GOODWIN CREEK @ MCBRIDE PROPERTY, NEAR BATESVILLE, MS. CONSTRUCTED FEB 26 - MAR 2, 2007 The final...

27
GOODWIN CREEK @ MCBRIDE PROPERTY, NEAR BATESVILLE, MS. CONSTRUCTED FEB 26 - MAR 2, 2007 The final design was based on the landowner’s required stream and riparian corridor functions (the Cadillac Plan)

Transcript of GOODWIN CREEK @ MCBRIDE PROPERTY, NEAR BATESVILLE, MS. CONSTRUCTED FEB 26 - MAR 2, 2007 The final...

GOODWIN CREEK @ MCBRIDE PROPERTY,

NEAR BATESVILLE, MS. CONSTRUCTED FEB 26 - MAR 2, 2007

The final design was based on the landowner’s required stream and riparian

corridor functions (the Cadillac Plan)

THIS METHOD IS A RON REDMAN

DISCOVERY (RRD)

1

23

4

5

6

7

8

9

10

11

12

Bend #1

Bend #2

Goodwin Creek @ McBride Property Design Layout for

Bends 1 & 2

Tieback/key- 1.0 ton/ft

LPSTP- 0.5 ton/ft

LPSTP- 1.0 ton/ft

KEY

Traffic Control Stones

Bendway Weirs 1.0 ton/ft

Boil-Up Pool 2.0 tons/ft

Bend 1

Bend 2

FLOW

BEND #1 WAS USED FOR THE LAST 10

YEARS TO DEVELOP THE ARS BANK

STABILITY NUMERICAL MODEL

DESIGN CHOSEN BY THE LANDOWNER FOR BEND #1:

LPSTP WITH BENDWAY WEIRS & MAXIMUM

VEGETATION. BANK ALMOST COMPLETELY

BUILT OUT INTO STREAM (UPPER BANK SLIGHTLY

LAID BACK AT EDGE)

Bend #1, Looking DS

Pix with outline of proposed work

FILLCUT

CUT

LPSTP

Typical post-project cross-section

Goodwin Creek-Cross Section-Soil Cut/Fill Area (Bend 1)

NOTE: All cut/fill activity will be in balance

KEY

LPSTP

Fill area

ELE +0.0

+12+15

Varies 7 to 14 ft

Cut areas

This left bank cut area will also provide a floodplain bench for the stream

6 ft

LPSTP

Top bank, right descending bank

Project designers Dr. Andrew Simon ARS-NSL & Dave Derrick, ERDC-CHL

GOODWIN CREEK–CONSTRUCTION-FEB 2007–DIRK SPENCER

THE PLAN

Actually Derrick’s

cheat sheet

PIX BY DANNY KLIMETZ

TREE & GRASS SEEDING & MULCHING

BEND #1

Ron Redman says break up the Sycamore tree seed balls & add them to the hydroseed mix

Or slap a Sycamore with the trackhoe & release a thousand seeds

GOODWIN CREEK – CONSTRUCTION - FEB 2007 -DERRICK

Sycamore seeds everywhere - BEND #1

GOODWIN CREEK – CONSTRUCTION - FEB 2007 -DERRICK

Redman’s trees seeds spread on ground - BEND #1

GOODWIN CREEK – CONSTRUCTION - FEB 2007 –SHARLA LOVERN

We talked the Pennington sales rep out of 4 bags of

“Pennington SLOPEMASTER Mix”

grass seed. This seed worked well in our

application. Extreme upper bank was not as lush or robust as other

areas. Possibly a lack of moisture issue?

GOODWIN CREEK–CONSTRUCTION-FEB 28, 2007–DANNY KLIMETZ

Seeding “Pennington Slope Master Mix” grass seed - BEND #1

GOODWIN CREEK–CONSTRUCTION-FEB 28, 2007–DANNY KLIMETZ

Hay bales for mulch - BEND #1

GOODWIN CREEK – CONSTRUCTION - FEB 2007 –SHARLA LOVERN

Rolling and spreading hay - BEND #1

GOODWIN CREEK – CONSTRUCTION - FEB 2007 –SHARLA LOVERN

Mulch the bank, this section is done - BEND #1

GOODWIN CREEK–CONSTRUCTION-FEB 28, 2007–DANNY KLIMETZ

Looking DS at mid & lower end of BEND #1

GOODWIN CREEK – CONSTRUCTION - FEB 2007 –SHARLA LOVERN

Looking DS @ the crew - BEND #1 – 99% DONE

GOODWIN CREEK – CONSTRUCTION - FEB 2007 -DERRICK

Bend #1 DONE!

Looking US & panning clockwise

Looking US BEND #1

GOODWIN CREEK – CONSTRUCTION - FEB 2007 -DERRICK

This PowerPoint presentation was developed & built by Dave Derrick.

Any questions or comments, call my personal cell @ 601-218-7717, or email @ [email protected]

Enjoy the information!!

The Bassett as a mountain lion