Georgia Association of MPOs November 29, 2012

North Augusta Park and Ride Project

Page 3: Georgia Association of MPOs November 29, 2012 North Augusta Park and Ride Project.

EXIT 5

AUGUSTA METRO AREA

Page 4: Georgia Association of MPOs November 29, 2012 North Augusta Park and Ride Project.

EXIT 5

AUGUSTA

NORTH AUGUSTA

Page 5: Georgia Association of MPOs November 29, 2012 North Augusta Park and Ride Project.

PalmettoParkway

Park & Ride Site

EXIT 5

Page 6: Georgia Association of MPOs November 29, 2012 North Augusta Park and Ride Project.

October 2009

Page 7: Georgia Association of MPOs November 29, 2012 North Augusta Park and Ride Project.

Issues

• Air quality• Demand• SCDOT to design and construct• City to maintain• Sustainable Design: stormwater, energy,

landscaping• Security• Image• Maintenance cost

Page 8: Georgia Association of MPOs November 29, 2012 North Augusta Park and Ride Project.

Main

JANUARY 2010

Page 9: Georgia Association of MPOs November 29, 2012 North Augusta Park and Ride Project.

Chronology

• August 2009 Project conceived• October 2009 User meeting held• January 2010 Sketch design complete• June 2010 ARTS funding approved• January 2011 Design contract advertised • April 2011 URS selected for design• October 2011 URS design contract

approved• October 2012 Preliminary plans at 95%

Page 10: Georgia Association of MPOs November 29, 2012 North Augusta Park and Ride Project.

December 2011

Page 11: Georgia Association of MPOs November 29, 2012 North Augusta Park and Ride Project.

October 2012

Page 12: Georgia Association of MPOs November 29, 2012 North Augusta Park and Ride Project.

Cost Estimates

• January 2010 $ 800,000• June 2010 $ 1,000,000• October 2012 $ 1,473,305

Page 13: Georgia Association of MPOs November 29, 2012 North Augusta Park and Ride Project.

North Augusta Park and Ride Project

QUESTIONS

Page 14: Georgia Association of MPOs November 29, 2012 North Augusta Park and Ride Project.