GENERATORS AND LOADS MODELS TO INVESTIGATE...
-
Upload
dinhnguyet -
Category
Documents
-
view
221 -
download
4
Transcript of GENERATORS AND LOADS MODELS TO INVESTIGATE...
23rdInternational Conference on Electricity Distribution Lyon, 15-18 June 2015
Paper 0780
CIRED2015 1/5
GENERATORS AND LOADS MODELS TO INVESTIGATE UNCONTROLLED
ISLANDING ON ACTIVE DISTRIBUTION NETWORKS
Paolo MATTAVELLI,
Riccardo SGARBOSSA
Roberto TURRI
University of Padova – Italy
Gianluca SAPIENZA,
Giovanni VALVO,
Cristiano PEZZATO,
Alberto CERRETTI
Enel Distribuzione – Italy
Ettore DE BERARDINIS
CESI – Italy
ABSTRACT
The number of distributed energy resources (DERs)
connected to low voltage (LV) distribution networks has
increased the concern on the unintentional/uncontrolled
islanding operations. To evaluate the effect of the
Distributed Generation (DG) on the uncontrolled
islanding events in LV network portions independent
studies have been performed, considering different LV
load dynamic characterization and inverter based models
for a correct evaluation of the islanding issue. P/f and
Q/V capabilities and regulation laws required by the
DERs stated by the most relevant standards have also
been considered. Field measurements, simulations in
different simulating environments as Real Time Digital
Simulator (RTDS), Simulink/Power System Blockset and
DIgSILENT Power Factory are reported.
INTRODUCTION
To evaluate the effect of the most relevant capabilities
and regulation laws required to distributed energy
resources (DERs) [1-2] on uncontrolled islanding in
distribution networks, two completely independent
studies have been performed, based on:
1) field measurements to assess LV load dynamic
behavior;
2) digital simulations performed in different simulation
environments (RTDS, Simulink/DigSILENT).
Suitable models for the inverter based generators and for
the loads are essential for a correct evaluation of the
phenomena. This need has recently led to the Joint
Working Group C4/C6.35/CIRED: “Modelling and
dynamic performance of inverter based generation in
power system transmission and distribution studies”.
Considering that inverter based models in standard
libraries do not include the several new DER capabilities
and may be not adequate for dynamic simulations (EMT-
time domain), additional models have been developed.
More precisely:
• University of Padova realized models in the time
domain (Power System Blockset), based on switching
inverter operation. Subsequently, porting of the model
in an equivalent RMS model to be adopted in
DigSILENT was performed by simplification firstly
to average models and then to RMS-phasor models, in
order to be used in dynamic simulation, together with
other network components (load, generator, etc).
• CESI and ENEL Distribuzione implemented in a Real
Time Digital Simulator (RTDS) digital models of PV
inverters, synchronous generators, loads and
protection systems.
The correct dynamic representation of the LV load
depending on the voltage and the frequency [3-4] is
important for the assessment of unintentional islanding
operation. Considering the data in [3-4] outdated, ENEL
decided to set up two field measurement campaigns in
order to assess the current typical LV equivalent load
behavior and to define updated sets of load model
parameters. In any case, in order to cover different
scenarios for uncontrolled islanding operation, analysis of
islanded operation has taken into account both load
representations, i.e. the old ones with the coefficient
reported in 1993 [3-4] and the new ones as resulting from
the two field measurement campaigns.
STANDARDS AND CONNECTION RULES
Recently, reference technical rules have been revised by
standards, introducing for DERs protection interface
systems and local control strategies, in order to integrate
the growing number of DGs [1-2]. Permissive thresholds
for voltage and frequency have also been introduced in
compliance with the Fault Ride Through (FRT)
philosophy [3- 4], as shown in Fig. 1.
a) b)
Figure 1-a) Frequency permissive and restrictive thresholds.
b) voltage FRT thresholds.
Moreover, local controls set by standards are required:
active and reactive power exchanged by DGs are function
of the frequency and voltage levels, as shown in Fig. 2,
introducing the droop characteristic Q=f (V) and P=f (f).
23rdInternational Conference on Electricity Distribution Lyon, 15-18 June 2015
Paper 0780
CIRED2015 2/5
These control strategies are aimed at facilitating the
electrical system stability but they can potentially
increase the risk of uncontrolled islanded network
operation.
a) b)
Figure 2 - a) Inverters could be required to participate to
the voltage regulation using Q injections from a minimum of
-0.4843 to the maximum of 0.4843 with respect to the rated
power; b) gradual limitation of the generated P according to
an over-frequency statism so=2.4% [1-2].
LV LOAD CHARACTERIZATION
For the load static and dynamic characteristics, the
approach proposed in [3-4] has been adopted, where the
active Pout and the reactive Qout load powers depend both
on frequency and amplitude of the voltage waveform,
i.e.:
{𝑃𝑜𝑢𝑡 = 𝑃0 {[∆𝑓 (
𝑘𝑝𝑓
1+𝑠𝑇1) + 1] (
𝑢𝑝
𝑢𝑜)
𝑘𝑝𝑢}
𝑄𝑜𝑢𝑡 = 𝑄0 {[∆𝑓 (𝑘𝑞𝑓
1+𝑠𝑇1) + 1] (
𝑢𝑝
𝑢𝑜)
𝑘𝑞𝑢} (1)
where 𝑢𝑝 = [∆𝑢 (1
1+𝑠𝑇1) + 𝑢𝑜] and Po and Qo are the
active and reactive power respectively absorbed at
nominal frequency f0 and nominal amplitude u0.
Moreover, kpf , kpu, kqf and kqu are parameters that describe
different type of loads (residential, industrial, agriculture)
and the voltage and frequency deviation from their
nominal parameters are denoted as ∆u = u − uo and ∆f =
(f − fo ) /fo , respectively.
The above-mentioned parameters describe the variation
of the load as a function of voltage and frequency,
therefore the campaign has been realized by using a
suitable synchronous generator able to supply the LV
network independently from the MV/LV transformer, as
shown in Fig. 3.
Figure 3 – Test field realization
Tests have been carried out at fixed voltage to determine
kpf , kqf, at fixed frequency to find kpf ,kqf, according to the
following equations:
𝑘𝑝𝑢 =log
𝑃
𝑃0
log𝑢𝑝
𝑢0
𝑘𝑞𝑢 =log
𝑄
𝑄0
log𝑢𝑝
𝑢0
𝑘𝑝𝑓 =1
𝑓∙ (
𝑃
𝑃0− 1) =
𝑓0
𝑓 − 𝑓0∙ (
𝑃
𝑃0− 1)
𝑘𝑞𝑓 =1
𝑓∙ (
𝑄
𝑄0− 1) =
𝑓0
𝑓 − 𝑓0∙ (
𝑄
𝑄0− 1)
(2)
where P0, Q0, U0, f0, are the initial active power reactive
power, supply voltage, frequency, for each test.
The initial and final values for the active/reactive power
at the corresponding values for the voltage or frequency
have been determined by interpolating several
measurements, for the kpu, kqu characterization, as shown
for the sake of example in Fig. 4.
Figure 4 – Example of P and Q variation as a function of up
Table 1 shows the mean values measured during these
tests. The values are quite different from the IEEE
campaign and they refer to a limited number of tests. This
difference may be justified by the different type of
electrical equipment currently used.
Residential loads Other loads
kpf
0.7 ÷ 1.0 -0.8 2.6 -0.7
kqf
-2.1 ÷ -1.5 -6.7 1.6 -4.0
kpu
0.9 ÷ 1.7 1.2 0.1 1.7
kqu
2.4 ÷ 2.6 6.1 0.6 5.3
Table 1 – Field tests results (average values).
V20/0.4 kV
G~
Other lines
Residential loads
Other load
MV Network
Synchronous generator
23rdInternational Conference on Electricity Distribution Lyon, 15-18 June 2015
Paper 0780
CIRED2015 3/5
The T1 parameter has been determined by applying step
voltage variations using the tap changer of the Primary
Substation HV/MV transformer. T1 value has been
confirmed to be about 0.1 s.
INVERTER AND LV NETWORK
DISTRIBUTION MODEL
DIgSILENT inverter model RMS vs
Simulink/Time domain model (Case A)
In this study a detailed inverter model, with embedded
voltage and current regulations typical for photovoltaic
applications, has initially been developed. In order to
study the uncontrolled islanding operations the average
values and the phasors representations are superior to the
detailed model in terms of computational requirements
and numerical convergence issues. Although different
conversion module configurations can been considered
[5], the analysis has focused on the single-stage system
and on the two level Voltage Source Inverter (VSI). A
three-phase inverter with EMI filter in addition to the
inductive output filter, as shown in Fig. 5, has been
considered.
Figure 5 Three phase inverter with L1,2,3 inductive filter and
EMI filter composed by Lf1,2,3 ,Cf1,2,3 and RCf1,2,3 as dumping
element of the filter (if present).
The switching function approach has been initially used
to fully represent the switching operation of the inverters,
as depicted in Fig. 6. However, for most of the islanded
analysis, the detailed switching operation has been
neglected, in order to reduce simulation time and
facilitate convergence, and an average model, where each
state variable is averaged over the PWM switching
period, is adopted, as generally shown in Fig. 6. The
averaging model is more efficient and with less numerical
convergence problem than the detailed switching model.
Moreover the presented average model has been
transferred in the d,q coordinates using a Park
Transformation, and completed with the required current,
voltage and Phase-Looked Loop (PLL) regulations and
with the required protection functions. At last we obtain a
dynamic model expressed in amplitude and phase of
voltages and currents instead of instantaneous sinusoidal
values.
Figure 6- Switching and average inverter model
The representation has been developed in
Maltab/Simulink environment and compared with
DIgSILENT software using RMS simulations. The
results show a good match between the two
environments.
With this modeling approach, the tested LV network is
shown in Fig. 7. It presents a DG unit, three loads, a
MV/LV Transformer and cables lines, whose lengths are
shown in Fig. 7, and characterized by R=0.164 Ohm/km,
X=0.0691 Ohm/km and B=185.35 µS/km. The switching
of the breaker starts the islanding events.
RTDS model (Case B)
After CESI residential loads characterization, a large 4-
wires unbalanced LV grid has been implemented by
ENEL-CESI in the Real-Time Digital Simulator (RTDS)
installed in the ENEL Smart Grid Test Center of Milano.
The RTDS allows to simulate a large number of power
ai
bi
civ
BC
C f 1 C f 2C f 3
RCf 1RCf 2 RCf 3
L1
L2
L3
L f 1
L f 2
L f 3
vAB
vCA
Figure 7 - LV distribution network used Case A
23rdInternational Conference on Electricity Distribution Lyon, 15-18 June 2015
Paper 0780
CIRED2015 4/5
system components and control model in real-time, in the
time domain, using the “Dommel algorithm”.
The LV grid, represented in Fig. 8, is composed by three
feeders (urban, rural, and urban-rural mixed feeder),
single and three-phase loads (with the caracteristics and
dynamics derived by the CESI load caracterization) and
18 PV inverter-based distributed generators (6 three-
phase 10 kWp, 3 three-phase 20 kWp, 4 single-phase 6
kWp, 5 single-phase 3 kWp).
Each generator is regulated in P,Q mode, where the P set-
point is generated using the P-f characteristic represented
in Figure 2 b). Indeed, the Q set-point is generated using
the Q-V characteristic represented in Fig. 2a. Generators
are synchronized to the grid voltage using a PLL and the
coupling to the grid is performed using a transformer
with short-circuit impedance equal to 6%. Finally, the
interface protection and the capability curve has been
modeled for each generator. The LV grid is fed, from the
MV grid, by a Dy11 MV/LV transformer. The grid
neutral wire is connected to the transformer secondary
winding neutral point. Lines are represented using the PI
section model, where the zero-sequence impedance takes
into account the neutral wire effect.
Figure 8 - RTDS model of the LV grid (Case B)
EXAMPLES OF SIMULATION RESULTS
In this work parametric analyses considering various
combinations of Q(V) and P(f) regulations have been
performed, taking into account the inertia of rotating
machines and the initial active and reactive power
unbalance, in order to identify the role of the different
parameters in determining islanding conditions. In the
following, few samples of the results obtained are
presented and discussed.
An Example of Results for Case A
The inverter model has been tested with dynamic load
models, including the residential and industrial model
parameters of [3]. Results show how uncontrolled
islanding operations occur in a LV network. Furthermore,
the influence of the standards regulation requirements
leads to islanding events starting from different power
balance conditions between loads and generator. Due to
space constraints, only results performed with
DIgSILENT Power Factory are reported here, but similar
results were obtained with the switching and average
Simulink models. The tests have been carried out
modifying the loads and inverter rated powers, in order to
analyze the islanded grid behavior under different initial
conditions.
Pg [kW] PL [kW]
Pg = PL 50 50.2
Pg < PL 50 59.1
Pg > PL 50 30.1
Fre
qu
ency
[H
z]
Time [s]
Vo
ltag
e p
.u.
Time [s] Figure 9 - Frequency and voltage at the LV Busbar 0.4 kV
Fig. 9 shows frequency and voltage of the islanded LV
grid portion between the standards imposed thresholds.
The uncontrolled islanded condition is facilitated by the
regulation of active and reactive power, but also due to a
regulation effect of the dynamic load model considered.
Examples of Results for Case B
RTDS simulation results are shown in Table 2. In this
case the load model parameters are based on the updated
measurements reported in Table 1.
It may be observed that:
1. With only PV static generation, without any Q(V) and
P(f) regulation, islanding is not possible even in case
of small power unbalance. The same occurs, if part of
PV generation is substituted by synchronous
machines.
2. With only PV static generation, with Q(V) and P(f)
regulation with hysteresis (according to CEI 0-21
Italian rules), islanding is not possible even in case of
small power unbalance. Instead, if hysteresis is
excluded for P(f) regulation (like requested in RfG
rules from ENTSOE), stable islanding operation is
23rdInternational Conference on Electricity Distribution Lyon, 15-18 June 2015
Paper 0780
CIRED2015 5/5
possible only if the generation is greater than the load.
This is possible because the P(f) may reduce the
generation power, according to the frequency growth,
until a new balance condition will be restored. The
same occurs, if part of PV generation is substituted by
synchronous machines.
3. With only PV static generation, with or without any
Q(V) and P(f) regulation, transient islanding is always
possible even in case of small power unbalance. In
this case the generation could be disconnected before
fast reclosing (operated on MV side) only if narrow
frequency thresholds are activated. On the other hand,
if part of PV generation is substituted by synchronous
machines, it is possible to disconnect the generation
during the fast reclosing only if a large power
unbalance is present. Again this phenomenon is due to
the inertia increment of rotating machines.
Of course, the above mentioned results have to be
considered as qualitative and not quantitative due to the
variability and uncertainty of all factors influencing the
transient to reach the island operation and during the
island operation itself: a) V and f measurement methods;
b) actuation periods of Q(V) and P(f) regulations; c)
loads behavior in function to V and f; d) power factor; e)
generators and loads inertia. These factors are not
completely determinable because, for some of them, a
reference to standards does not exist.
CONCLUSIONS
Before new network code on Requirements for
Generators (RfG), “narrow” band frequency thresholds
hindered stable island and guaranteed, with very high
probability, disconnection before fast reclosing operated
by the circuit breaker at the beginning of MV feeder.
After RfG requirements (partly introduced in some
Countries), the possibility of uncontrolled islanding
operation has significantly increased.
The conclusions of the present study are, anyway,
qualitative, because studies are valid only for the used
loads models and generators models; in particular, the
different dynamic response of the loads intentionally
adopted by the two studies, highly influences the
behaviour of the phenomena. In particular, it should be
better investigated the dynamic characterization of loads
(P and Q variation function of V and f, inertia, cos , etc)
in order to achieve sufficient level of details, not below
that of IEEE 1993 report [3] which is old and focused on
the creation of aggregations at HV level. With regards to
generators, different generators capabilities strongly
influence the system behaviour.
Finally, further potential influencing factors/elements are
not still fully investigated: fast voltage support, power
system stabilization, synthetic inertia, power factor
regulation [6], and energy storage systems. Such
elements should be included as well in dynamic studies,
in order to assess their effects on the system.
REFERENCES [1] CEI Comitato Elettrotecnico Italiano, “Standard-CEI 0-16,
Reference technical rules for the connection of active and
passive consumers to the HV and MV electrical networks of
distribution Company”, 2011-12.
[2] CEI Comitato Elettrotecnico Italiano, “Standard-CEI 0-21,
Reference technical rules for the connection of active and
passive users to the LV electrical Utilities”, 2011-12.
[3] IEEE Task Force on Load Representation for Dynamic
Performance, 1993 “Load Representation for dynamic
performance analysis”, IEEE Transactions on Power
Systems, Vol. 8, No.2.
[4] K. Tomiyama et al., 2003, “Modeling of Load During and
after System faults based on Actual Field
Data”,Proceedings IEEE Power Engineering Society
General Meeting
[5] Y. Xue, L. Chang, S. Bækhøj Kjær, J. Bordonau, and T.
Shimizu, 2004, " Topologies of Single-Phase Inverters for
Small Distributed Power Generators:An Overview", IEEE
Trans. on Power Electronics, Vol.19,No. 5, pp. 1305 - 1314.
[6] L. Cocchi , A. Cerretti et al. “Influence of average power
factor management on distribution network power losses"
CIRED 2015 Lyon conference.
Table 2 – RTDS simulation results.
Generation
type
No regulation
Q(V), P(f)
Regulation Q(V),
P(f) with histeresys
CEI 0-21
Regulation Q(V),
P(f) without histeresys
RfG
Stable island
NO NO YES (soglie strette non attive)
P%>0
NO NOYES (soglie strette non attive)
P%>0
Transient island,
not permanent
operation
YES
• Narrow tresholds enabled:<0.5 s
• Narrow tresholds disabled: <0.7 s, scatto
V
YES
• Narrow tresholds enabled: <0.6
s,
• Narrow tresholds disabled: <5 s,
trip V
YES
• Narrow tresholds enabled: <0.6 s
• Narrow tresholds disabled:<5.2 s,
large treshold trip or trip V
YES
• Narrow tresholds enabled:<0.8 s
• Narrow tresholds disabled: <1 s, scatto V
YES
• Narrow tresholds enabled:<1.5 s
• Narrow tresholds disabled: <9 s,
large strshold trip
YES
• Narrow tresholds enabled:<3 s
• Narrow tresholds disabled: <14 s,
large strshold trip
Disconnection
before FR
(0.6 s)
Frequency narrow tresholds if P%> 0%Frequency narrow tresholds if
P%> 10%
Frequency narrow tresholds if P%>
10%
Frequency narrow tresholds
If P%> 45%
Frequency narrow tresholds
If P%>99%
Frequency narrow tresholds
if P%> 99%
+
+
+