Golden Triangle Blvd. Progress Report March 27, 2007.
-
Upload
silvia-johns -
Category
Documents
-
view
215 -
download
0
Transcript of Golden Triangle Blvd. Progress Report March 27, 2007.
• City ……………… $7.3 Million• County…………… $7.3 Million• Federal…………… $11.0 Million
$25.6 Million
Funding
+ -Proposed
Urban Design• Median/Left Turn Lanes• Curb & Gutter• Sidewalks
Drainage Improvement
$18.3 Million
50+ Year (permanent fix)
Alternative
Rural Road
Barrow Ditches
Federal Strings (6-8 months)
5-10 Year (Band-Aid) Re-prioritization
Current Maintenance/Improvements
• Constructing Beach St. at Alta Vista• Left Turn Lanes• Re-timing Traffic Signals• Major Surface Repair (500 tons)• Re-stripe Roadway• Drainage west of SH 377• Keller-Hicks at Alta Vista
$7.3M PLAN$7.3M PLAN
Two New LanesTwo New Lanes(Approx. Life 10 (Approx. Life 10
Years)Years)
Rehabilitate Rehabilitate ExistingExistingRoadwayRoadway
(Approx. Life 5 (Approx. Life 5 Years)Years)
DitchDitch
DitchDitch
DitchDitch
$25.6M PLAN$25.6M PLAN
4-Lane Divided Arterial with Curb and Gutter
Raised Median
Underground Drainage
Traffic Signals
Left & Right Turn Lanes
FEDERAL FUNDING REQUIREMENTSFEDERAL FUNDING REQUIREMENTS
• Environmental Assessment– Coordination with multiple agencies– Public Involvement
• TxDOT / FHWA Review and Approval Processes– 30%, 60%, 90%, 100% Reviews– Bridge Design Review in Austin– Plan Review in Austin (6 months)
2005 2006 2007 2008 2009 2010
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Schematic Development (Survey, Traffic Studies, Funding Sources)
Environmental Study
Design
TxDOT (Austin) Review
UPRR Coordination
ROW Acquisition
Utility Relocations
Construction
TIMELINE TIMELINE (URBAN ROADWAY)(URBAN ROADWAY)
TIMELINE TIMELINE (RURAL ROADWAY)(RURAL ROADWAY)2005 2006 2007 2008 2009 2010
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Schematic Development (Survey, Traffic Studies)
Design
UPRR Coordination
ROW Acquisition
Utility Relocations
Construction