Glebe Substation Rebuild & Potomac Yards Terminal Station ...
Transcript of Glebe Substation Rebuild & Potomac Yards Terminal Station ...
Dominion p, Energy®
Glebe Substation Rebuild & Potomac Yards Terminal Station
Undergrounding Project
Update: February 27, 2019
o.iuon'
o,~m" Ccr r
N wHopi
Spor1gfi 1(
W,r11 pronghtld
Mountv,mon
NERC Reliability Issues Across Existing System
(Spring 2014 – Summer 2018):
Original Project Drivers
Overloads:
Ox 500/230kV Tx #1
Ox 500/230kV Tx #2
230kV Line Hayfield to Va Hills
230kV Line South Carlyle to N. Potomac Yards
230 kV Line Ox to Occoquan
230 kV Line Franconia to Belvoir
Proposed New Line:
Glebe – Potomac River
Tie-line strengthens the grid in Arlington &
Alexandria and improves operational performance
for Dominion Energy Virginia / Pepco customers
Current Project Drivers
• North Potomac Yards original special use permit has expired
- Dominion Energy required to vacate location by 2021
- Proposal to underground lines/structures on Richmond Hwy and
under Four Mile Run
- Cost $52.5 M
• Glebe Substation rebuild
- Existing 230 kilovolt (kV) facilities have reached end of life
- Gas-insulated substation (GIS) needed to make room for new
underground lines
- Cost $69 M
•i
GLEBESUB
.~ .. ". ..•..."' -th~=
1/1 :i: 25thSIS Aurora HIii s ~
: 76th SIS26~ .i;.
r 1'o-
Glebe Substation Rebuild / "' Potomac Yard Proposal
Highways, Railroads, Streets, Parks, Open Space, Schools,
Hospitals, Airports, Convalescent Centers, & Churches
Existing Substation
- - Existing Overhead Line AirC roo Rd Relocation to Underground O' 500'
-+--+- Railroad Line Airport INSET: Exiati Overhead Line Relocation to Unde round Pendi sec .. " -- Existing Overhead Line
C, - Gasline C,_, ,t Schools
6 Places of Worship
~ Par1<s & Open Space
+PJ~ County of Arlington / City of Alexandria
N 1000' (Main Map)
0 5 ml (Vicinity Map).., -- w• • O'
-· /
/.,:,.:,/llCV /
~\~cl it .. ~o ~ o
(,ti b/Jf'(\ '!to.. ~" "'(' t,.<~
o' af\5,,0<'
0
DATE: 12/18/2018
Late January 2019
-
-
-
-
Submitted 2202 letters to localities
Provided update to locality staff
Sent cultural advocacy letters to stakeholders
Ongoing updates to project website
February 2019
-
-
-
Review notes from staff
Review feedback from cultural advocacy groups
Ongoing meetings with community/civic associations
March 2019
-
-
Send communication to community residents/businesses
Submit application to VA State Corp. Commission (SCC)
– March 7. 2019
TBD
-
-
-
-
SCC Procedural Order issued
Local public hearing
Public evidentiary hearing
Order issued, construction schedule set
May 2022 - Target energize date
Target Schedule