loose Sand

Disturbed Sample (Split spoon) 4 - 8 Medium 10 - 30 Medium Dense8 - 15 Firm 30 - 50 Dense

Rock Sample 15 - 30 Very Firm >50 Very Dense

Gray, medium firm, Sandy CLAY and a little amount of silt

( 10.0 m ~ 12.5 m ).

-6.4411

Type of Sample

Gray, medium firm, Silty CLAY with sand ( 12.5 m ~ 18.5 m ).

Gray, medium dense, Silty SAND with a little amount of clay

( 18.5 m ~ 20.0 m ).

19 -14.44

16 -11.44

-13.44

13 -8.44

H-18

Page 19: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

3ProjectLocation : Botataung TownshipCoordinates : N-1855515.95,E-200826.3Elevation (m) : 4.56 m

Type of HammerBoring Started Hole No: 20 . 3 . 2013

: 35.5 m: 2.45 m: Than Maung

Sheet of 4: 1:The Improvement Of Water Supply

: AutomaticSOILINVERSTIGATIONLOG

Logged byChecked by

Water Level (m)Driller

: Phyo Ko Ko Oo: Wai Phyo Aung

Boring Completed Total Depth (m): 23 . 3 . 2013

Soil DescriptionSPT

(N-Value)

Field Bearing capacity calculated

from SPT value (Ton/ft2)

21 -16.44 21.00 2.88

Gray,medium dense, Silty SAND with little Clay

(20.0 m ~ 24.5 m ).

24

21

25

22 -17.44 2.52

2.28

3.00

25 -20.44 4.08

1923 -18.44

24 -19.44

27.00

24.00

Gray, dense, Silty SAND with little Clay ( 24.5 m ~ 30.0 m).

34

31

30

35

3.60

28 -23.44 4.20

26 -21.44 3.72

29 -24.44

-22.44

4.56

30 -25.44 5.1630.00

8 - 15 Firm10 - 30 Medium Dense

Rock Sample 15 - 30 Very Firm >50 Very Dense

Undisturbed Sample 2 - 4 Soft 4 - 10 Loose Sand4 - 8 Medium

30 - 50 Dense

Type of Sample Strength of Consistency of Cohesive Soils Density of Cohesionless Soils<2 Very Soft <4 Very Loose

27

Disturbed Sample (Split spoon)

38

43

H-19

Page 20: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

4ProjectLocation : Botataung TownshipCoordinates : N-1855515.95,E-200826.3Elevation (m) : 4.56 m

>5

: 35.5 m: 2.45 m: Than Maung

>50

SPT (N-Value)

Field Bearing capacity calculated

from SPT value (Ton/ft2)

Water Level (m)

>5

>50

-30.44 >5

>50

>5035

40

38

2 - 4 Soft 4 - 10 Loose Sand

Type of Sample Strength of Consistency of Cohesive Soils Density of Cohesionless Soils

36

37

39

Disturbed Sample (Split spoon) 4 - 8 Medium 10 - 30 Medium Dense8 - 15 Firm 30 - 50 Dense

Rock Sample 15 - 30 Very Firm >50 Very Dense

<2 Very Soft <4 Very LooseUndisturbed Sample

Soil Description

SheetType of Hammer : Automatic:The Improvement Of Water Supply

31 -26.44 >5>50

of 4: 1

Boring Completed : 23 . 3 . 2013 Total Depth (m)Logged by : Phyo Ko Ko Oo

33.00

Boring Started : 20 . 3 . 2013 Hole No

SOILINVERSTIGATIONLOG

-28.44 >5

34 -29.44

32 -27.44

33Gray, very dense,Silty SAND

( 30.0 m ~ 35.5 m ).

Checked by : Wai Phyo Aung Driller

H-20

Page 21: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

Fr To ( % ) ( % ) ( % ) ( % ) ( % ) ( % ) ( % ) ( % ) g/cm3 g/cm3 kg/cm2 ( ° ) kg/cm2 kg/cm2

1 1.00 1.45 2.57 5.70 86.00 NL NP NI 23.81 1.92 1.55 0.11 5.00 0.18

2 3.00 4.00 2.60 0.00 1.60 48.32 25.13 23.19 41.2 1.87 1.32 0.16 7.00 0.21 1.234 1.25 0.46

3 4.00 5.00 2.45 0.00 0.40 55.84 31.15 24.69 48.96 1.85 1.24 0.19 5.00 0.32 1.245 1.13 0.44

4 5.00 6.00 2.56 0.00 2.80 52.10 28.97 23.12 45.90 1.82 1.25 0.15 7.00 0.25 1.252 0.85 0.43

5 8.00 8.45 2.53 0.00 3.50 41.33 23.71 17.62 44.26 1.81 1.25 0.12 6.00 0.22

6 10.00 10.45 2.58 0.00 33.90 33.93 16.28 17.65 35.53 1.86 1.37 0.15 9.00 0.21

Bluish grey colour,Soft,Silty CLAY with trace sand. 99.60

97.20

Gravel Sand

SOIL TEST RESULTSProject : The Improvement 0f Water Supply Project

Location : Botahtaung , Yangon Borehole No

Date : 1-4-2013

Brown colour,loose, SANDwith some silt and clay with trace gravel.

Clay

8.30

Grey colour,firm,Sandy CLAY with some silt . 66.10

Silt

Bluish grey colour,Soft,Silty CLAY with trace sand. 98.40

Grey colour,medium firm,Silty CLAY with a little amount of sand.

96.50

Bluish grey colour,Soft,Silty CLAY with trace sand.

Consolidation Test

Initi

al V

oid

Rat

io (

e )

Pre-

cons

olid

atio

nPr

essu

re (

Com

pres

sion

In

dex

( Cc

)

TriaxialCompression

Test

(L.L) (P.L) ( P. I )Description of Soil

: BH-1

Moi

stur

e co

nten

t

Bul

k de

nsity

Dry

den

sity

U C

S T

est

CSr; N

o,

Dept

h ( m

)

Spec

ific

grav

ity Grain Size Analysis Atterberg Limit

H-21

Page 22: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

Fr To ( % ) ( % ) ( % ) ( % ) ( % ) ( % ) ( % ) ( % ) g/cm3 g/cm3 kg/cm2 ( ° ) kg/cm2 kg/cm2

7 15.00 15.45 2.60 0.00 20.70 40.62 20 20.62 36.20 1.85 1.35 0.18 8.00 0.25

8 18.00 18.45 2.60 0.00 17.60 38.41 20.48 17.93 33.53 1.79 1.34 0.12 10.00 0.31

9 21.00 21.45 2.52 0.00 80.00 NL NP NI 25.40 1.98 1.57 0.05 14.00 0.15

10 25.00 25.45 2.64 0.00 71.60 NL NP NI 27.84 1.95 1.52 0.07 13.00 0.16

11 30.00 30.45 2.55 0.00 86.50 NL NP NI 19.77 1.79 1.49 0.04 16.00 0.12

12 32.00 32.45 2.65 0.00 92.40 NL NP NI 21.2 1.86 1.53 0.03 18.00 0.13

Borehole No

SOIL TEST RESULTSProject : The Improvement 0f Water Supply Project : 10-4-2013Date

Sr; N

o,

Dep

th (

m )

Description of Soil

Spec

ific

grav

ity Grain Size Analysis

Location : Botahtaung , Yangon : BH-1

Consolidation Test

Gravel Sand Silt Clay (L.L) (P.L) ( P. I )

Initi

al V

oid

Rat

io (

e )

Pre-

cons

olid

atio

nPr

essu

re (

Pc

Com

pres

sion

In

dex

( Cc

)

C

TriaxialCompression

Test

U C

S T

est

Atterberg Limit

Moi

stur

e co

nten

t

Bul

k de

nsity

Dry

den

sity

Grey colour,dense,SANDwith some silt and clay. 28.40

Grey colour,dense,SANDwith alittle amount of silt and clay.

13.50

Grey colour,very dense,SAND with alittle amount of silt and clay.

7.60

Grey colour,firm,Silty CLAYwith some sand. 79.30

Grey colour,firm,Silty CLAYwith some sand. 82.40

Grey colour,medium dense,SAND with some silt and clay.

20.00

H-22

Page 23: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

UD

SPECIMEN DEPTH ( M )

Premeability Permeability at 20 c m/s 1.9x10-10

TP

2.1x10-10

Triaxial Cofficient of

1.9x10-9

TP TP

SAMPLE TYPE :

BORING NO : BH-1

: UD

Project

Location

Soil Test Results For Triaxial Permeability Test

Date:30.3.2013

UD

4.0 ( m )

5.0 ( m )

5.0 ( m )

6.0 ( m )

Date:6.4.2013

UD

: Botahtaung ,Yangon

: The Improvement Of Water Supply

From 3.0 ( m )

Date:25.3.2013

To 4.0 ( m )

H-23

Page 24: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

2

3. LOCATION OF THE PROJECT AREA

The proposed site of Lagonpy in Water Treatment Plant is situated near 56 Qrt, South Dagon Township, Yangon Division.

Boreholes Location Point of the Project Area

4. GEOLOGY OF YANGON AREA

The geology of Yangon area was classified into the following geological units:

(a) Quaternary deposits

- 4. Upper Delta Alluvium, Pleistocene and Recent

- 3. Lower Delta Alluvium, Pleistocene

(b) Tertiary deposits

- 2. Irrawaddian Series, Pliocene

- 1. Pegu Series, Oligocene-Miocene

The regional geological study has been made in an area which includes ridges

and deltaic lands lying south of the Bago Yoma. This area is in a north-south trending

synclinal basin containing a thick Tertiary - Quaternary deposits. Geologic succession of

the Yangon area is shown in table.

H-24

East Dagon BH-1~5 for Lagunpyin WTP

East

Page 25: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

H-25

Page 26: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

: Lagonpyin 1

Location : South Dagon TownshipCoordinates : N-1875468.35,E-211397.77Elevation (m) : 4.26 m

Brownish gray to reddish brown,

ProjectType of Hammer : Automatic Sheet of 5

: Water Treatment Plant Boring Started : 25.7.2013 Hole No : BH - 1

3.00

43

0.44

7

5

0.70 2

2 32

Boring Completed : 27.7.2013 Total Depth (m) : 42.5 mLogged by : Phyo Ko Ko Oo Water Level (m) : 1.3 mChecked by : Wai Phyo Aung Driller : Than Maung

8

0.44 2 2

1.22 3 4

51.45 5

11

13

Brownish gray to reddish brown,Soft to Stiff,Stily CLAY

with a little amount of sand.( 0.0 m ~ 10.0 m ).

6.00

9.00

0.44 1

0.505 1

24

4

2

2

7

2 3

H-26

Page 27: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

:Lagonpyin 2

Location : South Dagon TownshipCoordinates : N-1875468.35,E-211397.77Elevation (m) : 4.26 m

3

5

0.70 3 3

1.17 4 5

Gray, Firm to Stiff, Silty CLAYwith a little amount sand.

Boring Completed : 27.7.2013

Checked by : Wai Phyo Aung

Total Depth (m) : 42.5 mLogged by : Phyo Ko Ko Oo Water Level (m) : 1.3 m

Type of Hammer : Automatic Sheet of 5: Water Treatment Plant Boring Started : 25.7.2013 Hole No : BH - 1

Project

Driller : Than Maung

Gray to reddish brown,tiff to Very stiff, Silty CLAYwith a little amount sand.

(10.0 m ~ 12.5 m ).

12

16

6

10

12.0

1.40 5 5

1.87 6 8

7

8

1.53 5 6

2.10 7 8

3.28 9 13

7

10

15

0.94

5

4

6

0.94 3 3

5 5

3 4

1.29

8( 12.5 m ~ 16.5 m ). 15.0

18.0Brownish gray to brown,

Stiff to Very stiff, Silty CLAY( 16.5 m ~ 20.0 m ).

8

11

13

18

28

H-27

Page 28: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

: Lagonpyin 3

Location : South Dagon TownshipCoordinates : N-1875468.35,E-211397.77Elevation (m) : 4.26 m

Project

Boring Completed : 27.7.2013 Total Depth (m) : 42.5 mLogged by : Phyo Ko Ko Oo Water Level (m) : 1.3 mChecked by : Wai Phyo Aung Driller : Than Maung

Brown, Very stiff, Silty CLAYwith a little amount sand

( 20.0 m ~ 22.5 m ).

Type of Hammer : Automatic Sheet of 5: Water Treatment Plant Boring Started : 25.7.2013 Hole No : BH - 1

21.0 24

21

24.0

2.46 8 10

4.34 10 16

2.81 9 11

4.80 11 18

13

11

21

23

37

41

25

30

20

20

12

9

41

38

20

16

4.80 10 21

1.87 4 7

4.45 8 18

2.34 6 8Gray, Very stiff,

Silty CLAY with trace sand( 28.5 m ~ 30.0 m ).

Brown to reddish brown to gray,Dense to Very dense, Silty SAND

with tace clay( 22.5 m ~ 28.5 m ). 16 27

5.50 12 2247

>50

H-28

Page 29: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

: Lagonpyin 4

Location : South Dagon TownshipCoordinates : N-1875468.35,E-211397.77Elevation (m) : 4.26 m

16

21

Type of Hammer : Automatic Sheet of 5

Water Level (m) : 1.3 mDriller : Than Maung

Boring Started : 25.7.2013 Hole No : BH - 1Boring Completed : 27.7.2013 Total Depth (m) : 42.5 mLogged by : Phyo Ko Ko OoChecked by : Wai Phyo Aung

: Water Treatment PlantProject

Gray to reddish brown,Very stiff,Silty CLAY with trace sand

( 30.0 m ~ 36.5 m ).

8

9

9

11

17

18 9

2.46 8 10

1.87 5 8

1.99 6 8

2.10 7

23

25

37

Reddish brown,Dense to Very dense,Silty SAND with trace clay

( 36.5 m ~ 40.0 m ).

15 25

>5 19 26

4.34 11 16

>5 13 22

>50

>5

>50

>50

14

21

34

31

32

2.69 128 11

2.93 9 11

H-29

Page 30: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

: Lagonpyin 5: BH - 1

Location : South Dagon Township : 42.5 mCoordinates : N-1875468.35,E-211397.77 : 1.3 mElevation (m) : 4.26 m : Than Maung

Type of Hammer : Automatic Sheet of 5

Logged by : Phyo Ko Ko Oo Water Level (m)

Project

Checked by : Wai Phyo Aung Driller

: Water Treatment Plant Boring Started : 25.7.2013 Hole NoBoring Completed : 27.7.2013 Total Depth (m)

Reddish brown,Dense to Verydense,Silty SAND with trace clay

( 40.0 m ~ 42.5 m ).

>5

>5

21 28

27

37

35

>50

>50 24

H-30

Page 31: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

: Lagonpyin 1

Location : South Dagon TownshipCoordinates : N-1875403.81,E-211303.45Elevation (m) : 4.30 m

0.70

8

5

Boring Started : 8.8.2013 Hole No : BH - 2

8

10

11

: Wai Phyo Aung Driller : Than MaungChecked by

4 4

Project

4

6

Boring Completed : 11.8.2013 Total Depth (m) : 43.5 mLogged by : Phyo Ko Ko Oo Water Level (m) : 1.3 m

Type of Hammer : Automatic Sheet of 5

4

0.97 3

: Water Treatment Plant

3.00

5

0.70 4

3

0.88 4 5

2

026.00

9.00

0.33 1

0.20

3

4

1

Brown, Very soft to Stiff, Silty CLAY( 0.0 m ~ 10.0 m ).

1 1

20.44 2 2

H-31

Page 32: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

: Lagonpyin 2

Location : South Dagon TownshipCoordinates : N-1875403.81,E-211303.45Elevation (m) : 4.30 m

6

2.46 9

8

: 11.8.2013 Total Depth (m) : 43.5 mLogged by : Phyo Ko Ko Oo Water Level (m) : 1.3 mChecked by : Wai Phyo Aung

Boring Completed

Driller : Than Maung

Type of Hammer : Automatic Sheet of 5: Water Treatment Plant Boring Started : 8.8.2013 Hole No : BH - 2

Project

9

2.11 4 10

12521

1812.0

16

14 4

Gray to reddish brown

1.87 5 7

1.64

1.29 3 5 6

6

1.05 4 4

18.0

0.94 4 4

15.0 11

8

6

10

Gray to reddish brown,Firm to Very stiff, Silty CLAYwith a little amount of sand

( 10.0 m ~ 20.0 m )

4

59

1.29 4 5

1.29 5 5

2.11 6 8

11

11

18

H-32

Page 33: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

: Lagonpyin 3

Location : South Dagon TownshipCoordinates : N-1875403.81,E-211303.45Elevation (m) : 4.30 m

Gray to reddish brown,Very stiff to Hard, Clayey SILT

with a little amount of sand( 20.5 m ~ 26.5 m ).

15

3.05 10 11

21.0 22

21

20

15

4.34 11

Total Depth (m) : 43.5 mLogged by : Phyo Ko Ko Oo Water Level (m) : 1.3 mChecked by : Wai Phyo Aung Driller : Than Maung

Boring Completed : 11.8.2013

4.57 11 18

4.34 13

24.0

39

Type of Hammer : Automatic Sheet of 5: Water Treatment Plant Boring Started : 8.8.2013 Hole No : BH - 2

Project

17

Gray, Very stiff, Silty CLAYwith a little amount of sand ( 20.0 m ~ 20.5 m ).

37

37

26

2.11 8

27.0

30.0

1.99 7

8

2.46 8 10

7

1.99 7 8

1.87

9

6 8

1.87 5

11

10

9

8

9

8

Gray, Very stiff, Silty CLAYwith a little amount of sand

( 26.5 m ~ 30.0 m ).

21

18

17

16

16

17

H-33

Page 34: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

: Lagonpyin 4

Location : South Dagon TownshipCoordinates : N-1875403.81,E-211303.45Elevation (m) : 4.30 m

2.81 9 11

3.16 8 13

1.87 7 7

2.23 8

33.0

19

Gray, very stiff,Silty CLAY with a little amount of sand

( 30.0 m ~ 32.5 m ).

24

Light gray to reddish brown,Very stiff to Hard, Clayey SILT

with a little amount of sand( 32.5 m ~ 35.5 m ).

16

27

Type of Hammer : Automatic Sheet of 5

Water Level (m) : 1.3 m

Project

Logged by : Phyo Ko Ko Oo

: Water Treatment Plant Boring Started : 8.8.2013 Hole No : BH - 2Boring Completed

9

: 11.8.2013 Total Depth (m) : 43.5 m

Checked by : Wai Phyo Aung

9

10

13

14

Driller : Than Maung

>50

3.86 9 15

4.80 10 19

18

22

>50

>50

>5

33

41

>50

21

>5 25

>5 11

3.05 10

Light gray, Dense to Very dense,Silty SAND with trace clay

( 35.5 m ~ 38.5 m ).

26

Gray to brown, Hard,Clayey SILT with some sand

( 38.5 m ~ 40.0 ).

32

25

>50

27

21

H-34

Page 35: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

5Project : BH - 2Location : South Dagon Township : 43.5 mCoordinates : N-1875403.81,E-211303.45 : 1.3 mElevation (m) : 4.30 m

Gray to brown, Hard,Clayey SILT with some sand

( 40.0 m ~ 43.5 m ).

35

31>50

>50

>5

>5

>5

Hole NoBoring Completed : 11.8.2013 Total Depth (m)

: Than Maung

>50

>50

>50

32>50

Type of Hammer : Automatic Sheet of 5

Logged by : Phyo Ko Ko Oo Water Level (m)Checked by : Wai Phyo Aung Driller

: Water Treatment Plant Boring Started : 8.8.2013

H-35

Page 36: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

: Lagonpyin 1

Location : South Dagon TownshipCoordinates : N-1875351.14,E-211421.20Elevation (m) : 3.83 m

1 1 2

Project

3

Boring Completed : 6 . 8 . 2013 Total Depth (m) : 45.5 mLogged by : Phyo Ko Ko Oo Water Level (m) : 1.3 m

Type of Hammer : Automatic Sheet of 5: Water Treatment Plant

3.00

5

6

3

0.44 2 2

Boring Started : 2 . 8 . 2013 Hole No : BH - 3

Checked by : Wai Phyo Aung Driller : Than Maung

0.26

B t Fi Silt CLAY

2 3 30.53

9.00

2

4

4

1.67 4 7

3.23 7 12 17

0.44 1 2

15

Brown to grey,Firm, Silty CLAYwith some peats and lateric soils

( 0.0 m ~ 10.0 m ).

1 2 2

8

1.67 3 6 9

6.00 0.40

15

29

H-36

Page 37: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

: Lagonpyin 2

Location : South Dagon TownshipCoordinates : N-1875351.14,E-211421.20Elevation (m) : 3.83 m

40.94 4 4

20

17

8

Grey to brown, Very Stiff,SILT and CLAY

(10.0 m ~ 12.5 m ).

Project

2.34 6 9

1.99 5 9

11

Boring Completed : 6 . 8 . 2013 Total Depth (m) : 45.5 mLogged by : Phyo Ko Ko Oo Water Level (m) : 1.3 m

Driller : Than Maung

Type of Hammer : Automatic Sheet of 5: Water Treatment Plant Boring Started : 2 . 8 . 2013 Hole No : BH - 3

Checked by : Wai Phyo Aung

12.0

5

13

11

Light grey,Very stiff, SILT and CLAY( 18.5 m ~ 20.0 m ).

9

12

13

17

23

Grey, Firm to Stiff, Silty CLAYwith trace peats

( 12.5 m ~ 18.5 m ).

1.05 4 4

1.29 4 5

1.46 4 6

15.0

1.52 4 6

1.99 5 7

2.69 7 10

18.0

6

6

7

10

H-37

Page 38: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

: Lagonpyin 3

Location : South Dagon TownshipCoordinates : N-1875351.14,E-211421.20Elevation (m) : 3.83 m

4.34 12 16

4.34 10 18

3.51 9 11 19

21

19

214.45 9 17

21.0

: Than Maung

24.0

37

30

38

Lightgrey to reddish brown ,

Type of Hammer : Automatic Sheet of 5: Water Treatment Plant Boring Started : 2 . 8 . 2013 Hole No : BH - 3

Project

Boring Completed : 6 . 8 . 2013 Total Depth (m) : 45.5 mLogged by : Phyo Ko Ko Oo Water Level (m) : 1.3 mChecked by : Wai Phyo Aung Driller

37

23

3.16 8

7 10

18

15

13

11

11

12

3.87 9 15

27.0

30.0

2.69 6 10

2.58 8 10

2.34

12

6 9

2.46

33

Lightgrey to reddish brown ,Very stiff to Hard,SILT and CLAY

with trace peats( 20.0 m ~ 30.0 m ).

21

20

22

27

H-38

Page 39: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

: Lagonpyin 4

Location : South Dagon TownshipCoordinates : N-1875351.14,E-211421.20Elevation (m) : 3.83 m

3.87 11 15

4.92 14 19

2.93 8 11

3.28 9

23

33.0

42

28

Type of Hammer : Automatic Sheet of 5

Water Level (m) : 1.3 m

Project

Logged by : Phyo Ko Ko OoDriller : Than Maung

: Water Treatment Plant Boring Started : 2 . 8 . 2013 Hole No : BH - 3Boring Completed : 6 . 8 . 2013 Total Depth (m) : 45.5 m

Checked by : Wai Phyo Aung

14

16

18

12

33

Grey to reddish brown, Very stiff to Hard, SILT and CLAY

with trace peats and sand( 30.0 m ~ 37.5 m ).

25

15 18

20 28

10

>5 12

>5 16 21

>5 15 25 28

25

20

21

22

4.57 15 18

4.92 17

48

3.87

35.0

39

>50

33

42

46

H-39

Page 40: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

: Lagonpyin 5: BH - 3

Location : South Dagon Township : 45.5 mCoordinates : N-1875351.14,E-211421.20 : 1.3 mElevation (m) : 3.83 m

Project

Grey,Hard, SILT and CLAY with trace sand ( 40.0 m ~ 40.5 m ).

Grey, Very dense,Silty SAND with little clay

( 40.5 m ~ 45.5 m ).

>50

27

24

26

31

Hole NoBoring Completed

>50

>5

20

22

16

18 32

38

35

>50

Type of Hammer : Automatic Sheet of 5

: Than Maung

>50

: Wai Phyo Aung

34

>5

>5

>5

DrillerLogged by : Phyo Ko Ko Oo Water Level (m)

: 6 . 8 . 2013 Total Depth (m)

Checked by

: Water Treatment Plant Boring Started : 2 . 8 . 2013

>50 25 29>5 38

H-40

Page 41: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

: Lagonpyin 1

Location : South Dagon TownshipCoordinates : N-1875341.35,E-211536.40Elevation (m) : 3.68 m

0 1 1

Type of Hammer : Automatic Sheet of 5: Water Treatment Plant

Brown, Very soft to Soft,SILT and CLAY( 0.0 m ~ 2.5 m ).

3.00

2

3

2

1

Boring Completed : 31.7.2013 Total Depth (m) : 45.5 mLogged by : Phyo Ko Ko Oo

0.26 1 1 2

Hole No : BH - 4

Checked by : Wai Phyo Aung Driller : Than MaungWater Level (m) : 1.3 m

0.18 1 1

ProjectBoring Started : 29.7.2013

0.19

9.00 5

0.67 2 3 3

6.00 0.30 1 2 13

11

9

Grey, Very soft to Soft,Silty CLAY with trace peats

( 2.5 m ~ 8.0 m ).

Reddish brown,Firm to Stiff,SILT and CLAY with some lateric

( 8.0 m ~ 10.0 m ).

1.00 3 4

1.22 4 5 6

6

H-41

Page 42: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

: Lagonpyin 2

Location : South Dagon TownshipCoordinates : N-1875341.35,E-211536.40Elevation (m) : 3.68 m

4

5

0.94 3 4

1.05 3 4

2.34 7 10

1.41 5 6

10

Boring Completed : 31.7.2013 Total Depth (m) : 45.5 mLogged by : Phyo Ko Ko Oo Water Level (m) : 1.3 m

Driller : Than Maung

Type of Hammer : Automatic Sheet of 5: Water Treatment Plant Boring Started : 29.7.2013 Hole No : BH - 4

Project

Checked by : Wai Phyo Aung

12.0

20

Grey, Firm to Stiff,Silty CLAY with trace peats

( 12.5 m ~ 14.5 m ).

12

8

9

Brown to grey, Stiff to Very stiff, SILT and CLAY with some lateric soil

( 10.0 m ~ 12.5 m ).

20

4

1.17 4 5

1.41 4 6

4

5

6

0.94 4

9

15.0 8

1.52 4 6

1.99 7 8

4.69 14 20

18.0

12

13

40

7

Grey, Firm, SILT and CLAY( 14.5 m ~ 15.5 m ).

Grey,Stiff to Very stiff,SILT and CLAY with trace lateric soil

( 15.5 m ~ 20.0 m ).

10

17

H-42

Page 43: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

: Lagonpyin 3

Location : South Dagon TownshipCoordinates : N-1875341.35,E-211536.40Elevation (m) : 3.68 m

3.87 11 14

3.75 13 15

3.87 9 15

Project

18

19

17

183.63 11 13

21.0

Total Depth (m) : 45.5 mLogged by : Phyo Ko Ko Oo Water Level (m) : 1.3 mChecked by : Wai Phyo Aung Driller : Than Maung

Type of Hammer : Automatic Sheet of 5: Water Treatment Plant Boring Started : 29.7.2013 Hole No : BH - 4

Boring Completed : 31.7.2013

24.0

33

33

32

31

2.93 9

31

25

8

7 11

1.64 6 6

16

13

11

11

8

12

3.63 10 15

27.0

30.0

2.34 7 9

1.76 6 7

2.58

14

15

Brown, Stiff to Very stiff to Hard,SILT and CLAY with trace lateric soil

( 20.0 m ~ 30.0 m ).

20

22

H-43

Page 44: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

: Lagonpyin 4

Location : South Dagon TownshipCoordinates : N-1875341.35,E-211536.40Elevation (m) : 3.68 m

1.87 6 7

1.99 6

33.0 17

18

Type of Hammer : Automatic Sheet of 5

Water Level (m) : 1.3 m

Project

Logged by : Phyo Ko Ko OoChecked by : Wai Phyo Aung Driller : Than Maung

: Water Treatment Plant Boring Started : 29.7.2013 Hole No : BH - 4Boring Completed : 31.7.2013 Total Depth (m) : 45.5 m

1.99

9

10

9

10

7

16

17

Grey to reddish brown,Stiff to Very stiff, SILT and CLAY

with trace peats and sand( 30 0 m ~ 38 5 m )

6 8

2.11 8 8

3.28 7 13 15

30 19

18 22

8

4.69 10

3.16 8 12

3.51

35.0

11Brown,Firm,

Silty SAND with trace clay( 38.5 m ~ 40.0 m ).

20

23

28

40

27

1.34 10 10

2.69 8 10

10

13

15

( 30.0 m ~ 38.5 m ).

H-44

Page 45: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

: Lagonpyin 5: BH - 4

Location : South Dagon Township :Coordinates : N-1875341.35,E-211536.40Elevation (m) : 3.68 m

>5

>50

>50Brown, very dense,SILT and CLAY with trace clay

( 40.0 m ~ 42.5 m ).

Brown, very dnese,Silty SAND with trace clay

( 42.5 m ~ 45.5 m ).

Checked by : Wai Phyo Aung

35

37>50

26

26

24

28

12

16

15

Type of Hammer : Automatic Sheet of 5

Logged by : Phyo Ko Ko Oo Water Level (m): 31.7.2013 Total Depth (m)

ProjectHole No

Boring Completed

Driller

: Water Treatment Plant Boring Started : 29.7.2013

: 1.3 m: 45.5 m

>5

>5

>5

16 35

34

: Than Maung

>50

>5 39>50 2719

H-45

Page 46: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

: Lagonpyin 1: BH - 5

Location : South Dagon TownshipCoordinates : N-1875341.35,E-211536.40Elevation (m) : 3.68 m

3 5 6

ProjectType of Hammer : Automatic

5 7

0.97 3 4

Boring Started : 10.8.2013 Hole No

Checked by : Wai Phyo Aung Driller : Than Maung

0.97

1.05

Sheet of 5: Water Treatment Plant

3.00

Dark brown, Stiff, SILT and CLAY( 0.0 m ~ 3.5 m ).

7

Boring Completed : 12.8.2013 Total Depth (m) : 44.5 mLogged by : Phyo Ko Ko Oo Water Level (m) : 1.3 m

3

11

11

12

3

1.11 7 8 8

0.56 2 2

16

6.00

9.00

4 0.40 2 2 2

Brown to grey, Soft,Silty CLAY with some peats

( 3.5 m ~ 10.0 m ).0.56 2 2 35

5

H-46

Page 47: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

: Lagonpyin 2: BH - 5

Location : South Dagon TownshipCoordinates : N-1875341.35,E-211536.40Elevation (m) : 3.68 m

2.58 8 10

3.05 8 15

12

32

4.34 13 18

3.75 10 15

Checked by : Wai Phyo Aung

12.0

22

Grey to reddish brown, Very stiff, Silty CLAY with some lateric soil ( 10.0 m ~ 10.5 m ).

Type of Hammer : Automatic Sheet of 5: Water Treatment Plant Boring Started : 10.8.2013 Hole No

Project

Boring Completed : 12.8.2013 Total Depth (m) : 44.5 mLogged by : Phyo Ko Ko Oo Water Level (m) : 1.3 m

Driller : Than Maung

37 19

Grey to brown,Very stiff,SILT and CLAY with some lateric soil

( 10.5 m ~ 17.5 m ).

17

26

14

3.05 8

1.41 5 6

1.64 6 6

1.99 8 8

18.0 12

17

6

8

15.0 26

9

Grey, Stiff, Silty CLAY with some peats( 17.5 m ~ 20.0 m ).

21

16

11

2.46 7 10

1.87 6 8

15

11

8

H-47

Page 48: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

: Lagonpyin 3: BH - 5

Location : South Dagon TownshipCoordinates : N-1875341.35,E-211536.40Elevation (m) : 3.68 m

Boring Completed : 12.8.2013

24.0

Type of Hammer : Automatic Sheet of 5: Water Treatment Plant Boring Started : 10.8.2013 Hole No

Total Depth (m) : 44.5 mLogged by : Phyo Ko Ko Oo Water Level (m) : 1.3 mChecked by : Wai Phyo Aung Driller : Than Maung

21.0

2.11 7 8

Project

9

7

8

10

1.52 5 6

1.76 6 7

Grey, stiff to very stiff,Silty CLAY with some peats

( 20.0 m ~ 25.5 m ).

1.76 6 615

13

15

18

Brown to grey, Hard to Very hard,SILT and CLAY

( 25.5 m ~ 27.5 m ).

Brown, Hard, Clayey SILT( 27.5 m ~ 30.0 m ).

46

43

25

>5 15 21

2.93 8 12

>5

31

23

2.81 8 11

13

14 20

3.63 10 15

13

31

25

23

16

>5 17

24

>50

H-48

Page 49: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

: Lagonpyin 4: BH - 5

Location : South Dagon TownshipCoordinates : N-1875341.35,E-211536.40Elevation (m) : 3.68 m

15

16

15

15

1228

28

29

Checked by : Wai Phyo Aung Driller : Than Maung

: Water Treatment Plant Boring Started : 10.8.2013 Hole NoBoring Completed : 12.8.2013 Total Depth (m) : 44.5 m

Brown, Very stiff, Clayey SILT( 30.0 m ~ 31.5 m ).

Grey, Very stiff, SILT and CLAY( 31.5 m ~ 35.5 m ).

26

Type of Hammer : Automatic Sheet of 5

Water Level (m) : 1.3 m

Project

Logged by : Phyo Ko Ko Oo

3.28 9 13

3.40 8 14

3.05 9 11

3.28 10

16

16

21

30

47

Reddish brown, Hard, Clayey SILT( 35.5 m ~ 37.5 m ).

Grey,Dense, Silty SAND with little clay( 37.5 m ~ 40.0 m ) >5 21

31

40

>50

3.51 9 14

3.63 11 15

4.69 16 19

>5 19 22 25

48 27

28 31

15

>5 11

H-49

Page 50: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

: Lagonpyin 5: BH - 5

Location : South Dagon Township : 44.5 mCoordinates : N-1875341.35,E-211536.40 : 1.3 mElevation (m) : 3.68 m

Type of Hammer : Automatic Sheet of 5

Logged by : Phyo Ko Ko Oo Water Level (m): 12.8.2013 Total Depth (m)

Project: Water Treatment Plant Boring Started : 10.8.2013

>50

>50

>50

>50

>5

28

32

22

>5

>5

>5

20

Reddish brown to grey,Very dense, Clayey SILT

( 40.0 m ~ 44.5 m ).

Hole NoBoring Completed

>50

>50

>50

>50

: Than MaungChecked by : Wai Phyo Aung Driller

H-50

Page 51: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

Fr To ( % ) ( % ) ( % ) ( % ) ( % ) ( % ) ( % ) ( % ) g/cm3 g/cm3 kg/cm2 ( ) kg/cm2 kg/cm2

1 2.00 3.00 2.75 1.10 64.81 28.76 36.05 30.0 1.730 1.33 0.32 7.00 0.26 0.795 2.45 0.23

2 4.00 5.00 2.72 0.40 63.15 20.30 42.85 33.0 1.670 1.31 0.17 7.00 0.26 1.068 1.32 0.34

3 6.00 7.00 2.57 1.50 56.95 23.20 33.75 55.0 1.960 1.26 0.09 5.00 0.27 1.372 0.66 0.50

4 12.00 12.45 2.76 4.20 63.00 20.24 42.76 36.0 1.740 1.27

5 20.00 20.45 2.78 7.00 65.05 24.48 40.57 27.0 1.820 1.43

6 23.00 23.45 2.68 64.10 NL NP NI 21.1 1.880 1.55 0.05 14.00 0.16

7 32.00 32.45 2.75 18.30 58.90 21.70 37.20 37.0 1.910 1.39

8 40.00 40.45 2.70 49.80 NL NP NI 36.0 1.770 1.30 0.03 18.00 0.13

: 24-8-2013

Borehole No

Date

: BH-1

Brwon, Silty CLAY with a little amount of sand.

Reddish brown, Silty SAND with trace clay

93.00

50.20

Consodration Test

Init

ial V

oid

R

atio

( e

)

Pre

-co

nsol

idat

ion

Pres

sure

( P

c )

Com

pres

sion

In

dex

( Cc

)

Grey to brown, Silty CLAY with trace sand.

Brown, Silty SAND with trace clay. 35.90

81.70

Brown, Silty CLAY with a little amount of sand. 99.60

Grey to reddish brown,Silty CLAYwith a little amount of sand. 95.80

Brownish grey, Silty CLAY with a little amount sand.

Brownish grey, Silty CLAY

ClayC

TABLE 3.2 Summary of Soil PropertiesProject : Lagonpyin Water Treatment Plant Project

Location : E. 211397.77, N. 1875468.35

Spec

ific

g

ravi

ty Grain Size Analysis Atterberg Limit

Gravel Sand Sr; N

o,

TriaxialCompression

Test

Moi

stur

e co

nten

t

Bul

k de

nsit

y

Dep

th (

m )

Dry

den

sity

U C

S T

est

(L.L) (P.L) ( P. I )Description of Soil

Silt

98.90

98.50

H-51

Page 52: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

Fr To ( % ) ( % ) ( % ) ( % ) ( % ) ( % ) ( % ) ( % ) g/cm3 g/cm3 kg/cm2 ( ) kg/cm2 kg/cm2

1 3.00 3.45 2.73 0.10 65.50 28.50 37.00 33.96 1.82 1.36

2 5.00 6.00 2.74 0.20 64.50 39.50 25.00 52.77 1.80 1.17

3 8.00 9.00 2.70 68.00 28.00 40.00 55.00 1.95 1.25 0.07 5.00 0.15 1.461 1.38 0.63

4 10.00 11.00 2.71 0.30 56.75 20.25 36.50 53.5 1.82 1.20 0.09 7.00 0.23 1.201 1.43 0.45

5 15.00 15.45 2.75 2.20 40.62 20.00 20.62 54.3 1.74 1.13 0.11 6.00 0.21 1.041 1.80 0.39

6 21.00 21.45 2.78 3.70 57.17 36.36 20.81 25.69 1.91 1.52 0.18 8.00 0.22 1.248 1.23 0.49

7 25.00 25.45 2.76 0.80 74.77 26.58 48.19 36.05 1.84 1.35

8 39.00 39.45 2.71 14.60 55.65 35.52 20.13 35.69 1.92 1.43 0.12 10.00 0.31 1.213 1.4 0.44

99.70

Grey, Stiff, Silty CLAY with a little amount of sand.

Com

pres

sion

In

dex

( Cc

)

Pre

-co

nsol

idat

ion

Pres

sure

( P

c )

Init

ial V

oid

R

atio

( e

)

: BH-2Borehole No

: 24-8-2013Date

Consodration Test

Grey, Silty CLAY

Grey, Silty CLAY

: Lagonpyin Water Treatment Plant Project

97.80

100

99.20

85.40

TABLE 3.2 Summary of Soil Properties

: E. 211303.45 , N. 1875403.81

( P. I )

96.30

Reddish brown, Very Stiff, Silty CLAY

Grey, Clayey SILT

Sand (P.L) U C

S T

est

99.90

99.80

Brown, Stiff, Silty CLAY

Sr; N

o,

Dep

th (

m )

Description of Soil

Spec

ific

g

ravi

ty Atterberg Limit

Gravel

Moi

stur

e co

nten

t

CBul

k de

nsit

y

Dry

den

sity

TriaxialCompression

Test

Silt Clay (L.L)

Grain Size Analysis

Project

Location

Grey, Hard, Clayey SILT with a little amount of sand.

Grey to brown, Hard, Clayey SILTwith some sand.

H-52

Page 53: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

Fr To ( % ) ( % ) ( % ) ( % ) ( % ) ( % ) ( % ) ( % ) g/cm3 g/cm3 kg/cm2 ( ) kg/cm2 kg/cm2

1 3.00 4.00 2.73 0.10 61.35 26.58 34.77 35.75 1.78 1.31 0.36 3.00 0.15 0.895 1.91 0.16

2 5.00 6.00 2.71 0.05 56.35 21.83 34.52 52.00 1.80 1.18 0.40 5.00 0.20 0.912 1.89 0.3

3 10.00 10.45 2.75 0.80 55.50 24.22 31.28 25.88 1.92 1.53 0.42 6.00 0.25 1.064 1.02 0.41

4 14.00 15.00 2.73 71.00 32.00 39.00 40.00 1.83 1.31 0.43 3.00 0.56 1.071 5.10 0.45

5 24.00 24.45 2.78 6.60 52.45 29.90 22.55 21.88 1.98 1.62

6 32.00 32.45 2.75 2.90 51.13 27.62 23.51 22.55 1.86 1.52

7 40.00 40.45 2.75 12.20 36.00 29.00 7.00 21.42 1.84 1.51 0.15 19.00 0.30 1.252 1.29 0.50

8 45.00 45.45 2.69 48.50 NL NP NI 20.35 2.08 1.72

U C

S T

est

Consodration Test

TABLE 3.2 Summary of Soil PropertiesProject : Lagonpyin Water Treatment Plant Project Date : 24-8-2013

Location : E. 211421.20 , N. 1875351.14 Borehole No : BH-3

Gray, Very stiff, Silty CLAY

Gray, Silty CLAY

99.20

Gravel Sand

Brown to gray, Silty CLAY

Gray, Silty CLAY

Description of Soil

Spec

ific

g

ravi

ty Grain Size Analysis Atterberg Limit

Moi

stur

e co

nten

t

Bul

k de

nsit

y

Silt Clay (L.L) (P.L)

99.90

Dry

den

sity

( P. I )

Init

ial V

oid

R

atio

( e

)

Pre

-co

nsol

idat

ion

Pres

sure

( P

c )

Com

pres

sion

In

dex

( Cc

)

C

TriaxialCompression

Test

Gray,Very stiff, Clayey SILT with a little amount of sand.

Gray, Very dense, Silty SAND with allite amount of clay

100.00

93.40

97.10

51.50

99.50

87.80

Reddish brown, Hard, Silty CLAYtrace sand.

Gray, Hard, Clayey SILT with trace sand

Sr; N

o,

Dep

th (

m )

H-53

Page 54: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

Fr To ( % ) ( % ) ( % ) ( % ) ( % ) ( % ) ( % ) ( % ) g/cm3 g/cm3 kg/cm2 ( ) kg/cm2 kg/cm2

1 3.00 4.00 2.78 0.00 0.20 43.50 30.70 12.80 53.56 1.89 1.23 0.38 3.00 0.16 1.034 1.83 0.39

2 5.00 6.00 2.74 0.00 0.90 33.50 29.90 3.60 41.60 1.80 1.27 0.08 5.00 0.19 1.293 1.12 0.52

3 11.00 11.45 2.66 0.00 0.80 67.48 25.00 42.48 29.75 1.92 1.48 0.15 6.00 0.22 1.248 1.27 0.52

4 19.00 19.45 2.75 0.00 11.60 73.82 20.00 53.82 24.79 1.86 1.49

5 25.00 25.45 2.72 0.00 6.30 76.97 45.99 30.98 32.56 2.00 1.51

6 31.00 31.45 2.80 0.60 4.50 35.91 25.00 10.91 34.11 1.92 1.43

7 35.00 35.45 2.69 0.00 21.40 49.92 23.20 26.72 26.14 1.90 1.60 0.12 10.00 0.31 1.252 1.29 0.58

8 41.00 41.45 2.70 0.00 36.00 44.48 21.97 22.51 22.76 2.00 1.63 0.03 18.00 0.13 1.26 1.21 0.50

Gray, Silty CLAY with a little amount of sand. 99.80

Gray, Silty CLAY with a little amount of sand.

Brown, Very stiff, Silty CLAY with a little amount of sand.

Gray, Very stiff, Clayey SILT with trace sand.

Gray to brown, Very stiff, Silty CLAY with some sand.

Brown, Very dense, Sandy CLAYand silt.

Sr; N

o,

Dep

th (

m )

Description of Soil

Spec

ific

g

ravi

ty Grain Size Analysis Atterberg Limit

Moi

stur

e co

nten

t

Bul

k de

nsit

y

Dry

den

sity

Gravel Sand Silt

TABLE 3.2 Summary of Soil PropertiesProject : Lagonpyin Water Treatment Plant Project Date : 24-8-2013

: BH-4

88.40

99.20

Borehole No

Clay (L.L) (P.L) ( P. I )

Initi

al V

oid

R

atio

( e

)

Pre

-co

nsol

idat

ion

Pre

ssur

e ( P

c )

Com

pres

sion

In

dex

( Cc

)

C

TriaxialCompression

Test

U C

S T

est

Consodration Test

64.00

99.10

Brown, Hard, Clayey SILT with trace sand. 93.70

Gray, Very stiff, Clayey SILT with a little amount of sand and gravels.

Location : E. 211536.40 , N. 1875341.35

78.60

94.90

H-54

Page 55: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

Fr To ( % ) ( % ) ( % ) ( % ) ( % ) ( % ) ( % ) ( % ) g/cm3 g/cm3 kg/cm2 ( ) kg/cm2 kg/cm2

1 3.00 3.45 2.71 0.20 57.50 30.78 26.72 27.12 1.92 1.51 0.39 3.00 0.17 0.891 1.91 0.15

2 4.00 5.00 2.73 0.30 58.85 22.13 36.72 48.35 1.75 1.18 0.78 4.00 0.19 0.902 1.89 0.23

3 6.00 7.00 2.76 0.20 61.29 23.2 38.04 46.93 1.74 1.18 0.55 4.00 0.20 1.080 1.76 0.31

4 9.00 10.00 2.72 1.00 62.00 27.00 35.00 48.00 1.73 1.17 0.10 4.00 0.22 1.194 1.02 0.41

5 13.00 13.45 2.74 0.10 52.00 26.58 25.42 31.72 1.91 1.45 0.12 7.00 0.22 1.203 1.42 0.44

6 21.00 21.45 2.73 0.90 54.37 25.62 28.75 50.12 1.80 1.19

7 36.00 36.45 2.78 10.50 57.50 33.96 23.54 26.77 2.02 1.59

8 41.00 41.45 2.77 12.60 48.56 30.06 18.50 26.51 1.94 1.53

Dark brown, Stiff, Clayey SILT 99.80

Brown to gray, Silty CLAY 99.70

Gray, Silty CLAY 99.80

TriaxialCompression

Test

U C

S T

est

Consodration Test

Gravel Sand Silt Clay (L.L) (P.L) ( P. I )

Init

ial V

oid

R

atio

( e

)

Pre

-co

nsol

idat

ion

Pre

ssur

e ( P

c )

Com

pres

sion

In

dex

( Cc

)

C

Sr; N

o,

Dep

th (

m )

Description of Soil

Spec

ific

gr

avit

y Grain Size Analysis Atterberg Limit

Moi

stur

e co

nten

t

Bul

k de

nsit

y

Dry

den

sity

Project : Lagonpyin Water Treatment Plant Project Date : 24-8-2013

Location : E. 211536.40, N. 1875341.35 Borehole No : BH-5

TABLE 3.2 Summary of Soil Properties

Reddish brown, Hard, Clayey SILTwith trace sand. 89.50

Gray, Hard, Clayey SILT with trace sand.

99.90

Gray, Silty CLAY 99.00

Gray to brown, Very stiff, Silty CLAY

Gray, Stiff, Silty CLAY with a little amount of sand.

87.40

99.10

H-55

Page 56: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

Project

Location

SOIL TEST RESULTS For Triaxial Permeability

: Lagonpyin Water Treatment Plant

: South Dagon ,Yangon

:24 . 8 . 2013

UD

4.00

Date

UD

6.00

BH - 1

SPT

5.00

BORING NO :

3.00

TP

UD SPTSAMPLE TYPE :

SPECIMEN DEPTH ( M ) From 2.00

5.00

Triaxial Cofficient ofTP

0.17x10-90.38x10-9

To 3.00 5.45

Premeability Permeability at 20 c m/s 0.23x10-9

7.00

TP

0.38x10-9

TP

0.59x10-9

3.45

TP

H-56

Page 57: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

Project

Location

SOIL TEST RESULTS For Triaxial Permeability

: Lagonpyin Water Treatment Plant Date :24 . 8 . 2013

: South Dagon ,Yangon

BORING NO : BH - 2

SAMPLE TYPE : UD UD SPT UD SPT

10.00 12.00

To 6.00 9.00 9.45 11.00 12.45

SPECIMEN DEPTH ( M ) From 5.00 8.00 9.00

TP TP

Premeability Permeability at 20 c m/s 1.01x10-9 1.07x10-9 0.98x10-9 0.27x10-9 0.31x10-9

Triaxial Cofficient ofTP TP TP

H-57

Page 58: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

Project

Location

SOIL TEST RESULTS For Triaxial Permeability

: Lagonpyin Water Treatment Plant Date :24 . 8 . 2013

: South Dagon ,Yangon

BORING NO : BH - 3

SAMPLE TYPE : UD SPT UD UD SPT

14.00 15.00

To 4.00 4.45 6.00 15.00 15.45

SPECIMEN DEPTH ( M ) From 3.00 4.00 5.00

TP TP

Premeability Permeability at 20 c m/s 0.56x10-9 0.86x10-9 1.03x10-9 0.43x10-9 0.58x10-9

Triaxial Cofficient ofTP TP TP

H-58

Page 59: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

Project

Location

SOIL TEST RESULTS For Triaxial Permeability

: Lagonpyin Water Treatment Plant Date :24 . 8 . 2013

: South Dagon ,Yangon

BORING NO : BH - 4

SAMPLE TYPE : UD SPT UD SPT UD

6.00 7.00

To 4.00 4.45 6.00 6.45 8.00

SPECIMEN DEPTH ( M ) From 3.00 4.00 5.00

TP TP

Premeability Permeability at 20 c m/s 0.25x10-9 0.38x10-9 0.52x10-9 0.48x10-9 0.40x10-9

Triaxial Cofficient ofTP TP TP

H-59

Page 60: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

Project

Location

SOIL TEST RESULTS For Triaxial Permeability

: Lagonpyin Water Treatment Plant Date :24 . 8 . 2013

: South Dagon ,Yangon

BORING NO : BH - 5

SAMPLE TYPE : UD SPT UD SPT UD

7.00 9.00

To 5.00 5.45 7.00 7.45 10.00

SPECIMEN DEPTH ( M ) From 4.00 5.00 6.00

TP TP

Premeability Permeability at 20 c m/s 1.27x10-9 1.13x10-9 1.08x10-9 0.58x10-9 0.25x10-9

Triaxial Cofficient ofTP TP TP

H-60

Page 61: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

3. LO

Br

4. GE

an

sy

the

OCATION O

Theidge, Dagon

EOLOGY OF

The

The

nd deltaic la

nclinal basin

e Yangon ar

F THE PRO

e proposed n Seikkan an

Bore

F YANGON

e geology of

(a) Qua

(b) Tert

e regional ge

nds lying so

n containing

rea is shown

OJECT AREA

site of Lagond Thanlyin T

eholes Locat

AREA

f Yangon are

aternary dep

- 4. Upper D

- 3. Lower D

tiary deposits

- 2. Irrawadd

- 1. Pegu Se

eological stu

outh of the

g a thick Ter

n in table.

A

onpyin WateTownship, Y

ion Point of

ea was class

osits

Delta Alluvium

Delta Alluvium

s

dian Series,

eries, Oligoc

udy has bee

BagoYoma.

rtiary - Quat

r Treatment Yangon Divis

the Project A

sified into the

m, Pleistoce

m, Pleistoce

Pliocene

cene-Miocen

en made in a

. This area

ternary depo

Plant is situsion.

Area

e following g

ene and Rec

ene

ne

an area whic

a is in a nor

osits. Geolo

uated near D

geological un

cent

ch includes

rth-south tre

ogic success

Dagon

nits:

ridges

ending

sion of

H-61

East Dagon BH-6~7 for Bago river

Page 62: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

1

Location : Dagon Seikkan TownshipCoordinates : N-1862002.371,E-210562.598Elevation (m) : 3.26m

0 10 20 30 40 50 TD(6in) TD(6in)

3 0.26

Type

ofsa

mpl

e

1 2.26

2

Dept

h(m

)

Elev

atio

n(m

)

Casi

ng(m

)

2

2

2

2

0.18 1 1

SoilDescription

Grap

hicL

og

Grey, Very soft, Clayey SILT with little roots

( 0.0 ~ 3.45 ) m.

SPT(N Value)

1

4

Project

1

1

Boring Completed : 1.12.2013 Total Depth (m) : 40.5 mLogged by : Win Ko Ko Lwin Water Level (m) : 3.2 m

Type of Hammer : Automatic Sheet of 5

1

0.18 1

: Water Treatment Plant

3.00

: Lagonpyin ( Bago River )

FieldBearingcapacity

calculatedfromSPT

value(Kg/cm2)

1

SPT(No.ofBlow)

SD(6in)

0.18

1

Boring Started : 29.11.2013 Hole No : BH - 6

: Phyo Ko Ko Oo Driller : Maung HtayChecked by

1 1

1.26

0.74 0.20 1

StrengthofConsistencyofCohesiveSoils<2 VerySoft

VeryLoose2 4 Soft

LooseSand4 8 Firm

8 15 Stiff

15 30 VeryStiff

>30 Hard

1.74

2.74 26.00

5

Grey, Very soft to Firm, Clayey SILT ( 3.45 ~ 10.00 ) m.

2

6

7 3.74

10

6

<4

4 10

10 30

30 50

>50

MediumDense

Dense

VeryDense

SiltyCLAY

SandySILT

SiltySANDRockSample

DisturbedSample(Split spoon)

UndisturbedSampleClayeySILT

DensityofCohesionlessSoilsTypeofSample

9

8 4.74

5.74

6.74

9.00

0.22 1 1 1

0.70 2 3 3

110.22 1

``

H-62

Page 63: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

2

Location : Dagon Seikkan TownshipCoordinates : N-1862002.371,E-210562.598Elevation (m) : 3.26m

0 10 20 30 40 50 TD(6in) TD(6in)

0.47 1 2

0.59

12.0

4

4

4

5 1

8.74

13 9.74

14 10.74

3

11 7.74

12 0.47 1

Water Level (m) : 3.2 m

Type

ofsa

mpl

e

Checked by : Phyo Ko Ko Oo

Type of Hammer : Automatic Sheet of 5: Water Treatment Plant Boring Started : 29.11.2013 Hole No : BH - 6

Project: Lagonpyin ( Bago River )

Grap

hicL

og

Dept

h(m

)

Elev

atio

n(m

)

Casi

ng(m

)

SPT(N Value)SoilDescription

Boring Completed

Driller : Maung Htay

2

FieldBearingcapacity

calculatedfromSPT

value(Kg/cm2)

SPT(No. ofBlow)

SD(6in)

0.47 2

3

1

2

1 2

: 1.12.2013 Total Depth (m) : 40.5 mLogged by : Win Ko Ko Lwin

StrengthofConsistencyofCohesiveSoils<2 VerySoft

VeryLoose2 4 Soft

LooseSand4 8 Firm

8 15 Stiff

15 30 VeryStiff

>30 Hard

19

20

0.82 2 3

0.70 3

MediumDense

3

0.82 3 3

18 14.74

15.74

RockSample

DisturbedSample(Split spoon)

UndisturbedSample

17

15

SandySILT >50 VeryDense

10 30

16.74

ClayeySILT <4

Densityof CohesionlessSoils

12.74

13.74

SiltySAND 30 50 Dense

SiltyCLAY 4 10

TypeofSample

4

4

4

3

Grey, Firm to Stiff, Clayey SILY ( 10.00 ~ 20.00) m.

5

6

6

6

7

11.74 15.0

3

0.70 2 3

18.0

0.70 2 2

7

16

0.59 2 2 3

H-63

Page 64: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

3

Location : Dagon Seikkan TownshipCoordinates : N-1862002.371,E-210562.598Elevation (m) : 3.26m

0 10 20 30 40 50 TD(6in) TD(6in)SD(6in)

1.41 4 5

0.94 4

24.0

8

11

Casi

ng(m

)

SPT(N Value)

Dept

h(m

)

Elev

atio

n(m

)

SoilDescription

Grap

hicL

og

Type of Hammer : Automatic Sheet of 5: Water Treatment Plant Boring Started : 29.11.2013 Hole No : BH - 6

Project: Lagonpyin ( Bago River )

Total Depth (m) : 40.5 mLogged by : Win Ko Ko Lwin Water Level (m) : 3.2 mChecked by : Phyo Ko Ko Oo Driller : Maung Htay

Boring Completed : 1.12.2013

FieldBearingcapacity

calculatedfromSPT

value(Kg/cm2)

SPT(No. ofBlow)

Type

ofsa

mpl

e

21.0 5

7

4

7

1.06 3 4

1.29 3 4

12

4

921 17.74

Grey, Firm to Stiff, Clayey SILT ( 20.00 ~ 24.45 ) m.

24 20.74

22 18.74

23 19.74

StrengthofConsistencyofCohesiveSoils<2 VerySoft

VeryLoose2 4 Soft

LooseSand4 8 Firm

8 15 Stiff

15 30 VeryStiff

>30 Hard

29

25 21.74

28 24.74

13

16

16

17

14

1830

30 50

23.74

Dense

26.74 10

7 7

1.64 5

7

8

9

10

7

1.88 7

27.0

30.0

1.88 7

8

1.52 6 6

7

2.11 5 8

1.99

7

SandySILT >50 VeryDense

10 30 MediumDense

TypeofSample Densityof CohesionlessSoils

ClayeySILTUndisturbedSample <4

SiltyCLAY 4 10

RockSample

25.74

SiltySAND

DisturbedSample(Split spoon)

Grey, Medium dense, Silty SAND with a little amount of Clay

( 24.45 ~ 30.00 ) m.

26 22.74

27

H-64

Page 65: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

4

Location : Dagon Seikkan TownshipCoordinates : N-1862002.371,E-210562.598Elevation (m) : 3.26m

0 10 20 30 40 50 TD(6in) TD(6in)

Checked by : Phyo Ko Ko Oo

11

25

26

29

31 27.74

Dept

h(m

)

Elev

atio

n(m

)

Casi

ng(m

)

Driller : Maung Htay

SPT(N Value)

34

19

FieldBearingcapacity

calculatedfromSPT

value(Kg/cm2)

SPT(No. ofBlow)

SD(6in)

2.23 5 8

>5 30

: 1.12.2013 Total Depth (m) : 40.5 m

Grey, Medium dense, Silty SAND with a little amount of Caly

( 30.00 ~ 31.45 ) m.

30.74

29.74

32 28.74

33

15

Type

ofsa

mpl

e

Type of Hammer : Automatic Sheet of 5

Water Level (m) : 3.2 m

Project

Logged by : Win Ko Ko Lwin

: Water Treatment Plant Boring Started : 29.11.2013 Hole No : BH - 6Boring Completed

: Lagonpyin ( Bago River )

SoilDescription

Grap

hicL

og

>50

>50

>50

33.0 >5 15 29

>5 14 25

StrengthofConsistencyofCohesiveSoils<2 VerySoft

VeryLoose2 4 Soft

LooseSand4 8 Firm

8 15 Stiff

15 30 VeryStiff

>30 Hard

27

25

25

22

Grey, Very dense, Silty SAND ( 31.45 ~ 40.00 ) m.

35 31.74

>50

31

22

RockSample 30 50 Dense

40

38 34.74

36.74

36 32.74

37 33.74 >50

16

>5 16

>5 11

DisturbedSample(Split spoon) 10 30

>50

>50

MediumDense

SandySILT >50 VeryDense

SiltyCLAY 4 10

>5 15

SiltySAND

TypeofSample Densityof CohesionlessSoils

ClayeySILTUndisturbedSample <4

39 35.74 >50

>50

>5 25 30

26 31

>5 12 22

>5 15 25

H-65

Page 66: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

5: BH - 6

Location : Dagon Seikkan Township : 40.5 mCoordinates : N-1862002.371,E-210562.59 : 3.2 mElevation (m) : 3.26m

0 10 20 30 40 50 TD(6in) TD(6in)

Type of Hammer : Automatic Sheet of 5

Logged by : Win Ko Ko Lwin Water Level (m)

: Water Treatment Plant Boring Started : 29.11.2013 Hole NoBoring Completed : 1.12.2013 Total Depth (m)

Project

: Maung Htay

: Lagonpyin ( Bago River )

SPT(No.ofBlow)

SD(6in)

Checked by : Phyo Ko Ko Oo Driller

44

42

43

SoilDescription

Grap

hicL

og

Dept

h(m

)

Elev

atio

n(m

)

Casi

ng(m

)

SPT(N Value)

FieldBearingcapacity

calculatedfromSPT

value(Kg/cm2)

Type

ofsa

mpl

e

41

Grey, Very dense, Silty SAND ( 40.00 ~ 40.45 ) m.

ENDOFBOREHOLE

StrengthofConsistencyofCohesiveSoils<2 VerySoft

VeryLoose2 4 Soft

LooseSand4 8 Firm

8 15 Stiff

15 30 VeryStiff

>30 Hard

RockSample 30 50

45

47

46

48

Dense

SiltyCLAY 4 10DisturbedSample (Split spoon) 10 30 MediumDense

SandySILT >50 VeryDense

SiltySAND

Typeof Sample DensityofCohesionlessSoils

ClayeySILTUndisturbedSample <4

50

49

H-66

Page 67: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

1

Location : Thanlyin TownshipCoordinates : N-1861365.045,E-211005.719Elevation (m) : 4.31m

0 10 20 30 40 50 TD(6in) TD(6in)

: Lagonpyin ( Bago River )

Dark grey, Medium dense, Sandy SILT ( 0.00 ~ 1.45 ) m.

0.60

10

3.00

FieldBearingcapacity

calculatedfromSPT

value(Kg/cm2)

SPT(No.ofBlow)

SD(6in)

1.85

2

2 4

2.31

0.31 2

21

SPT(N Value)

: Water Treatment Plant

Casi

ng(m

)

Boring Started : 25.11.2013 Hole No : BH - 7

: Phyo Ko Ko Oo Driller : Maung HtayChecked by

Project

10

4

Boring Completed : 27.11.2013 Total Depth (m) : 40.5 mLogged by : Win Ko Ko Lwin Water Level (m) : 2.0 m

Type of Hammer : Automatic Sheet of 5

11

0.53 2

Brownish grey, Firm to Soft, Clayey SILT (

(1.45 ~ 6.45 ) m.

4

6

6

3 1.31

Type

ofsa

mpl

e

1 3.31

2

SoilDescription

Grap

hicL

og

Dept

h(m

)

Elev

atio

n(m

)

StrengthofConsistencyofCohesiveSoils<2 VerySoft

VeryLoose2 4 Soft

LooseSand4 8 Firm

8 15 Stiff

15 30 VeryStiff

>30 Hard

5

2

2

6.00 0.56

9.00

Grey, Very soft, Clayey SILT ( 6.45 ~ 10.00 ) m.

3

7 2.69

10

ClayeySILT

DensityofCohesionlessSoilsTypeofSample

9

8 3.69

4.69

5.69

0.22 1 1 1

0.23 1 1 1

<4

4 10

10 30

30 50

>50

MediumDense

Dense

VeryDense

SiltyCLAY

SandySILT

SiltySANDRockSample

DisturbedSample(Split spoon)

UndisturbedSample

5

6

0.69

1.69

0.30 1 1

3 22

2

``

H-67

Page 68: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

2

Location : Thanlyin TownshipCoordinates : N-1861365.045,E-211005.719Elevation (m) : 4.31m

0 10 20 30 40 50 TD(6in) TD(6in)

8

Boring Completed

Driller : Maung Htay

2

FieldBearingcapacity

calculatedfromSPT

value(Kg/cm2)

SPT(No. ofBlow)

SD(6in)

0.47 2

4

3

4

1 2

Type of Hammer : Automatic Sheet of 5: Water Treatment Plant Boring Started : 25.11.2013 Hole No : BH - 7

Project: Lagonpyin ( Bago River )

: 27.11.2013 Total Depth (m) : 40.5 mLogged by : Win Ko Ko Lwin Water Level (m) : 2.0 m

Type

ofsa

mpl

e

Checked by : Phyo Ko Ko Oo

9.69

3

SoilDescription

Grap

hicL

og

Dept

h(m

)

Elev

atio

n(m

)

Casi

ng(m

)

SPT(N Value)

11 6.69

12 0.70 2

Grey to yellowish brown,Soft to Firm to Stiff, Clayey SILT

with a little amount of peats( 10 00 ~ 18 45 ) m

12.0

4

6

6 2

7.69

13 8.69

14

0.94 2 4

0.70

StrengthofConsistencyofCohesiveSoils<2 VerySoft

VeryLoose2 4 Soft

LooseSand4 8 Firm

8 15 Stiff

15 30 VeryStiff

>30 Hard

Yellowish brown to grey,Stiff to Firm, Clayey SILT

( 18.45 ~ 20.00 ) m.

11

12

10

0.59 2 2 3

16

15.0

5

1.29 3 5

18.0

0.47 2 2

( 10.00 ~ 18.45 ) m.

SiltyCLAY 4 10

TypeofSample

7

5

2

6

5

4

8

10.69

Densityof CohesionlessSoils

11.69

12.69

SiltySAND 30 50 DenseRockSample

DisturbedSample (Split spoon)

UndisturbedSample

17

15

SandySILT >50 VeryDense

10 30

15.69

ClayeySILT <4

19

20

1.41 3 5

1.17 3

MediumDense

5

0.94 3 3

18 13.69

14.69

H-68

Page 69: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

3

Location : Thanlyin TownshipCoordinates : N-1861365.045,E-211005.719Elevation (m) : 4.31m

0 10 20 30 40 50 TD(6in) TD(6in)

21 16.69

Yellowish brown to grey,Stiff to Firm, Clayey SILT

( 20.00 ~ 23.45 ) m.

23 18.69

24 19.69 0.94 4 4

FieldBearingcapacity

calculatedfromSPT

value(Kg/cm2)

SPT(No. ofBlow)

Type

ofsa

mpl

e

21.0 4

4

3

4

0.82 3

4

Total Depth (m) : 40.5 mLogged by : Win Ko Ko Lwin Water Level (m) : 2.0 mChecked by : Phyo Ko Ko Oo Driller : Maung Htay

Boring Completed : 27.11.2013

3

7

Dept

h(m

)

Elev

atio

n(m

)

22 17.69

Type of Hammer : Automatic Sheet of 5: Water Treatment Plant Boring Started : 25.11.2013 Hole No : BH - 7

Project: Lagonpyin ( Bago River )

SoilDescription

Grap

hicL

og

SD(6in)

0.82 3 3

0.82 3

24.0

7

8

Casi

ng(m

)

SPT(N Value)

7

StrengthofConsistencyofCohesiveSoils<2 VerySoft

VeryLoose2 4 Soft

LooseSand4 8 Firm

8 15 Stiff

15 30 VeryStiff

>30 Hard

RockSample

24.69

SiltySAND

DisturbedSample(Split spoon)

Grey, Firm, Clayey SILT ( 23.45 ~ 30.00 ) m.

30

26 21.69

27

10 30 MediumDense

TypeofSample Densityof CohesionlessSoils

ClayeySILTUndisturbedSample <4

SiltyCLAY 4 10

SandySILT >50 VeryDense

30.0

0.82 3

3

0.94 3 4

3

0.82 3 3

0.94

8

6

7

7

0.70 3

27.0 3

30 50

22.69

Dense

25.69 4

3 4

0.70 3

4

3

4

4

3

8

629

25 20.69

28 23.69

H-69

Page 70: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

4

Location : Thanlyin TownshipCoordinates : N-1861365.045,E-211005.719Elevation (m) : 4.31m

0 10 20 30 40 50 TD(6in) TD(6in)

SoilDescription

Grap

hicL

og

28.69

32 27.69

33

FieldBearingcapacity

calculatedfromSPT

value(Kg/cm2)

1.17 4 5

0.82 4 4

7

29.69

8

10

7

33.0

Grey, Firm to Hard, Clayey SILT with a little amount of Sand

( 30.00 ~ 37.45 ) m.

Type of Hammer : Automatic Sheet of 5

Water Level (m) : 2.0 m

Project

Logged by : Win Ko Ko Lwin

: Water Treatment Plant Boring Started : 25.11.2013 Hole No : BH - 7Boring Completed

: Lagonpyin ( Bago River )

4

: 27.11.2013 Total Depth (m) : 40.5 m

Type

ofsa

mpl

e

Checked by : Phyo Ko Ko Oo

431 26.69

Dept

h(m

)

Elev

atio

n(m

)

Casi

ng(m

)

Driller : Maung Htay

SPT(N Value)

34

3

SPT(No. ofBlow)

SD(6in)

0.82

3 4

5

3

3

0.94

StrengthofConsistencyofCohesiveSoils<2 VerySoft

VeryLoose2 4 Soft

LooseSand4 8 Firm

8 15 Stiff

15 30 VeryStiff

>30 Hard

10 21

35

SiltyCLAY 4 10

>50

25

>5

SiltySAND

TypeofSample Densityof CohesionlessSoils

ClayeySILTUndisturbedSample <4

39 34.69 >50

>50

>5 26

6

40

38 33.69

35.69

36 31.69

37 32.69

Dense

Grey, Very dense, Silty SAND with a little amount of Clay

( 37.45 ~ 40.00 ) m.

DisturbedSample (Split spoon) 10 30

>50

MediumDense

SandySILT >50 VeryDense

RockSample 30 50

30.69

32

31

20

21

17

>5 10

>5 13

>50

3

30

30

24 35

0.70 4 3

>5

H-70

Page 71: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

5: BH - 7

Location : Thanlyin Township : 40.5 mCoordinates : N-1861365.045,E-211005.71 : 2.0 mElevation (m) : 4.31m

0 10 20 30 40 50 TD(6in) TD(6in)

SoilDescription

Grap

hicL

og

Dept

h(m

)

Elev

atio

n(m

)

Casi

ng(m

)

SPT(N Value)

FieldBearingcapacity

calculatedfromSPT

value(Kg/cm2)

Type

ofsa

mpl

e

41

Grey, Very dense, Silty SAND with a little amount of Clay

( 40.00 ~ 40.45 ) m.

43

SPT(No.ofBlow)

SD(6in)

Checked by : Phyo Ko Ko Oo Driller

44

42

Type of Hammer : Automatic Sheet of 5

Logged by : Win Ko Ko Lwin Water Level (m)

: Water Treatment Plant Boring Started : 25.11.2013 Hole NoBoring Completed : 27.11.2013 Total Depth (m)

Project

: Maung Htay

: Lagonpyin ( Bago River )

ENDOFBOREHOLE

StrengthofConsistencyofCohesiveSoils<2 VerySoft

VeryLoose2 4 Soft

LooseSand4 8 Firm

8 15 Stiff

15 30 VeryStiff

>30 Hard

Typeof Sample DensityofCohesionlessSoils

ClayeySILTUndisturbedSample <4

50

49

SiltyCLAY 4 10DisturbedSample(Split spoon) 10 30 MediumDense

SandySILT >50 VeryDense

SiltySAND

46

48

DenseRockSample 30 50

45

47

H-71

Page 72: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

Fr To ( % ) ( % ) ( % ) ( % ) ( % ) ( % ) ( % ) ( % ) g/cm3 g/cm3 kg/cm2 ( ° ) kPa kPa

1 3.00 3.45 2.62 2.00 86.00 12.00 41.00 20.00 21.00 36.0 1.810 1.33

2 5.00 6.00 2.67 1.00 89.00 10.00 43.00 22.00 21.00 39.0 1.790 1.29 12.00 5.00 12.00 1.085 80 0.46

3 7.00 8.00 2.65 11.00 81.00 8.00 42.00 22.00 20.00 37.0 1.840 1.34 14.00 5.00 16.00 0.948 140 0.25

4 9.00 10.00 2.64 5.00 73.00 22.00 50.00 22.00 28.00 40.0 1.850 1.32 20.00 5.00 35.00 0.983 165 0.24

5 12.00 12.45 2.62 13.00 49.00 21.00 28.00 35.0 1.880 1.39 18.00 4.00 35.00

6 17.00 17.45 2.64 8.00 53.00 20.00 33.00 32.0 1.890 1.43 15.00 4.00 22.00

7 26.00 26.45 2.65 2.00 71.00 NA NA NA 28.0 1.890 1.48

8 35.00 35.45 2.69 1.00 62.00 NA NA NA 20.0 1.840 1.53

Remark: Gravels size was 2mm to 3.35mm

TABLE 3.2 Summary of Soil PropertiesProject : Lagonpyin Water Treatment Plant Project (Bago River)

Location : E. 210562.598, N. 1862002.371

Spe

cifi

c

grav

ity Grain Size Analysis Atterberg Limit

Gravel Sand Sr;

No,

TriaxialCompression

Test

Moi

stur

e co

nte

nt

Bu

lk d

ensi

ty

Dep

th (

m )

Dry

den

sity

U C

S T

est

(L.L) (P.L) ( P. I )C

Description of Soil Silt

Grey, Medium Dense Silty SAND 27.00

37.00

Grey, Soft Clayey SILT

Grey, Firm Clayey SILT 87.00

Grey, Soft Clayey SILT

: 12-12-2013

Borehole No

Date

Consodration Test

Init

ial V

oid

Rat

io (

e )

Pre

-co

nsol

idat

ion

P

ress

ure

( P

c )

Com

pre

ssio

n

Inde

x (

Cc

)

Grey, Very Dense Silty SAND

Grey, Very Soft Clayey SILT

Grey, Firm Clayey SILT 92.00

: BH-6

Grey, Very Soft Clayey SILT

Clay

H-72

Page 73: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

Fr To ( % ) ( % ) ( % ) ( % ) ( % ) ( % ) ( % ) ( % ) g/cm3 g/cm3 kg/cm2 ( ° ) kPa kPa

1 2.00 3.00 2.67 1.00 68.00 31.00 61.00 25.00 36.00 32.00 1.92 1.45 81.00 7.00 90.00 0.839 220 0.34

2 7.00 8.00 2.66 14.00 64.00 22.00 53.00 19.00 34.00 32.00 1.81 1.37 10.00 2.00 18.00 0.979 150 0.34

3 9.00 10.00 2.66 2.00 64.00 34.00 45.00 21.00 24.00 28.00 1.99 1.55 19.00 5.00 28.00 0.739 115 0.20

4 14.00 14.45 2.65 3.00 73.00 24.00 49.00 19.00 30.00 33 1.86 1.40

5 19.00 19.45 2.68 3.00 75.00 22.00 43.00 19.00 24.00 33 1.80 1.41

6 25.00 25.45 2.62 2.00 75.00 23.00 46.00 23 23.00 35 1.83 1.36 25.00 8.00 48.00

7 32.00 32.45 2.65 2.00 12.00 49.00 37.00 72.00 26 46.00 34 1.87 1.40 30.00 5.00 62.00

8 38.00 38.45 2.69 75.00 NA NA NA 24 1.98 1.60

Remark: Gravels size was 2mm to 3.35mm

Project

Location

( P. I )Sr;

No,

Dep

th (

m )

Description of Soil

Spe

cifi

c

grav

ity Atterberg Limit

Gravel

Moi

stur

e co

nte

nt

CBu

lk d

ensi

ty

Dry

den

sity

TriaxialCompression

Test

Silt Clay (L.L)

Grain Size Analysis

Grey, Very Soft Clayey SILT

Sand (P.L) U C

S T

est

Grey, Very Soft Clayey SILT

Grey, Firm Clayey SILT

Grey, Very Dense Silty SAND

: E. 211005.719 , N. 1861365.045

Yellowish brown, Stiff Clayey SILT

Com

pre

ssio

n

Inde

x (

Cc

)

Pre

-co

nsol

idat

ion

P

ress

ure

( P

c )

Init

ial V

oid

Rat

io (

e )

: BH-7Borehole No

: 12-12-2013Date

Consodration Test

Grey, Firm Clayey SILT

Grey, Firm Clayey SILT

: Lagonpyin Water Treatment Plant Project (Bago River)

25.00

TABLE 3.2 Summary of Soil Properties

Grey, Very Soft Clayey SILT

H-73

Page 74: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

Project

Location

BORING NO :

7.00

UD

9.00

Date

BH - 6

SOIL TEST RESULTS For Triaxial Permeability

: Lagonpyin Water Treatment Plant

: Dagon Seikkan ,Yangon

:12 . 12 . 2013

UD UDSAMPLE TYPE :

SPECIMEN DEPTH ( M ) From 5.00

8.00

TP TP

10.00

Triaxial Cofficient of TP

Premeability Permeability at 20 c m/s 5.10x10-9 3.60x10-92.00x10-9

To 6.00

H-74

Page 75: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

Project

Location

SOIL TEST RESULTS For Triaxial Permeability

: Lagonpyin Water Treatment Plant Date :12 . 12 . 2013

: Thanlyin ,Yangon

BORING NO : BH - 7

SAMPLE TYPE : UD UD UD

To 3.00 8.00 10.00

SPECIMEN DEPTH ( M ) From 2.00 7.00 9.00

Premeability Permeability at 20 c m/s 0.73x10-9 0.27x10-9 0.09x10-9

Triaxial Cofficient of TP TP TP

H-75

Page 76: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

2

3.0 LOCATION OF THE PROJECT SITE

The proposed site of The Improvement Of Water supply is situated near Dagon University, EastDagonTownship, YangonDivision. The location of project site is shown in Fig. (1) .

Fig. (1) Location Map of the Project Area

4.0 METHODS OF INVESTIGATION

Wash boring method up to the depth of 40m and sampling program of 1m up to depth of 40m intervals were specified. Borehole sounding test or Standard Penetration Test was performed in accordance with ASTM-D1586 standard. Bore logging and visual soil classification were made. The ground water table was measured and recorded. The soil profile and its corresponding SPT-N values are graphically presented in this report. It is compiled with the lab test result on the disturbed but representative samples.

5.0 GEOLOGY OF YANGON AREA

The geology of Yangon area was classified into the following geological units:

(a) Quaternary deposits

- 4. Upper Delta Alluvium, Pleistocene and Recent

- 3. Lower Delta Alluvium, Pleistocene

(b) Tertiary deposits

- 2. Irrawaddian Series, Pliocene

- 1. Pago Series, Oligocene-Miocene

H-76

North Dagon BH-1 for Zone7 Service Reservoir

Page 77: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

1ProjectLocation : East Dagon TownshipCoordinatesElevation (m) : 2.78 m

0 10 20 30 40 50

: N-1872962.98,E-204352.74

3

1

Very Loose

Gray colour, soft to very soft,Silty CLAY with some peat.

( 5.5 m ~ 8.5 m )

Dark gray colour, very soft,Silty CLAY with some peat.

( 8.5 m ~ 10.0 m )

: 9 . 4 . 2013

SOILINVERSTIGATIONLOG

Cas

ing

(m)

SPT(N-Value)

of 4: 1: 40.5 m

Sheet

: 4.3 m: Than Maung

Field Bearing capacity calculated

from SPT value(Ton/ft2)Ty

pe o

f sa

mpl

e

Type of Hammer : AutomaticBoring Started : 6 . 4 . 2013 Hole No

Total Depth (m)Logged by : Phyo Ko Ko Oo

DrillerWater Level (m)

Checked by : Wai Phyo Aung

1

Soil Description

Gra

phic

Log

Elev

atio

n

(m)

Dep

th (m

)1.78

Brown, soft, Silty CLAY( 0.0 m ~ 1.5 m ).

2

:The Improvement Of Water Supply Boring Completed

Gray colour,very soft, Silty CLAY( 1.5 m ~ 5.5 m )

6

5

3

4

-2.22

-3.22

3.00

Disturbed Sample (Split spoon)

Rock Sample

Undisturbed Sample

0.78

-0.22

-1.22

6.00

Type of Sample

10

8

7

Very FirmHard

Medium

9

Very Soft

0.118

0.118

0.118

0.235-7.22

-4.22

-5.22

-6.22 9.00

0.370

UD

UD

UD

0.105

0.315

Density of Cohesionless Soils

4 - 10

Medium Dense

Very Dense

10 - 30

30 - 50 Dense

<4

Loose Sand

>50

4

1

1

1

2

Soft

Strength of Consistency of Cohesive Soils

<2

2 - 4

>30

4 - 8

8 - 15

15 - 30

Firm

H-77

Page 78: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

2ProjectLocation : East Dagon TownshipCoordinatesElevation (m) : 2.78 m

0 10 20 30 40 50

Checked by : Wai Phyo Aung: N-1872962.98,E-204352.74

Rock Sample

Dark gray colour, soft,Silty CLAY with some peat.

( 10.0 m ~ 11.5 m )

Gray to brown colour,medium firm, Silty CLAY

( 11.5 m ~ 13.5 m )

Dark gray, medium firm,Silty CLAY with alittle amount of peat

( 15.5 m ~ 17.5 m ).

Gray, very firm,Silty CLAY with lateritic soil

( 17.5 m ~ 20.0 m ).

Very Dense

4 - 8

2.85

20 -17.22 2.97

Disturbed Sample (Split spoon) Medium

Type of Sample Density of Cohesionless Soils

<4 Very LooseUndisturbed Sample

4 - 10 Loose Sand

15 - 30

4

19

23

24

10 - 30 Medium Dense8 - 15 Firm 30 - 50 Dense

Very Firm >50

Strength of Consistency of Cohesive Soils

<2 Very Soft

2 - 4 Soft

2.35

0.495

15 -12.22 15.00 0.495

0.495

17 -14.22 0.6185

16

18.00

0.618

14 -11.22

: 40.5 m: 4.3 m: Than Maung

0.495

12 -9.22 12.00 0.990

13 -10.22

Type

of

sam

ple Field Bearing

capacity calculated from SPT value

(Ton/ft2)

:The Improvement Of Water Supply Boring Started : 6 . 4 . 2013 Hole NoBoring Completed : 9 . 4 . 2013 Total Depth (m)Logged by : Phyo Ko Ko Oo Water Level (m)

Driller

Type of Hammer : Automatic

SPT(N-Value)

Sheet of 4: 1

4

8

5

4

Gra

phic

Log

Dep

th (m

)

Elev

atio

n

(m)

Cas

ing

(m)

SOILINVERSTIGATIONLOG

Dark gray colour,soft, Silty CLAY.

( 13.5 m ~ 15.5 m )

Soil Description

11 -8.22

-13.22

4

19 -16.22

18 -15.22

H-78

Page 79: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

3ProjectLocation : East Dagon TownshipCoordinatesElevation (m) : 2.78 m

0 10 20 30 40 50

-25.22

-22.22

22 -19.22

27

: N-1872962.98,E-204352.74

38

41

Disturbed Sample (Split spoon) 4 - 8 Medium

Type of Sample Strength of Consistency of Cohesive Soils

Gra

phic

Log

: Wai Phyo Aung

10 - 30

Soil Description

Hole NoSheet of 4

: 1Type of Hammer : Automatic

:The Improvement Of Water Supply

-24.22 27.00

24 -21.22 24.00

Boring Started : 6 . 4 . 2013

28

Medium Dense8 - 15 Firm 30 - 50 Dense

Rock Sample 15 - 30 Very Firm >50 Very Dense

Undisturbed Sample 2 - 4 Soft 4 - 10 Loose Sand

29 -26.22 4.70

30 -27.22 30.00 5.07Density of Cohesionless Soils

<2 Very Soft <4 Very Loose

4.33

4.33

38

36

35

35

2.10

26 -23.22 4.45

23 -20.22 3.34

4.95

25 4.70

17

27

40

Field Bearing capacity calculated

from SPT value(Ton/ft2)

21 -18.22 21.00 2.35

: 40.5 m: 4.3 m: Than Maung

Total Depth (m)Water Level (m)Driller

Type

of

sam

ple

Dep

th (m

)

Elev

atio

n

(m)

Cas

ing

(m)

SPT(N-Value)

19

Boring Completed : 9 . 4 . 2013Logged by : Phyo Ko Ko OoChecked by

Graywish brown, very firm,Silty CLAY with alittle amount of sand

(20.0 m ~ 23.5 m ).

Brown, dense, Silty SANDwith alittle amount of clay

( 23.5 m ~ 30.0 m )

SOILINVERSTIGATIONLOG

H-79

Page 80: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

4ProjectLocation : East Dagon TownshipCoordinatesElevation (m) : 2.78 m

0 10 20 30 40 50

47

38

: N-1872962.98,E-204352.74

39

45C

asin

g (m

)

Soil Description

49

>50

Firm 30 - 50

35 -32.22

38 -35.22

-30.22

>50

>50

>50

>50

Type of Sample Strength of Consistency of Cohesive Soils Density of Cohesionless Soils

>5

<4 Very Loose

8 - 15

Gra

phic

Log

Dep

th (m

)

-37.22

Elev

atio

n

(m)

31 -28.22

33.00

36.0036 -33.22

37 -34.22

34 -31.22

32 -29.22

33

>5

4.70

>5

>5

5.57

5.81

Gray,verydense, SiltySAND(35.5m~40.5m)

DenseRock Sample 15 - 30 Very Firm >50 Very Dense

Undisturbed Sample 2 - 4 Soft 4 - 10 Loose Sand

Disturbed Sample (Split spoon) 4 - 8 Medium 10 - 30 Medium Dense

<2 Very Soft

40

: 9 . 4 . 2013 Total Depth (m)Logged by : Phyo Ko Ko Oo Water Level (m)Checked by : Wai Phyo Aung Driller

>5

>5

39 -36.22

: 4.3 m: Than Maung

SPT(N-Value)

Type

of

sam

ple Field Bearing

capacity calculated from SPT value

(Ton/ft2)

4.82

: 40.5 m

Sheet of 4: 1

Type of Hammer : Automatic:The Improvement Of Water Supply Boring Started : 6 . 4 . 2013 Hole No

Boring Completed

Brown, dense, Silty SANDwith alittle amount of clay

( 30.0 m ~ 31.5 m )

Yellowishbrown,dense,SiltySANDwithalittleamount of clay

(31.5m~33.5m)

Gray,dense, SiltySAND(33.5m~35.5m)

SOILINVERSTIGATIONLOG

H-80

Page 81: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

Fr To ( % ) ( % ) ( % ) ( % ) ( % ) ( % ) ( % ) ( % ) g/cm3 g/cm3 kg/cm2 ( ° ) kg/cm2 kg/cm2

1 2.00 3.00 2.58 0.00 3.10 64.03 36.67 27.36 39.96 1.84 1.31 0.19 3.00 0.21 0.990 1.39 0.29

2 3.00 4.00 2.58 0.00 4.83 59.44 33.61 25.83 40.80 1.79 1.27 0.14 6.00 0.22 1.090 1.35 0.35

3 4.00 5.00 2.59 0.00 2.76 66.27 36.94 29.33 41.24 1.76 1.25 0.21 2.00 0.24 1.060 1.40 1.32

4 6.00 6.45 2.57 0.00 5.87 51.33 31.19 20.14 42 1.71 1.20 0.23 4.00 0.18

5 9.00 9.45 2.51 0.00 5.10 57.36 32.74 24.62 46.88 1.79 1.22 0.21 1.00 0.22

6 15.00 15.45 2.53 0.00 7.43 49.68 29.75 19.93 50 1.89 1.26 0.28 4.00 0.19

7 18.00 18.45 2.55 1.20 46.00 39.41 20.00 19.41 23.48 1.99 1.61 0.17 9.00 0.20

Moi

stur

e co

nten

t

Bul

k de

nsity

Dry

dens

ity

U C

S T

est

C

Dark gray colour, soft Silty CLAY with trace amount of sand. 92.57

: 8-5-2013

Gray colour, Silty CLAY with trace amount of sand.

Clay

96.90

Silt

: BH-1

Dark gray colour, Silty CLAY with sand and trace amount of Gravels. 52.80

Dark gray colour, very soft SiltyCLAY with trace amount of sand.

Consolidation Test

Initi

al V

oid

R

atio

( e

)

Pre-

cons

olid

atio

n Pr

essu

re (

Pc)

Com

pres

sion

In

dex

( Cc

)

TriaxialCompression

Test

(L.L) (P.L) ( P. I )Description of Soil

Gray colour, Silty CLAY with trace amount of sand. 97.24

94.90

Gravel Sand

Spec

ific

grav

ity Grain Size Analysis Atterberg Limit

SOIL TEST RESULTSProject : The Improvement of Water Supply Project

Location : East Dagon Township, Yangon Borehole No

Date

Gray colour, very soft Silty CLAY with trace amount of sand. 94.13

Gray colour, Silt CLAY with trace amount of sand. 95.17

Sr; N

o,

Dept

h ( m

)

H-81

Page 82: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

Fr To ( % ) ( % ) ( % ) ( % ) ( % ) ( % ) ( % ) ( % ) g/cm3 g/cm3 kg/cm2 ( ° ) kg/cm2 kg/cm2

8 22.00 22.45 2.59 0.00 48.61 24.83 15.38 9.45 27 1.97 1.55 0.20 4.00 0.21

9 26.00 26.45 2.62 0.00 55.40 NL NP NI 29.23 1.82 1.41 0.19 10.00 0.16

10 30.00 30.45 2.60 0.00 68.31 NL NP NI 21.00 1.96 1.62 0.17 12.00 0.08

11 32.00 32.45 2.57 3.10 75.00 NL NP NI 26.35 1.86 1.47 0.19 13.00 0.23

12 36.00 36.45 2.58 0.00 60.40 NL NP NI 22.55 2.05 1.67 0.22 15.00 0.18

13 38.00 38.45 2.63 0.00 82.20 NL NP NI 28.00 1.9 1.48 0.26 12.00 0.14

: 8-5-2013Date

Brown colour, dense, Silty SAND with a little amount of clay.

Brown colour, dense, Silty SAND with a little amount of clay.

44.60

31.89

Gray colour, very dense, SiltySAND with trace amount of clay. 17.80

U C

S T

est

Atterberg Limit

Moi

stur

e co

nten

t

Bulk

den

sity

Dry

dens

ity

Graywish brown colour, very firm Silty CLAY with sand. 51.39

Yellowish brown colour, dense, Silty SAND with trace amount of clay.

21.90

Gray colour, very dense, Silty SAND with trace amount of clay. 39.60

Gravel Sand Silt Clay (L.L) (P.L) ( P. I )

Initi

al V

oid

R

atio

( e

)

Pre-

cons

olid

atio

n Pr

essu

re (

Pc )

Com

pres

sion

In

dex

( Cc

)

C

TriaxialCompression

Test

Sr; N

o,

Dept

h ( m

)

Description of Soil

Spec

ific

grav

ity Grain Size Analysis

Location : East Dagon Township, Yangon : BH-1

Consolidation Test

Borehole No

SOIL TEST RESULTSProject : The Improvement 0f Water Supply Project

H-82

Page 83: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

: The Improvement of Water Supply Project

Soil Test Results For Triaxial Permeability Test

SAMPLE TYPE :

BORING NO : BH-1

Project

Location

: UD

Premeability Permeability at 20 c m/s

TP

3.9 x10-10

Triaxial Cofficient of

4.1 x10-104.2 x10-10

TP TP

UD

4.00

Date: 8.5.2013

5.00

: East Dagon ,Yangon

From

To 3.00

3.00

4.00

SPECIMEN DEPTH ( M ) 2.00

Date: 15.4.2013

UD

Date: 28.4.2013

H-83

Page 84: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

2

3.0 LOCATION OF THE PROJECT SITE

The proposed site of The Improvement Of Water supply is situated near 56 Ort, South Dagon Township, Yangon Division. The location of project site is shown in Fig. (1) .

Fig. (1) Location Map of the Project Area

4.0 METHODS OF INVESTIGATION

Wash boring method up to the depth of 50m and sampling program of 1m up to depth of 50m intervals were specified. Borehole sounding test or Standard Penetration Test was performed in accordance with ASTM-D1586 standard. Bore logging and visual soil classification were made. The ground water table was measured and recorded. The soil profile and its corresponding SPT-N values are graphically presented in this report. It is compiled with the lab test result on the disturbed but representative samples.

5.0 GEOLOGY OF YANGON AREA

The geology of Yangon area was classified into the following geological units:

(a) Quaternary deposits

- 4. Upper Delta Alluvium, Pleistocene and Recent

- 3. Lower Delta Alluvium, Pleistocene

(b) Tertiary deposits

- 2. Irrawaddian Series, Pliocene

- 1. Pegu Series, Oligocene-Miocene

H-84

South Dagon BH-1 for Zone8 Service Reservoir

Page 85: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

1ProjectLocation : South Dagon TownshipCoordinatesElevation (m) : 3.00 m

0.36

1.26

0.99

1.50

2.24

2.65

3

4Gray to brown, medium dense,

Silty SAND ( 1.5 m ~ 6.5 m ).

Graywish brown, medium dense to dense, Silty SAND

( 6.5 m ~ 10.0 m ).

4

1.00

0.00

-1.00

-2.00

-3.00

3.00

14

11

17

-7.00

5

Type of Sample

-5.00

-6.00 9.00

2.51

2.28

3.76

3.08

-4.00 22

33

27

Strength of Consistency of Cohesive Soils Density of Cohesionless Soils

4 - 10

<2

2 - 4

6.00

8

7

6

20

>30

Medium Dense

Very Dense

4 - 8 10 - 30 8 - 15

15 - 3030 - 50 DenseFirm

Disturbed Sample (Split spoon)

Rock Sample

Undisturbed Sample

Soil Description

2.00Brown, soft, Silty SAND and Clay

( 0.0 m ~ 1.5 m ).

2

:The Improvement Of Water Supply Boring Completed

: N-1865562.43,E-207987.62: 30 . 3 . 2013

SOILINVERSTIGATIONLOG

SPT (N-Value)

of 5: 1: 50.0 m

Sheet

: 4.4 m: Than Maung

Field Bearing capacity calculated

from SPT value (Ton/ft2)

Type of Hammer : AutomaticBoring Started : 27 . 3 . 2013 Hole No

Total Depth (m)Logged by : Phyo Ko Ko Oo Water Level (m)Checked by : Wai Phyo Aung Driller

>50 Very FirmHard

Medium

9

Very Soft Very Loose

Loose Sand

22

26

<4

1

10

Soft

H-85

Page 86: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

2ProjectLocation : South Dagon TownshipCoordinatesElevation (m) : 3.00 m

40

30

14

Type of Sample

Undisturbed Sample

8 - 15 Firm 30 - 50

-11.00

37

3.14

16 -13.00

4.44

20 -17.00 2.6422

19 -16.00

10 - 30 Medium Dense

: 1

Field Bearing capacity calculated

from SPT value (Ton/ft2)

:The Improvement Of Water Supply Boring Started : 27 . 3 . 2013 Hole NoBoring Completed : 30 . 3 . 2013 Total Depth (m)Logged by : Phyo Ko Ko Oo Water Level (m)Checked by : Wai Phyo Aung Driller

SOILINVERSTIGATIONLOG

: N-1865562.43,E-207987.62

SPT (N-Value)Soil Description

: 50.0 m: 4.4 m: Than Maung

3.60

12 -9.00 12.00 4.80

13 -10.00

11

3.60

14 1.68

15 -12.00 15.00 1.44

UD

12

3.84

Dense

<4 Very Loose2 - 4 Soft 4 - 10 Loose Sand

Rock Sample 15 - 30 Very Firm >50 Very Dense

4 - 8

Type of Hammer : Automatic Sheet of 5

Gray, Sandy CLAY with silt ( 15.5 m ~ 17.0 m ).

Gray, medium dense to dense, Silty SAND

( 17.0 m ~ 20.0 m ).

Disturbed Sample (Split spoon) Medium

-8.00

18 -15.00 18.00

Graywish brown, medium dense to dense, Silty SAND

( 10.0 m ~ 13.5 m ).

Gray, firm, Sandy CLAY with silt ( 13.5 m ~ 15.5 m ).

26

32

30

17 -14.00

Strength of Consistency of Cohesive Soils Density of Cohesionless Soils<2 Very Soft

H-86

Page 87: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

3ProjectLocation : South Dagon TownshipCoordinatesElevation (m) : 3.00 m

21 -18.00

: N-1865562.43,E-207987.62

Gray,medium dense to dense, Silty SAND with alittle amount of Clay

(20.0 m ~ 23.5 m ).

of 5: 1

SOILINVERSTIGATIONLOG

21.00

Boring Completed : 30 . 3 . 2013Logged by : Phyo Ko Ko OoChecked by

Field Bearing capacity calculated

from SPT value (Ton/ft2)

Type of Hammer : Automatic:The Improvement Of Water Supply Boring Started : 27 . 3 . 2013 Hole No

Sheet

Soil DescriptionSPT

(N-Value)

: Wai Phyo Aung

3.36

: 50.0 m: 4.4 m: Than Maung

Total Depth (m)Water Level (m)Driller

28

26 -23.00 4.32

23 -20.00 4.08

3.12

25 3.60

26

30

36

Very Loose<2 Very Soft <4

27

4.68

4.08

39

34

34

29 -26.00

30 -27.00 30.00 4.8040

36

Medium Dense8 - 15 Firm 30 - 50 Dense

Rock Sample 15 - 30 Very Firm >50 Very Dense

Disturbed Sample (Split spoon) 4 - 8 Medium 10 - 30

Undisturbed Sample 2 - 4 Soft 4 - 10

Density of Cohesionless Soils

28 -25.00 4.6839

22 -19.00

Loose Sand

-24.00

4.32

27.00

24 -21.00

Type of Sample Strength of Consistency of Cohesive Soils

Gray, very firm to hard, Silty CLAY with alittle amount of sand

( 23.5 m ~ 28.5 m ).

Gray, hard, Clayey SILT with a little amount of sand

( 28.5 m ~ 30.0 m ).

24.00

-22.00

H-87

Page 88: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

4ProjectLocation : South Dagon TownshipCoordinatesElevation (m) : 3.00 m

Gray, very firm to hard, Clayey SILT with a little amount of sand

( 30.0 m ~ 40.0 m ).

SOILINVERSTIGATIONLOG

3.96

3.12

31 -28.00

Sheet of 5: 1

33

Field Bearing capacity calculated

from SPT value (Ton/ft2)

Boring Completed : 30 . 3 . 2013 Total Depth (m)Logged by : Phyo Ko Ko Oo Water Level (m)Checked by : Wai Phyo Aung Driller

: N-1865562.43,E-207987.62

34 -31.00

32 -29.00

39.00

33

2.40

2.40

2.64

-30.00

26

20

22

20

24

26

2.88

3.12

39 -36.00 3.48

3.242738 -35.00

4.20Type of Sample Strength of Consistency of Cohesive Soils Density of Cohesionless Soils

3540 -37.00

Very Dense

Undisturbed Sample 2 - 4 Soft 4 - 10 Loose Sand

Disturbed Sample (Split spoon) 4 - 8 Medium 10 - 30 Medium Dense

<2 Very Soft <4 Very Loose

8 - 15 DenseRock Sample 15 - 30 Very Firm >50

Hole No: 50.0 m: 4.4 m: Than Maung

SPT (N-Value)Soil Description

Type of Hammer : Automatic:The Improvement Of Water Supply Boring Started : 27 . 3 . 2013

29

36 -33.00

37 -34.00

33.00

36.00

Firm 30 - 50

35 -32.00

H-88

Page 89: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

5ProjectLocation : South Dagon TownshipCoordinatesElevation (m) : 3.00 m

43

SOILINVERSTIGATIONLOG

Disturbed Sample (Split spoon) 4 - 8 Medium 10 - 30

<2 Very Soft <4

42 -39.00

Medium Dense8 - 15 Firm 30 - 50 Dense

Rock Sample 15 - 30 Very Firm >50 Very Dense

Undisturbed Sample 2 - 4 Soft 4 - 10 Loose Sand

-47.00 >5

Very Loose

: N-1865562.43,E-207987.62

Type of Sample Strength of Consistency of Cohesive Soils Density of Cohesionless Soils

-42.00 5.7648

47 >50

-45.00

-44.00 >5

>5

49 -46.00

>50

>50

>5050

48

>5

48.00

>5

-40.00 5.2844

44 -41.00 5.7648

45.00

: 50.0 m: 4.4 m: Than Maung

Boring Completed : 30 . 3 . 2013 Total Depth (m)Logged by : Phyo Ko Ko Oo Water Level (m)Checked by : Wai Phyo Aung Driller

Sheet of 5: 1

Type of Hammer : Automatic:The Improvement Of Water Supply Boring Started : 27 . 3 . 2013 Hole No

5.1643

Soil DescriptionSPT

(N-Value)

Field Bearing capacity calculated

from SPT value (Ton/ft2)

4.683941 -38.00

42.00

Gray, Hard, Clayey SILT with a little amount of sand

( 40.0 m ~ 50.0 m )

46 -43.00 >50

45

H-89

Page 90: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

Fr To ( % ) ( % ) ( % ) ( % ) ( % ) ( % ) ( % ) ( % ) g/cm3 g/cm3 kg/cm2 ( ° ) kg/cm2 kg/cm2

1 2.00 2.45 2.60 0.00 44.10 NL NP NI 28.92 1.85 1.46 0.16 24.00 0.10

2 4.00 4.45 2.60 0.00 75.10 NL NP NI 24.33 1.91 1.54 0.14 25.00 0.15

3 8.00 8.45 2.64 0.00 91.50 NL NP NI 23.36 1.81 1.47 0.40 11.00 0.36

4 12.00 12.45 2.63 0.00 91.30 NL NP NI 23.82 1.84 1.51 0.45 19.00 0.50

5 16.00 17.00 2.61 0.00 44.80 41.33 23.74 17.59 35.62 1.86 1.38 0.18 3.00 0.60 1.033 2.00 0.40

6 19.00 19.45 2.58 0.00 46.60 38.86 21.32 17.54 34.77 1.79 1.33 0.30 17.00 0.35

Graycolour ,medium dense,SiltySAND with trace amount of Clay 8.50

8.70

Gravel Sand

SOIL TEST RESULTSProject : The Improvement of Water Supply Project

Location : South Dagon , Yangon Borehole No

Date : 26-4-2013

Gray to Brown colour,medium dense,Silty SAND with some Clay.

Clay

55.90

Gray colour, hard, Sandy CLAY with Silt . 53.40

Silt

Gray colour,medium dense, Silty SAND with some Clay. 24.90

Gray colour,Sandy CLAY with Silt . 55.20

Gray colour, dense,Silty SAND with trace amount of Clay

Consolidation Test

Initi

al V

oid

R

atio

( e

)

Pre-

cons

olid

atio

n Pr

essu

re (

Pc)

Com

pres

sion

In

dex

( Cc

)

TriaxialCompression

Test

(L.L) (P.L) ( P. I )Description of Soil

: BH-1

Moi

stur

e co

nten

t

Bul

k de

nsity

Dry

den

sity

U C

S T

est

CSr; N

o,

Dep

th (

m )

Spec

ific

grav

ity Grain Size Analysis Atterberg Limit

H-90

Page 91: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

Fr To ( % ) ( % ) ( % ) ( % ) ( % ) ( % ) ( % ) ( % ) g/cm3 g/cm3 kg/cm2 ( ° ) kg/cm2 kg/cm2

7 21.00 21.45 2.58 0.00 84.60 NL NP NI 19.40 1.90 1.59 0.25 13.00 0.32

8 24.00 24.45 2.59 0.00 10.90 33.48 20.79 12.69 34.67 1.77 1.31 0.37 10.00 0.40

9 28.00 28.45 2.59 0.00 16.91 31.55 21.37 10.18 32.16 1.72 1.30 0.55 14.00 0.33

10 32.00 32.45 2.58 0.00 0.70 36.10 13.20 22.90 32.10 1.83 1.39 0.35 9.00 0.50

11 37.00 37.45 2.58 0.00 1.50 36.46 25.00 11.46 32.23 1.75 1.32 0.32 10.00 0.46

12 44.00 44.45 2.58 0.00 1.70 33.77 21.70 12.07 34.17 1.89 1.41 0.36 14.00 0.55

Borehole No

SOIL TEST RESULTSProject : The Improvement 0f Water Supply Project : 26-4-2013Date

Location : South Dagon , Yangon : BH-1

Consolidation TestTriaxialCompression

Test

U C

S T

est

Atterberg Limit

Moi

stur

e co

nten

t

Bul

k de

nsity

Dry

den

sity

98.30

Gray colour,medium dense,SiltySAND with alittle amount of Clay. 15.40

Gray colour, very firm, Silty CLAY with some Sand. 89.10

Gray colour, hard, Silty CLAY with some Sand. 83.10

Sr; N

o,

Dep

th (

m )

Description of Soil

Spec

ific

grav

ity Grain Size Analysis

Gray colour, very firm, ClayeySILT with alittle amount of Sand. 99.30

Gray colour, very firm, ClayeySILT with alittle amount of Sand. 98.50

Gravel Sand Silt Clay (L.L) (P.L) ( P. I )

Initi

al V

oid

R

atio

( e

)

Pre-

cons

olid

atio

n Pr

essu

re (

Pc )

Com

pres

sion

In

dex

( Cc

)

C

Gray colour, hard, Clayey SILT with trace amount of Sand.

H-91

Page 92: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

: The Improvement of Water Supply Project

Soil Test Results For Triaxial Permeability Test

1.7x10-6

To 17.00

TP

SPECIMEN DEPTH ( M )

: South Dagon ,Yangon

From 16.00

Date:29.4.2013

Premeability Permeability at 20 c m/sTriaxial Cofficient of

SAMPLE TYPE :

BORING NO : BH-1

: UD

Project

Location

H-92

Page 93: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

The Project for the Improvement of Water Supply, Sewerage and Drainage System in Yangon City Vol IV Water Supply System Feasibility Study, Appendix

I-1

I REVIEW FOR PRELIMINARY DESIGN OF LAGUNBYIN WTP

A series of discussions on design of Lagunbyin water treatment plant have been made with YCDC in

the design review stage and revisions were made on the design by JICA Study Team.

1. Intake Canal

Intake canal was shifted from irrigation canal to existing natural creek by determination in discussion

with YCDC and MOAI in October, 2013.

2. Designed Ground Level

Designed water levels are calculated by hydraulic calculation in the review. In order to apply existing

foundation pillars as much as possible, Bottoms of sedimentation basins and filters are set as nearly

existing ground level (+2.926m =+9.6').

3. Existing Foundation Pillars

Arrangement and size of the facilities which can apply existing foundation pillars under construction

by YCDC are adopted. The location of sedimentation basins, the size of filters, and the size of clear

water reservoir are changed by the review.

4. Pre-sedimentation Pond

Precipitation tests proved that turbidity decreases to 65% by settling time of approximately 12 hours.

In order to take raw water of low turbidity, pre-sedimentation pond with retention time of 12 hours

above is designed by the review. And since much sand settles on the bottom of the pond, the pond has

1m storage space toward the bottom from LWL.

5. Intake Pump

The Number of intake pump proposed by F/S was 4 units (3 duty + 2 stand-by). On the other hand,

YCDC have proposed 6 units (4 duty + 2 stand-by).

6. Dividing Well

On the YCDC design, raw water of different quality is directly led to each sedimentation basin from

each intake pump. Since PAC dosing rate differs by each basin on such a design, control of aluminum

injection is complicated.

In order to supply raw water of the same quality to sedimentation basins, dividing well is generally

installed in Japan. Dividing well/ tower is designed by cylindrical shape in order to distribute raw

water equally to 4 sedimentation basins, and weirs are installed in the tower.

7. Iron Removal

According to water quality tests, iron of 0.3 mg/L (beyond the standard value) has been detected. In

order to secure contact time of raw water with air, weirs in dividing well are set up highly.

Page 94: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

The Project for the Improvement of Water Supply, Sewerage and Drainage System in Yangon City Vol IV Water Supply System Feasibility Study, Appendix

I-2

8. PAC Dosing Facility

PAC currently used by Nyaunghnapin WTP is adopted from the result of jar tests by YCDC.

According to YCDC, coagulating effect of PAC is better than aluminum sulfate. Hydraulic jump

method currently used by Nyaunghnapin WTP is adopted as coagulant mixing.

9. Flocculation Basin

Horizontal and vertical zigzag flow method as Nyaunghnapin WTP with same mixing for flocculation

is adopted. The widths of channels are set up by capacity calculation on the review in order that raw

water and PAC might mix completely. And inlet flow to flocculation basins and sedimentation basins

is changed into underflow in order that floc might not break.

10. Sludge Discharge Method of Sedimentation Basin

As sludge discharge method on the design of F/S, the bottoms of sedimentation basins have a slope,

and have several hoppers. Since this design had insufficient sludge discharge, YCDC suggested that

the bottoms should have more hoppers.

11. Tube Settler in Sedimentation Basin

The installation area of tube settler on the YCDC design is a few one. Based on the design standard of

Japan, installation area is reconsidered on the review.

12. The number of Filter

The number of filters on the YCDC design is 24 basins x 2 trains. According to train of sedimentation

basin, the number is changed into 6 basins x 4 trains on the review.

13. Flow Rate of Filter

On the YCDC design, flow rate is 240 m/day of the upper limit in two-layer filtration. In order to take

stabilized raw water quality, flow rate is limited to maximum 150 m/day on the review.

14. Backwashing Method of Filter

Nyaunghnapin WTP has backwashing with surface washing for filters. YCDC suggested that the

maintenance of above method takes time and effort, and many mud balls have been produced on the

surface of filters. YCDC proposed that backwashing adopted air washing for the new WTP. And

YCDC proposed that control valves are installed within backwashing pumps and air blowers.

15. Under Drain System of Filter

YCDC proposed that strainer type which can be manufactured in Myanmar is applied to under drain

system. This method is already adopted in Phase2 of Nyaunghnapin WTP. The processing effect is not

so good although traditional Tee Pee type (Made in Red Indian) is adopted in Phase1.

Page 95: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

The Project for the Improvement of Water Supply, Sewerage and Drainage System in Yangon City Vol IV Water Supply System Feasibility Study, Appendix

I-3

16. Inlet and Outlet Valves of Filter

In order to control flow by a motor, handling spaces are provided for periphery of weirs and valves on

the review.

17. Clear Water Reservoir

Capacity of clear water reservoir is little on YCDC design. The capacity of 1 hour above is designed

on the review, and the number of reservoirs is set to 2 trains.

18. Chlorination Facility

About chlorination facility, YCDC proposed that Electrolyzer (On-site generation of liquid

hypochlorite) installed in existing Yegu pumping station is suitable from a viewpoint of finances and

procurement. YCDC can procure easily the salt which is material of hypochlorite generated by

Electrolyzer. According to YCDC, the viewpoint of cost to procurement is hard for imported products,

such as Gas cylinder, Liquid chlorine and Powder.

Since a rough maintenance for Electrolyzer might cause explosion, the Study Team advised keeping

up sufficient maintenance.

19. Sludge Treatment

YCDC proposed that Wash Water Drainage Basin, Sludge Basin, and Lagoon should be constructed at

the same time as water treatment facilities. In addition, Sludge Thickener will be added according to

water quality conditions of raw water.

20. Pipeline

All connection of each structure are pipelines. As for The pipe linked directly with structure,

settlement should be taken into consideration. Therefore, installation of flexible joint is recommended.

If they cannot be supplied, several collar joints should be installed.

21. Measurement Equipment

As for measurement equipment proposed by F/S, arrangement was changed in this review.

22. SCADA

YCDC and the Study Team identified that SCADA associated equipment (flow meter, Water quality

measurement equipment) is included in Associated equipment of Electrical of yen loan.

23. Structure

Expansion joint is set in each structure every 20-30 m. In the clear water reservoir which needs water

tightness, crack-inducing joint is taken into consideration as an alternative.

24. Revised Drawings by the Review

Revised drawings by review are given in the following pages.

Page 96: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

Water From Lagunpyin Dam

Sluice Gate

No.

2 M

ain

Roa

d

No. 7 Road

To Y

ango

n

Lagunbyin Water Treatment Plant General Layout Plan

Lagunbyin WTP

40MGD=181,800m3/day

Expansion canal will be carried out by MoAI.

Retention pond

Gate

+5.06+4.50

+5.06

+5.06

+5.06

+5.06

+5.06 +5.06

+5.06

+1.377

+5.06+5.06

+5.06

+5.06

+5.06

+5.06

+5.06

+5.06+5.06

+5.06

+5.06

+5.06

+4.50

+4.50

+2.134 +2.134 +2.134 +2.134

-0.04

-0.04

-0.04

-0.04

-0.04

Village

Lagoon Old Fish Pond

Project for the Improvement of Water Supply, Sewerage and Drainage System in Yangon Cityproject

DrawingTitle

ScaleDate Drawing No.

W - 1

General Layout PlanLagunbyin Water Treatment Plant

Rev12 Oct. 2013 A3; S=1:2,500

Intake Gate

Pumping HouseIntake

Dividing Well

Sedimentation Basin

Rapid Sand Filter

Wash WaterDrainage Basin

Treated WaterReservoir

Pumping HouseTransmission

Sludge Thickener

Sludge Basin

AdministrationBuilding

Power House

PAC DosingFacilities

Chlorine Dosing Facilities Pre Sedimentation Pond(118,700m3~ Effective Depth3.00m)

Rapid Sand Filter

Gabion

Existing Canal

I-4

Page 97: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

No.

2 M

ain

Roa

dTo

Yan

gon

Retention pond

Gate

+5.06+4.50

+5.06

+5.06

+5.06

+5.06

+5.06

+1.377

+5.06+5.06

+5.06

+5.06

+5.06

+5.06

+5.06+5.06

+5.06

+5.06

+5.06

+4.50

+4.50

+2.134 +2.134

-0.04

-0.04

Village

Lagoon

OFFIC

EM

EET

ING

ROOM

G.M

ROO

MLA

BORA

TRY

ELE

CTRIC RO

OM

LOCK

ER RO

OMTO

ILETST

ORE

ROO

M

Old Fish Pond

Project for the Improvement of Water Supply, Sewerage and Drainage System in Yangon Cityproject

DrawingTitle

ScaleDate Drawing No.

W - 2

General Layout PlanLagunbyin Water Treatment Plant

Rev12 Oct. 2013 A3; S=1:1,500

40MGD=181,800m3/day

Power Station

AdministrationBuilding

Sluge Thickener Sluge Basin

Treated Water Reservoir

TransmissionPumping House

IntakePumping House

Rapid Sand Filter

Dividing Well

PAC DosingFacilities

Chlorine Dosing Facilities

Lagoon (Existing Old Fish Pond)

Intake Gate

Lagunbyin Water Treatment Plant General Layout Plan

Wash Water Drainage

Rapid Sand Filter

Sedimentation Basin

Sedimentation Basin

Sedimentation Basin

Sedimentation Basin

I-5

Page 98: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

Lagunbyin WTP Water Level Chart40MGD=181,800m3/day

[ Clear Water Treatment System ]

▽WL+3.962

▽+2.134

▽+5.06

▽-0.04

▽HWL+3.96

▽HWL+4.56

▽+0.56

▽+5.06

P.GL+5.06 P.GL+5.06 P.GL+5.06

P.GL+5.06 P.GL+5.06 P.GL+5.06

φ1200 φ800

φ800

φ1200

φ1200

▽WL+3.962

▽+2.134

Back Wash Drainage PipeBack Wash Drainage Pipe

supernatant

Wash Water Return Pipe

Sludge Removal Pipe

Sludge Removal Pipe

P.GL+5.06

WL+3.962

Sedimentation Basin Rapid FilterDividing Well

6 Units (2 Stand-by)4 Units x 2 Compartments 6 Units x 4 Compartments1 UnitsTube Settler System

4 Units x 2 Compartments

Canal Recieving WellMixing TankFlocculation Basin

Horizontal Baffled

Post-ChlorineMixing Basin

Clear WaterReservoir

2 Compartments

Intake Gate andPumping

Pre-SedimentationPond

1 Units

HWL+3.960

HWL+15.700

WL+13.200

(LWL+0.960)

WL+12.700

WL+11.444WL+11.297

WL+11.154WL+11.061WL+11.969WL+10.905

WL+10.900

WL+9.900 WL+7.200HWL+6.250

LWL+0.750

Sludge Basin Thickener Wash Water Drainage Basin

4 Units 4 Units2 Units

Lagoon

1 Unit

Canal Crossing

Pipe Bridge

[ Wastewater Treatment System ]WL+5.060 WL+5.060 WL+5.060 WL+3.962 HHWL+4.560

WL+10.300

( +16.6' )

E.GL+2.926( +9.6' )

E.P.L -0.610

( -2' )

E.P.L +3.658( +12' )

Water TransmissionPumping Station

5 Units (1 Stand-by)

P.GL+5.06( +16.6' )

E.GL+2.926( +9.6' )

2 Compartments

WL+11.450

WL+7.400

WL+9.700

WL+9.500

+5.95

Project for the Improvement of Water Supply, Sewerage and Drainage System in Yangon Cityproject

DrawingTitle

ScaleDate Drawing No.

W - 3

Water Level ChartLagunbyin Water Treatment Plant

Rev03 Oct. 2013 A3; S=NONE

I-6

Page 99: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

Lagunbyin WTP Water Flow Sheet40MGD=181,800m3/day

Pre-sedimentation

Water IntakePumping Well

Pond

WellDividing

Sluice Valve

Symbol

M Motor Operated Sluice Valve

Butterfly Valve

Motor Operated Butterfly Valve

Check Valve

FlFlow Indicator

Electromagnetic Flowmeter

Item Name

Pressure Reducing Valve

Tu

pH

Co

Cl 2 Residual Chlorine Meter

Color Meter

pH Meter

Turbidity Meter

Pressure Gauge

Electric Pole

Ultrasonic Level Indicator

M

[ Legend ]

Ultrasonic Flowmeter

Sedimentation BasinRapid Sand Filter

Water TransmissionPumping Station

Sludge BasinBackwash Water Thickener

Sludge Lagoon

Clear Water Reservoir

Overflow

Drainage Basin

Backwash Water

Drain

Post-chlorine Mixing Basin

Drain

DrainSupernatant

Tu pH

TupH Tu pH

Tu pH Cl 2 Co

Cl 2

Intermediate-Cl

Intermediate-Cl

Intermediate-Cl

Intermediate-Cl

Post-Cl

Post-Cl

PAC Pre-Cl

Irrig

atio

n C

anal

PumpsBackwash

Blowers

To Service reservoirs

Project for the Improvement of Water Supply, Sewerage and Drainage System in Yangon Cityproject

DrawingTitle

ScaleDate Drawing No.

W - 4

Water Flow SheetLagunbyin Water Treatment Plant

Rev02 Oct. 2013 A3; S=NONE

I-7

Page 100: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

28,000

18,000

6,500 6,500 5,000

7,000

7,000

7,000

7,000

4,000

600

400

4,3002,7007,000

600

2,000

400

2,000

600

600

P.GL+5.06

1:1.5

▽HWL+3.96

▽-0.04

▽-1.74

600 4,800 700 4,300 600 6,200 6,500 4,700 600

18,6005,0009,6005,400

38,600

700

6,750

200

7,650

600 9,000

300

4,950

700

1,700

Pre-Sedimentation Pond Intake Gate Water Intake Pumping Station

Pre-Sedimentation Pond Intake Gate Water Intake Pumping Station

PLAN

SECTION A - A

Intake Gate and Pumping Station

decided in detailed design.Note : The values are indicative, and detailed values shall be

AA

Handrail H=1.10

Oil fence L=17m

Q= 2.31 m3/secQ= 1.16 m3/sec

Q= 1.16 m3/sec

Landing Steps

SP

dia

. 120

0

SP

dia

. 900

SP dia. 1200

4,000

Pumping Station's roof could be changed.

Wall Opening, dia.1400mm

2,000750▽HWL+3.96

E.GL+2.926

Gate 1400 x 1400

▽+5.21 ▽+5.21

Foundation pillars

SP dia. 600

Inake Pump

ValveValve

Motorized Butterfly valve

Slant Surface Concrete

Electrical crane

Caulking

Expansion Joint

▽-0.54

Manual Coarse Screen, Opening 100mm

Handrail H=1.10

2,000750

Pump Sump 1.0m x 1.0m

TOP

BO

TTO

M

750

750

P.GL+5.06

P.GL+5.06

28,500

11,900

6,500 5,000

7,000

7,000

7,000

7,000

= 2.

31 m

3/se

cQ

= 20

0,00

0 m

3/da

y

To D

ivid

ing

Wel

l

▽+3.46

5,500

P.GL+5.06

Electric Room

Electric Room

TOP PLAN

Water Intake Pumping Station

+5.21

P.GL+5.06

Windows, Doors, Ventilations, Lighting, etc. shall be decided in detail design.

A

Air valve

A

A

Manual Coarse Screen, Opening 100mm

2,800

5,0009,6005,400 18,600

3,700

Maintenance space

(Grand floor)

(Basement floor)

(Top floor)

11,500

28,600

6,600

Crack-inducing joint t=20mm

+5.21

▽-1.74

+5.21

▽+3.46

▽-0.54

▽-0.54

▽-1.74

P.GL+5.06

Protective concrete layer

Note: Be careful of shearing stress

Expansion Joint

5,500

CL

Two or more collar joints should be installed.

SP or PE dia. 1200

Intake Pump; 4 duty + 2 stand-by

2

3

2

3

6

9

11

20

12

8

9

8

10

12

13

17

40

33

33

32

31

31

25

20

SILT&CLAY1.18M

-4.32M

Silty CLAY

-8.82M

SILT&CLAY

Silty CLAY-10.82M

-11.82M SILT&CLAY

SILT&CLAY

Project for the Improvement of Water Supply, Sewerage and Drainage System in Yangon Cityproject

DrawingTitle

ScaleDate Drawing No.

W - 5

Intake Gate & Pumping Station Plan and SectionLagunbyin Water Treatment Plant

Rev02 Oct. 2013 A3; S=1:400

I-8

Page 101: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

WL+15.70

WL+13.20

▽+10.20

P.GL+5.06 P.GL+5.06

▽+3.60

6,500

500

6,100

700

100

200

500

2,000

500 9,000 500

2,000

500

15,000

13,800

SECTION A - A

11,640

2,460

PLAN

Dividing Well

500500

9,000500500

11,000

2,000

2,500

R4,500

R7,000

1,200

1,200

15,000

8,300

decided in detailed design.Note : The values are indicative, and detailed values shall be

= 0.55 m3/sec

Q= 47,700 m3/day

R4,500

2,977

R7,000

500

15,000

9,000

R4,500

10,014

9,000

Top Middle Bottom

Handrail H=1.10

300

E.GL+2.926

561

1,500

Overflow

From Intake Pumping Station

300

1,200 1,200

950

3,350

Overflow

9,000

Handrail H=1.10

To Sedimentation Basin

SP or PE dia. 800

To Sedimentation Basin

SP or PE dia. 800

To Sed

imen

tation

Bas

in

SP or PE di

a. 80

0

To Sedim

entat

ion B

asin

SP or P

E dia.

800

P.GL+5.06

2,000

From

Inta

ke P

umpi

ng S

tatio

n

Overflow

SP or PE dia. 600

1,460

To Sedimentation BasinSP or PE dia. 800

100

220

PAC, Chlorine

Injecting point

▽+10.20

▽+10.20

▽+10.20

▽+3.60

▽+5.36

▽+4.50

▽+2.96

▽+3.72

Overflow weir

500 2,000 5003,000 500500

500

Foundation pillars

5,280 5,600

▽+15.48

▽+16.70

▽+16.70

Door

Windows, Doors, Ventilations, Lighting, etc. shall be decided in detailed design.

1,200 1,2001,200 1,200

AA

Slant Surface Concrete

Two or more collar joints should be installed.

SP or PE dia. 1200

Overflow

S

P or P

E dia. 600

SP or PE dia. 1200

Project for the Improvement of Water Supply, Sewerage and Drainage System in Yangon Cityproject

DrawingTitle

ScaleDate Drawing No.

W - 6

Dividing Well Plan & SectionLagunbyin Water Treatment Plant

Rev02 Oct. 2013 A3; S=1:200

I-9

Page 102: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

Sedimentation Basin Plan

26,850

500

4,950

400

4,950

1,125

250

3,900

4001,200 400

5,650

500

400

4,450

400

5,250

2,500400

500 3,000

400

1,200250

2,950250

3,550250

2,000

250

6,900 250 5,102 250 24,0985001,500

250

27,100 1,750

500

12,700

450

12,700

500

250

7,300

CB

7,550

decided in detailed design.Note : The values are indicative, and detailed values shall be

250Wall Opening, 200 x 200mm

From Dividing WellSP or PE dia. 800

Valve

Tube Settler

MID

DLE

BO

TTO

M

24,850

Trough 300x300mm

Main Trough 600x600mm

Wall Opening, 1000 x 1000mm

To FiltersSP or PE dia. 800

500

2,000

TOP

Expansion Joint

2,225

500

500

▽+3.60

Pipe gallery

Pipe gallery

▽+3.60

400

▽+5.80

▽+4.40

dia. 150dia. 150

Dra

inin

g pi

pe d

ia. 2

50

▽+4.50 ▽+3.16

1,600

11,575

1,60023,0001,6001,4001,6001,6001,850 1,4001,4001,4001,475 2,100 2,900 5,750 3,980

Expansion Joint

Expansion Joint

800

13,975

11,575

1,600

800

Windows, Doors, Ventilations, Lighting, etc. shall be decided in detailed design.

3,200

2,000

2,000

Handrail H=1.10

▽+3.60

To S

ludg

e Ba

sins

CL

CL

Project for the Improvement of Water Supply, Sewerage and Drainage System in Yangon Cityproject

DrawingTitle

ScaleDate Drawing No.

W - 7

Sedimentation Basin PlanLagunbyin Water Treatment Plant

Rev04 Oct. 2013 A3; S=1:250

I-10

Page 103: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

P.GL+5.06

WL+12.70

▽+6.06

WL+10.90

▽+3.60

Sedimentation Basin Cross Section

SECTION A - A

Sedimentation BasinFlocculation BasinReceiving Well

SECTION B - B SECTION C - C

Flocculation Basin Receiving Well Sedimentation Basin

6,600

600

2,500

700

100

200

10,7008,240

2,460

5,200

600

2,500

700

6,840

2,460

9,300

5,300

5009,300

5,300

500

9,300

P.GL+5.06 P.GL+5.06

P.GL+5.06 P.GL+5.06

500500

12,700450

12,700500

500

27,850

500500

4,9504002,225

22512,700500

500

27,850

5005,650

400

1,200

400

3,900

250

1,125

1,300

1,200

1,000

1,000

1,4001,400 900@11=9,900

WL+11.45

WL+12.70

WL+10.90

15,750 2,000

500

6,650 250 5,100250

24,100500

1,500

2,900 27,600 1,750250

8,300

700

100

200

9,000

decided in detailed design.Note : The values are indicative, and detailed values shall be

2,500

700

100

200

3,000

2,500

PVC Dia.150mm x 20row x 5rank

250

WL+10.30

From Dividing WellSP or PE dia. 800

E.GL+2.926

Slant Surface Concrete

E.GL+2.926

Expansion JointHandrail H=1.10

Tube Settler

Trough 300x300mm

180

E.GL+2.926E.GL+2.926

▽+13.30

▽+3.60

Main Trough 600x600mm

WL+10.90

WL+11.50

1,600

300

Windows, Doors, Ventilations, Lighting, etc. shall be decided in detailed design.

Baffle WallNote: Total area of flowuniforming wall holes

shall be 6% of the flow's cross-section

Baffle WallPre-cast concrete or Wooden board

▽+6.70

▽+6.70

25,349500

Filling sand or concrete

▽+11.90

E.GL+2.926 E.GL+2.926

▽+13.30

500▽+6.70

WL+11.45▽+11.90

1,600 1,600 1,400 1,400 1,400 1,400

1,600

1,600

dia. 150▽+5.80

▽+3.60 ▽+3.60

▽+4.40

Valve

WL+6.70

Wall Opening, 200 x 200mm

WL+10.90

▽+3.60

WL+6.70

P.GL+5.06

Foundation pillars

Slant Surface Concrete

1,600 1,6001,600 1,600

Tube Settler

Trough 300x300mm

Main Trough 600x600mm

60°

4004,950

▽+11.90

▽+11.90

▽+6.70

▽+5.80

▽+4.50 ▽+4.765

2,000 2,000

WL+10.90

300

Support

To FiltersSP or PE dia. 800

Foundation pillars

CLCL

▽+3.60 295

Support

Foundation pillars

Filling sand or concrete

11

11

12

4

5

5

-0.18M

SILT&CLAY

-6.82M

SiltyCLAY

5

6

3

4

4

5

Silty CLAY

Project for the Improvement of Water Supply, Sewerage and Drainage System in Yangon Cityproject

DrawingTitle

ScaleDate Drawing No.

W - 8

Sedimentation Basin Cross SectionLagunbyin Water Treatment Plant

Rev04 Oct. 2013 A3; S=1:250

I-11

Page 104: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

Rapid Sand Filter Plan

A

A

B

B

5,300 1,200 7,250 500 7,250 500 7,250 500 7,250 500 7,250 500 7,250

1,200

5,500250

1,500

48,200

4,550

250

4,80020,500

2,800

10,250

250

6,250

4,000

250

10,250

500

1,800

500

1,500

500

CL

5,250250

Expansion Joint500

Expansion Joint

From Sedimentation BasinSP or PE dia. 800

▽+3.16

MID

DLE

BO

TTO

MTO

P

Sample of Filter basin

Expansion Joint

6,000

Backwash Pump

Blower

TROUGH 500 x 500A

14,000

500

20,500

12,000

CL

500

5,500

▽+4.30 ▽+4.30

▽+5.95

▽+7.05

▽+7.05

▽+7.80

▽+5.95 ▽+5.95

▽+8.10

▽+5.95

▽+5.95

Anthracite t=200mm

Silica SAND t=600mm

Gravel t=300mm

500

5,000

To Clear Water ReservoirSP or PE dia. 1200

Expansion Joint

Backwash DrainSP or PE Dia. 500mm

decided in detailed design.Note : The values are indicative, and detailed values shall be

Windows, Doors, Ventilations, Lighting, etc. shall be decided in detailed design.

6,500

250

2,000

▽+4.30

GL+5.06

Backwash Water Gallery

5,500 250

1,500

5,250

▽+8.10▽+8.10

▽+8.40 ▽+8.40

▽+10.50

▽+3.16

+7.20

500 5,000 500

▽+8.40

▽+8.40

▽+8.40

▽+10.50

▽+8.40

▽+5.30

5,500

250

5,500

▽+10.50

▽+8.40

▽+10.50

▽+10.50

Backwash Water Gallery

Drain Valve

▽+4.30

▽+5.20

Backwashing Orifice

Air-washing Orifice

▽+2.90

▽+8.40

2,300

500

1,500

A

C

C

Expansion Joint

Air-washing ValveMotor-operated Valve

Outlet ValveMotor-operated Valve

Backwashing ValveMotor-operated Valve

Inlet Valve

Drain ValveMotor-operated Valve

Motor-operated Valve

39,600

Lighting

Backwashing Pipe Dia.600mm

Air-washing Pipe Dia.300mm

Clean-water Pipe Dia.800mm

V=300m2V=120-150m3/day

A=66m2

Designed V=0.80m/min

Designed V=0.75m/min

Project for the Improvement of Water Supply, Sewerage and Drainage System in Yangon Cityproject

DrawingTitle

ScaleDate Drawing No.

W - 9

Rapid Sand Filter PlanLagunbyin Water Treatment Plant

Rev02 Oct. 2013 A3; S=1:300

I-12

Page 105: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

23,750

WL+7.20

WL+9.50 WL+9.50WL+9.90

WL+9.70WL+9.50

GL+5.06

GL+5.06

GL+5.06

5,500

700

100

200

500 4,8001,200

5,5002501,500

5005,500

2501,500

5005,500

2501,500

50022,750

1,200

6,200

700

100

200

2,450

1,400 250

700

2,100

300

3,800

700

300

5001,800

500

4,850250

1,500

250

1,750

250

1,650

2501,500

250

10,250

500

1,800500

47,500

6,500

19,800 19,800

7,200

2,100

300

2,400

250

1,150

700

Rapid Sand Filter Cross Section

SECTION A - A

SECTION B - B

WL+9.90

From Sedimentation BasinSP or PE dia. 800To Clear Water Reservoir

SP or PE dia. 1200Existing Foundation pillars

Ex.PL+3.658

Inlet Pipe Dia. 500mm

300

▽+10.50

▽+8.40

Existing Foundation pillars

Ex.PL+3.658

CL

GL+5.06

Valve

▽+3.16

300

4,550250

Anthracite t=200mmSilica SAND t=600mm

Gravel t=300mm

▽+7.05

▽+7.80

WL+7.40

Slant Surface Concrete

▽+4.30

300

500

Expansion Joint

12,00012,000 9,000 500500

▽+10.50 ▽+10.50

▽+10.50

23,750

6,000

1,500

500 500

4,5004,500

Backwashing Orifice

Air-washing Orifice

Strainer @150mm

Filling sand or concrete

▽+5.95▽+5.95

▽+4.30

▽+8.40

▽+5.30

decided in detailed design.Note : The values are indicative, and detailed values shall be

Windows, Doors, Ventilations, Lighting, etc. shall be decided in detailed design.

▽+5.95

▽+8.10

WL+9.50 WL+9.50

Sample of strainer

▽+4.30

▽+8.40

5,500

▽+4.80▽+5.20

▽+4.30

▽+7.05

▽+7.80

▽+5.95

▽+5.95

▽+4.30

▽+2.90

▽+4.30

Expansion Joint

Backwashing Pipe Dia.600mm

Air-washing Pipe Dia.300mmClean-water Pipe Dia.800mm

Backwashing Orifice

Air-washing Orifice

Drainage

▽+8.90

▽+4.80▽+5.20

▽+8.90

14,000

500

20,500

500500

5,000

300

5,200

WL+7.20 WL+7.40

▽+2.90

SECTION C - C

GL+5.06

5,500

700

100

200

6,500

CL

▽+8.90

To Clear Water ReservoirSP or PE dia. 1200

Backwash Pump

Backwash PumpBlower

Inlet ValveDrain ValveMotor-operated Valve Motor-operated Valve

Air-washing ValveMotor-operated Valve

Outlet ValveMotor-operated Valve

Handrail H=1.10

Air-washing ValveMotor-operated Valve

Outlet ValveMotor-operated Valve

Backwashing ValveMotor-operated Valve

GL+5.06

2,100

Silica sand Thickness = 0.6m Uniform Coefficient = Less than1.4 Effective Size = 0.6mmAnthracite Thickness = 0.2m Uniform Coefficien = Less than1.6 Effective Siz = 1.2mm

Designed Filteration Velocity = 120-150m3/dayDesigned Filteration Area = 66m2 x 6basins x 4systems

8

10

11

8

2

3

4

21

18

16

14

11

8

9

11

11

Silty CLAY Project for the Improvement of Water Supply, Sewerage and Drainage System in Yangon Cityproject

DrawingTitle

ScaleDate Drawing No.

W - 10

Rapid Sand Filter Cross SectionLagunbyin Water Treatment Plant

Rev02 Oct. 2013 A3; S=1:300

I-13

Page 106: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

38,260

Clear Water Reservoir Plan

500

4,570

4,570

4,270

3,020

600

23,100

23,

100

46,200

4,1005,000

6,0006,0006,000

18,000

7,500

7,500

7,500

7,500

30,000

500

4,5704,570

37,060

8,540

600

600

2,100

2,100

A A

Crack-inducing Joint

9,830

16,845 21,415

decided in detailed design.Note : The values are indicative, and detailed values shall be

Windows, Doors, Ventilations, Lighting, etc. shall be decided in detailed design.

4,5704,5704,5704,5704,570

500

4,570

4,570

4,57

04,570

4,570

4,570

4,570

4,570

4,570

CL

BO

TTO

MTO

P

600

3,020600

3,770

3,720

1,100

1,100

500

500

9,7404,

570

▽-2.90

▽-2.90

▽+7.25

▽+0.15

▽-2.90 ▽+0.15

▽+5.36

GL+5.06

▽+7.25

600600

To Z

on7

and

8 R

eser

voir

SP

or P

E d

ia. 1

200

Expansion Joint

Suction PipeSP Dia. 1200mm

Inlet Valve

Yen Loan YCDC

Expansion Joint

From FiltersSP or PE dia. 1200

Dia. 1200mm

Outlet ValveDia. 1200mm

Q=

2.10

m3/

sec

Pump Sump 1.0m x 1.0m

SP

dia

. 120

0

SP d

ia. 1

200

▽+2.9

6

Ventilator

600

V=4,800m3

Project for the Improvement of Water Supply, Sewerage and Drainage System in Yangon Cityproject

DrawingTitle

ScaleDate Drawing No.

W - 11

Lagunbyin Water Treatment Plant

Rev03 Oct. 2013 A3; S=1:400

I-14

Page 107: H RESULT OF SOIL INVESTIGATION - JICAopen_jicareport.jica.go.jp/pdf/1000017297_03.pdf · H RESULT OF SOIL INVESTIGATION ... It is compiled with the lab test result on the disturbed

GL+5.06GL+5.06GL+5.06

Clear Water Reservoir Cross Section

SECTION A - A

SECTION B - B

600 17,400600

4,700 4,700800

3,720800

32,340 6002,420

600600

EXP.J

500

4,570 3,020600500

300

6,800

800

7,900

1,590

300

4,910

600

3,600

800

3,760

9,060

800

8,060

200

3,050

2,250

800

18,600 9,400 37,660 3,620

37,060

500

5,600

500 HWL+6.25

LWL+0.75

GL+5.06 GL+5.06

5,500

7,900

300

6,800

800

500 500 500

4,270600

600

5,470

300

4,910

800

6,010

decided in detailed design.Note : The values are indicative, and detailed values shall be

500

uPVC Dia. 40mm

Sample of Crack-inducing Joint

Reinforcing bar

Steel Sheet t=10mm

Notch 20 x 20mm

Ex.PL-0.610

Existing Foundation pillars

Ex.PL-0.610

Existing Foundation pillars

Ex.PL-0.610

Windows, Doors, Ventilations, Lighting, etc. shall be decided in detailed design.

2,100

1,100

4,570 4,570 4,570 4,570 4,570 4,570 4,570

Crack-inducing Joint

3,620

1,500

▽+7.25

▽+0.15▽-0.65

▽-2.90▽-2.90

▽+0.15

▽+5.36

4,570 4,570

23,100

4,570 4,570 4,570 4,5704,570 4,570 4,570 4,570

500

500

2,100

1,100

23,100

EXP.J

HWL+6.25

LWL+0.75

▽+7.25

HWL+6.25

LWL+0.75

▽+7.25

Yen Loan YCDC

2,190

Outlet ValveDia. 1200mm

▽-1.65

▽+2.96

Inlet ValveDia. 1200mm1,500

1,5001,500

Wall Opening500 x 1500mm

Handrail H=1.10Electrical crane

▽+0.15

▽+5.36

Ventilator

5,500

Out

side

Ints

ide

(Cle

ar W

ater

)

Note: When cracks are detected,that should be repaired immediately.

Silty CLAY

Silty CLAY

Silty CLAY

Silty SAND

Silty CLAY

Silty SAND

7

5

5

4

4

11

13

12

16

6

10

8

8

11

13

18

28

24

21

37

47

41

50

41

38

20

16

16

17

18

21

23

25

37

>50

>50

>50

>50

>50

-8.24M

-12.24M

-5.24M

Silty CLAY

-18.24M

-24.24M

-32.24M

-38.24M8

10

11

8

2

3

4

21

18

16

14

11

8

9

11

26

11

18

37

39

37

21

18

17

16

16

17

16

19

Silty CLAY

-22.20M

Cleyey SILT

Silty CLAY

-16.20M

Project for the Improvement of Water Supply, Sewerage and Drainage System in Yangon Cityproject

DrawingTitle

ScaleDate Drawing No.

W - 12

Lagunbyin Water Treatment Plant

Rev03 Oct. 2013 A3; S=1:400

I-15