GSEP13GLSCM045_SCM Operations Assignement

download GSEP13GLSCM045_SCM Operations Assignement

of 15

Transcript of GSEP13GLSCM045_SCM Operations Assignement

  • 8/12/2019 GSEP13GLSCM045_SCM Operations Assignement

    1/15

    Annual Demand D 5600

    Cost C 45

    Setup Cost S 1350

    Holding Cost (@20%) H 9 per unit/year

    Lead Time L 2 Weeks

    Production Schedule 1 per monthStandard Deviation Sigma 15 for Weekly Demand

    Working per year 50 Weeks

    Service Level 95%

    Normsinv of 95% Z 1.6449

    Annual Demand 5600

    No of Containers Required 10

    Fixed Cost per container 800

    Total Fixed Cost per year 8000

    Per Chair Cost 47

    Total Cost of Chair 263200

    Total Final Cost 271200

    Loss if Importing from

    Korea v/s Current Setup -900

    Loss if Importing from

    Korea v/s 4 Setups/Year -7500

    Loss if Importing fromKorea v/s 4 Setups/Year -7410

    Answer 3: As per the c

    we clearly see that eve

    cheaper to make the c

    KOREAN ALTERNATIVE

    Given Data

    Answer 1: In the curre

    run is small due to whi

    Lot size for each produ

    reduce the no of produ

  • 8/12/2019 GSEP13GLSCM045_SCM Operations Assignement

    2/15

    Current Production Lot Q 466.67 EOQ

    Total Production Cost D*C 252000 Production Run Required

    Total Setup Cost S*12 16200

    Total Holding Cost H*(Q/2) 2100

    Final Cost to Company 270300

    Total Production Qty/RunProduction Cost

    Setup Cost

    Sigma * sqrt(L) 21.21320344 Holding Cost

    Weekly Demand 112 Total Cost

    Weekly Demand in 2 Weeks 224 Total Saving

    Saftey Stock 34.89261461

    Reorder Point 259

    Total Production Qty/Run

    Production CostSetup Cost

    Holding Cost

    Total Cost

    Total Saving

    lucations done for importing the chairs from korea

    n if the current lot size of production is used it is

    airs inhouse rather than importing it from korea.

    EOQ Modeli

    Total Cost Considering 4 Pr

    Total Cost Considering 5 Pr

    Current Scenario

    Reorder Point

    t production model, the lot size of each production

    h the setup cost is more. If we you use EOQ to find the

    ction run depending on the annual demand, this will

    ction runs hence decreasing the annual setup cost.

  • 8/12/2019 GSEP13GLSCM045_SCM Operations Assignement

    3/15

    Q* 1297

    Q*/D 4.31765613

    1400252000

    5400

    6300

    263700

    6600

    1120

    2520006750

    5040

    263790

    6510

    ng

    duction Run/Year

    duction Run/Year

  • 8/12/2019 GSEP13GLSCM045_SCM Operations Assignement

    4/15

    S.No Month Demand Sales staff forecast Error Abs. Error CFE

    Cummulat

    ive

    Abs.Error

    Point Wise

    MAD

    1 April 234 225 9 9 9 9 9.00

    2 May 254 240 14 14 23 23 11.50

    3 June 264 263 1 1 24 24 8.00

    4 July 227 230 -3 3 21 27 6.75

    5 August 242 239 3 3 24 30 6.00

    6 September 233 227 6 6 30 36 6.00

    7 October 254 239 15 15 45 51 7.29

    8 November 266 260 6 6 51 57 7.13

    9 December 351 320 31 31 82 88 9.78

    10 January 212 234 -22 22 60 110 11.00

    253.7 60 110

    MAD 11

    CFE 60

    TS 5.454545

    BIAS 6

    MAPE 0.043358

    alpha 0.4

    S.No Month DemandForcasting Using

    Alpha 0.4Error abs error CFE

    Cummulat

    ive

    Abs.Error

    Point Wise

    MAD

    1 April 234 245 -11 11 -11 11 11.00

    2 May 254 241 13 13 2 24 12.00

    3 June 264 246 18 18 20 42 14.00

    4 July 227 253 -26 26 -6 68 17.00

    5 August 242 243 -1 1 -7 69 13.80

    6 September 233 243 -10 10 -17 79 13.17

    7 October 254 239 15 15 -2 94 13.43

    8 November 266 245 21 21 19 115 14.38

    9 December 351 253 98 98 117 213 23.67

    10 January 212 292 -80 80 37 293 29.30

    255 17 251

    MAD 35.85714

    CFE 17

    TS 0.474104

    Exponential Smoothening

  • 8/12/2019 GSEP13GLSCM045_SCM Operations Assignement

    5/15

  • 8/12/2019 GSEP13GLSCM045_SCM Operations Assignement

    6/15

    Point

    Wise

    Tracking

    Signal

    1.00

    S.No

    2.00 1

    3.00 2

    3.11 3

    4.00 4

    5.00 5

    6.18 6

    7.16 7

    8.39 8

    5.45 9

    10

    PointWise

    Tracking

    Signal

    -1.00

    0.17

    1.43

    -0.35

    -0.51

    -1.29

    -0.15

    1.32

    4.94

    1.26

    Ignoring the 1st 3 values as the fist value is based on assumed forcast of 245, the second

    forcast, the third value will be 40% 0f 60% which is 36% based on initia

    In this method of forcasting the issue lies in the continous increasing tracking

    signal, this is because of the bias in the forcasting system.

    0.00

    1.00

    2.00

    3.00

    4.00

    5.00

    6.00

    7.00

    8.00

    9.00

    0 2 4 6 8 10 12

    Point Wise Tracking Signal Exisiting Method

    -2.00

    -1.00

    0.00

    1.00

    2.00

    3.00

    4.00

    5.006.00

    0 1 2 3 4 5 6 7 8

    Point Wise Tracking Signal For Exponential Smoothing

    Method

  • 8/12/2019 GSEP13GLSCM045_SCM Operations Assignement

    7/15

    In the exponential smoothing method the TS is found to be in between the limits of +/-

    1.5 but then the MAD is 35.85, which shows that the Abs error variation is still very high.

    And this causes a lag between demand and forcast.

    COMPARISION BETWEEN FORCASTING METHOD

    Demand Sales staff forecast Forcasting Using

    Alpha 0.4

    Forcast after

    Bias Removal

  • 8/12/2019 GSEP13GLSCM045_SCM Operations Assignement

    8/15

    Month demand sales staff forecastForcast afterBias Removal error abs. Error CFE

    April 234 225 231 3 3 3

    May 254 240 246 8 8 11

    June 264 263 269 -5 5 6

    July 227 230 236 -9 9 -3

    August 242 239 245 -3 3 -6

    September 233 227 233 0 0 -6

    October 254 239 245 9 9 3

    November 266 260 266 0 0 3

    December 351 320 326 25 25 28

    January 212 234 240 -28 28 0

    253.7 0 90

    MAD 9

    CFE 0

    TS 0

    BIAS 0

    MAPE 0.035475

    alue will be 60% based on our assumed first

    l assumed value of forcast

    Alternative Method

    In this Bias removal method we have taken out the bias

    method. By this we have made a model which has a Tra

    biasness.

    -2.00

    -1.00

    0.00

    1.00

    2.00

    3.00

    4.00

    5.00

    0 2 4 6

    Point Wise Tracking Signal Bias Re

  • 8/12/2019 GSEP13GLSCM045_SCM Operations Assignement

    9/15

    This comparision graph between the demand and the different forcasted values by usin

    method, shows clearly that Bias removal method is the best method which can be used

    forcasting because it follows the trend of the demand and there is no biasness in ther s

    which is there in sales force model.

    Exponetial smoothing shows a lage in forcasting te spike in demand.

  • 8/12/2019 GSEP13GLSCM045_SCM Operations Assignement

    10/15

    Cummulat

    ive

    Abs.Error

    Point

    Wise

    MAD

    Point

    Wise

    TrackingSignal

    3 3.00 1.00

    11 5.50 2.00

    16 5.33 1.13

    25 6.25 -0.48

    28 5.60 -1.07

    28 4.67 -1.29

    37 5.29 0.57

    37 4.63 0.65

    62 6.89 4.06

    90 9.00 0.00

    which was acting in sales force forcasting

    cking signal of Zero and MAD of 9 with no

    8 10 12

    oval Method

  • 8/12/2019 GSEP13GLSCM045_SCM Operations Assignement

    11/15

    g different

    in

    stem

  • 8/12/2019 GSEP13GLSCM045_SCM Operations Assignement

    12/15

    Demand (Weekly Avg) cars/outlet

    No of Outlets

    Total Demand

    Std Deviation

    Lead Time

    Std Deviation of DemandTarget Service Level

    Z

    Saftey Stock per Outlet

    Saftey Stock for 4 Outlet

    Demand (Weekly Avg) (25 cars/outlet)

    Std Deviation

    Lead Time

    Std Deviation of Demand

    Target Service Level

    Z

    Saftey Stock 19

    100

    10

    2

    14.14213562

    90%

    1.281551566

    When we have a decentralized m

    more because std deviation for e

    centralized model the std deviati

    level the safety stock decreases i

    The Assumption here are:

    1. Target Service Level remains Sa

    2. Demand between the outlets a

    Proposed Centralized Model

    Current Decentralized Model

    25

    4

    100

    5

    2

    7.07106781290%

    1.281551566

    9.061938024

    37

  • 8/12/2019 GSEP13GLSCM045_SCM Operations Assignement

    13/15

    del the safety stock requirement is

    ch outlet is taken. When we use a

    n gets lowered. Hence for the same Service

    Centralized model.

    me.

    re negatively correlated.

  • 8/12/2019 GSEP13GLSCM045_SCM Operations Assignement

    14/15

    Annual Demand D 25300 boxes

    Cost C 112 per box

    Setup Cost S 1560

    Holding Cost (@30%) H 33.6

    Lead Time L 3 Weeks

    Standard Deviation Sigma 54 for Weekly Demand

    Working per year 50 Weeks

    Service Level 95%

    Normsinv of 95% Z 1.644853627

    EOQ Q* 1533

    Production Run Required Q*/D 16.50358774

    Sigma * sqrt(L) 93.53074361

    Weekly Demand 506

    Weekly Demand in 3 Weeks 1518

    Saftey Stock 153.8443829

    Reorder Point 1672

    IPOH

    SR

    BO

    OH 0

    SR 1000

    BO 500

    IP 500

    Present Week 1 Week 2 Week 3

    Stock On Hand 0 1000 0 2672

    Scheduled Receipts 1000 2672 2672 0

    Backorders 500 1000 500 1000

    Avg Weekly Demand - 500 500 500

    Planned Orders 2672 0 0 1500

    Given Data

    Production Run Required as per EOQ Modeling

    Reorder Point

    IP=OH+SR-BO

    As per the calculation my recomm

    the maximum cost benefit, also It i

    case the first order which has to b

    sum of Re-order qty and EOQ qua

    reorder again once they go below

    Inventory Position

    Inventory PositionOn-Hand Inventory

    Open Order in Pipeline

    Back-orderAs the Inventory Position is less th

    the order to the factory.Assuming

    are allowed and does not result in

    2672 units (Reorder Quantity (167

    (present 500 + next one week 500

    3rd week the company should ord

    depleted.

  • 8/12/2019 GSEP13GLSCM045_SCM Operations Assignement

    15/15

    Total Production Qty/Run 1582

    Production Cost 2833600

    Setup Cost 24960

    Holding Cost 26577.6

    Total Cost 2885138

    Total Production Qty/Run 1489

    Production Cost 2833600

    Setup Cost 26520

    Holding Cost 25015.2

    Total Cost 2885135

    Week 4 Week 5 Week 6 Week 7 Week 8 Week 9

    1172 672 1672 1172 672 1672

    1500 1500 0 1500 1500 0

    0 0 0 0 0 0

    500 500 500 500 500 500

    0 0 1500 0 0 1500

    Total Cost Considering 17 Production Run/Year

    Total Cost Considering 16 Production Run/Year

    ntdation would be to go for a 17 Production run/year to have

    s seen that the EOQ is less than the Re-order point qty. In this

    made by warehouse should be equal to or greater than the

    tity, and then as per the demand or usage they should

    re-order qty.

    an the Re-order point the warehouse should place

    that the Avg demand is 500 and that backorders

    lost sales, the company should place an order for

    ) + Accumulated back order till next week

    ) + Week 2 & 3 demand (1000) - SR(1000). After

    er EOQ quantity and if reqd. safety stock if it is