ABB Service Company Limited Weekly Progress ReportPower Products Division
Site:Riyadh PS-9027 380kV GIS GIS Team ( FAA 2657-6 )
Supervisor Name: Mohammed Madian
Week Start Date: 23 11 14
Week End Date: 30 11 14
Activities: Installation/ Gas Preparation
Day Details
Sunday
(23/11)
C07:-Installation of all interconnection elements for Side 1A. (3 in total).
- Scaffolding reassembled for Side 1B interconnection installation
preparation.
- Humidity Filter change on Side 1B (3 out of 9 has been changed and
Vacuum was applied.
C08:
- Circuit breaker boxes were entered inside building, unboxed.
- All shock indicators were checked with the supervision of SEC
personnel.
-
8/10/2019 GIS -PS9027_Weekly Progress Report 2014-11-26
2/9
Monday
(24/11)
C07:
- 3 more Humidity filters have been changed on side 1B.
- Vacuum was applied and gas filling is almost done.
C08:
-
Floor Cleaning and circuit breaker alignment finalized.
- Installation of two CBs
Tuesday
(25/11)
C07:
- All filters in Side1B are installed and vacuumed. Gas filling is in
progress.
C08:
- All Circuit Breakers have been installed and levelled.
-
8/10/2019 GIS -PS9027_Weekly Progress Report 2014-11-26
3/9
Wednesday
(26/11)
C08:
- Three CT risers were installed on side 2A from box(1000243068).
- One CT was found damaged on the outside with the NCR No.
16785-004.
-
Unboxing of 3 more CT risers.
Thursday
(27/11)
C08:
-
Humidity filters changing process is in place and had begun.
Saturday
(29/11)
C08:
- Installation of All available CT risers. Two more CT risers are
remaining.
- One CT riser was noted damaged inside the box. NCR No.16785-005
-
8/10/2019 GIS -PS9027_Weekly Progress Report 2014-11-26
4/9
Sunday
(30/11)
C07:
- Scaffolding prepared for installation of interconnection elements in
Side 1B.
- All Interconnection elements have been installed on side 1B.
-
Preparation of Exit line is in place.
-
Steel support is entered into the building and currently being set
up.
- Preparation of cable trays is in place and initial installation had
started.
Comments:
1-
The metal support (triangular base) for the steel support for the high-speed acting switch is not
available on site or missing (Two are available). Check image below for further illustration. The
NCR with the number 16785-006 documents the mentioned issue. In the meantime two
triangular bases are being installed.
-
8/10/2019 GIS -PS9027_Weekly Progress Report 2014-11-26
5/9
2-
The washers that were missing have been found in a humidity absorbent box that is dated 2013
However, all the humidity absorbent boxes that had been sent to this project are dated 2014.
Noted that the washers were not placed in the specified box in the relevant packing list with the
CB support.
3-
The exit line work has already started as indicated in the below pictures.
4-
The C-Clamps that has been provided are extra as we already have four C clamps on hand. Those
four C clamps were brought from the Al-daeree site and hence all interconnection elements
have been installed. The extra two c clamps are unnecessary.
-
8/10/2019 GIS -PS9027_Weekly Progress Report 2014-11-26
6/9
5-
We have 20 disconnectors that require 40 aluminum bars depending on the type of
disconnector switch However, all 40 bars are in one size although it should be of different sizes
depending on the type of connection.
6-
In regards to C08 CT riser installations, two are still not yet connected due to the fact that it had
come in separate pieces that must be all coupled together along with the drive box. A specialist
may be required to perform this task.
-
8/10/2019 GIS -PS9027_Weekly Progress Report 2014-11-26
7/9
7-
In regards to the interconnection elements: it has been pointed out that the mentioned material
is not complete or do not comply with the packing list. While 6 interconnection elements are
needed 5 are only available on site. Awaiting feedback about this case.
8-
The LCCs have arrived on site on the 1stof Dec,2014 at 1400h.
9-
The below T-connection is available on site and not specified where it should be installed.
-
8/10/2019 GIS -PS9027_Weekly Progress Report 2014-11-26
8/9
10-
The exit line work is currently pending or will be on hold due to the location not being prepared
instead there is excavation where the surge arresters should be placed.
11-
Notes about the subcontractor workers:
a.
The provided team is not experienced in any kind of GIS installation work.
b.
Weak background about mechanical works.
c.
The performance is poor and the lack of commitment is quite obvious in addition to the lack
of discipline on site.
Al Fanar Manpower:
Alfanar Manpower
S.
No. Employee Name Job title Work Category
1 Mohammed Gamal Abdelmegid Mech foreman
GIS
2 Mohammed Nazmulhaqe Electrician
3 Ravi Elangovan Elangovan Electrician
4 Nabeel Hayat Ranjha Muhan Electrician
5 Mohammad Jamirul Islam Line Man
6 Lito Majadr Pipe Fitter
7 Raul Tapuroc Pipe Fitter
8 Parkash Neupane Madhu Labour
9 Naryan Bahadur Gharti Surya Labour
-