Grid Standard

download Grid Standard

of 54

Transcript of Grid Standard

  • 8/12/2019 Grid Standard

    1/54

    1

    Grid Connec t iv i ty Standards,Gr id standards

    alka

    NPTI, PSTI

    Bangalore

  • 8/12/2019 Grid Standard

    2/54

    2

    CEAs Standards for

    Grid Connectvity

  • 8/12/2019 Grid Standard

    3/54

    3

    1.Transmission system Planning & Design

    i. The transmission licensee shall plan and design the

    inter state/ intra state transmission system based on thefollowing

    a. CEA Manual on Transmission Planning Criteria: 1994

    b. CEA Report of the Committee for Updating the Best Practices

    in Transmission System for the Country: 2002.

    c. Latest Issue of CBIP Manuals on: Layout of Substations,

    Transmission Towers

    d. Grid code

    e. State Grid code

  • 8/12/2019 Grid Standard

    4/54

    4

    1.Transmission system Planning & Design

    ii. The integrity of the regional grid is not affected under various

    operating conditions including stipulated system contingenciesa. all elements of the transmission system shall be designed

    taking into account the specifiedfactors of safetyin regard to

    electrical, mechanical and civil aspects in the respective

    standardsb. optimal system to be chosen after performing load flow, short

    circuit, stability studiesof the various transmission alternative

    The system designed shall not impinge on the rating of thesubstation equipment in any other sub station in the vicinity.

  • 8/12/2019 Grid Standard

    5/54

    5

    2. Overhead Transmission Lines

    i. The transmission line proposed to be connected shall be

    comply with the followinga. Tower design shall be based on the technical standards for the

    construction of electrical lines specified by the authority under

    section 73(b) of the Act

    b. Foundation design for the tower to be developed by thetransmission licensee for various soil categories.

    c. Use of multi circuit and narrow based towers wherever ROW

    constraints exist

    d. Each type of tower to be type tested for mechanical strength

    ii. Clearance from PTCC shall be obtained

  • 8/12/2019 Grid Standard

    6/54

    6

    3. EHV/HV Underground Cables

    i. Cables proposed to be connected to the system, shall comply with the

    following

    a. Shall be ofXLPE typecorresponding to IS 7098

    b. Cable conductor to be of adequate sizeconsidering continuous current,

    short circuit current, voltage drop etc, & shall correspond to IS-8130

    c. Cables to be provided with propersheathing, armoring & screening

    d. Prior permission from appropriate authority to be obtained for diggingtrenches, precautions to be taken

    e. Route maps to be kept at Substation & markers shall be fixed to trace the

    cables

    f. Road crossing to be carried out by providing Hume pipes or GI pipes

    g. Jointing & termination to be carried out as per relevant standards

    ii. Clearance from PTCC shall be obtained

  • 8/12/2019 Grid Standard

    7/54

    7

    4. Substations

    Planning and design of substations to be based on the following

    Security of supply, extendibilty, maintainabilty andoperational flexibility

    Statutory safety requirements

    Protection from direct lightening stroke

    Switching scheme:-

    765 kV Substation: Double bus double breaker

    400 kV Substation: One and half breaker scheme/ double main

    and transfer bus bar scheme

    220 kV Substation: Double main and transfer scheme/ double

    main with breaker by-pass scheme

    132kV Substation: Main and transfer scheme

    below 132 kV Substation: as decided by licensee

  • 8/12/2019 Grid Standard

    8/54

    8

    4. Substations

    Planning and design of substations to be based on the following

    v. All EHV circuit breakers to be of SF6 typevi. Isolators to be pneumatic or motor operated

    vii. ICTs to be provided with OLTCs

    viii. Surge arrestors to be of metal oxide type (as per IEC 60099)

    ix. Control room to be extensible

    x. All substation structures to be of lattice steel. Structures to

    conform to IEC 865, IS-875, IS-802, IS-800

    xi. Electrical, mechanical and civil designs to be standardised to

    the extent possible

  • 8/12/2019 Grid Standard

    9/54

    9

    4. Substations

    Planning and design of substations to be based on the following

    xii. Power Supply to the sub station auxillariesa. AC Supply;

    2 HT supplies shall be arranged from independent sources.

    In addition, a DG set of suitable capacity to be provided

    b. DC Supply:

    2 sets of 220 V batteries each equipped with own charger for

    substations of 220 kV & above. 2 sets of 50 V batteries for

    PLCC system.

    for substations of 132 kV & below, 1 set of battery each tobe provided

    xii. For high current, XLPE cables to be employed. For LV/MV

    systems, PVC cables corresponding to IS-1554, can be

    employed

  • 8/12/2019 Grid Standard

    10/54

    10

    4. Substations

    Planning and design of substations to be based on the following

    xiv. Reliable communication link shall be provided on all EHTlines for voice, Fax, protection, telemetry & SCADA

    xv. Substation grounding shall be done in accordance with IEEE-80

    xvi. Size and no. of ICTs to be selected such that outage of one

    shouldnt overload the remaining ICTs or the underlyingsystem

    xvii. The stuck breaker condition in the substation shall not causedisruption of more than 4 feeders in 132 or 220 kV system,

    more than 2 feeders in 400 kV system and more than onefeeder in 765 kV system

    xviii. In substations of 220 kV and above, control room, PLCCroom, Relay testing room and electronic laboratory shall be airconditioned

  • 8/12/2019 Grid Standard

    11/54

    11

    5. Earth Fault Factor

    In the event of a point in the EHT system of a transmission licensee

    being earthed, the Earth fault Factor shall be less than 1.4

    6. Electromagnetic CompatibilityA line or equipment in the transmission system shall not generate

    excessive electromagnetic field and the RIV (radio

    interference voltage) shall be within permissible limits as per

    relevant standards

  • 8/12/2019 Grid Standard

    12/54

    12

    7. Insulation coordination

    i. For new connections, the CTU/ STU/ transmission licensee,

    shall inform the transmission users seeking connectivity, theBIL and important parameters of the equipment and ratings of

    the surge arresters in its system adjacent to the connection

    point.

    ii. The transmission users and licensees seeking connectivity

    shall furnish to the CTU/ STU, the BIL of the proposed

    system/ important items of the equipment and the rating of the

    surge arresters adjacent to the connection point

    iii. The CTU/ STU/ transmission licensee shall determine the

    ratings of the surge arresters to be installed at the connection

    point

    iv. Requisite insulation coordination to be done by the CTU/

    STU/ transmission licensee.

  • 8/12/2019 Grid Standard

    13/54

    13

    8. Grid standards

    The transmission utility, transmission licensee and the load dispatch

    center shall comply with the CEAs Grid standards

  • 8/12/2019 Grid Standard

    14/54

    14

    Grid Standards

  • 8/12/2019 Grid Standard

    15/54

    15

    1. Short title and commencement and application

    These are CEA (Grid standards) Regulations, 2010These regulations came into force on their publication in

    official gazette i.e.June 26, 2010

    These shall apply to the entities, appropriate LDCs, and RPCs.

    2. DefinitionsBulk consumermeans a consumer who avails supply at

    voltages of 33 kV or above

    Entity - means a Generating company or a transmission licenseeor a distribution licensee or a bulk consumer

    Voltage UnbalanceRatio of the maximum voltage deviation of

    the phase voltage from the average phase voltage to the average

    phase voltage

  • 8/12/2019 Grid Standard

    16/54

    16

    3. Standards for operation and

    maintenance of transmission lines

    All entities

    LDCs

    RPCs

    a) Frequency ControlOperating Range : 49.5 to 50.2 Hz or as per grid

    code, except during the transient periodfollowing tripping.

  • 8/12/2019 Grid Standard

    17/54

    17

    b) Operating Voltage Limits

    S.No. Normal system

    Voltage (kV rms)

    Maximum (kV

    rms)

    Minimum (kV

    rms)

    1 765 800 728

    2 400 420 380

    3 220 245 198

    4 132 145 122

    5 110 121 99

    6 66 72 60

    7 33 36 30

  • 8/12/2019 Grid Standard

    18/54

    18

    c) Temporary over voltage range d) voltage unbalance limits

    S.No. Nominal System

    Voltage (kV rms)

    Temporary over voltage

    Phase to Neutral (kV peak)

    Voltage

    unbalance (%)

    1 765 914 1.5

    2 400 514 1.5

    3 220 283 24 132 170 3

    5 33 Decided by the state

    commission in the respective

    State grid code

    3

  • 8/12/2019 Grid Standard

    19/54

    19

    e) Max fault clearance time

    S.No. Normal system Voltage

    (kV rms)

    Maximum time

    in milliseconds

    1 765 and 400 100

    2 220 and 132 160

    Time delay for Back up breaker operation 200 ms.

  • 8/12/2019 Grid Standard

    20/54

    20

    f) Grid shall with stand one of the following

    contingencies without loss of stability

    Outage of one single largest generating unit

    Outage of a 132 kV double circuit line

    Outage of a 220 kV double circuit line

    Outage of a 400 kV single circuit line

    Outage of a 400 kV single circuit line with seriescompensation

    Outage of a 765 kV single circuit line without series

    compensation Outage of one pole of HVDC Bipolar line

    Outage of one interconnecting transformer

  • 8/12/2019 Grid Standard

    21/54

    21

    g) N-1 criteria for system stability- system shall

    be stable for one of the following contingencies

    Tripping of single largest generating unit

    Transient SLG fault of a 765 kV line close to bus

    A SLG Fault on 400 kV line and isolation of the line

    A fault on one circuit of a 400 kV double circuit line in

    operation

    A transient SLG fault in one of the 400 kV double circuit

    line when the second circuit is already under outage

    A 3 ph fault in 220 kV or 132 kV line

    A fault in one pole of HVDC bipolar in a HVDC

    Converter station

  • 8/12/2019 Grid Standard

    22/54

    22

    h) Limits for harmonic distortion in

    Transmission systems

    S.No. System Voltage (kV rms) Total harmonic

    distortion (%)

    Individual

    Harmonic of any

    particular

    frequency (%)

    1 765 1.5 1.0

    2 400 2.0 1.5

    3 220 2.5 2.0

    4 33 to 132 5.0 3.0

  • 8/12/2019 Grid Standard

    23/54

    23

    4. Operations planning

    Regional Power Committee shall periodical ly review theperformance of the gridfor the past period

    RPC shall plan stable operation of the grid for future,considering various parameters and occurrences such as

    frequency profile, voltage profile,

    line loading,

    grid incident,

    grid disturbance, performance of protection schemes and

    protection coordination

  • 8/12/2019 Grid Standard

    24/54

    24

    5. Maintenance planning

    The RPC shal l prepare annual maintenance planfor

    Generating stations, ISTS

    Coordinate the annual maintenance planfor inter

    regional transmission system

    Organise monthl y operating committee meetingsin the

    region to review and revise the coordinated generation and

    transmission system plan

    The SLDCshall do the above for intra-state consti tuents

    in consultation with the concerned transmission licensees

    The generating company/ transmission licensee shall

    obtain approval of the appropr iate LDCbefore actual shut

    down

  • 8/12/2019 Grid Standard

    25/54

    25

    6. Coordination in operations

    No enti ty shal l introduce or take out the element of the

    gridwithout the concurrence of the appropriate LDC

    except in case of risk of safety of plant and personnel in

    which case it must intimate the appropriate LDC.

    The appropriate LDC shall inform all affected partiesof

    the outage

  • 8/12/2019 Grid Standard

    26/54

    26

    7. Operating instructions

    Every generating company and transmission licensee shall

    provide written operating instructions for each equipment

    and operating procedure for sequence of operationsof power

    system equipment in their control room

    These instructions to be consistent with the manufacturers

    instructions

    Instructions and procedures to be reviewed and revisedby

    generating company/ licensee.

  • 8/12/2019 Grid Standard

    27/54

    27

    8. RLDCs and SLDCs Instructions to be recorded

    All operating instructions given by RLDC and SLDC throughphone, fax, email shall be given a unique operating code number

    and recorded . Voice recorder to be maintained for recording and

    reproduction of conversation with time stamp/ tag.

    Above records shall be preserved for six months.

  • 8/12/2019 Grid Standard

    28/54

    28

    9. Under frequency relay settings

    All entities shall set their UF relays and DF /DT relaysin

    accordance with RPC plan to provide adequate load relief forgrid security and ensure the operation of these relays at the set

    frequencies.

    All entities shall include the Fr relay details in their daily report

    to the RLDCs and RPCs. RPC shall carry our inspection of the

    relays as and when required.

  • 8/12/2019 Grid Standard

    29/54

    29

    10. Islanding schemes

    The RPC shall prepare islanding schemes for separation

    of systemswith a view to save healthy system from total

    collapse in case of grid disturbance.

    All entities shall ensure proper implementation of the

    islanding schemes.

    11 Categorization of Grid incident and

  • 8/12/2019 Grid Standard

    30/54

    30

    11. Categorization of Grid incident and

    Grid disturbance based on severity

    Grid Incidentmeans tripping of one or more power systemelements of the grid, which requires rescheduling of load/

    generator, without total loss of supply at the substation or loss

    of integrity of the grid at 220 kV and above(132 kV in case of

    NE region)

    Grid Disturbancemeans tripping of one or more power

    system elements of the grid, resulting in total failure of supply at

    the substation or loss of integrity of the transmission system at220 kV and above(132 kV in case of NE region)

  • 8/12/2019 Grid Standard

    31/54

    31

    11. Categorization of Grid incident and Grid

    disturbance based on severity (contd)

    Severity of grid incidents

    GI 1: Tripping of one or more power system elements which requires

    rescheduling of generator/ load, without loss of supply at a substation or

    loss of integrity of grid at 220 kV level(132 kV in NE region)

    GI 2: Tripping of one or more power system elements which requires

    rescheduling of generator/ load, without loss of supply at a substation or

    loss of integrity of grid at 400 kV level and above (220 kV in NER).

    Severity of Grid disturbance

    GD 1: When Generation or Load loss in a region < 10%

    GD 2: When Generation or Load loss in a region is between 10% to 20% GD 3: When Generation or Load loss in a region is between 20% to 30%

    GD 4: When Generation or Load loss in a region is between 30% to 40%

    GD 5: When Generation or Load loss in a region is between 40% to 50%

  • 8/12/2019 Grid Standard

    32/54

    32

    12. Reporting of events affecting grid operation

    Any tr ipping of generating station or transmission elementshall be promptly reported by the respective entity to theappropriate LDC in the prescribed format.

    The appropriate LDC shal l intimate the event to the SLDCand RLDCof the affected regions for further dissemination toall concerned.

  • 8/12/2019 Grid Standard

    33/54

    33

    13. Reporting of grid disturbance

    The RLDC shall inform occurrence of the grid disturbanceto the constituents and RPC at the earliest

    The disturbance resulting in failure of power supply to large

    areas in a state shall also be reported by RLDC to Authoritywithin 24 hoursof the occurrence of the grid disturbance.

    The RLDC shall also post on its web site a brief grid

    disturbance report indicating the affected area or the system,extent of outage and the likely cause of initiation.

    14 Restoration of grid following incidence or

  • 8/12/2019 Grid Standard

    34/54

    34

    14. Restoration of grid following incidence or

    disturbance

    TheRLDC in consultation with RPCshall develop proceduresfor

    enabling restoration and normalization of the gridfor inter-statesystemat the earliest.

    The SLDCshall also develop restoration procedures for intra-state

    system.

    The restoration procedures shall be reviewedfollowing addition of

    generating station or transmission line or at least once in two years

    and revised if considered necessary.

    The above procedures shall be made available to, and be followed

    by all concerned (entities, RLDCs and SLDCs).

    15 Operational data during normal and grid

  • 8/12/2019 Grid Standard

    35/54

    35

    15. Operational data during normal and grid

    disturbance conditions

    All real time dataas required by the appropriateLDC shall befur nished by the entities.

    All data required by RPC, in discharge of the responsibilities to

    it, shall be furnished by RLDC.

    All operational data, including disturbance recorder and eventlogger reports, for analysing grid incident / disturbanceshall be

    furnished by al l enti ties within 24 hrs to RLDC and RPC.

    All equipments such as disturbance recorders and event loggers

    shall be kept in healthy conditions. The RPC shall recommend remedial measuresto be taken on

    the disturbance report of RLDC to prevent recurrence of GI and

    GD.

  • 8/12/2019 Grid Standard

    36/54

  • 8/12/2019 Grid Standard

    37/54

    37

    17. Communication Facilities

    The communication facilities installed by the transmission

    licensee shall be in accordance with CEA(Technical Standards

    for Connectivi ty to the Grid) Regulations, 2007and shall bemaintained in good operating condition.

  • 8/12/2019 Grid Standard

    38/54

    38

    18. Safety procedure

    The enti ty shall prepare contingency procedures for use

    of operatorsat each sub-station and switchyards and theseshall be regularly updated.

    All operating personnel shall be trained in conti ngency

    procedures at regular intervalsand they shall follow theprocedures.

    The f i re f ighting equipment shal l be made available at allsub-stations, switchyards, etc and shall be checked

    periodically for its upkeep and mock exercises in firefighting shall be carried out at least once in a year.

  • 8/12/2019 Grid Standard

    39/54

    39

    19. Maintenance of tools and equipment

    The maintenance staf f shall be made aware ofthe list of

    tools, devices and equipment for various maintenance and

    rectification works on Transmission lines, Substations,

    Switchyards and Converter stations and the tools shall be madereadily available and certi f ied for usage.

  • 8/12/2019 Grid Standard

    40/54

    40

    20. Maintenance procedures

    The entity shall prepare maintenance proceduresfor each

    equipment in line with the manufacturers

    recommendations and prudent utility practices.

  • 8/12/2019 Grid Standard

    41/54

    41

    21. Hot line methods

    The hot line techniques for maintenance of cri tical

    transmission l ines and sub-stationsshall be adopted where

    ever possible.

    Only trained staff shal l be used for the hot line techniques

    and the tools employed shall have necessary certification from

    a national or international laboratory before use.

    22 Emergency Restoration System

  • 8/12/2019 Grid Standard

    42/54

    42

    22. Emergency Restoration System

    Each transmission licensee shall have an arrangement for

    restoration of transmission lines of 400 kV and above and

    strategic 220 kV lines through the use of emergency restoration

    system in order to minimise the outage of the Transmission

    L ines in case of tower failures.

    (Emergency Restoration Systemmeans a system comprising

    of transmission towers or structures of modular construction,

    complete with associated components such as insulators, hardware

    fittings, accessories, foundation plate, guys, anchors or installation

    tools and the like to facilitate quick restoration of damaged orfailed transmission line towers or sections)

    23 Inspection and patrolling

  • 8/12/2019 Grid Standard

    43/54

    43

    All essential parameters which indicate the healthiness of the

    equipment in a sub station, shall be inspected by the shif t

    engineer once in each shif tand periodically by the officer in

    charge.

    Overhead linesshall be patrolled at periodicity decided by the

    transmission licensee and different patrolling schedules shall

    be implemented by the transmission licensee for normal

    terrain, vulnerable terrain and most vulnerable terrain .

    The important l inesshall be inspected by senior engineers

    after patrolling by junior staff and maintenance works such as

    tree cutting, replacement of damaged insulators shall be

    carried out immediately after patrolling wherever required.

    23. Inspection and patrolling

    24 Maintenance schedules

  • 8/12/2019 Grid Standard

    44/54

    44

    Entities shall identify cri tical equipmentand as far as possible, practice

    condition based maintenancefor such equipment in place of time based

    maintenance.

    In case of time based maintenance, the periodicity of maintenance of lines

    and substations located in polluted area or coastal area shall be more

    frequent.

    The maintenance of lines passing through and sub-stations located in such

    areas should be completed before onset of winterso as to minimise

    tripping under conditions of fog or due to salt deposit on insulator discs in

    coastal areas and once before onset of summer.

    The maintenance work on various items of equipment may be advanced

    depending on the condition of the equipment.

    24. Maintenance schedules

  • 8/12/2019 Grid Standard

    45/54

    45

    25. Use of diagnostic Techniques forCondition monitoring of equipment

    The diagnostic methods of maintenance shall be preferred over

    traditional time based maintenance.

  • 8/12/2019 Grid Standard

    46/54

    46

    26. Thermo-vision scanning

    The thermo-vision scanning for hot spots on all overhead

    lines and sub station equipmentat voltage level of 220 kV

    and above shall be carried out at least once in a yearand

    necessary remedial measures shall be taken where hotspots are detected.

  • 8/12/2019 Grid Standard

    47/54

    47

    27. Failure Analysis

    All failures of the equipment and tower collapse shall be

    analyzed by the enti tyto avoid recurrence and a copy of thereport shall be submitted to the RPC and Authority

    The authority may appoint a group of experts for investigation

    and analysis and the representatives of the manufacturers may

    be invited to participate in such analysis. All relevant datawhich may help the group of experts in

    analysing the failures shall be furnished by the respective

    Entities.

    The recommendations of the group of expertsshall besubmitted to the authority and the recommendations accepted

    by the authority shall be implemented and circulated to all

    within the organisation and to other organisations to prevent

    recurrence of such failures.

    28 Inventory Control and Spare Parts

  • 8/12/2019 Grid Standard

    48/54

    48

    28. Inventory Control and Spare Parts

    Management

    The required spare parts shall be kept in stock, to ensure

    speedy maintenance of the equipment.

    Computerised materials management system shall bedeveloped by the entities to optimise inventory.

  • 8/12/2019 Grid Standard

    49/54

    49

    29. Maintenance Audit

    An internal audit committeemay be established by the

    entities to verify whether actual maintenance works are

    carried out at site in compliance of the procedures and the

    policy of the transmission company.

    The observations of the committeeshall be put up to the

    management of the entity for perusal and taking corrective

    action, if any.

    30 R id l Lif A t

  • 8/12/2019 Grid Standard

    50/54

    50

    30. Residual Life Assessment

    The RLA shall be carried out for all major equipment

    including transformers, reactors, breakers, etc as envisaged by

    relevant standards specified by the Bureau of Indian standards,

    manufacturers instruction or industry best practices and

    suitable remedial action for breach of the same shall be taken

    by the management of the entity.

  • 8/12/2019 Grid Standard

    51/54

    51

    31. Disaster Management

    The maintenance staff shal l be trainedin disastermanagement and a detailed procedure for the same shall bedeveloped by the entity and displayed prominently.

    The detailed procedure shall be reviewed per iodical lyandalso based on mock exercises carried out by the entity.

    The equipment including vehicles, diesel generating setsand fire fighting equipment, etc shall be kept at sub-stationor at appropriate location for disaster management.

  • 8/12/2019 Grid Standard

    52/54

    52

    32. Maintenance records

    The records of all maintenance carried out for each equipment

    shall be kept in the table and formats in electronic form and

    hard copy and the next due date for maintenance of each item

    of work shall be clearly marked in such tables and formats.

  • 8/12/2019 Grid Standard

    53/54

    53

    33. Training

    Every personinvolved in O&M of transmission lines shall betrained at the induction level and at least once in a year.

    The shi f t staffshall be trained to make them thorough incarrying out operations at each substation and every person

    concerned with real time operation shall be trained.

    Every grid operatorshall undergo training in real time digitalsimulator and a refresher course at least once in two years.

    The maintenance personnelof every entity shall also be trainedin preventive and breakdown maintenance of variousequipment and the personnel shall be trained in detailedmaintenance procedures.

  • 8/12/2019 Grid Standard

    54/54

    Thank you