GOVERNMENT OF UTTARAKHAND
World Bank assisted
Uttarakhand Disaster Recovery Project (UDRP)
INDEPENDENT CONSULTANT FOR
ENVIRONMENTAL AND SOCIAL AUDIT
ESMF Audit Report
February 2016
Submitted By
Samaj Vikas Development Support Organisation
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas i
Table of contents
1. BACKGROUND .......................................................................................................................1
1.1 The Disaster ...................................................................................................................1
1.2 Uttarakhand Disaster Recovery Project .................................................................1
1.3 Environmental and Social Audit ...............................................................................3
1.3.1 Need for Environment and Social Audit .................................................................................................... 3
1.3.2 Objectives of ESA ............................................................................................................................................... 3
1.3.3 Scope of ESA ........................................................................................................................................................ 4
1.4 Audit Process .................................................................................................................5
1.5 Sampling Plan ................................................................................................................6
1.5.1 Sample Size .......................................................................................................................................................... 6
1.5.2 Selected Samples ............................................................................................................................................... 6
1.5.3 Spatial Distribution ........................................................................................................................................... 8
2. ENVIRONMENT AND SOCIAL MANAGEMENT FRAMEWORK .................................. 10
2.1 Understanding ESMF ................................................................................................. 10
2.1.1 Environmental – Legal and Regulatory Framework........................................................................... 10
2.1.2 Social – Legal and Regulatory Framework............................................................................................. 11
2.1.3 Statutory Clearances and Authorizations Required ........................................................................... 11
2.1.4 E&S Requirements in a Sub-Project Cycle .............................................................................................. 13
2.2 Categorization of projects ....................................................................................... 15
2.2.1 Environmental Categorization ................................................................................................................... 15
2.2.2 Social Categorization ..................................................................................................................................... 16
3. GENERAL INFORMATION ABOUT SELECTED SAMPLE SUB-PROJECTS ............... 17
4. AUDIT RESULTS AND FINDINGS .................................................................................... 21
4.1 Compliance with ESMF ............................................................................................. 21
4.1.1 Statutory Clearances ..................................................................................................................................... 21
4.2 Desk Review Findings ............................................................................................... 28
4.2.1 Environmental and Social Data Sheets .................................................................................................... 31
4.2.2 Environmental Management Plan ............................................................................................................ 31
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas ii
4.2.3 Labour Licence ................................................................................................................................................ 32
4.2.4 Labour Insurance............................................................................................................................................ 33
4.2.5 NoC for Hot Mix Plants.................................................................................................................................. 33
4.2.6 NoC for Construction Water........................................................................................................................ 34
4.2.7 PUC for Construction Vehicles ................................................................................................................... 34
4.2.8 Authorization of Quarries ............................................................................................................................ 35
4.3 Site Visit Findings ...................................................................................................... 36
4.3.1 Health / Safety and PPE................................................................................................................................ 37
4.3.2 Labour Camps .................................................................................................................................................. 43
4.3.3 On-Site EMP Implementation ..................................................................................................................... 48
4.3.4 Monitoring of Environmental Parameters ............................................................................................. 56
5. GOOD PRACTICES, IDENTIFIED ISSUES AND SUGGESTIONS .................................. 59
5.1 Some Good Practices ................................................................................................. 59
5.2 Observations and Suggestions ............................................................................... 60
6. SUB-PROJECTS IN PICTURES .......................................................................................... 64
List of Annexures
Annexure I: Summary: Compliance status of ESMF ........................................................................................ 76
Annexure II: Checklist for Environmental and Social Audit ......................................................................... 82
Annexure III: Travel Schedule of ESA Team to Sub-Project Sites........................................................... 90
Annexure IV: Pictures of Training Workshop .......................................................................................................... 91
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas iii
List of Tables
Table 1: Components of UDRP ............................................................................................................................................ 2
Table 2: Sample Size for Audit ............................................................................................................................................ 5
Table 3: Sample Size selected for Audit ......................................................................................................................... 6
Table 4: Selected Road Sub-Projects for First Audit Cycle ................................................................................... 7
Table 5: Selected Public Buildings for First Audit Cycle ........................................................................................ 8
Table 6: Selected Bridges for First Audit Cycle .......................................................................................................... 8
Table 7: Spatial Distribution of Selected Sub-Projects for First Audit Cycle .............................................. 8
Table 8: Statutory Clearances and Authorizations Required as per ESMF ............................................... 12
Table 9: E & S Activities and Responsibilities during the sub-project cycle ............................................ 14
Table 10: General Information about the Selected Sub-Projects ................................................................... 18
Table 11: Status of Statutory Compliances in selected Road Sub-Projects .............................................. 24
Table 12: Status of Statutory Compliances in Selected Bridge Sub-Projects ........................................... 26
Table 13: Status of Statutory Compliances in Selected Public Building Sub-Projects ........................ 27
Table 14: E&S: Compliances and Non-Compliances - Desk Review Findings ......................................... 29
Table 15: Major Social and Environmental Concerns Identified ................................................................... 32
Table 16: Site Visit Findings – Health / Safety Issues and Use of PPE ........................................................ 37
Table 17: Labour Camps and Facilities Provided ................................................................................................... 43
Table 18: On-Site Environmental Management Plan Implementation ....................................................... 48
Table 19: Monitoring of Environmental Parameters ........................................................................................... 56
Table 20: Non-Compliances and Additional Corrective Measures Required .......................................... 76
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas iv
List of Figures
Figure 1: Environment and Social Audit Process Flow .......................................................................................... 9
Figure 2: ESMF Flow Chart ................................................................................................................................................ 13
Figure 3: Status of Tree Cutting Permission in Sub-Projects ........................................................................... 21
Figure 4: Status of NoC for HMP in Reviewed Sub-Projects ............................................................................. 22
Figure 5: Status of E&S Screening in Reviewed DPR ............................................................................................ 31
Figure 6: Status of Labour License in Reviewed Sub-Projects ........................................................................ 32
Figure 7: Status of Labour Insurance in Reviewed Sub-Projects ................................................................... 33
Figure 8: Status of NoC for Construction Water ..................................................................................................... 34
Figure 9: Status of PUC for Construction Vehicles ................................................................................................. 34
Figure 10: Status of Availability of First Aid Kit...................................................................................................... 40
Figure 11: Status of Use of PPE ........................................................................................................................................ 41
Figure 12: Status of Safety Signs ..................................................................................................................................... 42
Figure 13: Labour Camps in Reviewed Sub-Projects ........................................................................................... 45
Figure 14: Status of NoC for Labour Camps .............................................................................................................. 45
Figure 15: Status of Rent Agreement for Labour Camps .................................................................................... 46
Figure 16: Status of Facilities Provided in Labour Camps ................................................................................. 47
Figure 17: Status of Compensatory Plantation ........................................................................................................ 51
Figure 18: Status of Noise Barrier .................................................................................................................................. 51
Figure 19: Status of Water Sprinkling for Dust Suppression ........................................................................... 52
Figure 20: Status of Project Information Board ...................................................................................................... 53
Figure 21: Status of Identification of Muck Disposal Site .................................................................................. 54
Figure 22: Status of Environmental Monitoring ..................................................................................................... 58
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas v
List of Acronyms
Acronym Description
ADB Asian Development Bank
ARAP Abbreviated Resettlement Action Plan
ATR Action Taken Reports
CSM Construction Supervision Manual
CTE Consent to Establish
CTO Consent to Operate
DEA Department of Economic Affairs
DM District Magistrate
DPR Detailed Project Report
DSC Design and Supervision Consultants
EHS Environment, Health and Safety
EIA Environmental Impact Assessment
EMP Environmental Management Plan
ESA Environmental and Social Audit
ESDS Environmental and Social Data Sheets
ESMF Environmental and Social Management Framework
GCC General Conditions of Contract
GoI Government of India
HMP Hot-Mix Plant
IA Implementing Agency
JRDNA Joint Rapid Damage and Needs Assessment
LA Land Acquisition
MDR Main District Road
NH National Highway
NOC No Objection Certificate
O&M Operation and Maintenance
ODR Other District Road
PAD Project Appraisal Document
PAF Project Affected Family
PAP Project Affected Person
PIP Project Implementation Plan
PIU Project Implementation Unit
PMU Project Management Unit
PPE Personal Protection Equipment
PRI Panchayati Raj Institutions
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas vi
RAP Resettlement Action Plan
SA Social Assessment
SCC Special Conditions of Contract
SH State Highway
SIA Social Impact Assessment
SMP Social Management Plan
SPCB State Pollution Control Board
UDRP Uttarakhand Disaster Recovery Project
USAC Uttarakhand Space Applications Center
VR Village Roads
WB World Bank
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 1
1. Background
Uttarakhand comprises of 13 districts that are grouped into two regions (Kumaon and Garhwal)
and has a total geographical area of 53,484 sq. km. The economy of the State primarily depends
on agriculture and tourism. The State has a very fragile terrain that, by virtue of its very origin,
is prone to natural disasters.
The entire State falls within Zone IV and Zone V (Zone V represents the highest level of
seismicity) of the Earthquake Zoning Map of India. The districts of Bageshwar, Chamoli,
Pithoragarh, Rudraprayag and Uttarkashi fall within the Seismic Zone V.
Every year, the state faces massive losses, particularly during the monsoon season, due to rains,
cloudbursts, flash floods, landslides, floods, hailstorms and water logging events.
1.1 The Disaster
Monsoon in June 2013 arrived almost two weeks earlier than expected. During June 15 to 17,
2013, cloud bursts and heavy (64.5 - 124.4 mm) to very heavy rainfall (124.5 – 244.4 mm) hit
several parts of the higher reaches of the Himalayas. This unprecedented rainfall resulted in a
sudden increase in water levels, giving rise to flash floods in the Mandakini, Alakananda,
Bhagirathi and other river basins and also caused extensive landslides at various locations.
Districts of Bageshwar, Chamoli, Pithoragarh, Rudraprayag and Uttarkashi were worst hit by
this disaster. Numerous landslides and toe erosion by the sediment loaded rivers caused
breaching of roads/highways at many locations and washed away several bridges (steel girder
bridges, beam bridges, suspension/cable bridges).
The World Bank (WB) and the Asian Development Bank (ADB) on receiving a request from the
Department of Economic Affairs (DEA), Government of India (GoI), fielded a Joint Rapid Damage
and Needs Assessment (JRDNA) Mission within the State.
Accordingly a loan assistance of US $ 250.00 million was granted on October 25, 2013 with an
objective to restore housing, rural connectivity and build resilience of communities in the
affected district of Uttarakhand. Out of five components of UDRP project (described in table-1),
this ESMF audit report is prepared covering only 1st and 2nd component of UDRP project which
are “Resilient Infrastructure Reconstruction” and “Restoration of the Rural Road Connectivity”.
1.2 Uttarakhand Disaster Recovery Project
Based on the findings from the JRDNA, The Uttarakhand Disaster Recovery Project (UDRP)
proposes the following five components that cover the immediate recovery and reconstruction
needs within the most affected districts of the State and future oriented risk reduction efforts. A
short description of objectives and activities in each of the components is given overleaf
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 2
Table 1: Components of UDRP
Utt
ara
kh
an
d D
isa
ste
r R
eco
ve
ry P
roje
ct
Component Sub-Component Description Resilient Infrastructure Reconstruction
The objective of this component is to
focus on the immediate needs of
reconstruction of damaged houses and
public buildings.
Resilient Permanent Housing
Building 2,500 permanent houses that would be multi-disaster resilient.
Resilient Public Buildings
Support the reconstruction of damaged public buildings, such as Panchayati Raj Institution
(PRI), Block and District offices and technical education institutes, including restoration of
partially damaged and reconstruction of fully damaged structures.
Rural Road Connectivity
The objective of this component is to
restore the connectivity lost due to the
disaster through the reconstruction of
damaged roads and bridges: village
roads, Other District Roads (ODRs),
bridle roads and bridle bridges. The
roads and bridges will be designed to
withstand earthquake and flood forces
as per the latest official design
guidelines.
Village/ Rural Roads
This will support the reconstruction of about 3,600 kms of damaged village roads,
following the PMGSY program standards and will include construction of new drainage
woks and bridges, retaining and breast walls and other structures to prevent landslides,
and minor realignments.
Other District Roads (ODR)
This will involve the reconstruction of about 675 kms of damaged ODRs, linking village
roads to Major District Roads (MDRs), State Highways (SH) and/or National Highways
(NH) to increase access and provide opportunities for overall economic development.
Bridle Roads and Bridges
This will undertake the reconstruction of about 440 kms bridle roads and about 140 bridle
bridges, facilitating pedestrian connectivity for remotely located villages.
Technical Assistance and Capacity Building for Disaster Risk Management
Enhance the capabilities of government entities and others in risk mitigation and response.
Risk Assessment, Modelling and Capacity Enhancement of Uttarakhand Space Applications
Centre (USAC).
Financing Disaster Response Expenses
To support the financing of eligible expenses already incurred by the state during the
immediate post –disaster response period.
Implementation Support
To support the incremental operating costs of the project, including the operation of the
Project Management Unit (PMU) and the respective Project Implementation Units (PIUs)
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 3
1.3 Environmental and Social Audit
1.3.1 Need for Environment and Social Audit
The ESMF requires detailed
supervision, monitoring and evaluation
of the impact of the project on the
environment and social aspects. In
order to ensure this, PMU has made
specific arrangements at state and
district level. At the PMU an
Environmental Specialist and a Social,
Community Development and Gender
Specialists are appointed on full time
basis to guide project implementing
agencies, consultants and contractors
in complying with the ESMF. These two
specialists are primary focal points for all environmental and social aspects and for ESMF
compliance. These two specialists are engaged on a day to day basis in environmental and social
safeguards implementation and monitoring; they also do capacity building of the implementing
agencies, consultants and contractors while hand-holding them during implementation.
At the field level, staffs of implementing agencies have experience to implement projects
concerning their departments. However, implementation of the provisions of ESMF is new to
these staff and hence several orientations and trainings are proposed as a part of this ESMF to
build their capacity. Further, to implement and supervise the environmental and social aspects
as per the ESMF, design and supervision consultants have also been appointed.
In order to achieve the objectives of this ESMF and to ensure the safeguards are implemented in
a proper manner within provisions of Contract Agreement, an Independent environment and
Social Audit (ESA) has been carried out.
1.3.2 Objectives of ESA
The core objective of ESA is to assess effectiveness in implementation of ESMF, its compliance
during project execution and to suggest implementable corrective action. Beside this the
elaborated objectives are to:
Review and verify compliance of ESMF during project planning and implementation.
Assess the impacts of the sub projects on local environment and communities and how
the project area is sensitive to the project activities.
Assess the effectiveness of implementation of ESMF in the subproject activities
Fundamental Principles of Audit
Regular and Comparative
Verified and Disclosed
Comprehensive and Inclusive
Equity and Social Responsibility
Participatory and Engaging
Transparency and Accountability
Peoples Wellbeing and Caring
Multidirectional and Multi-perspective
Gender Sensitive and Encouraging Women
Exhibit 1: Fundamental Principles of Audit
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 4
Review and verify how effectively the provisions made in Environmental and Social
Management Plan and are being implemented.
Identify and document good practices during project execution.
Assess institutional and administrative effectiveness and make recommendations on
improving ESMF compliance.
1.3.3 Scope of ESA
Scope of ESA is to:
Review and evaluate the method adopted for collection of environmental and social
data, screening, preparation of mitigation plans and its implementation in sub-projects.
Review how ESMF is integrated into the Contract Agreement (CA) of civil work.
Check for availability and compliance of applicable clearances and permission from the
statutory authorities.
Check for Environmental Management Plan (EMP) and Resettlement Action Plan (RAP)
(if any) preparation and implementation.
Incorporating Environmental and Social Management requirements into Bidding
Documents.
Review of Institutional arrangements for implementation, monitoring & reporting of
Environmental and Social components/ activities and identify gaps/ areas that need
improvement including capacity building requirements.
Carry out field visits to selected/ sampled sub-projects to assess how environmental and
social issues have been addressed (or being addressed) on the ground.
Identify and document good practices from proactive sub-projects which can be
replicated across the state and sector.
Prepare an ESA report that clearly specifies
o deviations in implementing environmental and social measures, if any,
o enhancement and positive measures to be taken at the sub-project level, if any
o Provide recommendations for further improvement of environmental and social
management practices at the sub-project level.
The ESA Consultant is to review and verify for compliance the sampled sub-project activities,
including environmental and social standards, environmental, health and social safeguard
measures, taking into consideration the ESMF and larger regulatory frameworks of the Central
and State Government.
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 5
1.4 Audit Process
Sample Selection for Audit
The environmental and social audit is planned to be conducted on the sample basis. The
samples are to be selected using multi-stage stratified random sampling criteria. The sampling
plan as agreed upon during the World Bank review mission during third week of November
2015 is as under
Table 2: Sample Size for Audit
S. No Component Total No. Sampling Size Remarks
1. Roads 215 8% No. of Projects have reduced from 379 planned originally to 215 hence the sample size is increased to get broad and clear findings
2. Bridges 83 10% Tender have been awarded for three projects.
3 Public Building 20 20% Tender awarded for 5 projects.
Sampling Criteria
Samples are selected in a manner that they are
Distributed spatially to cover all districts.
Distributed to cover different type of roads – Village Roads, ODR, Bridle Roads
Distributed uniformly to cover the projects based on their status of implementation – under
implementation, nearing completion (>75%), Completed
A sub-project will be sampled maximum twice during the project period; once during initial
phase of implementation and once nearing or after completion.
The Sampling plan will be finalized in consultation and close coordination with Social and
Environmental Experts at the PMU/ PIU
Desk review
Review Detailed Project Reports (DPRs), monthly and quarterly progress reports prepared by
the Design and Supervision Consultants,, reports prepared by Environmental and Social
Specialists for PIUs, PMU reports, World Bank Aide Memoire, Action Taken Reports (ATRs) on
Aide Memoire, any other reports/documents pertaining to the project environmental and social
aspects.
Review of any environmental and social grievances, their redressal and effectiveness of
grievance redressal mechanism
Review environmental and social aspects of any relevant technical manuals prepared by
PMU and/or implementing agencies, DSCs as part of the project and their dissemination.
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 6
Field Verification
Field visits to selected sample sites, especially designated sites for debris disposal.
Field verification at locations where construction activities are underway and
interviews with UDRP field staff, consultants and contractor’s nominated Environmental
Officer.
Field verification of labour camps, to review environment and social as well as health
and hygiene aspects
Interviews with various key stakeholders at field level from Public Works Department,
residents and community groups directly or indirectly affected by the project, especially
people who have given consent for temporary usage of their land.
Examine and seek views on health and safety issues from the project employees, and
the feedback on the activities from the local and other potentially affected communities,
especially vulnerable groups
Documents (including photographic evidence) of good and bad practices identified in
sample sites
Detailed Checklist for review of Sub-Projects is presented in Annexure II
1.5 Sampling Plan
1.5.1 Sample Size
The sample size for first ESA is as under
Table 3: Sample Size selected for Audit
S. No Component Total No. Sampling Size Sample Agreement
Signed Selected Samples
1. Roads 379 5% 19 215 19
2. Bridges 83 10% 9 3 3
3 Public Building 20 20% 4 5 2
Initially, 4 buildings were selected for audit purpose but due to bad weather conditions on the planned day of visit to these sites in Rudraprayag,, led the audit team to modify the samples in order to avoid any variations in travel plans; with due information to PMU.
The audit team will take up these sites during the second audit cycle.
1.5.2 Selected Samples
On the basis of sampling criteria and agreed sample size the samples selected for purpose of
audit are as under;
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 7
Roads
Table 4: Selected Road Sub-Projects for First Audit Cycle
S. No District Zone Sub Project Name UID Len (Km) Cost Lacs
PKG No.
Exp. (lacs)
Physical
Progress (%) PROGRESS
1. Chamoli Garhwal Tharali-Junidhar Motor Road 1275 3.6 308.9 108 0 0 NO PROGRESS
2. Chamoli Garhwal Salor - Dungra MR 1217 6 266.28 92 0 0 NO PROGRESS
3. Dehradun Garhwal Sahiya Patan Samalta Panuwa MR 1577 11 581.91 71 61.54 15.67 LESS THAN 75%
4. Haridwar Garhwal GT road to Lavva road 1751 1.5 23 55 11.41 56.75 LESS THAN 75%
5. Haridwar Garhwal Raipur link road 1818 1.2 204 56 211.93 86.05 MORE THAN 75%
6. Pauri Garhwal Uffalda-Dhelchauri MR 2270 7.5 328.52 75 20.71 7.15 LESS THAN 75%
7. Pauri Garhwal Arkani-Janasu-Khandukhal MR 2120 5.2 205.36 75 40.39 22.16 LESS THAN 75%
8. Rudraprayag Garhwal Salya-Tulanga MR 2519 6 357.63 29 43.33 9.71 LESS THAN 75%
9. Rudraprayag Garhwal Ukhimath Mansoona MR 2548 3 165.86 21 171.45 86.08 MORE THAN 75%
10. Tehri Garhwal Kempti Byepass Motor Road 2749 5.75 348.81 18 293.83 96.98 MORE THAN 75%
11. Uttarkashi Garhwal Gagnani Motor Pull to Bhangeli Motor Road
3151 4.6 444.04 83 20.24 20.96 LESS THAN 75%
12. Uttarkashi Garhwal Nakuri Singoth Motor Road 3183 6 33 2 30.73 100 MORE THAN 75%
13. Almora Kumaun Khunt -Almora Road 1055 11.5 124.63 62 0 43.38 LESS THAN 75%
14. Bageshwar Kumaun Harinagri-Kulau-Gwaldam MR 1118 17 956.1 109 54.22 18.18 LESS THAN 75%
15. Bageshwar Kumaun Kanda-Saniudiay-Rawatsera MR 1111 20 1049.6
3 10 588.82 63.33 LESS THAN 75%
16. Champawat Kumaun Punav-Sipty Nayari Motor Road 1355 8 517.53 47 236.32 59.64 LESS THAN 75%
17. Nanital Kumaun Padampuri Harakhan Kathgodam Motor Road
2004 30 1603.5
3 52 818.11 56.94 LESS THAN 75%
18. Pithoragarh Kumaun Badabe Seligya MR 2374 9.5 371.27 11 217.77 62.25 LESS THAN 75%
19. Pithoragarh Kumaun Acholi jaakh MR 2370 8 328.08 104 0 0 NO PROGRESS
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 8
Buildings
Table 5: Selected Public Buildings for First Audit Cycle
District Zone Sub-Project Name UID Sanctioned Cost Package No. Tender Status
Pauri Garhwal Food Godown, srinagar 7318 247.91 2258 Agreement signed
Rudraprayag Garhwal Govt Inter College Kotgi 7308 421.39 2256 Agreement signed
Bridges
Table 6: Selected Bridges for First Audit Cycle
District Zone Sub Project Name UID Span (m)
Cost in Lacs
Package No.
Expenditure in lacs
Physical Progress (%)
Chamoli Garhwal Bridge over Alaknanda river at Aarudi- Paturdi
4006 140 1243 506 0 0
Chamoli Garhwal Chepado Bridge 4004 120 1073 501 0 0
Uttarkashi Garhwal Didsari Bridge 4003 100 994 504 0 0
1.5.3 Spatial Distribution
Distribution of samples based on their spatial location is presented in Table below. From the
table it is evident that the works related to Bridges and Public Buildings have initiated in
Garhwal region only. While the number of roads where Contract Agreement have been signed
are much higher in Garhwal region ie 76% as compared to Kumaun region 24%.
Table 7: Spatial Distribution of Selected Sub-Projects for First Audit Cycle
Zone Roads Bridges Public Buildings
Total No. Selected % Total No. Selected % Total No. Selected %
Garhwal 163 12 7.4% 3 3 100% 5 2 40%
Kumaun 52 7 13.5% - - - - - -
Total 215 19 8.8% 3 3 100% 5 2 40%
Detailed travel schedule to sub-project sites is provided in Annexure III
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 9
3. Post Audit Report
2. On-Site Auditing Activities
1. Pre –Audit Preparation
Check Audit ToR
(Objectives, scope & criteria)
ToR
Audit Protocol
Project Objectives
Project Scope, Size, Components, etc.
Audit findings:
Non-compliance/ issue of concern
Conclusion
Recommendations
Closing Meeting
Audit Report
Findings
Report
Environmental Social Management Plan
Initial document review
Opening meeting
Collect evidence:
Documents, interviews, observations
Audit Team Meeting
Audit Sample, Questionnaire, Checklists
Checklist,
Register of interviews, Register of documents, Register of observations
Contact UDRP/PIU Implement Agencies
Prepare work documents
Plan Audit
Appoint Audit Team
Audit Plan
Project Appraisal Document (PAD)
Project Implementation Plan (PIP)
Aide Memoirs,
ESMF Document,
EMPs/ SMPs
Environment & Social Assessment (ESA)
Progress Monitoring Reports
Figure 1: Environment and Social Audit Process Flow
The detailed Audit Process Flow Diagram is presented below
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 10
2. Environment and Social Management Framework
2.1 Understanding ESMF
ESMF deals with the laws, regulations and policies, of Government of India, Government of
Uttarakhand and the World Bank’s OPs, related to environment and social issues. The ESMF
provides the regulatory framework for environmental and social components, for implementing
agencies to comply with during execution of project.
2.1.1 Environmental – Legal and Regulatory Framework
The environmental regulatory framework, consisting of various laws , act s and
regulations, which are applicable to the sub-projects are given below:
Operational Policies
OP/BP 4.01: Environmental Assessment - Potential environmental consequences of
projects identified early in project cycle. EAs and mitigation plans required for projects
with significant environmental impacts or involuntary resettlement.
OP/BP 4.04: Natural Habitats - Prohibits financing of projects involving "significant
conversion of natural habitats unless there are no feasible alternatives".
OP/BP 4.36: Forestry - Prohibits financing for commercial logging operations or
acquisition of equipment for use in primary moist tropical forests.
Environmental Regulations
The Environment (Protection) Act No.29 of 1986
Water and Air (Prevention and Control of Pollution) Act, 1974 & 1981 (Central Act 6 of
1974) as amended in1988
Forest (Conservation) Act No. 69 of 1980 and amended in 1988
National Forest Policy, 1988
Joint Forest Management, 1993
The Wildlife (Protection) Act I972, Amendment 1991
EIA Notification of MoEF 2006
The Ancient Monuments, Archaeological sites and Remains Act, 2010
Biological Diversity Act 2002 / Biological Diversity Rules 2004
Other state governed act and rules like Van Panchyat Act 2005 , Uttarakhand
This policy and regulatory analysis suggests that the proposed sub-projects to be taken does not
fall under any of the project categories listed in Schedule-I of the Environmental Impact
Assessment Notification 2006 (and its subsequent amendment) and hence does not require any
prior environmental clearance from the Ministry of Environment Forests and Climatic Change
(MoEFCC), GOI. None of the audited sub-projects falls under notified ecologically sensitive or
fragile regions the Environment Protection Act, 1986. Moreover, all of the audited sub-projects
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 11
are of restoration of existing facilities/infrastructure and do not require additional land or
diversion of forest land.
2.1.2 Social – Legal and Regulatory Framework
The social regulatory framework, consisting of various laws, acts and regulations, which
are applicable to the sub-projects are given below:
Operational Policies
OP/BP 4.12: Involuntary Resettlement - Implemented in projects which displace people.
OP/BP 4.11: Physical Cultural Resources - to assist in the preservation of cultural
property, such as sites having archeological, paleontological, historical, religious and unique
cultural values.
Legal Regulations
The Land Acquisition (LA) Act of 1894
National Resettlement and Rehabilitation Policy, 2007
The Right to Fair Compensation and Transparency in Land Acquisition and
Resettlement Act 2013
Other Applicable Acts
Minimum Wages Act, 1948
Contract Labour Act, 1970
The Bonded Labour System (Abolition) Act, 1976
Child Labour (Prohibition and Regulation) Act 1996 along with Rules, 1988
Children (Pledging of Labour) Act, 1933 (as amended in 2002)
The Persons with Disabilities (Equal Opportunities, Protection of Rights and Full
Participation) Act, 1995
The Persons with Disabilities (Equal Opportunities, Protection of Rights and Full
Participation) Rules, 1996
Un-touchability Offences Act, 1955
The Scheduled Castes and the Scheduled Tribes (Prevention of Atrocities) Act, 1989
The Scheduled Castes and the Scheduled Tribes (Prevention of Atrocities) Rules, 1995
2.1.3 Statutory Clearances and Authorizations Required
Certain permissions, clearances and authorizations are needed to be obtained from competent
authorities during the design, planning and implementation of the sub-projects. This will
depend mainly on the area, type, size and scope of the sub-project.
This requirement is summarized below:
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 12
Table 8: Statutory Clearances and Authorizations Required as per ESMF
S. No. Clearance / Authorization Relevant Act Competent Authority Responsibility
1.
Environment Clearance / NOC (For sub-projects which requires such clearance, eg. housing and new roads, roads in hilly terrain (above 1000 AMSL) and in ecologically sensitive areas, if their location requires)
EIA Notification, 2006 (including amendments) issued under Environment Protection Act, 1986
State Pollution Control Board;
MoEFCC, Govt. of India,
National Board of Wildlife
PMU/ Line Department
2. Forest clearance Forest Conservation Act, 1980 State Forest Department,
MoEFCC, Govt. of India PMU/ Line Department
3. Tree Cutting Permission Forest Conservation Act, 1980 State Forest Department,
MoEFCC, Govt. of India PMU/ Line Department
4. Hot mix plants, Wet Mix Macadam plants, Crushers, Batching Plants
Air (Prevention and Control of Pollution) Act, 1981 and
Noise Pollution (Regulation and Control) Rules, 2000
State Pollution Control Board Concerned Contractor
5. Storage, handling and transport of hazardous materials
Hazardous Waste (Management and Handling) Rules, 1989 and
Manufacturing, Storage and Import of Hazardous Chemicals Rules, 1989
State Pollution Control Board Concerned Contractor
6. Location/ layout of workers camp, equipment and storage yards
Environment Protection Act, 1986 and Manufacturing, Storage and Import of Hazardous Chemicals Rules, 1989
State Pollution Control Board Concerned Contractor
7. Discharges from Labour Camp Water (Prevention and Control of Pollution) Act, 1974
State Pollution Control Board Concerned Contractor
8. Permission for sand mining from river bed Environment Protection Act, 1986 Mines and Geology Department, GoU
Concerned Contractor
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 13
2.1.4 E&S Requirements in a Sub-Project Cycle
The applicable environmental and social aspects are required to be fulfilled during the sub-
project cycle; i.e., during pre-planning, planning, implementation and Operation and
Maintenance (O&M) are listed in the below table and the flow chart.
Environmental and Social Management Flow Chart
Identification of E&S Impacts of Sub-Projects
Filling of ESDS for Screening
Categorization Category E2/S2 Category E1/S1
EMP/ARAP Prepared
EIA/SIA Prepared
EMP / RAP Prepared
Environment and Social Appraisal
Sub-Project Approval
EMP / RAP / ARAP Implementation
E&
S C
om
pli
an
ce
cert
ific
ati
on
by
G
P
Qu
arte
rly
Mo
nito
ring
Re
vie
w b
y
Wo
rld B
an
k
ES
MF
G
uid
elin
es
Re
vie
w b
y
Wo
rld B
an
k
Figure 2: ESMF Flow Chart
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 14
Table 9: E & S Activities and Responsibilities during the sub-project cycle
Phase ESMF Activity Objectives Responsibility Result
Pre-Planning Identification
Environmental and Social impacts
To collect basic information on environmental and social aspects of the sub-project.
Implementing Agencies (IAs)
ESDS prepared and attached with the project proposal / concept note
Planning
Screening and Categorization
Environmental and Social classification of the sub-project
To ensure that sub-projects with potentially significant environmental / social issues are identified at an early stage for detailed environmental / social assessment.
DPIU
Design Consultants
As per ESMF, Sub-project classified as E1/E2 for Environmental and S1/S2 for Social Categorization.
Preparation
Environmental and Social Assessment and Management Plans
To conduct Environmental / Social Assessment and Prepare Management Plans for integration into sub-project DPR
Independent Consultants
EA/ SA done. EMP / RAP Prepared and disclosed prior to start of procurement for that sub-project.
Appraisal
Environmental and Social appraisal
To ensure that relevant environmental and social issues have been identified and appropriate mitigation measures have been designed to address them.
PMU Environmental Expert, Social Expert
Environmental and social appraisal of the project for approval of the sub-project
Approval
Environmental and Social approval
To ensure that mitigation measures and their cost are integrated in scheme design and implementation plans
PMU Technical Sanction for sub-projects with environmental and social mitigation measures
Implementation
Implementation Implementation of Environmental and social mitigation measures.
To ensure that the prescribed environmental and social mitigation measures are being implemented in project.
Design Supervision Consultant (DSC)
PMU/PIU/DSC
Compliance of Environmental and Social Mitigation Measures Quarterly reports on Safeguards Implementation and compliance of EMP/SMP Orientation cum training to PIU and Contractor’s staff on Environmental Safeguard.
O&M
Monitoring and Evaluation Environmental supervision, monitoring and evaluation IEC and capacity building
To ensure that environmental and social aspects are integrated in the O&M phase. To monitor and evaluate identified performance indicators.
PMU External Consultants
Monitoring and evaluation report on effectiveness of Environmental Mitigation Measures and performance indicators. of
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 15
2.2 Categorization of projects
2.2.1 Environmental Categorization
Sub-projects are assigned one of two categories (E1 & E2) for environmental assessment
depending on the significance of the associated environmental impacts of the various Project
components. The category is assigned based on the project's potential for environmental
impact. Under the operational policies and directives (OPs or ODs) of the World Bank, the
projects funded by the Bank are evaluated. They are thus “pre-screened” to avoid significant
environmental impacts and assess the requirement of various statutory clearances. The project
components included are roads, bridges and public buildings.
The World Bank Operational Policy OP 4.01 stipulates carrying out Environmental Assessment
for projects proposed for banks financial assistance. As set out in BP 4.01, the project in the
earlier stage of development is assigned any one of the following three categories after
examining the project type, location, sensitivity, scale and potential environmental risks
associated with the project.
The E1 category sub-projects require conducting a comprehensive Environmental
Impact Assessment (EIA) and preparation of an Environment Management Plan (EMP)
by Independent Consultants prior to preparation of DPR for appraisal by PMU. This EIA
and EMP need to be disclosed before the start of procurement for that sub-project.
The E2 category sub-projects need not conduct an EIA, but require an EMP, which is to
be prepared by Design Consultants following the guidelines given in this ESMF. This
EMP becomes a part of the DPR, which will be appraised by PMU. If, under special
circumstances, PMU identifies a need for a limited environmental assessment, then it
needs to be conducted.
The project may be categorized as E1 & E2 for environmental Screening by World Bank. As per
the World Bank Operational Policy 4.01, for projects proposed for banks financial assistance, an
environmental audit has been conducted as part of Bank’s EA requirement.
Environmental Audit would examine the compliance with the ESMF for the sampled sub-
projects. The audit would identify appropriate measures, where possible, to mitigate areas of
concern with regard to environmental management and monitoring for the sampled
components. It would also examine the institutional framework to ensure proper
implementation of the environmental safeguards against planned setup in ESMF.
All sampled sub-projects under Uttarakhand Disaster Reconstruction project fall into “E2
category” and hence the design consultant will prepare the EMP for the respective projects. The
rationale for using the design consultant to prepare the EMP for E2 category subprojects is that
the impacts are moderate to minimal and the model EMP given in the ESMF need to be adopted
and modified to prepare a specific sub-project EMP.
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 16
2.2.2 Social Categorization
Based on the number of project affected persons (PAPs) who may be affected by the project and
magnitude of impact, projects have been categorized as either S-1 or S-2 projects
S-1 Projects: The S1 category sub-projects require conducting a comprehensive Social
Assessment (SA) and preparation of a Resettlement Action Plan (RAP), by Independent
Consultants prior to preparation of Detailed Project Report (DPR) for appraisal by PMU.
This SIA and RAP need to be disclosed before the start of procurement for that sub-
project.
If 20 or more PAFs are affected or if PAPs are physically displaced this will require a
detailed Social Assessment Report that would include Resettlement Plan prepared by
Independent Consultants
S-2 Projects: The S2 category sub-projects need not conduct SA but need to prepare an
Abbreviated Resettlement Action Plan (ARAP), and need to include the Social
Management Plan (SMP) which is to be prepared by Design Consultants following the
guidelines given in this ESMF. The preparation of ARAP requires a census survey of the
PAFs. This SMP becomes a part of the DPR, which will be appraised by PMU. If, under
special circumstances, PMU identifies a need for a limited social assessment, then it
needs to be conducted.
All sampled sub-projects under UDRP did not cause any physical displacement and less than
10% of their productive assets are lost (or) and less than 20 PAPs are affected in any single sub-
project; thus there was no need for any Social Assessment and preparation of RAP.
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 17
3. General Information about Selected Sample Sub-Projects
The general information about the sub-projects selected as samples, is presented in the table
overleaf. The samples were selected on the basis of the multi-stage stratified random sampling
using the sample selection criteria as discussed in previous section of the report. The general
information on selected sub-projects provide the detailed profile of these sub-projects detailing
out the physical activities related to the project and budgetary requirements for the project etc.
Table 10 provides the detailed information about the selected sub-projects viz. – Design
Consultants, Implementing Agency, Supervision Consultants, Contractor, Cost of Project, EMP
Budget and Actual Start and Expected Completion Dates.
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 18
Table 10: General Information about the Selected Sub-Projects
DIS
TRIC
T
NA
ME
OF
PR
OJE
CT
UID
PR
OJE
CT
IMP
LEM
ENTI
NG
A
GEN
CY
DP
R C
ON
SULT
AN
T
SUPE
RV
ISIO
N C
ON
SULT
AN
T
CO
NTR
AC
TOR
NA
ME
PR
OJE
CT
CO
ST
EMP
BU
DG
ET
LEN
GTH
OF
RO
AD
/BR
IDG
ES
STA
RT
DA
TE
EXP
ECTE
D C
OM
PLE
TIO
N D
ATE
AS
PER
DP
R
AS
PER
TE
ND
ER/B
ID
DO
CU
MEN
T
AS
PER
DP
R
AS
PER
TE
ND
ER/B
ID
DO
CU
MEN
T
Bridges
CHAMOLI BRIDGE OVER ALAKNANDA RIVER AT AARUDI- PATURDI
4006 PWD YOOSHIN & ICT
YONGMA ENGINEERING LTD
V K GUPTA ASSOCIATES
102,149,390 102,149,390 309,600 309,600 140 MTR
28/07/2015 27/10/2016
CHAMOLI CHEPADO BRIDGE 4004 PWD YOOSHIN & ICT
YONGMA ENGINEERING LTD
KGL INFRASTRUCTURE
56,500,000 68,202,000 NA NA 120 MTR
7/08/2015 10/07/2016
UTTARKASHI DIDSARI BRIDGE 4003 PWD YOOSHIN & ICT
YOOSHIN & STERLING V K GUPTA ASSOCIATES
99,400,000 66,400,000 75,200 75,200 100 MTR
7/01/2015 30/09/2016
Public Buildings
PAURI GARHWAL
FOOD GODOWN, SRINAGAR
7318 USIDCL TECHNICAL CONSULTANCY SERVICE
TECHNICAL CONSULTANCY SERVICES
PURNANAND VYAS
24,215,000 25,862,413 203,425 652,000 - 10/09/2015 9/12/2016
RUDRAPRAYAG GOVT INTER COLLEGE KOTGI
7308 USIDCL TECHNICAL CONSULTANCY SERVICE
USIDCL M/S SURAT SINGH & SONS
42,599,000 42,599,000 98,000 98,000 - 10/09/2015 12/09/2016
Roads
ALMORA KHUNT-ALMORA MR 1055 PWD PWD ROYAL HOSKINING DHV JAGAT SINGH KANWAL KHATYARI
10,795,000 12,463,000 386,000 303,000 11.5 24/06/2015 23/09/2016
BAGESHWAR HARINAGRI-KULAU-GWALDAM MR
1118 PWD ROYAL HOSKINING DHV
ROYAL HOSKINING DHV ANIL MALIK CONTRACTOR
95,610,000 92,930,000 692,000 844,000 16.8 14/07/2015 13/10/2016
BAGESHWAR KANDA-SANIUDIAY-RAWATSERA MR
1111 PWD PWD ROYAL HOSKINING DHV ESPAN INFRASTRUCTURE LTD
91,216,000 103,151,000 327,000 77,000 20 22/09/2014 21/12/2015
CHAMOLI SALOR - DUNGRA MR 1217 PWD SELADIA ASSOCIATES
SHELADIA ASSOCIATES RAINA CONSTRUCTION
26,628,000 26,628,000 490,700 490,000 6 8/07/2015 11/06/2016
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 19
DIS
TRIC
T
NA
ME
OF
PR
OJE
CT
UID
PR
OJE
CT
IMP
LEM
ENTI
NG
A
GEN
CY
DP
R C
ON
SULT
AN
T
SUPE
RV
ISIO
N C
ON
SULT
AN
T
CO
NTR
AC
TOR
NA
ME
PR
OJE
CT
COST
EMP
BU
DG
ET
LEN
GTH
OF
RO
AD
/BR
IDG
ES
STA
RT
DA
TE
EXP
ECTE
D C
OM
PLE
TIO
N D
ATE
AS
PER
DP
R
AS
PER
TE
ND
ER/B
ID
DO
CU
MEN
T
AS
PER
DP
R
AS
PER
TE
ND
ER/B
ID
DO
CU
MEN
T
CHAMOLI THARALI-JUNIDHAR MR 1275 PWD PWD SHELADIA ASSOCIATES SANSUN CONSTRUCTION
30,887,000 30,887,000 443,000 387,000 3.6 18/09/2015 17/12/2016
CHAMPAWAT PUNAV-SIPTY NAYARI MR 1355 PWD PWD YONGMA & STERLING PANCHGHATI CONSTRUCTION
43,047,000 46,317,000 363,000 362,000 6.2 20/08/2014 1/11/2016
DEHRADUN SAHIYA PATAN SAMALTA PANUWA MR
1577 PWD PWD EGIS GAMBHIR SINGH 58,191,000 52,221,000 NA NA 12.6 24/06/2015 23/09/2016
HARIDWAR GT ROAD TO LAVVA MR 1751 PWD PWD EGIS LINK ENTERPRISES 22,039,000 20,914,000 106,000 106,000 1.5 1/09/2014 31/12/2015
HARIDWAR RAIPUR LINK ROAD 1818 PWD PWD EGIS LINK ENTERPRISES 20,400,000 19,031,000 420,000 420,000 1.2 1/09/2014 30/11/2015
NAINITAL PADAMPURI HARAKHAN KATHGODAM MR
2004 PWD PWD ROYAL HOSKINING DHV ESPAN INFRASTRUCTURE LTD
131,040,000 140,446,000 802,000 208,000 30 20/08/2014 19/11/2015
PAURI GARHWAL
UFFALDA-DHELCHAURI MR
2270 PWD PWD EGIS DIVYA JYOTI CONSTRUCTION CO
30,988,000 32,852,000 489,000 489,000 7.5 22/06/2015 21/9/2016
PAURI GARHWAL
ARKANI-JANASU-KHANDUKHAL MR
2120 PWD PWD EGIS DIVYA JYOTI CONSTRUCTION CO
19,362,000 20,536,000 417,356 417,356 5.2 22/06/2015 21/9/2016
PITHORAGARH BADABE SELIGYA MR 2374 PWD PWD YONGMA ENGINEERING & STERLING
RAJENDRA SINGH BALDIA
27,950,000 21,412,500 346,000 346,000 10.5 22/09/2014 21/12/2015
PITHORAGARH ACHOLI JAAKH MR 2370 PWD YONGMA ENGINEERING & STERLING
YONGMA ENGINEERING & STERLING
M & P INFRASTRUCTURWE
27,218,000 27,218,000 433,000 433,000 8 8/07/2015 10/07/2016
RUDRAPRAYAG UKHIMATH MANSOONA MR
2548 PWD PWD SELADIA ASSOCIATES VIJAY BUILDERS 17,750,803 17,289,283 950,000 950,000 3 29/05/2014 28/08/2015
RUDRAPRAYAG SALYA-TULANGA MR 2519 PWD PWD SELADIA ASSOCIATES STAR CONSTRUCTION
35,157,257 41,993,259 300,000 323,000 6 8/04/2015 7/07/2016
TEHRI KEMPTI BYEPASS MR 2746 PWD PWD EGIS SHIV SHANKAR CONSTRUCTION COMPANY
27,050,000 30,332,000 66,500 66,500 5.75 10/11/2014 9/02/2016
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 20
DIS
TRIC
T
NA
ME
OF
PR
OJE
CT
UID
PR
OJE
CT
IMP
LEM
ENTI
NG
A
GEN
CY
DP
R C
ON
SULT
AN
T
SUPE
RV
ISIO
N C
ON
SULT
AN
T
CO
NTR
AC
TOR
NA
ME
PR
OJE
CT
COST
EMP
BU
DG
ET
LEN
GTH
OF
RO
AD
/BR
IDG
ES
STA
RT
DA
TE
EXP
ECTE
D C
OM
PLE
TIO
N D
ATE
AS
PER
DP
R
AS
PER
TE
ND
ER/B
ID
DO
CU
MEN
T
AS
PER
DP
R
AS
PER
TE
ND
ER/B
ID
DO
CU
MEN
T
UTTARKASHI GAGNANI MOTOR PULL TO BHANGELI MR
3151 PWD SHELADIA ASSOCIATES
SHELADIA ASSOCIATES SEEMA CONSTRUCTION
44,404,000 42,946,810 1,066,00
0 1,066,000 4.6 6/11/2015 9/10/2016
UTTARKASHI NAKURI SINGOTH MR 3183 PWD PWD SHELADIA ASSOCIATES VINOD KUMAR CHAUHAN
16,901,000 18,394,000 47,000 47,000 - 6/10/2015 9/09/2016
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 21
4. Audit Results and Findings
4.1 Compliance with ESMF
The detailed compliance requirements as per the ESMF were reviewed for each sub-project
selected as sample in first Audit cycle. Project wise compliances matrix of ESMF is presented in
Table No 10 below.
4.1.1 Statutory Clearances
EIA Clearance
None of the selected sample sub-projects require environmental clearance as per schedule
under the provisions of EIA Notification 2006. Also, none of the selected sub-projects lies in
notified Ecologically Sensitive Area and all selected sub-projects have been classified into E2
category.
Forest Clearance
Forest clearance is not required as the selected sub-projects do not require any land diversion
of protected / reserved forest.
Tree Cutting Permission
Out of the 24 selected sub-
projects for first round of audit
7 projects require Tree Cutting
Permission from Department of
Forestry.
Tree Cutting is required in the
following projects
Raipur Link Road (UID
- 1818), Haridwar – 2
trees
Tharali-Junidhar Road, (UID – 1275), Chamoli – 25 trees
Bridge over Alaknanda River at Aarudi- Paturdi (UID – 4006), Chamoli – yet to be
determined
Chepado Bridge (UID – 4004), Chamoli – yet to be determined
Didsari Bridge (UID – 4003), Uttarkashi – 2 trees
Food Godown (UID – 7318), Pauri – 4 trees
Govt. Inter College, Kotgi (UID – 7308), Rudraprayag – 1 tree
Although tree cutting permission is required for all the above mentioned projects, efforts are
being made to protect the trees on Raipur Link Road, Haridwar and Food Godown, Pauri by
2 8%
17 71%
5 21%
Status of Tree Cutting Permission in Sub-Projects
Compliance
Not Required
Non-Compliance
Figure 3: Status of Tree Cutting Permission in Sub-Projects
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 22
changing the design. In Govt. College Kotgi, the contractor has managed to save the tree from
felling by slightly changing the location of building within the premises.
Tree Cutting permission has been obtained for Food Godown, Pauri only till the time of first audit.
The letter for obtaining tree cutting permission has been submitted to the Forest Department with
a copy marked to District Magistrate for Didsari Bridge in Uttarkashi.
PIU of Raipur Link Road (UID – 1818), Tharali- Junidhar MR (UID – 1275), Bridge over Alaknanda
at Arudi-Patrudi (UID – 4006), Chepado Bridge (UID – 4004) need to initiate the process of
obtaining Tree Cutting Permission from the Forestry Department.
NoC for HMP/Batching Plant
Out of the 24 sub-projects
reviewed in first audit cycle 4
projects require setting up of Hot
Mix Plant and therefore, require
NOC from DM as well as SPCB.
Hot Mix Plants (HMP) is to be
established for packages of
following audited sub-projects
Kanda Sariudiyan
Rawatsera MR (Uid –
1111), Bageshwar
Ukhimath Mansoona MR (UID - 2548), Rudraprayag
Kempti Bypass MR (UID – 2746), Tehri
Padampuri - Herakhan - Kathgodam MR (UID – 2004), Nainital
Out of these four audited sub-
projects, Consent to Establish
(CTE) and Consent to Operate
(CTO) for none of the HMPs
were available.
Contractor on Kanda –
Sariudiyan – Rawatsera MR
project had taken a written
NoC for establishing the HMP
for the project at the location
however the CTE and CTO
from SPCB need to be
obtained.
In case of Padampuri – Herakhan - Kathgodam project the
contractor as well as supervision consultants were not aware of the
requirements of CTE and CTO from SPCB. The contractor had
obtained verbal NOC from the DM.
Both the contractor and Supervision Consultants mentioned that
the verbal NoC from DM was a sufficient authorization required to
operate the HMP.
The Audit Team during visit to the site apprised both the
contractor as well as the Supervision Consultants that the
authorization from SPCB is required in the form of CTE and CTO for
establishing and operating the HMP
Exhibit 2: Non-compliance due to lack of Awareness
0 0%
2 8.3%
2 8.3%
20 83.3%
Status of NOC for HMP in Sub-Projects
CompliancePartial ComplianceNon-ComplianceNot Required
Figure 4: Status of NoC for HMP in Reviewed Sub-Projects
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 23
All contractors who intend to establish HMP or Batching Plant need to obtain the following
documents authorizing them to establish and operate the plant – NoC from DM, CTE and CTO from
SPCB.
Storage, Handling and Transport of Hazardous Materials
None of the sub-projects selected for audit require storage, handling or transportation of
Hazardous materials hence authorization from SPCB is not required.
Location / Layout of Workers Camp
The workers camps are required in only those cases where the workers / laborers from other
place are moved in to the project location for construction related activities. Since the volume of
works in the sub-projects is quite low, the number of laborers required for construction related
activity is also not too high. On an average 20-25 workers / laborers are required in each sub-
project.
NoC from State Pollution Control Board is not required for any of the labour camps, established
in the sub-projects reviewed.
Permission for Sand Mining/Borrow Area /Aggregate
These permissions are not applicable to sub-projects selected for audit as all the contractors are
procuring construction material from government approved mines/quarries.
Supervision Consultants should ensure that the contractor submits the proof of royalty payment. A
copy of documents showing that the agency from which the aggregate and sand is procured, has a
valid license/permission, must be obtained by contractor.
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 24
Table 11: Status of Statutory Compliances in selected Road Sub-Projects
S.
No
.
Dis
tric
t
Su
b-P
roje
ct
Na
me
UID
EIA
Cle
ara
nc
e
Fo
rest
Cle
ara
nc
e
Tre
e C
utt
ing
P
erm
issi
on
No
C f
or
HM
P/
WM
M P
lan
t
Sto
rag
e /
T
ran
spo
rta
tio
n o
f H
az
. M
ate
ria
ls
No
C f
or
Wo
rke
rs
Ca
mp
No
C f
or
Dis
ch
arg
es
fro
m
La
bo
ur
Ca
mp
Sa
nd
Min
ing
P
erm
issi
on
Re
qu
ire
d
Ob
tain
ed
Re
qu
ire
d
Ob
tain
ed
Re
qu
ire
d
Ob
tain
ed
Re
qu
ire
d
Ob
tain
ed
Re
qu
ire
d
Ob
tain
ed
Re
qu
ire
d
Ob
tain
ed
Re
qu
ire
d
Ob
tain
ed
Re
qu
ire
d
Ob
tain
ed
1. CHAMOLI SALOOR DUNGRA MOTOR MARG 1217 × × × × × × × × × × × × × ×
2. CHAMOLI THARALI JUNIDHAR MOTOR MARG 1275 × × × × × × × × × × × × ×
3. DEHRADUN SAHIYA PATAN SAMALTA PANUWA MOTOR MARG
1577 × × × × × × × × × × × × × ×
4. HARIDWAR GT ROAD TO LAVVA ROAD 1751 × × × × × × × × × × × × × ×
5. HARIDWAR RAIPUR LINK ROAD 1818 × × × × × × × × × × × × ×
6. PAURI GARHWAL
UFALDA DHELCHURI MOTOR MARG 2270 × × × × × × × × × × × × × ×
7. PAURI GARHWAL
ARKANI JANASAU MOTOR MARG 2120 × × × × × × × × × × × × × ×
8. RUDRAPRAYAG UKHIMATH MANSOONA MOTOR MARG
2548 × × × × × × × × × × × × ×
9. RUDRAPRAYAG SALYA TULANGA MOTOR MARG 2519 × × × × × × × × × × × × × ×
10. TEHRI KEMPTI BYPASS MOTOR MARG 2746 × × × × × × × × × × × × × ×
11. UTTARKASHI GANGNANI MOTOR PULL TO BHANGELI MOTOR MARG
3151 × × × × × × × × × × × × × ×
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 25
S.
No
.
Dis
tric
t
Su
b-P
roje
ct
Na
me
UID
EIA
Cle
ara
nc
e
Fo
rest
Cle
ara
nc
e
Tre
e C
utt
ing
P
erm
issi
on
No
C f
or
HM
P/
WM
M P
lan
t
Sto
rag
e /
T
ran
spo
rta
tio
n o
f H
az
. M
ate
ria
ls
No
C f
or
Wo
rke
rs
Ca
mp
No
C f
or
Dis
ch
arg
es
fro
m
La
bo
ur
Ca
mp
Sa
nd
Min
ing
P
erm
issi
on
Re
qu
ire
d
Ob
tain
ed
Re
qu
ire
d
Ob
tain
ed
Re
qu
ire
d
Ob
tain
ed
Re
qu
ire
d
Ob
tain
ed
Re
qu
ire
d
Ob
tain
ed
Re
qu
ire
d
Ob
tain
ed
Re
qu
ire
d
Ob
tain
ed
Re
qu
ire
d
Ob
tain
ed
12. UTTARKASHI NAKURI SINGROTH MOTOR MARG 3183 × × × × × × × × × × × × × ×
13. ALMORA ALMORA KHUNT MOTOR MARG 1055 × × × × × × × × × × × × × ×
14. BAGESHWAR HARINAGAR KULAU GWALDAM MOTOR MARG
1118 × × × × × × × × × × × × × ×
15. BAGESHWAR KANDA SARIUDIYAN RAWATSERA MOTOR ROAD
1111 × × × × × × × × × × × × ×
16. PITHORAGARH BADABE SELIYA MOTOR MARG 2374 × × × × × × × × × × × × × ×
17. PITHORAGARH AINCHOLI JAKH MOTOR MARG 2370 × × × × × × × × × × × × ×
18. NAINITAL PADAMPURI HAIDAKHAN KATHGODAM MOTOR ROAD
2004 × × × × × × × × × × × × ×
19. CHAMPAWAT PUNAVE SIPTY MOTOR MARG 1355 × × × × × × × × × × × × × ×
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 26
Bridges
Table 12: Status of Statutory Compliances in Selected Bridge Sub-Projects S
. N
o.
Dis
tric
t
Su
b-P
roje
ct
Na
me
UID
EIA
Cle
ara
nc
e
Fo
rest
Cle
ara
nc
e
Tre
e C
utt
ing
P
erm
issi
on
No
C f
or
HM
P/
WM
M P
lan
t
Sto
rag
e /
T
ran
spo
rta
tio
n o
f H
az.
Ma
teri
als
No
C f
or
Wo
rke
rs
Ca
mp
No
C f
or
Dis
ch
arg
es
fro
m
La
bo
ur
Ca
mp
Sa
nd
Min
ing
P
erm
issi
on
Re
qu
ire
d
Ob
tain
ed
Re
qu
ire
d
Ob
tain
ed
Re
qu
ire
d
Ob
tain
ed
Re
qu
ire
d
Ob
tain
ed
Re
qu
ire
d
Ob
tain
ed
Re
qu
ire
d
Ob
tain
ed
Re
qu
ire
d
Ob
tain
ed
Re
qu
ire
d
Ob
tain
ed
1. CHAMOLI BRIDGE OVER ALAKNANDA RIVER AT AARUDI- PATURDI
4006
2. CHAMOLI CHEPADO BRIDGE 4004
3. UTTARKASHI DIDSARI BRIDGE 4003
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 27
Public Buildings
Table 13: Status of Statutory Compliances in Selected Public Building Sub-Projects S.
No
.
Dis
tric
t
Sub
-Pro
ject
Nam
e
UID
EIA
Cle
aran
ce
Fore
st C
lear
ance
Tree
Cu
ttin
g Pe
rmis
sio
n
No
C f
or
HM
P/W
MM
Pla
nt
Sto
rage
/ T
ran
spo
rtat
ion
of
Haz
. Mat
eria
ls
No
C f
or
Wor
kers
Cam
p
No
C f
or
Dis
char
ges
from
La
bo
ur
Cam
p
San
d M
inin
g Pe
rmis
sio
n
Req
uir
ed
Ob
tain
ed
Req
uir
ed
Ob
tain
ed
Req
uir
ed
Ob
tain
ed
Req
uir
ed
Ob
tain
ed
Req
uir
ed
Ob
tain
ed
Req
uir
ed
Ob
tain
ed
Req
uir
ed
Ob
tain
ed
Req
uir
ed
Ob
tain
ed
1. RUDRAPRAYAG KOTGI INTER COLLEGE 7308
2. PAURI FCI GODOWN 7318
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 28
4.2 Desk Review Findings
Prior to the initiation of field visits to the selected sub-project site the Audit team conducted a
detailed desk review of the Environmental and Social aspects of the project. During the desk
review DPR, tender documents/contract agreement, environmental monitoring reports, labour
licence and insurance were reviewed and copy of the relevant documents were collected.
The Environmental and Social Aspects analysed during the desk review are as under
Preparation of ESDS Sheets / Environmental and Social Screening Reports
Environmental Management Plan
Labour Licenses
Labour Insurance
Hot Mix Plant
o Whether required or established
o NOC from DM obtained
o CTE / CTO from SPCB obtained
Tree Cutting Permission
NOC for use of Ground / Surface / Community Water
PUC for vehicles
Procurement of construction material from Authorized Quarries – copy if royalty
paid
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 29
Table 14: E&S: Compliances and Non-Compliances - Desk Review Findings
S. N
o.
Dis
tric
t
Sub
-Pro
ject
UID
Envi
ronm
en
tal S
cree
nin
g R
epo
rts
ESD
S Sh
eets
Lab
ou
r Li
cen
se
Lab
ou
r In
sura
nce
HM
P/W
MM
Pla
nts
NO
C f
or
use
of
Gro
un
d/
Surf
ace
Wat
er
PU
C f
or V
ehic
les
Au
tho
riza
tio
n o
f Q
uar
ries
Rem
arks
Reqd. NOC CTE CTO
1. ALMORA KHUNT-ALMORA MR 1055 Y Y Y Y N NA NA NA N N Y
2. BAGESHWAR HARINAGRI-KULAU-GWALDAM MR 1118 Y N Y Y N NA NA NA N Y Y Social Screening report not available, Drum Plant will be used.
3. BAGESHWAR KANDA-SANIUDIAY-RAWATSERA MR 1111 Y Y Y Y Y Y N N Y Y Y CTE / CTO not obtained
4. CHAMOLI SALOR - DUNGRA MR 1217 Y Y N Y N NA NA NA N Y Y Procured from other plant
5. CHAMOLI THARALI-JUNIDHAR MR 1275 Y Y N N N NA NA NA N N Y Alignment not clear requires felling of 25 trees
6. CHAMOLI BRIDGE OVER ALAKNANDA RIVER AT AARUDI- PATURDI
4006 Y Y Y Y N NA NA NA N Y Y Tree cutting permission required.
7. CHAMOLI CHEPADO BRIDGE 4004 Y Y N N N NA NA NA N NA Y Tree cutting permission required. Construction not yet started
8. CHAMPAWAT PUNAV-SIPTY NAYARI MR 1355 Y Y Y Y N NA NA NA N Y Y
9. DEHRADUN SAHIYA PATAN SAMALTA PANUWA MR
1577 Y Y Y Y N NA NA NA N Y Y
10. HARIDWAR GT ROAD TO LAVVA MR 1751 Y Y Y Y N NA NA NA N Y Y
11. HARIDWAR RAIPUR LINK ROAD 1818 Y Y Y Y N NA NA NA N Y Y Efforts are being made to prevent tree cutting
12. NAINITAL PADAMPURI HARAKHAN KATHGODAM MR
2004 Y Y Y Y Y Y N N N Y Y NOC from DM required, CTE/CTO required
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 30
S. N
o.
Dis
tric
t
Sub
-Pro
ject
UID
Envi
ronm
en
tal S
cree
nin
g R
epo
rts
ESD
S Sh
eets
Lab
ou
r Li
cen
se
Lab
ou
r In
sura
nce
HM
P/W
MM
Pla
nts
NO
C f
or
use
of
Gro
un
d/
Surf
ace
Wat
er
PU
C f
or V
ehic
les
Au
tho
riza
tio
n o
f Q
uar
ries
Rem
arks
Reqd. NOC CTE CTO
13. PAURI UFFALDA-DHELCHAURI MR 2270 Y Y N Y N NA NA NA N Y Y NOC from DM required, CTE/CTO required
14. PAURI ARKANI-JANASU-KHANDUKHAL MR 2120 Y Y N Y N NA NA NA N Y Y NOC from DM required, CTE/CTO required
15. PAURI FOOD GODOWN, SRINAGAR 7318 Y Y N N N NA NA NA N Y Y Efforts are being made to prevent tree felling
16. PITHORAGARH BADABE SELIGYA MR 2374 Y Y Y Y N NA NA NA N N Y PUC for vehicles required
17. PITHORAGARH ACHOLI JAAKH MR 2370 Y Y Y Y Y N N N N N Y PUC for vehicles, CTE/CTO required
18. RUDRAPRAYAG UKHIMATH MANSOONA MR 2548 Y Y Y Y Y Y N N N Y Y
19. RUDRAPRAYAG SALYA-TULANGA MR 2519 Y Y Y Y N NA NA NA N Y Y
20. RUDRAPRAYAG GOVT INTER COLLEGE KOTGI 7308 Y Y N Y N NA NA NA Y Y Y Tree cutting permission required.
Efforts are being made to prevent tree cutting
21. TEHRI KEMPTI BYEPASS MR 2746 Y Y N N Y N N N N N Y CTE/CTO required
22. UTTARKASHI GAGNANI MOTOR PULL TO BHANGELI MR
3151 Y Y y Y N NA NA NA N N Y
23. UTTARKASHI NAKURI SINGOTH MR 3183 Y Y Y Y N NA NA NA N Y Y
24. UTTARKASHI DIDSARI BRIDGE 4003 Y Y Y Y N NA NA NA N Y Y
FULL COMPLIANCE
PARTIAL COMPLIANCE
NON-COMPLIANCE
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 31
4.2.1 Environmental and Social Data Sheets
The ESMF requires basic
environmental and social data
pertaining to the proposed sub-
project to be compiled at the field
data collection stage. For this
purpose, an Environmental and
Social Data Sheet (ESDS) and a
Socio-Economic Survey format were
formulated for sub-projects.
The sub-project Implementing
Agency (IA)/DSC fills up the ESDS
with the facilitation support of the
DPIUs duly identifying the environmental and social issues of concern. Supplementary notes on
environmental and social concerns to be added to those data sheets.
The ESDS are evaluated to prepare Environmental and Social Screening Reports included in the
DPR and / or Tender Documents for the contractor.
DPR of almost all sub-projects selected for audit contained the environmental and social screening
reports except for Harinagar – Kulau – Gwaldam (UID – 1118), Bageshwar sub-project, where
the Social Screening Report was not available in the DPR.
4.2.2 Environmental Management Plan
On the basis of ESDS a mitigation plan is prepared for environmental and social management.
However in all the audited sub-projects reviewed a generic Environment Management Plan has
been prepared and no site specific social or environmental issues were considered during the
preparation of DPR.
As a result social and environmental issues are hindering the implementation of projects
particularly in case of Bridges. Sub-projects and related social and environmental issues are
presented in table below
23 96%
1 4%
Status of E&S Screening Reports in Reviewed DPR
Compliance
Partial Compliance
Figure 5: Status of E&S Screening in Reviewed DPR
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 32
Revise the EMP – Account for Site Specific Issues
It would be very helpful for the PMU if the Supervision Consultants are advised to update the EMP in
taking into account the site specific social and environmental aspects for each of the sub-project. Some
of the points that must be remembered while suggesting the revision of EMP are
Sub-Projects where progress is 50% or less may be taken up for revision of EMP.
EMP may be revised in a time bound manner using the existing resources.
Exhibit 3: Revise the EMP
Table 15: Major Social and Environmental Concerns Identified
4.2.3 Labour Licence
Out of the 24 sub-projects reviewed
during the first audit cycle 8 sub-projects
did not have the labour licence. These
sub-projects are
Salor – Dungra MR (UID – 1217),
Chamoli
Tharali – Junidhar MR (UID –
1275), Chamoli
Chepado Bridge (UID – 4004),
Chamoli
Uffalda - Dhelchauri MR (UID – 2270), Pauri
Arkani – Janasu – Khandukhal MR (UID – 2120), Pauri
District Sub-Project UID
LA Requirement
(sq. m.) PAFs Tree
Cutting Pole
Shifting
Govt. Private
Chamoli Tharali – Junidhar MR 1275 - - - 25 -
Chamoli Bridge over Alaknanda River at Aarudi- Paturdi 4006 3000 1640 6 * -
Chamoli Chepado Bridge 4004 * * * * *
Dehradun Sahiya Patan Samalta Panuwa MR 1577 - - - - 2
Haridwar Raipur Link Road 1818 - - - 2 4
Pauri Food Godown 7318 2000 - - 4 1
Rudraprayag Govt. Inter College, Kotgi 7308 - - - 1 1
Uttarkashi Didsari Bridge 4003 - 5070 6 2 -
* not yet identified
16 67%
2 8%
6 25%
Status of Labour Licence in Reviewed Sub - Projects
Compliance
Partial Compliance
Non-Compliance
Figure 6: Status of Labour License in Reviewed Sub-Projects
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 33
Kempti Bypass MR (UID -2746), Tehri
Food Godown, Srinagar (UID – 7318), Pauri
Govt. Inter College, Kotgi (UID – 7308), Rudraprayag
Labour Licence for Public Building Projects could not be obtained as the concerned PIU is not
yet registered with the Office of Labour Commissioner. The process of registration has been
initiated by the PIU in coordination with the PMU.
DSC must ensure that the contractors of all the sub-projects obtain the labour licence for the
requisite number of labours deployed in the sub-project / package. A copy of the labour licence
must be submitted to the DSC and PIU for records.
4.2.4 Labour Insurance
Labour Insurance is required in all
sub-projects where labour whether
local or migrant is engaged in
construction activities. Contractor
must obtain insurance of its
laborers so as to ensure that
adequate financial provisions are
available in case of any injuries
during accident or emergency.
Out of the 24 sub-projects
reviewed contractors of following
four sub-projects have not
obtained Labour Insurance.
Tharali – Junidhar MR (UID – 1275), Chamoli
Chepado Bridge (UID - 4004), Chamoli
Food Godown, Srinagar (UID – 7318), Pauri
Kempti Bypass MR (UID – 2746), Pauri
DSC must ensure that Contractors of all sub-projects obtain labour insurance for adequate number
of its staff and labourers engaged in construction related activities. A copy of the insurance must
be made available to the PIU and DSC office for records.
4.2.5 NoC for Hot Mix Plants
NoC from DM as well as SPCB is required wherever Hot Mix Plants are to be established. The
details and status of NOC is presented in Section 4.1.1: Statutory Clearances/ NoC for
HMP/Batching Plant
20 83%
4 17%
Status of Labour Insurance in Reviewed Sub-Projects
Compliance
Non Compliance
Figure 7: Status of Labour Insurance in Reviewed Sub-Projects
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 34
4.2.6 NoC for Construction Water
Water for Construction or sprinkling is sourced either from ground water sources –
pumps/tube wells or surface water sources – river / drain / canal or community water sources
– public taps, community wells etc.
In most of the cases, contractors of sub-projects reviewed are obtaining construction water
from community sources and therefore require a NoC from the village head or Sarpanch or local
community leader.
In almost all the 24 sub-projects
reviewed during first audit cycle, the
contractor has informed the sarpanch
as wells as the community members
about the project however NoC for
construction water is obtained by the
contractors of following 2 projects
only
Kanda-Saniudiay-Rawatsera
MR (UID – 1111), Bagheshwar
Govt. Inter College, Kotgi (UID
– 7308), Rudraprayag.
DSC of all sub-projects must ensure that the contractor has adequately informed the sarpanch or
village head or local community leader and a copy of the same must be maintained at the PIU and
office of DSC for records.
4.2.7 PUC for Construction Vehicles
All construction vehicles must
comply with the existing emission
norms defined by Central Pollution
Control Board (CPCB). Contractors
of all sub-projects must ensure that
a valid PUC certificate is obtained
for all construction vehicles used,
during entire phase of construction
activity.
Out of the 24 sub-projects reviewed
during the first audit cycle the PUC
for construction vehicle was not
available at the time of review in following 7 sub-projects
17 71%
7 29%
Status of PUC in Reviewed Sub-Projects
Compliance
Non Compliance
Figure 9: Status of PUC for Construction Vehicles
2 8%
22 92%
Status of NoC for Water in Reviewed Sub-Projects
Compliance
Non Compliance
Figure 8: Status of NoC for Construction Water
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 35
Khunt – Almora MR (UID – 1055), Almora
Tharali – Junidhar MR (UID – 1275), Chamoli
Badabe – Silingiya MR (UID – 2374), Pithoragarh
Acholi – Jakh MR (UID – 2370), Pithoragarh
Kempti Byepass MR (UID – 2746), Tehri
Gagnani Motor Pull to Bhangeli MR (UID – 3151), Uttarkashi
Chepado Bridge (UID – 4004), Chamoli
The contractors of sub-projects in Pithoragarh claimed that there is no operational Pollution
Certification center hence they are unable to obtain the PUC for their vehicles.
DSC must ensure that the contractors of all sub-projects obtain PUC for all construction vehicles
engaged in construction activity. DSC must maintain a sub-project wise record of list of vehicles
used, registration number, details of PUC along with the expiry date so that the contractors may be
informed for renewal prior to expiry of expiry of PUC.
4.2.8 Authorization of Quarries
Contractor shall procure construction material only from permitted sites and licensed / authorized
quarries.
In all the sub-projects reviewed during first audit cycle the contractors are procuring the construction
material from authorized quarries and a copy of royalty paid is submitted to the PIU.
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 36
4.3 Site Visit Findings
The Audit team after conducting detailed review of documents and interviews with the PIU
officials and other concerned staff of the Design Supervision Consultants (DSC) and Contractor
visited the project sites to review the actual implementation of EMP and SMP as mentioned in
the ESDS / Screening Reports and verify its compliance on-site.
The detailed list of parameters assessed during the site visits are as under
Health and Safety Issues
o EHS Awareness or Training Programs imparted by the contractor/DSC
o First Aid Kit
o Personal Protect Equipment (PPE)
o Safety and information Sign Boards
Labour Camps and Facilities Provided
o Type of labour camp – Rented or Constructed
o Road Accessibility to Labour Camp
o No. of Labour
o Labour Staying in Camps
o No. of Women Labour
o Sanitation Facilities Provided
o Potable Water Source and Storage
o Solid Waste Disposal Arrangements
o Electrification
Environmental Management Plan Implementation
o Compensatory / Road Side Tree Plantation
o Noise Barrier
o Dust Suppression
o Road User and Workers Safety
o Project Information Sign Boards
o Muck Disposal Sites
o Clearance or Grubbing of Site Disposal
Environmental Monitoring
o Air
o Water (both surface and ground water)
o Soil
o Noise
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 37
4.3.1 Health / Safety and PPE
Table 16: Site Visit Findings – Health / Safety Issues and Use of PPE S.
NO
.
DIS
TRIC
T
SUB
-PR
OJE
CT
UID
EHS
AW
AR
ENES
S P
RO
GR
AM
FIR
ST A
ID K
IT
PPE
SAFE
TY S
IGN
*
REMARKS
HA
RD
HA
TS
REF
LEC
TIV
E JA
CK
ETS
SAFE
TY S
HO
ES
SAFE
TY
GO
GG
LES
SAFE
TY B
ELTS
HA
ND
GLO
VES
NO
SE M
ASK
1. ALMORA KHUNT-ALMORA MR 1055 N N N Y N NR NR NR NR N
Workers not provided safety shoes and hard hats
Arrangement of First Aid Box
2. BAGESHWAR HARINAGRI-KULAU-GWALDAM MR
1118 N Y Y Y N NR NR NR NR N Workers not using safety shoes
3. BAGESHWAR KANDA-SANIUDIAY-RAWATSERA MR
1111 N Y N N N NR NR NR NR N Workers not using any of PPE
Worker handling hot-mix wearing slippers
4. CHAMOLI SALOR - DUNGRA MR 1217 N Y Y N N NR NR N NR N Workers not wearing jackets and shoes
5. CHAMOLI THARALI-JUNIDHAR MR 1275 N N NA NA NA NR NR NR NR N Construction work stalled
6. CHAMOLI BRIDGE OVER ALAKNANDA RIVER AT AARUDI- PATURDI
4006 N Y Y Y N NR NR NR NR N No construction work
Workers not wearing safety shoes
7. CHAMOLI CHEPADO BRIDGE 4004 N N NA NA NA NR NR NR NR N Construction work not yet started
8. CHAMPAWAT PUNAV-SIPTY NAYARI MR 1355 N Y Y Y Y NR NR NR NR Y Workers using proper PPE
9. DEHRADUN SAHIYA PATAN SAMALTA PANUWA MR
1577 N N Y Y N NR NR NR NR N Workers not using safety shoes
Arrangement of First Aid Box
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 38
S. N
O.
DIS
TRIC
T
SUB
-PR
OJE
CT
UID
EHS
AW
AR
ENES
S P
RO
GR
AM
FIR
ST A
ID K
IT
PPE
SAFE
TY S
IGN
*
REMARKS
HA
RD
HA
TS
REF
LEC
TIV
E JA
CK
ETS
SAFE
TY S
HO
ES
SAFE
TY
GO
GG
LES
SAFE
TY B
ELTS
HA
ND
GLO
VES
NO
SE M
ASK
10. HARIDWAR GT ROAD TO LAVVA MR 1751 N NA NA NA NA NR NR NR NR NA Construction work completed
11. HARIDWAR RAIPUR LINK ROAD 1818 N N Y Y N NR NR NR NR Y Workers should use PPE
First Aid Box need to be maintained
12. NAINITAL PADAMPURI HARAKHAN KATHGODAM MR
2004 N N Y Y Y NR NR N NR N Workers using proper PPE
13. PAURI UFFALDA-DHELCHAURI MR 2270 N Y Y Y Y NR NR NR NR Y Proper use of PPE observed
14. PAURI ARKANI-JANASU-KHANDUKHAL MR
2120 N Y Y Y N NR NR NR NR Y Workers not using safety shoes
15. PAURI FOOD GODOWN, SRINAGAR
7318 N Y Y Y Y NR NR NR NR Y Proper use of PPE observed
16. PITHORAGARH BADABE SELIGYA MR 2374 N Y Y Y N NR NR NR NR Y Workers not wearing safety shoes
17. PITHORAGARH ACHOLI JAAKH MR 2370 N Y N Y N NR NR NR NR N Workers not wearing hard hats and safety shoes
18. RUDRAPRAYAG UKHIMATH MANSOONA MR
2548 N N NA N NA NR NR NR NR N Workers not using any PPE
Arrangement for First Aid Kit
19. RUDRAPRAYAG SALYA-TULANGA MR 2519 N Y Y Y N NR NR NR NR Y Workers not wearing safety shoes
20. RUDRAPRAYAG GOVT INTER COLLEGE KOTGI
7308 N Y Y Y Y NR NR Y NR Y Proper use of PPE observed
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 39
S. N
O.
DIS
TRIC
T
SUB
-PR
OJE
CT
UID
EHS
AW
AR
ENES
S P
RO
GR
AM
FIR
ST A
ID K
IT
PPE
SAFE
TY S
IGN
*
REMARKS
HA
RD
HA
TS
REF
LEC
TIV
E JA
CK
ETS
SAFE
TY S
HO
ES
SAFE
TY
GO
GG
LES
SAFE
TY B
ELTS
HA
ND
GLO
VES
NO
SE M
ASK
21. TEHRI KEMPTI BYEPASS MR 2746 N N N N N NR NR NR NR N Workers not provided Boots
First Aid Kit need to be maintained
22. UTTARKASHI GAGNANI MOTOR PULL TO BHANGELI MR
3151 N N Y Y N NR NR N NR N Complete use of PPE
Arrangement of First aid box
23. UTTARKASHI NAKURI SINGOTH MR 3183 N NA NA NA NA NR NR NR NR N Construction Work completed
24. UTTARKASHI DIDSARI BRIDGE 4003 N N Y Y N NR N N NR N Workers not wearing safety shoes
Arrangement of First Aid Box
* Mostly carried out after completion of Construction activities
NR – Not Required
N – Required but not done or not complied
Y – Required and done or complied
NA – Not Applicable
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 40
EHS Awareness Program
Training of workers on Health and Safety issues is to be undertaken by the contractors of all sub-projects
as per the contractual requirements. No EHS Awareness program was conducted by the contractor in any
of the sub-projects reviewed during first audit cycle.
DSC must ensure that the contractor of all sub-projects must organize EHS Awareness and training program
on quarterly basis. The contractor should inform the DSC as well as the PIU about the training program and
a report detailing out the topics discussed, queries raised by the trainees, photographs of the session and
attendance list must be prepared and submitted to the DSC as well as the PIU.
First Aid Kit
First Aid Kit is required in all projects
where any construction activity is
undertaken. Contractors of all sub-
projects should maintain a proper First
Aid Kit at the project site – one at the
construction camp, adequate
arrangements on site where construction
activity is underway.
Out of the 24 sub-projects reviewed
during the first audit cycle contractors of
almost 50% of the projects did not have
first aid kit in place. These projects are
Khunt – Almora MR (UID – 1055), Almora
Tharali – Junidhar MR (UID – 1275), Chamoli
Chepado Bridge (UID – 4004), Chamoli
Sahiya – Patan – Samalta – Panuwa MR (UID – 1577), Dehradun
Raipur Link Road (UID – 1818), Haridwar
Padampuri – Herakhan – Kathgodam MR (UID – 2004), Nainital
Ukhimath Mansoona MR (UID – 2548), Rudraprayag
Kempti Byepass MR (UID – 2746), Tehri
Gagnani Motor Pull to Bhangeli MR (UID – 3151), Uttarkashi
Didsari Bridge (UID – 4003), Uttarkashi
12 50%
10 42%
2 8%
Status of Availability of First Aid Kit in Reviewed Sub-Projects
Compliance
Non Compliance
Project Completed
Figure 10: Status of Availability of First Aid Kit
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 41
Personal Protection Equipment
The Contractor is required to comply with
all the precautions as required for the safety
of workers as per the International Labour
Organization (ILO) Convention No. 62.
Contractors should supply all necessary
safety appliances such as safety goggles,
helmets, masks, etc., to the workers and
staff.
However in the reviewed sub-projects most
of the contractors as well as the staff were
ignorant of the safety issues. In several
cases the contractor had not provided the
safety equipment like boots and gloves to the staff as well as laborers. In some cases where the protection
equipment had been provided, the workers were ignorant and were not using them while engaged in
construction activities.
On the site of Hot Mix Plant of Kanda – Saniudiay –
Rawatsera MR (UID – 1111), Bageshwar, a worker
was found handling the hot-mix in slippers as seen in
Picture 1.
The ESA team found that the workers on following
four projects were using the complete set of PPE.
Punave – Sipty – Nyari MR (UID – 1355),
Champawat
Uffalda – Dhelchauri MR (UID – 2270), Pauri
Food Godown, Srinagar (UID – 7318), Pauri
Govt. Inter College, Kotgi (UID – 7308), Rudraprayag
DSC must ensure that the contractors of all sub-projects provide adequate PPE to its staff and laborers. A
record of the same may be maintained. Any non-compliance observed during the site inspections may be
noted and the contractor be advised to comply with immediate effect.
Picture 1: Worker handling Hot-Mix in slippers
4 17%
17 71%
3 12%
Status of Use of PPE in Reviewed Sub-Projects
Compliance
Non Compliance
Not required
Figure 11: Status of Use of PPE
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 42
Safety Sign
Safety Sign must be displayed at all
places where construction activity is
underway. Contractor must ensure that
caution tape is used at locations
wherever construction activity is taking
place.
Out of the 24 projects reviewed during
first audit cycle contractors only in
following 8 sub-projects had displayed
safety signs.
Punave – Sipty – Nyari MR (UID
– 1355), Champawat
Raipur Link Road (UID – 1818),
Haridwar
Uffalda – Dhelchauri MR (UID –
2270), Pauri
Arkani – Janasu MR (UID –
2120), Pauri
Food Godown, Kotgi (UID –
7318), Pauri
Badabe – Silingiya MR (UID
2374), Pithoragarh
Salya – Tulanga MR (UID –
2519), Rudraprayag
Govt. Inter College (UID –
7308), Rudraprayag
Contractors should use proper safety signs at construction sites to in order to ensure safety of workers as
well as road users. DSC must ensure that the contractor displays safety sign near schools, hospitals,
residential buildings and other noise sensitive receptors.
8 33%
16 67%
Status of Safety Signs in Reviewed Sub-Projects
Compliance
Non Compliance
Figure 12: Status of Safety Signs
Picture 2: Safety Sign Displayed on Badabe-Silingiya MR
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 43
4.3.2 Labour Camps
Table 17: Labour Camps and Facilities Provided S.
NO
.
DIS
TRIC
T/B
LOC
K
SUB
-PR
OJE
CT
NA
ME
UID
NO
OF
LAB
OU
R
EMP
LOYE
D
NO
OF
WO
MEN
LA
BO
UR
NO
OF
LAB
OU
R
STA
YIN
G IN
CA
MP
LAB
OR
CA
MP
No
C f
rom
Sar
pan
ch
REN
T A
GR
EEM
ENT
AC
CES
SEB
ILIT
Y T
O
RO
AD
SAN
ITA
TIO
N
PO
TAB
LE W
ATE
R
SOLI
D W
AST
E D
ISP
OSA
L
LIG
HTE
NIN
G
1. ALMORA KHUNT-ALMORA MR 1055 50 4 0 NR NA NA NA NA NA NA NA
2. BAGESHWAR HARINAGRI-KULAU-GWALDAM MR 1118 40 0 35 RENTED N Y OK GOOD GOOD GOOD GOOD
3. BAGESHWAR KANDA-SANIUDIAY-RAWATSERA MR 1111 15 3 0 RENTED Y Y OK GOOD GOOD GOOD GOOD
4. CHAMOLI BRIDGE OVER ALAKNANDA RIVER AT AARUDI- PATURDI
4006 10 0 10 RENTED N Y OK GOOD GOOD GOOD GOOD
5. CHAMOLI CHEPADO BRIDGE 4004 10 0 10 RENTED N Y OK GOOD GOOD GOOD GOOD
6. CHAMOLI SALOR - DUNGRA MR 1217 80 6 80 RENTED N Y POOR POOR GOOD POOR GOOD
7. CHAMOLI THARALI-JUNIDHAR MR 1275 25 0 25 RENTED N N PROJECT ROAD GOOD GOOD GOOD GOOD
8. CHAMPAWAT PUNAV-SIPTY NAYARI MR 1355 10 0 10 RENTED N Y OK GOOD GOOD GOOD GOOD
9. DEHRADUN SAHIYA PATAN SAMALTA PANUWA MR 1577 40 0 10 RENTED N N CONNECTED WITH
MAIN ROAD POOR POOR POOR POOR
10. HARIDWAR GT ROAD TO LAVVA MR 1751 20 0 0 NR NA NA NA NA NA NA NA
11. HARIDWAR RAIPUR LINK ROAD 1818 20 0 0 NR NA NA NA NA NA NA NA
12. NAINITAL PADAMPURI HARAKHAN KATHGODAM MR
2004 90 10 40 RENTED N Y OK GOOD GOOD GOOD POOR
13. PAURI ARKANI-JANASU-KHANDUKHAL MR 2120 20 0 10 RENTED N Y CONNECTED WITH
MAIN ROAD GOOD GOOD GOOD GOOD
14. PAURI FOOD GODOWN, SRINAGAR 7318 25 2 25 CONSTRUCTED N NR CONNECTED GOOD GOOD GOOD GOOD
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 44
S. N
O.
DIS
TRIC
T/B
LOC
K
SUB
-PR
OJE
CT
NA
ME
UID
NO
OF
LAB
OU
R
EMP
LOYE
D
NO
OF
WO
MEN
LA
BO
UR
NO
OF
LAB
OU
R
STA
YIN
G IN
CA
MP
LAB
OR
CA
MP
No
C f
rom
Sar
pan
ch
REN
T A
GR
EEM
ENT
AC
CES
SEB
ILIT
Y T
O
RO
AD
SAN
ITA
TIO
N
PO
TAB
LE W
ATE
R
SOLI
D W
AST
E D
ISP
OSA
L
LIG
HTE
NIN
G
15. PAURI UFFALDA-DHELCHAURI MR 2270 30 0 10 RENTED N Y CONNECTED WITH
MAIN ROAD GOOD GOOD GOOD GOOD
16. PITHORAGARH ACHOLI JAAKH MR 2370 35 0 0 NR NA NA NA NA NA NA NA
17. PITHORAGARH BADABE SELIGYA MR 2374 70 0 70 RENTED N Y On ROAD GOOD GOOD GOOD GOOD
18. RUDRAPRAYAG GOVT INTER COLLEGE KOTGI 7308 25 5 25 CONSTRUCTED Y NA VILLAGE ROAD GOOD GOOD GOOD GOOD
19. RUDRAPRAYAG SALYA-TULANGA MR 2519 35 0 10 RENTED N Y ON PROJECT ROAD GOOD GOOD GOOD GOOD
20. RUDRAPRAYAG UKHIMATH-MANSOONA MR 2548 8 0 0 NR NA NA NA NA NA NA NA
21. TEHRI KEMPTI BYEPASS MR 2746 30 0 20 CONSTRUCTED N NR CONNECTED POOR POOR POOR POOR
22. UTTARKASHI DIDSARI BRIDGE 4003 15 3 15 CONSTRUCTED N NR CONNECTED POOR GOOD POOR GOOD
23. UTTARKASHI GAGNANI MOTOR PULL TO BHANGELI MR
3151 20 2 10 CONSTRUCTED N NR CONNECTED POOR GOOD GOOD POOR
24. UTTARKASHI NAKURI-SIGOTH MR 3183 15 0 0 NR NA NA NA NA NA NA NA
NR – Not Required Y – Required and done or complied
N – Required but not done or not complied NA – Not Applicable
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 45
Construction / Labour Camps
Movement of migrant labours to the
project site may lead to interaction of
labour with the community members /
village people in different ways.
These workers use community resources
– hand pumps, public taps etc., as source
for potable water.
In order to avoid any representation /
conflict / resistance from the community
members, the contractors should inform
the sarpanch or local head of the village or community about the project and obtain a written NoC from the
village head or sarpanch for establishment of labour camp and use of community water resources.
Though not a mandatory requirement it will be a safeguard for the contractor and deployed laborers.
In most of the cases rented accommodation is arranged by the contractors with adequate facilities.
However in a few cases labor camps had to be constructed as temporary shelter for the migrating
workers. Labour camps have been
constructed in the following 5 sub-
projects
Gagnani Motor Pull to Bhangeli MR (UID – 3151), Uttarkashi
Didsari Bridge (UID – 4003), Uttarkashi
Kempty By-Pass (UID – 2746), Tehri
Food Godown, Srinagar (UID – 7318), Pauri
Govt. Inter College, Kotgi (UID – 7308), Rudraprayag
Contractors of none of the sub-projects
had obtained the written NoC from the sarpanch of the nearest village or community head, for
establishment of labour camp and use of community water resources except following two sub-projects
Kanda – Sanudiay – Rawatsera MR (UID – 1111), Bageshwar
Govt. Inter College, Kotgi (UID – 7308), Rudraprayag
Rent Agreement for rented labor camps in following sub-projects was not available for
Tharali – Junidhar MR (UID -1275), Chamoli
Sahiya – Patan – Samalta MR (UID-1577), Dehradun
13 54%
5 21%
6 25%
Labour Camps in Reviewed Sub-Projects
Rented
Constructed
Not Required
Figure 13: Labour Camps in Reviewed Sub-Projects
2 8%
6 25%
16 67%
Status of NoC for Labour Camps in Reviewed Sub-Projects
Compliance
Not Required
Non-Compliance
Figure 14: Status of NoC for Labour Camps
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 46
Rent Agreement for rented labor camps was available for following 11 sub-projects
Harinagar – Kulaun MR (UID - 1118), Bageshwar
Bridge over Alaknanda at Arudi-Patrudi (UID - 4006), Chamoli
Chepado Bridge (UID – 4004), Chamoli
Salor-Dungra MR (UID – 1217), Chamoli
Badabe – Silingiya MR (UID - 2374), Pithoragarh
Punave-Sipty MR (UID - 1355), Champawat
Padampuri-Herakhan-Kathgodam MR (UID - 2004), Nainital
Uffalda-Dhelchauri MR (UID - 2270), Pauri
Arkani-Janasu MR (UID - 2120), Pauri
Badabe-Singiya MR (UID - 2374), Pithoragarh
Kanda-Simidiyan-Rawatsera MR (UID – 1111), Bageshwar
Rent Agreement or NoC is not required in case of following sub-projects
Completed projects
GT Road to Lavva MR (UID - 1751), Haridwar
Ukhimath-Mansoona MR (UID – 2548), Rudraprayag
Nakuri – Singoth MR (UID – 3183), Uttarkashi
Local Labor
Almora-Khunt MR (UID – 1055), Almora
Raipur Link Road (UID – 1818), Haridwar
Acholi Jakh MR (UID – 2370), Pithoragarh
The supervision consultants should ensure that the contractors constructing the labour camps must have a
written NOC from the village sarpanch (land owner in case
of private land) of the nearest village for establishing the
labour camp and use of community water resources and
those contractors using the rented accommodation should
have a proper rent agreement.
Facilities in Labour Camps
The contractor should provide following facilities in the
labour / construction camp for all workers employed by
him, free of cost, for the entire duration of construction
11 46%
11 46%
2 8%
Status of Rent Agreement for Labour Camps in Reviewed Sub-Projects
Compliance
Not Required
Non-Compliance
Figure 15: Status of Rent Agreement for Labour Camps
Picture 3: Fire Fighting Facilities in Construction Camp at Didsari Bridge
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 47
work:
Adequate Accommodation
Provision and storage of potable drinking water
Adequate sanitation facilities for both male and female workers
Arrangement for waste disposal
First Aid Facilities
Fire Fighting Arrangement
Electrification
Proper Access to site
Out of the 24 sub-projects reviewed during first audit cycle the facilities
provided in construction camps were found to be satisfactory in 12 sub-
projects and partially satisfactory in following 4 projects
Salor Dungra MR (UID – 1217), Chamoli
Padampuri-Herakhan-Kathgodam MR (UID – 2004), Nainital
Didsari Bridge (UID – 4003), Uttarkashi
Gagnani Motor Pull to Bhangeli MR (UID – 3151), Uttarkashi
Facilities provided in following 2 sub-projects were not satisfactory
Sahiya – Patan – Samalta –
Panuwa MR (UID – 1577),
Dehradun
Kempti Byepass MR (UID – 2746),
Tehri
12 50%
4 17% 2
8%
6 25%
Status of Facilities in Labour Camps in Reviewed Sub-Projects
SatisfactoryPartially SatisfactoryNot-SatisfactoryNot Required
Figure 16: Status of Facilities Provided in Labour Camps
Picture 4: Adequate Arrangements for workers in Construction camp
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 48
4.3.3 On-Site EMP Implementation
Table 18: On-Site Environmental Management Plan Implementation
SR NO
DISTRICT PROJECT NAME UID
CO
MPE
NSA
TOR
Y/
RO
AD
SID
E P
LAN
TATI
ON
NO
ISE
BA
RR
IER
DU
ST
SUP
PR
ESSI
ON
RO
AD
USE
R &
W
OR
KER
SA
FETY
PR
OJE
CT
INFO
RM
ATI
ON
SI
GN
MU
CK
DIS
PO
SAL
SITE
SITE
CLE
AR
AN
CE O
R G
RU
BB
ING
AS
PER
DP
R
AC
TUA
L
AS
PER
DP
R
AC
TUA
L
AS
PER
DP
R
AC
TUA
L
AS
PER
DP
R
AC
TUA
L
AS
PER
DP
R
AC
TUA
L
IDE
NTI
FIED
No
C
1 ALMORA KHUNT-ALMORA MR 1055 NR NA NR NA R N R N R Y NR NR NR
2 BAGESHWAR HARINAGRI-KULAU-GWALDAM MR 1118 NR NA R N R N R N R Y NR NR Y
3 BAGESHWAR KANDA-SANIUDIAY-RAWATSERA MR 1111 NR NA R N R N R N R Y N N Y
4 CHAMOLI SALOR - DUNGRA MR 1217 NR NA NR NA R N R N R N Y N N
5 CHAMOLI THARALI-JUNIDHAR MR 1275 NR NA NR NA R N R N R N Y N Y
6 CHAMOLI BRIDGE OVER ALAKNANDA RIVER AT AARUDI- PATURDI
4006 NR NA NR NA NR NA R N R Y NR NR Y
7 CHAMOLI CHEPADO BRIDGE 4004 NR NA NR NA NR NA R N R N NR NR NA
8 CHAMPAWAT PUNAV-SIPTY NAYARI MR 1355 NR NA NR NA R N R Y R Y Y N Y
9 DEHRADUN SAHIYA PATAN SAMALTA PANUWA MR
1577 NR NA NR NA R N R N R Y Y N N
10 HARIDWAR GT ROAD TO LAVVA MR** 1751 NR NA NR NA R Y R Y R Y NR NR NR
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 49
SR NO
DISTRICT PROJECT NAME UID
CO
MPE
NSA
TOR
Y/
RO
AD
SID
E P
LAN
TATI
ON
NO
ISE
BA
RR
IER
DU
ST
SUP
PR
ESSI
ON
RO
AD
USE
R &
W
OR
KER
SA
FETY
PR
OJE
CT
INFO
RM
ATI
ON
SI
GN
MU
CK
DIS
PO
SAL
SITE
SITE
CLE
AR
AN
CE O
R G
RU
BB
ING
AS
PER
DP
R
AC
TUA
L
AS
PER
DP
R
AC
TUA
L
AS
PER
DP
R
AC
TUA
L
AS
PER
DP
R
AC
TUA
L
AS
PER
DP
R
AC
TUA
L
IDE
NTI
FIED
No
C
11 HARIDWAR RAIPUR LINK ROAD 1818 NR NA NR NA R Y R Y R Y NR NR Y
12 NAINITAL PADAMPURI HARAKHAN KATHGODAM MR
2004 NR NA R N R N R N R Y N N N
13 PAURI UFFALDA-DHELCHAURI MR 2270 NR NA R N R Y R Y R Y Y N Y
14 PAURI ARKANI-JANASU-KHANDUKHAL MR 2120 NR NA NR NA R Y R Y R Y Y N Y
15 PAURI FOOD GODOWN, SRINAGAR 7318 R N* NR NA R Y R Y R N NR NR NR
16 PITHORAGARH BADABE SELIGYA MR 2374 NR NA NR NA R Y R Y R Y Y N Y
17 PITHORAGARH ACHOLI JAAKH MR 2370 NR NA NR NA R N R N R Y N N y
18 RUDRAPRAYAG UKHIMATH MANSOONA MR** 2548 NR NA NR NA R NA R N R Y NR NR Y
19 RUDRAPRAYAG SALYA-TULANGA MR 2519 NR NA NR NA R Y R Y R Y Y N Y
20 RUDRAPRAYAG GOVT INTER COLLEGE KOTGI 7308 R N* R N R Y R Y R N Y N Y
21 TEHRI KEMPTI BYEPASS MR** 2746 NR NA R N R NA R NA R Y N N N
22 UTTARKASHI GAGNANI MOTOR PULL TO 3151 NR NA NR NA R Y R Y R Y Y NR Y
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 50
SR NO
DISTRICT PROJECT NAME UID
CO
MPE
NSA
TOR
Y/
RO
AD
SID
E P
LAN
TATI
ON
NO
ISE
BA
RR
IER
DU
ST
SUP
PR
ESSI
ON
RO
AD
USE
R &
W
OR
KER
SA
FETY
PR
OJE
CT
INFO
RM
ATI
ON
SI
GN
MU
CK
DIS
PO
SAL
SITE
SITE
CLE
AR
AN
CE O
R G
RU
BB
ING
AS
PER
DP
R
AC
TUA
L
AS
PER
DP
R
AC
TUA
L
AS
PER
DP
R
AC
TUA
L
AS
PER
DP
R
AC
TUA
L
AS
PER
DP
R
AC
TUA
L
IDE
NTI
FIED
No
C
BHANGELI MR
23 UTTARKASHI NAKURI SINGOTH MR 3183 NR NA NR NA R Y R Y R Y NR NR Y
24 UTTARKASHI DIDSARI BRIDGE 4003 NR NA NR NA R N R Y R Y N N Y
* after completion of construction activities
** Construction activities completed
NR – Not Required
N – Required but not done or not complied
Y – Required and done or complied
NA – Not Applicable
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 51
Compensatory / Road Side Plantation
Compensatory or road side plantation is
required where ever tree cutting is
necessary to clear the site for
construction activities. As per the
recommendations in ESMF, “Trees felled
will be replaced as per the compensatory
afforestation criteria in accordance with
the Forest (Conservation) Act, 1980. Two
trees will be planted for every tree lost
along the sub-project roads”
Out of the reviewed 24 sub-projects there
is a provision of compensatory plantation
in DPR of both Public Building Projects. While tree cutting is required on two road projects and three
bridge projects there is no provision of compensatory plantation on these projects in DPR.
Sub-Projects where plantation whether compensatory or for improving aesthetics is required are
Tharali – Junidhar MR (UID – 1275), Chamoli
Bridge over Alaknanda River at Arudi – Patrudi (UID – 4006), Chamoli
Chepado Bridge (UID – 4004), Chamoli
Raipur Link Road (UID – 1818), Haridwar
Food Godown, Srinagar (UID – 7318), Pauri
Govt. Inter College, Kotgi (UID – 7308), Rudraprayag
Didsari Bridge (UID – 4003), Uttarkashi
PIU must ensure that wherever tree cutting is required, provision of compensatory or road side plantation is
made.
Noise Barrier
Noise barrier is required near residential
buildings and noise sensitive receptors
(schools, hospitals, religious places).
There is a provision of noise barrier in 6
sub-projects reviewed during first audit
cycle. None of these sub-projects have
noise barriers installed. These sub-
projects are
2 8%
17 71%
5 21%
Status of Compensatory Plantation in Reviewed Sub-Projects
Provision
Not Required
No Provision
Figure 17: Status of Compensatory Plantation
5 21%
1 4%
18 75%
Status of Noise Barrier in Reviewed Sub-Projects
Provisions
No Provision
Not Required
Figure 18: Status of Noise Barrier
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 52
Harinagar – Kualau – Gwaldam MR (UID – 1118), Bageshwar
Kanda – Saniudiay – Rawatsera MR (UID – 1111), Bageshwar
Padampuri – Herakhan – Kathgodam MR (UID – 2004), Nainital
Uffalda – Dhelchauri MR (UID – 2270), Pauri
Govt. Inter College, Kotgi (UID – 7308), Rudraprayag
Apart from the above sub-projects noise barriers are also required on Acholi – Jakh MR (UID – 2370),
Pithoragarh where there are two schools adjacent to the road being constructed.
Dust Suppression
As per the provisions in ESMF “Unpaved
haul roads near/passing through
residential and commercial areas to be
watered thrice a day”.
Out of the 24 selected sub-projects for
review in first audit cycle water
sprinkling for dust suppression is being
done only on following 10 sub-projects
GT Road to Lavva MR (UID –
1751), Haridwar
Raipur Link Road (UID – 1818),
Haridwar
Uffalda – Dhelchauri MR (UID –
2270), Pauri
Arkani – Janasu MR (UID –
2120), Pauri
Food Godown, Srinagar (UID –
7318), Pauri
Badabe – Silingiya MR (UID –
2374), Pithoragarh
Salya – Tulanga MR (UID –
2519), Rudraprayag
Govt. Inter College, Kotgi (UID – 7308), Rudraprayag
Gagnani Motor Pull to Bhangeli (UID – 3151), Uttarkashi
Nakuri – Singoth Road (UID – 3183), Uttarkashi
Water sprinkling though required but is not done on 10 sub-projects. While it is not required on 2 bridge
projects in Chamoli and no status is available for following 2 completed sub-projects
Ukhimath – Mansoona MR (UID – 2548), Rudraprayag
Kempti Byepass MR (UI – 2746), Tehri
10 42%
2 8%
2 8%
10 42%
Status of Water Sprinkling in Reviewed Sub-Projects
ComplianceNot RequiredCompletedNon Compliance
Figure 19: Status of Water Sprinkling for Dust Suppression
Picture 5: Water Sprinkling on Uffalda-Dhelchauri MR, Pauri
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 53
Project Information Board
Project Information Board is to be displayed at the start and end point of the Road and Bridge Projects
and at the entrance gate of Public Building Project. Project Information Board must be visible from
distance and should not obstruct the
line of sight of the road users.
Project Information Board has been not
been displayed in following sub-projects
Salor – Dungra MR (UID – 1217),
Chamoli
Tharali – Junidhar MR (UID –
1275), Chamoli
Chepado Bridge (UID – 4004),
Chamoli
Improper Project Information Board
Food Godown, Srinagar (UID –
7318), Pauri
Govt. Inter College, Kotgi (UID – 7308), Rudraprayag
PIU must ensure that the information board must contain the
contact details of the Executive Engineer or PIU official along
with other information related to the project, so that the local
community members may contact the project officials
directly for reporting any issues or grievances.
It was observed that the Project Information Board of
different formats was being used in different projects.
DSC must ensure that proper format of Project Information
Board is used, providing all necessary information related to
the project and contact details of the concerned PIU official for
grievance redressal.
Project Information Board must contain all relevant details
about the project including contact details of the concerned
project authorities for reporting of grievances
Out of the 20 sub – projects contact information of the project officials was not available on the
Information Boards of following 3 sub-projects
Badabe – Silingiya MR (UID – 2374), Pithoragarh
Punave – Sipty – Nayari MR (UID – 1355), Champawat
Padampuri – Herakhan – Kathgodam MR (UID – 2004), Nainital
Picture 6: Information Board with no
Contact Details
19 79%
2 8%
3 13%
Status of Project Information Board in Reviewed Sub-Projects
Compliance
Partial Compliance
Non Compliance
Figure 20: Status of Project Information Board
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 54
Muck Disposal
Muck/Debris Disposal site has to be identified in projects where site clearance is required and
construction activities are expected to result in generation of large quantities of debris, which need to be
disposed.
Contractor in coordination with the PIU
need to identify the site for storage and
disposal of debris refuse. Debris
generated from the clearance
operations or during construction shall
be deposited only at pre-identified
waste disposal locations.
Muck disposal sites are required in 13
sub-projects out of the 24 reviewed in
first audit cycle. In the remaining 11
sub-projects the debris generated is
used either for filling purpose on the project or for leveling of ground surface on community land.
Contractor need to obtain NoC from the
owner of the land in case of private land
or from the village head or Sarpanch in
case of community land.
Out of the 13 sub-projects where muck
disposal site is required, the site has been
identified in only following 9 sub-projects
Salor – Dungra MR (UID – 1217),
Chamoli
Tharali – Junidhar MR (UID –
1275), Chamoli
Punave – Sipty – Nyari MR (UID –
1355), Chamoli
Sahiya – Patan MR (UID – 1577),
Dehradun
Uffalda – Dhelchauri MR (UID –
2270), Pauri
Arkani – Janasu MR (UID – 2120),
Pauri
Badabe – Silingiya MR (UID –
2374), Pithoragarh
10 42%
9 37%
5 21%
Identification of Muck Disposal Site in Reviewed Sub-Projects
Identified
Not Required
Not Identified
Figure 21: Status of Identification of Muck Disposal Site
Picture 7: Identified Muck Disposal Site on Arkani-Janasu MR
Picture 8: Muck Disposal at Punave-Sipty MR
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 55
Saliya – Tulanga MR (UID – 2519),
Rudraprayag
Gagnani – Motor Pull to Bhangeli MR
(UID – 3151), Uttarkashi
Govt. College Kotgi (UID – 7308),
Rudraprayag
Contractor of none of the sub-projects has
obtained NoC from sarpanch or owner of the
land.
Site Clearance / Grubbing
Clearance of site shall involve removal of all debris / waste material from site, so that the debris collected
on project site does not pose safety risk to road users. During site clearance, all cut and grubbed materials
shall be kept at a secured location so that it does not raise any safety concerns.
Site Clearance was found to be a matter of concern on following sub-projects
Salor – Dungra MR (UID – 1217),
Chamoli
Sahiya – Patan MR (UID – 1577),
Dehradun
Padampuri – Herakhan – Kathgodam
MR (UID – 2004), Nainital
Kempti Byepass MR (UID – 2746),
Tehri
Picture 9: Debris Collected near school on PHK MR
Picture 10: Un-cleared Debris on Kempty - Byepass MR
Picture 11: Debris on Sahiya Patan MR
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 56
4.3.4 Monitoring of Environmental Parameters
Table 19: Monitoring of Environmental Parameters
SR NO
DISTRICT PROJECT NAME UID
ENVIRONMENTAL MONITORING
REMARKS AIR
WA
TER
NO
ISE
SOIL
AS
PER
DP
R
AC
TUA
L
AS
PER
DP
R
AC
TUA
L
AS
PER
DP
R
AC
TUA
L
AS
PER
DP
R
AC
TUA
L
1 ALMORA KHUNT-ALMORA MR 1055 R N/A R N/A R N/A R N/A No Documents were available
2 BAGESHWAR HARINAGRI-KULAU-GWALDAM MR 1118 R Y R Y R Y R Y
3 BAGESHWAR KANDA-SANIUDIAY-RAWATSERA MR 1111 R Y R Y R Y R Y
4 CHAMOLI SALOR - DUNGRA MR 1217 R N R N R N R N Not done
5 CHAMOLI THARALI-JUNIDHAR MR 1275 R N R N R N R N Not done
6 CHAMOLI BRIDGE OVER ALAKNANDA RIVER AT AARUDI- PATURDI
4006 R Y R Y R Y R Y
7 CHAMOLI CHEPADO BRIDGE 4004 R N R N R N R N Not done
8 CHAMPAWAT PUNAV-SIPTY NAYARI MR 1355 R Y R Y R Y R Y
9 DEHRADUN SAHIYA PATAN SAMALTA PANUWA MR 1577 R Y R Y R Y R Y
10 HARIDWAR GT ROAD TO LAVVA MR 1751 R Y R Y R Y R Y
11 HARIDWAR RAIPUR LINK ROAD 1818 R Y R Y R Y R Y
12 NAINITAL PADAMPURI HARAKHAN KATHGODAM MR 2004 R Y R Y R Y R Y
13 PAURI UFFALDA-DHELCHAURI MR 2270 R Y R Y R Y R Y No document provided
14 PAURI ARKANI-JANASU-KHANDUKHAL MR 2120 R Y R Y R Y R Y No document provided
15 PAURI FOOD GODOWN, SRINAGAR 7318 R Y R Y R Y R Y
16 PITHORAGARH BADABE SELIGYA MR 2374 R N R N R N R N Not done. Lab not identified
17 PITHORAGARH ACHOLI JAAKH MR 2370 R N R N R N R N Not done. Lab not identified
18 RUDRAPRAYAG UKHIMATH MANSOONA MR 2548 R Y R Y R Y R Y No document provided
19 RUDRAPRAYAG SALYA-TULANGA MR 2519 R Y R Y R Y R Y
20 RUDRAPRAYAG GOVT INTER COLLEGE KOTGI 7308 R Y R Y R Y R Y
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 57
SR NO
DISTRICT PROJECT NAME UID
ENVIRONMENTAL MONITORING
REMARKS AIR
WA
TER
NO
ISE
SOIL
AS
PER
DP
R
AC
TUA
L
AS
PER
DP
R
AC
TUA
L
AS
PER
DP
R
AC
TUA
L
AS
PER
DP
R
AC
TUA
L
21 TEHRI KEMPTI BYEPASS MR 2746 R Y R Y R Y R Y
22 UTTARKASHI GAGNANI MOTOR PULL TO BHANGELI MR 3151 R Y R Y R Y R Y
23 UTTARKASHI NAKURI SINGOTH MR 3183 R Y R Y R Y R Y
24 UTTARKASHI DIDSARI BRIDGE 4003 R Y R Y R Y R Y
N/A – Not Available
NR – Not Required
N – Required but not done or not complied
Y – Required and done or complied
NA – Not Applicable
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 58
Environmental Monitoring
The contractor shall undertake seasonal
monitoring of air, water, noise and soil
quality through an approved monitoring
agency. The parameters to be monitored,
frequency and duration of monitoring as
well as the locations to be monitored shall
be as per the Environmental Monitoring
Plan.
Monitoring shall be conducted at different
stages of construction activity
Pre-Construction stage – baseline
information
Construction Stage – thrice in a year excluding monsoon seasons
Post-Construction Stage – impact evaluation
Most of the contractors have got the environmental monitoring done through certified labs. Contractors
of 6 sub-projects have not yet initiated the process of environmental monitoring. These sub-projects are
Khunt – Almora MR (UID – 1055), Almora
Salor – Dungra MR (UID – 1217), Chamoli
Tharali – Junidhar MR (UID – 1275), Chamoli
Chepado Bridge (UID – 4004), Chamoli
Badabe – Silingiya MR (UID – 2374), Pithoragarh
Acholi – Jakh MR (UID – 2370), Pithoragarh
Following issues have been identified in sub-projects reviewed during first audit cycle
Environmental Monitoring Plan has not been formulated in any of the sub-projects
In few cases the frequency of monitoring was not adequate
o Harinagar – Kulau – Gwaldam MR (UID – 1118), Bageshwar
No photographs were taken while conducting the tests in any of the sub-projects.
PIU must be informed about the location and timing, prior to the tests.
Environmental testing laboratories have not been identified in Pithoragarh.
Non-availability of baseline information on sub-projects.
18 75%
6 25%
Status of Environmental Monitoring on Reviewed Sub-Projects
Compliance
Non-Compliance
Figure 22: Status of Environmental Monitoring
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 59
5. Good Practices, Identified Issues and Suggestions
5.1 Some Good Practices
In most of the audited sub-projects, it is observed that the contractor’s main focus was to
complete the work as soon as possible. In some cases, this has led to paying inadequate
attention to implementation of EMP/SMP or other environmental and social aspects of the
project. It is important to note that some contractors have shown a lot of enthusiasm in taking
care of their labor and other environmental and social aspects of the project. Some of the good
practices identified during the audit cycle are as under
Government Inter College Kotgi (UID-7308): M/S Surat Singh and Sons, the contractor of
Public Building in Kotgi has initiated a children education program for the children of all
laborers.
All the kids in school going age have been provided admission in a school near the labor camp
location. A special arrangement has been made to provide for the Day care, a female worker
from the camp is assigned a responsibility to take care of the kids after school timings. The
Care Taker is paid wages as per the prevailing wage rate.
This is unique work done by contractor in UDRP project.
Enclosure of construction site to trap unwanted dust at Govt Inter College Kotgi (UID-
7308), Rudraprayag.
Use of muck for leveling of nearby PWD road at Punav-Sipty Nayari Motor Road (UID-
1355), Champawat.
Provision of Solar power light at Punave-Sipty Nayari Motor Road (UID-1355),
Champawat
Change in alignment of Didsari Bridge (UID – 4003), Uttarkashi, to prevent damage to
existing private building.
Trolley installed as a temporary arrangement to cross the river at site of Didsari Bridge
(UID – 4003), Uttarkashi.
o Around 60-70 school going children benefit from the use of trolley every day.
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 60
5.2 Observations and Suggestions
Revise the EMP – Account for Site Specific Issues
It would be very helpful for the PMU if the Supervision Consultants are advised to update the
EMP in taking into account the site specific social and environmental aspects for each of the
sub-project.
ARAP: ARAP should be prepared in case private land / property is to be acquired. ARAP is
required particularly for all the Bridge Projects reviewed.
ARAP is required for Bridge over Alaknanda River at Arudi Patrudi (UID – 4006), Chepado
Bridge (UID – 4004) and Didsari Bridge (UID – 4003).
Tree Cutting Permission: Required from Department of Forestry with a copy to DM,
wherever tree cutting is required for clearance of site for construction purpose.
Tree cutting permission had been obtained for Food Godown, Srinagar (UID – 7318), Pauri and
letter have been submitted for the Didsari Project (UID – 4003), Uttarkashi.
PIU of Raipur Link Road (UID – 1818), Tharali Junidhar MR (UID – 1275), Bridge over
Alaknanda at Arudi-Patrudi (UID – 4006), Chamoli, Chepado Bridge (UID – 4004), Chamoli
need to initiate the process of obtaining Tree Cutting Permission from the Forestry
Department. PMU may facilitate the process of obtaining requisite permissions.
Shifting of Utilities: Almost all the sub-projects require shifting of public utility like
drinking water supply lines or hand pumps or electric poles.
The contractors of all these sub-projects where the utility shifting is required may initiate the
process of informing the concerned departments and getting the utility structures shifted.
Shifting of Electric Poles: Wherever electric poles are located within the RoW the
Electricity department must be informed and a process for shifting of electric poles initiated.
Shifting of Electric Poles is required in Sahiya Patan Samalta Panuwa MR (UID 1577),
Dehradun, Raipur Link Road (UID – 1818), Haridwar, Food Godown (UID – 7318), Pauri, Govt.
Inter College (UID-7308), Rudraprayag.
Shifting of Drinking Water Supply Pipeline: Wherever the drinking water supply
pipeline is located within the RoW the concerned department PHED/PWD must be informed
and arrangement for shifting of such pipelines be made.
Shifting of Drinking Water Pipeline is required in almost all audited Road Projects.
Muck Disposal Site: Site for Muck disposal should be identified at DPR stage and re verify
during project execution. Also approval / NoC from the village head (land owner in case of
private land) should be in place
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 61
NOC is required for Kanda-Saniudiay-Rawatsera MR, Salor - Dungra MR, Tharali-Junidhar MR,
Punav-Sipty Nayari MR, Sahiya Patan Samalta Panuwa MR, Uffalda - Dhelchauri MR,
Padampuri – Herakhan - Kathgodam MR, Arkani – Janasu MR, Badabe – Silingiya MR, Salya –
Tulanga MR, Kempti Bypass MR.
CTE/CTO for HMP/WMM: Where ever there is provision and requirement of establishing
HMP/WMM or construction camp, work should be started only after getting necessary
approval from pollution control board.
HMP have been established for following audited sub-projects Kanda Sariudiyan Rawatsera
MR (UID – 1111), Bageshwar, Ukhimath Mansoona MR (UID - 2548), Rudraprayag, Kempti
Bypass MR (UID – 2746), Tehri, Padampuri - Herakhan - Kathgodam MR (UID – 2004),
Nainital and contractors of none of these projects has obtained the CTE/CTO from SPCB.
PPE - Contractor shall take care of Public as well as worker’s health & safety. All the worker
and supervisors must have ADEQUATE Personal Protection Equipment (PPE).
DSC must ensure that the contractor has provided adequate PPE to its entire staff and
labourers and they use PPE at site.
Labor Camps should be provided with adequate facility including drinking water storage,
proper sanitation, lighting, and waste disposal facilities. Contractors shall ensure that the
laborers residing in the camp have adequate and easy access to site or nearest road from the
camp.
The DSC must ensure that the labor camps are properly maintained and adequate facilities are
provided in these camps.
Water Sprinkling - Contractor should carry out and maintain a record / log book of water
sprinkling on approach roads to site.
Environmental Monitoring activity should be done thrice in a year excluding monsoon
season.
Before conducting environmental monitoring (air, water, noise and soil), contractor shall
intimate PIU and DSC about scheduled of monitoring/sampling. DSC Environmental
Specialist must supervise the sampling/monitoring and insure samples have been collected
in scientific manner. Each of the sampling / monitoring activity should be photographed and
need to be submitted to PIU. DSC and PIU must ask laboratory/contractor for their
accreditation certificate with annexure showing they are authorized to monitor given
parameters in EMP.
Use of Water for Construction: DSC/Contractor should ensure that the adequate written
consent is obtained from ground water board/local authority/panchayat head, for use of
ground water / surface water or water from community sources for construction activities.
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 62
PUC of Vehicles: DSC should ensure that the contractor has submitted valid PUC certificates
of the vehicles engaged in construction work.
The Supervision Consultant should maintain a record of vehicles engaged in construction work
and their registration numbers, insurance as well as PUC certificate.
Authorized Quarry - DSC should ensure that the aggregates/sand (inputs) is procured
from approved quarry and proper certification / authorization documents should be
collected and records are maintained.
Capacity Building: PMU may take up a capacity building initiative for the PIUs to ensure
that the mandatory documents and reports (ARAP) are prepared in proper formats. A
sample set of documents (insurance, PUC, monitoring report, labour license etc.) and
necessary approval (copy of clearances) should be provided to PIU for better understanding.
Grievance Redressal: Contractors / Supervision Consultants of none of the sub-projects
have maintained a record of grievances received or redressed.
All the contractors and supervision contractors must be advised to maintain a proper record of
grievance received along with the date, contact details of the person raising concern,
responsible person to whom the grievance is assigned, suggested actions, action taken, closure
date etc.
Training of Workers: Contractors and DSC should ensure that proper training to workers
is provided on use and importance of PPE and health and safety issues. The same must be
recorded and the training report submitted along with the photographs of sessions. It
should also be repeated periodically as some of the worker may be shifted / relocated and
replaced after some time of
project execution.
Safety Issues: Contractor /
Supervision Consultants should
ensure that safety sign board and
caution tapes are properly
installed wherever the
construction activity is taking
place.
Contractors/Supervision consultants (DSC) should ensure that safety signage, informatory
boards and noise barriers are installed near schools, hospitals near the construction site.
Site Clearance: Site clearance is one aspect which is rather ignored by some contractors,
particularly on Salor – Dungra MR (UID – 1217), Chamoli, Sahiya – Patan MR (UID – 1577),
School on Acholi – Jakh Road, Pithoragarh
There is a school on the valley side just below the road
on Acholi – Jakh MR (UID – 2370), Pithoragarh.
Construction activities on the road may result in undue
noise, dust and risk of debris falling inside the school
compound. The Contractor / Supervision Consultants
shall take due care that the construction activities on
the road does not pose any health or safety risk to the
children in school.
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 63
Dehradun, Padampuri – Herakhan – Kathgodam MR (UID – 2004), Nainital and Kempty
Byepass MR (UID – 2746), Tehri.
Contractors of all sub-projects should ensure that the debris generated during construction
activities is cleared from the site and stored at demarcated location, so that it does not pose
any risk to the workers as well as the road users and also care should be taken that the debris
does not damage existing public utility structures.
Some Other Suggestions:
Input of Environmental and Social Staff of DSC: In order to ensure that all the
provisions laid down in ESMF are complied with, the Environmental and Social Experts
of DSC, should visit the sub-project sites minimum once in a month.
Appreciation: On the basis of their performance in complying with the provisions and
environmental and social safeguard measures as detailed in ESMF, the contractors, may
be awarded a letter of Appreciation or a trophy, during a workshop or at any other
project related event, as a token of appreciation.
This will motivate the contractors to strive for excellence and therefore they will make
sincere efforts to take up the environmental and social aspects.
Penalty Clause: Regular non-compliance, of provisions under ESMF, by the contractor,
must lead to penalty.
Neither General Conditions of Contract (GCC) nor Special Conditions of Contract (SCC) of
the Bidding Document have penalty clause / provisions of penalty.
PMU shall prepare the terms and conditions on the basis of which, the penalty clause can
be introduced and a reasonable penal amount, as per the laid down provisions, may be
deducted from the payments to the contractor in case of any non-compliance by the
contractor.
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 64
6. Sub-Projects in Pictures
Govt. Inter College, Kotgi (UID – 7308), Rudraprayag
Picture 12: ESA Team reviewing the Documents at Govt. College, Kotgi
Picture 13: Construction on site at Govt. College, Kotgi Picture 14: Workers using PPE at Govt. College, Kotgi
Picture 15: Electric Pole need to be shifted at Govt. College, Kotgi
Picture 16: Site Enclosure to trap dust at Govt. College, Kotgi
Picture 17: Improper Project Information Board at Govt. College, Kotgi
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 65
Food Godown, Srinagar (UID – 7318), Pauri
Picture 18: Improper Project Information Board Picture 19: One of the Tree that need to be cut Picture 20: Construction camp at Food Godown, Pauri
Picture 21: Proper Use of PPE at Food Godown Picture 22: Path to Labor Camp at Food Godown Picture 23: ESA Team conducting Audit at Food Godown, Pauri
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 66
Didsari Bridge (UID – 4003), Uttarkashi
Picture 24: Trolley to cross the river and in the background are structures saved from demolishing
Picture 25: Fire Safety measures available at the construction and labour camp
Picture 26: Debris from excavation collected on banks of Alaknanda River
Road Projects – Some Specific Highlights
Picture 27: Proper Use of Caution Tape on Khunt-Almora MR
Picture 28: Water Pipeline need to be shifted on Harinagar – Kulau – Gwaldam MR
Picture 29: Safety Sign needed near School on Harinagar – Kualau – Gwaldam MR
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 67
Picture 30: Improper Handling of Bitumen on Harinagar – Kulau – Gwaldam MR
Picture 31: Improper Handling of construction material on Harinagar – Kulau – Gwaldam MR
Picture 32: Consultations Conducted on Kanda-Rawatsera MR
Picture 33: No PPE used by laborers on Kanda-Rawatsera MR
Picture 34: Oil Spillage at HMP on Kanda-Rawatsera MR Picture 35: Labor cum construction camp on Kanda-Rawatsera MR
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 68
Picture 36: Unsafe location of Labour Camp near HT pole on Salor – Dungra MR
Picture 37: Water Pipeline need to be shifted on Salor – Dungra MR
Picture 38: 25 Trees on Tharali – Junidhar MR need to be cut
Picture 39: Proper use of PPE on Punave – Sipty MR Picture 40: Debris Disposal on at Site on Punave – Sipty MR Picture 41: 25 Debris from Punave-Sipty MR used for levelling PWD road
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 69
Picture 42: Water Pipeline need to shifted on Punave – Sipty MR
Picture 43: Vehicles parked on road on Sahiya Patan MR Picture 44: Proper Information Sign Board on Sahiya – Patan MR
Picture 45: Proper use of Caution Tape on Sahiya Patan MR
Picture 46: Construction camp on Sahiya Patan MR Picture 47: Water Tanker used for Water Sprinkling on Sahiya – Patan MR
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 70
Picture 48: Unhygenic and unsafe Labor Camp on Sahiya Patan MR
Picture 49: Improper Disposal of Debris on Sahiya Patan MR
Picture 50: Remains of Damaged original Bridge on Sahiya – Patan MR
Picture 51: Cross-Drainage not provided on GT Road to Lavva MR
Picture 52: Audit Team Conducting Consultations on GT Road to Lavva MR
Picture 53: Unconstructed patch on GT Road to Lavva MR
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 71
Picture 54: One of the four Poles that need to be shifted on Raipur Link Road
Picture 55: Water Tanker used for sprinkling water on Raipur Link Road
Picture 56: Tree on Raipur Link Road that need to be cut
Picture 57: Improper Information Board with no contact information on Padampuri – Herakhan – Kathgodam MR
Picture 58: Workers in Slippers on Padampuri – Herakhan – Kathgodam MR
Picture 59: Hand-Pump likely to be damaged need to be relocated on Padampuri – Herakhan – Kathgodam MR
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 72
Picture 60: Improper Debris disposal near school on Padampuri – Herakhan – Kathgodam MR
Picture 61: Local villager complaining about poor construction quality on Padampuri – Herakhan – Kathgodam MR
Picture 62: Hand-Pump buried in debris likely to be damaged , need to be relocated on Padampuri – Herakhan – Kathgodam MR
Picture 63: Hot-Mix Plant for Padampuri – Herakhan – Kathgodam MR
Picture 64: Water Sprinkling on Uffalda – Dhelchuri MR Picture 65: Platform of the Hand-Pump likely to be damaged , need to be reconstructed after completion of works on Uffalda-Dhechauri MR
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 73
Picture 66: Safety Signs, noise barrier and dust trap required near school on Uffalda-Dhelchauri MR
Picture 67: Proper arrangements and facilities in Labour Camp on Uffalda – Dhelchuri MR
Picture 68: Workers wearing jackets and hard hats but in slippers on Arkani-Janasu MR
Picture 69: Proper Use of Caution Tape on Arkani-Janasu MR
Picture 70: Planned Muck Disposal Site on Arkani-Janasu MR
Picture 71: Audit Team reviewing contents of First Aid Kit on Badabe – Silingiya MR
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 74
Picture 72: Water Pipeline need to be shifted on Badabe – Silingiya MR
Picture 73: Safety Signages properly displayed on Badabe – Silingiya MR
Picture 74: Water Tanker used for sprinkling water on Badabe – Silingiya MR
Picture 75: Improper Disposal of debris on Pvt. Land on Badabe – Silingiya MR
Picture 76: Worker without any PPE on Acholi – Jakh MR Picture 77: Worker without any PPE on Ukhimath Mansoona MR
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 75
Picture 78: Proper Use of Caution Tape on Salya-Tulanga MR
Picture 79: Rented accommodation for labourers with proper facilities on Salya Tulanga MR
Picture 80: Improper Storage of Potable Water in Labor Camps of Kempty Bypass
Picture 81: Labor Camp with Improper facilities on Kempty Bypass
Picture 82: ESA Team conducting consultations with labourers on Kempty Bypass
Picture 83: Workers using PPE on Gagnani Motor Pull to Bhangeli MR
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 76
Annexure I: Summary: Compliance status of ESMF
Table 20: Non-Compliances and Additional Corrective Measures Required
S. No. Name of Sub Project (UID) EMP being
Implemented Actions Proposed / Additional Corrective Measures Required Remarks
UDRP Public Buildings
1 Govt Inter College Kotgi (7308) Yes
Labour Licence required
PUC certificate of construction vehicles
Project Information Sign board in proper format
Arrange for shifting of electric pole on construction site
Overall EMP implementation is very satisfactory as Labour licence could not be obtained because the USIDCL is not yet registered with the Office of Labour Commissioner
2 Food Godown, Srinagar (7318) Yes
Arrange for improvement in sanitation condition of labour camp
Labour licence & Labour Insurance need to be obtained
PUC certificate of construction vehicles
Overall very Satisfactory implementation
UDRP Road & Bridge Project
Roads Projects
1 Gagnani Motor Pull to Bhangeli Motor Road (3151)
Yes
List of construction vehicle and their PUC certificate
Village consent for use of Water for construction activity
Proper use of PPE by workers
Labour camp need to be maintained and adequate sanitation facilities provided
Arrangement of First aid box
Consent from village head for use of community water for construction activity
Log book of Water sprinkling for dust suppression need to be maintained
Need to incorporate the suggestions as mentioned.
2 Nakuri Singoth Motor Road (3183) Yes Actual construction work completed
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 77
S. No. Name of Sub Project (UID) EMP being
Implemented Actions Proposed / Additional Corrective Measures Required Remarks
3 Kempti Byepass Motor Road (2749)
Partially
CTE/CTO for Hot Mix Plant
Labour licence & workmen insurance
Construction waste/debris should be removed from within RoW
List of construction vehicle and their PUC certificate
Further improvement in sanitation condition of labour camp
Use of PPE
Labour camp need to be maintained
Arrangement of First aid box
Consent for use of Water for construction activity from village head
Water sprinkling for dust suppression
Overall very unsatisfactory implementation of EMP
4 GT road to Lavva road (1751) Yes Consent for use of Water for construction activity Construction Almost Completed
5 Raipur link road (1818) Yes
Tree cutting permission for tree at chainage km 0+250
Consent for use of Water for construction activity
Shifting of Electric Poles
Overall Satisfactory implementation however road user safety must be taken care of as the electric poles within road alignment pose a risk to drivers particularly during night as the road provides connectivity to industrial area.
6 Sahiya Patan Samalta Panuwa MR (1577)
Yes
Complete use of PPE
Labour camp need to be maintained
Arrangement of First aid box
Consent from village head for muck disposal site
Overall Satisfactory but proper arrangement of sanitation facilities in labour camp needs to be made.
7 Arkani-Janasu-Khandukhal MR (2120)
Yes
Consent for use of Water for construction activity from village head
Village Consent for debris disposal site
Environmental Monitoring Report
Overall satisfactory implementation of EMP. However certain documents need to be maintained and copies
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 78
S. No. Name of Sub Project (UID) EMP being
Implemented Actions Proposed / Additional Corrective Measures Required Remarks
Labour licence
Log book of Water sprinkling for dust suppression
submitted to PIU.
8 Uffalda-Dhelchauri MR
(2270) Yes
Village consent for use of Water for construction activity
Village Consent for debris disposal site
Environmental Monitoring Report
Labour licence
Log book of Water sprinkling for dust suppression
Overall satisfactory implementation of EMP. However certain documents need to be maintained and copies submitted to PIU.
9 Salya-Tulanga MR (2519) Yes
Village Consent for debris disposal site
Environmental Monitoring Report
Use of PPE
Log book of Water sprinkling for dust suppression
Overall Satisfactory implementation however suggested measures need to be implemented.
10 Ukhimath Mansoona MR (Urban area) (2548)
Yes Consent for use of Water for construction activity Actual construction work completed
11 Salor - Dungra MR (1217) Partially
Consent for use of Water for construction activity
Location of labour camp and sanitation condition is not good, need to be relocated.
Complete use of PPE
Labour licence
Village Consent for debris disposal site
Environmental Monitoring Report
Water sprinkling for dust suppression
Several non-compliances observed, EMP implementation is not satisfactory.
The DSC needs to follow-up regularly to ensure that the all necessary documentation is in place and copy of the same is submitted to the PIU.
12 Tharali-Junidhar Motor Road (1275)
Partially
Around 25 trees are within RoW, need to be removed. Tree cutting permission required.
Consent for use of Water for construction activity
No documents were available. Very Unsatisfactory progress of EMP implementation
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 79
S. No. Name of Sub Project (UID) EMP being
Implemented Actions Proposed / Additional Corrective Measures Required Remarks
Complete use of PPE
Labour licence
Village Consent for debris disposal site
Environmental Monitoring Report
Water sprinkling for dust suppression
13 Harinagri-Kulau-Gwaldam MR (1118)
Partially
Consent for use of Water for construction activity
Monitoring frequency is not correct
Log book of Water sprinkling for dust suppression
Frequency of Environmental Monitoring should be as per standard
Overall Satisfactory implementation of EMP however some documents need to be maintained and submitted to PIU.
14 Kanda-Saniudiay-Rawatsera MR (1111)
Partially
CTE/CTO for Hot Mix Plant
Water sprinkling for dust suppression
Complete use of PPE
Concrete platform for keeping oil tanks
Improvement in sanitation condition of the HMP camp.
Most of construction work completed. However several non-compliances observed which need to be implemented as suggested.
15 Khunt -Almora Road (1055) Partially Complete use of PPE
There is change in negative CoS of contractor work. Contract document may have to be revised.
Satisfactory implementation of EMP
16 Padampuri Harakhan Kathgodam Motor Road (2004)
Partially
CTE/CTO for Hot Mix Plant (Hot mix plant is very near to habitation i.e.<200m, need relocation or CTE/CTO in the earliest possible)
Complete use of PPE
Labour camp need to be maintained
Arrangement of First aid box
Water sprinkling for dust suppression
Need to implement corrective measures on priority basis.
Unsatisfactory implementation of EMP
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 80
S. No. Name of Sub Project (UID) EMP being
Implemented Actions Proposed / Additional Corrective Measures Required Remarks
Disposal of used bitumen drums
Removal of debris from RoW and culverts.
Consent for use of Water for construction activity
Frequency of Environmental Monitoring should be as per standard
17 Badabe Seligya MR (2374) Yes
Consent for use of Water for construction activity
Complete use of PPE
Log book of Water sprinkling for dust suppression
PUC certificate of construction equipment and vehicles
Overall Satisfactory implementation of EMP however suggested corrective measures need to be taken up and records maintained and copies need to be submitted to PIU
18 Acholi jaakh MR (2370) Yes
Consent for use of Water for construction activity/ water procurement bill.
Environmental Monitoring
Complete use of PPE
Log book of Water sprinkling for dust suppression
Dust trap for road crossing school area
PUC certificate of construction equipments
Several non-compliances observed, DSC must ensure that the Contractor completes all the requirements as suggested. Overall un-satisfactory implementation of EMP
19 Punav-Sipty Nayari Motor Road (1355)
Consent for use of Water for construction activity
Log book of Water sprinkling for dust suppression
Very satisfactory implementation of EMP. Proper documentation is maintained. However some suggestions need to be incorporated.
Bridge Project
1 Didsari Bridge (4003) Yes
Tree cutting permission
Improvement in sanitation condition of labour camp
Correction of monitoring frequency
ARAP need to be prepared
Overall Satisfactory however ARAP need to be prepared.
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 81
S. No. Name of Sub Project (UID) EMP being
Implemented Actions Proposed / Additional Corrective Measures Required Remarks
2 Bridge over Alaknanda river at Aarudi- Paturdi (4006)
-
Physical work/ actual construction work not started on ground
ARAP required as Pvt. Land is acquired and no. of PAFs < 20
Tree cutting requirement be determined and necessary permissions be obtained
Construction stalled due to opposition from affected community.
Overall satisfactory however some non-compliance was observed.
ARAP need to be prepared
3 Chepado Bridge (4004) -
Physical work/ actual construction work not started in ground
Alignment need to be finalized.
LA requirements need to be determined
tree cutting requirements be determined and Tree cutting permission be obtained
Construction Not yet started
ARAP may be required.
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 82
Annexure II: Checklist for Environmental and Social Audit
Uttarakhand Disaster Recovery Project Environmental and Social Audit
Samaj Vikas 90
Annexure III: Travel Schedule of ESA Team to Sub-Project Sites
S. No.
District From To Sub-Projects Reviewed
1. Uttarkashi Wednesday, November 04, 2015 Friday, November 06, 2015 Gagnani-Bhangeli MR Didsari Bridge Nakuri-Singoth MR
2. Tehri Saturday, November 07, 2015 Saturday, November 07, 2015 Kempty Bypass MR
3. Haridwar Saturday, November 21, 2015 Saturday, November 21, 2015 GT Road to Lavva MR Raipur Link Road
4. Dehradun Monday, November 23, 2015 Monday, November 23, 2015 Sahiya - Patan MR
5. Pauri Tuesday, November 24, 2015 Thursday, November 26, 2015 Uffalda-Dhelchauri MR Arkani Janasu MR Food Godown, Srinagar
6. Rudraprayag Friday, November 27, 2015 Saturday, November 28, 2015 Salya-Tulanga MR Ukhimath Mansoona MR GIC, Kotgi
7. Chamoli Sunday, November 29, 2015 Tuesday, December 01, 2015
Arudi-Patrudi Bridge Salor Dungra MR Chepado Bridge Tharali-Junidhar MR
8. Bageshwar Wednesday, December 02, 2015 Thursday, December 03, 2015 Kanda-Rawatsera MR Harinagar-Gwaldam MR
9. Almora Thursday, December 03, 2015 Thursday, December 03, 2015 Khunt-Almora MR
10. Nainital Friday, December 04, 2015 Friday, December 04, 2015 Padampuri-Herakhan-Kathgodam MR
11. Pithoragarh Saturday, December 05, 2015 Monday, December 07, 2015 Badabe-Silingia MR Acholi-Jakh MR
12. Champawat Tuesday, December 08, 2015 Tuesday, December 08, 2015 Punave-Sipty MR
13. Almora Tuesday, February 09, 2016 Tuesday, February 09, 2016 Training / Workshop for Kumaon region
14. Dehradun Monday, February 15, 2016 Monday, February 15, 2016 Training / Workshop for Garhwal region
15. Dehradun Tuesday, February 16, 2016 Tuesday, February 16, 2016 Presentation of Final Report