General principles of tariff.pdf
-
Upload
rajeevagrawal -
Category
Documents
-
view
26 -
download
0
Transcript of General principles of tariff.pdf
-
General Principles of
Tariff
-
Conclusion
ABT
Power Tariff Evolution
Tariff Principles
Introduction
Presentation Outlines
-
Introduction
-
What is Regulation
Regulation is defined as
The act of regulating;
A rule or order prescribed for management or government;
A regulating principle;
A percept, rule or order prescribed by superior or competent authority relating to action of those under its control
Blacks Law Dictionary
-
Electricity a concurrent subject as per Constitution of India
Both Centre and States can legislate
In case of repugnancy or conflict, Central legislation prevails
Basic Legal Framework
-
STAKEHOLDERS REGULATORY FRAMEWORK
CONSUMER
DISTRIBUTORS
GENERATORS
REGULATOR
CPPs
REGULATOR
TRANSMITTERS
TRADER
TRANSMITTERS
PX
RE
GU
LA
TO
R
GOVT.
-
The Electricity supply industry was earlier governed by three Acts i.e. before enactment of the Electricity Act- 2003, namely
Indian Electricity Act, 1910
Electricity (Supply) Act, 1948
Electricity Regulatory Commissions Act, 1998
The above three Acts now repealed in Electricity Act, 2003
History of Electricity Regulation in
India
-
Indian Electricity Act 1910 laid down basic framework for the power sector in the country along with all the policies governing the electricity supply in India
o Growth of the sector through private licensees
o Licence by State Govt.
o Provision for licence for supply of electricity in a specified area
o Legal framework for laying down of wires and other works
o Provisions laying down relationship between licensee and consumer
Indian Electricity Act, 1910
-
The supply of electricity was limited to urbanareas and most of the country was deprived ofelectricity
The situation was so grim that afterindependence not a single private organizationwas competent to administer the power supplyin the country, thereby, making way for stateparticipation in the power sector
Indian Electricity Act, 1910
-
Post-Independence Policy
The Act concentrated on increasing state monopolyover the sector by
Mandated creation of SEBs
Establishment of CEA
Need for the State to step in (through SEBs) to extendelectrification (so far limited to cities) all across the countryespecially in rural areas
As a result of this, 19 SEBs (State Electricity Boards)were formed under the Act which enjoyed monopoly overgeneration, transmission and distribution at intra-state level
However the power situation lacked in quality, security andreliability
Electricity (Supply) Act, 1948
-
Main amendments to the existing Acts
1956 Amendment- to increase role of State Govt to monitor SEBs
Amendment in 1964 to enable REBs
Amendment in 1975 to enable generation in Central sector
Amendment to bring in commercial viability in thefunctioning of SEBs Section 59 amended to make the earning of a minimum return of 3%
on fixed assets a statutory requirement (w.e.f 1.4.1985)
Amendment in 1991 to open generation to private sector (foradditional capacity requirement) and establishment of RLDCs
Amendment in 1998 to provide for private sectorparticipation in transmission and also provision relating toTransmission Utilities
Legal Framework Old Laws
-
In order to strictly implement reforms and rationalizing of thetariff structure, second generation reforms were introduced
In 1998 the GOI implemented The Electricity RegulatoryCommission Act, 1998
It emphasized on the establishment of state and central levelelectricity regulatory commissions (ERCs) (independentregulatory bodies) for rationalizing the tariff structure, creatingtransparency in policy formulation, to frame and promoteefficient and environmentally benign policies and for greaterinvolvement of private participation
Objective distancing of Govt./Govt. organization fromfunctioning of SEBs i.e. regulation and tariff determination
Electricity Regulatory Commission
Act, 1998
-
Resultant Industry Structure
-
Need for New Legislation
The SEBs incurred heavy loses and failed to make the necessarypayments to the CPSUs, owing to their bulky design, these utilitieswere inevitably becoming cumbersome to manage, therefore, theadministration decided to unbundle the utilities into more'manageable' size which paved the way for the Electricity Act 2003
Requirement of harmonizing and rationalizing the provisions in the existing laws to a self-contained comprehensive legislation
Create competitive environment which would result in enhancing quality and reliability of services to consumers
Distancing of Govt. from regulatory responsibilities
Obviating need for individual States to enact their own reform laws
Requirement of introducing newer progressive concepts like power trading, open access, Appellate Tribunal etc.
Special provision for the Rural areas
-
Regulatory Milestones
1910 1948 1975 1998 2003
IE Act ES Act EA Central Utilities ERC ACT
British India-
agglomeration of provincesIndian Union
Isolated Private LicenseesIsolated
SEBs
Regional
SystemCentral Utilities Central Utilities, IPPs,
CTU, SEBs
Early British Model State Govt Central Govt Regulator
Country
Status
Sectoral
Makeu
p
Institutional
Structure
Electricity Regulation in India
-
This Act seeks to consolidate
The laws relating to generation, transmission, distribution, trading and useof electricity
Taking measures conducive to development of electricity industry,promoting competition
Protecting interest of consumers and supply of electricity to all areas, Rationalization of electricity tariff ensuring transparent policies regarding
subsidies
Promotion of efficient and environmentally benign policies Constitution of Electricity Regulatory Commissions to rationalize electricity
tariff and establishment of Appellate Tribunal and for matters connected
Electricity Act, 2003 - enacted June 10th 2003, envisages development in an open, nondiscriminatory, competitive, market driven environment in the interest of the consumers/ suppliers of power
Legal Framework
Electricity Act-2003
-
Objectives of
Electricity Act
2003
Liberal Framework
Competitive Environment
Private Investments
DelicensesGeneration
Rural Distribution Delicenced
Controlling Theft of
Electricity
Restructure Electricity
Boards
Regulatory Commission/
Appellate Tribunal
Open Access
Trading
Competitive Bidding
-
Industry Structure After Electricity Act 2003
-
National Electricity Policy and Plan
Central Govt. to prepare National Electricity Policy and TariffPolicy in consultation with State Govt. and CEA Feb 05
National Electricity Plan for a period of 5 years issued by CEAin accordance with National Electricity Policy Aug 07
National Policy on rural electrification including stand alonesystems (including renewable and non-conventional energysources) to be issued by Central Government in consultationwith State Government Aug 06
Policy for electrification and distribution in rural distributionPanchayats, Co-operatives, NGOs, franchisees
Rule Making through Notifications for carrying out various provisions of the Act
Powers to issue directions to the Regulatory Commissions on issues involving public interest
Role of Government
-
Total village electrification by year 2010
By year 2012 :
Per capita availability 1000 units
Installed capacity over 200,000 MW
Spinning reserves 5%
Minimum lifeline consumption of 1 unit per household per day
Inter-regional transmission capacity 37,000 MW
Energy efficiency/ conservation savings about 15%
National Electricity Policy
-
Mandates competitive procurement of power andtransmission services transitional window of 5 years periodgiven to public sector companies
Encourage efficiency in operations by sharing of gains betweenlicensees and consumers
Promote Multi-Year Tariff (MYT) framework
Encourage loss reduction Strategies
Tariff design : Linkage of tariffs to cost of service
gradual reduction in cross subsidy (+/- 20% of average costof supply)
Progressive reduction in Cross-subsidy surcharge for openaccess
Tariff policy - Jan 06
-
Tariff Principles
-
o Electricity Provides consumers with the ability torealize numerous conveniences in their everydaylives
One does not buy electricity as an end product
o One buys electricity as an input which is then utilizeto produce consumable goods or services or to enjoydomestic comforts
Features of Electricity
23
-
Electricity is different from other commodity
o Electricity is not Visible
o It can not be touched
o It can not be stored
o Production & Consumption of
electricity inseparable
o Can only be sent through wires
o Travels at a speed of light
o Can not carry a brand mark
o Transfer of ownership is not possible
o It obeys laws of physics
o Electricity has demand side flaws
Features of Electricity
24
-
Tariff should provide correct pricing signals toinvestors as well as consumer
Protection of consumer interest and alsoinvestors risk by Stable and predictable over aperiod of time
Appropriate incentive for efficiencyenhancement and rational use of energy bysuppliers and consumers
Tariff Principles
25
-
Economic conservation of societal resources,i.e. scarce national economic resources mustbe allocated efficiently
Socio-economic need of the country, i.e. tariffmust be made affordable to all sectors of theeconomy and minimum level of service evento the low income group of the society
Transparency and simplicity in determinationof tariff
Encourage market determination of prices
Tariff Principles
26
-
Institutional Arrangement Options
Government monopoly
Private monopoly without regulation
Private monopoly with (National, Regionalor Local) regulation
Two Basic Regulatory Forms
Rate-of Return (ROR) also known as Cost-of-Service (COS)
Performance Based Ratemaking (PBR)
Tariff Principles
27
-
In ROR regulations, role of regulation is toencourage enough investment to meetcustomer demand and to compensate investorswith a reasonable rate of return
Under ROR or COS regulation, regulatordetermines The value of invested capital The allowed rate of return on invested capital Appropriate expenses
Required Revenue = Expenses + {allowed rateof return x (Allowed Investment)}
Tariff Principles ROR
28
-
Performance Based Ratemaking (PBR) orincentive regulations sets performance targets -both operational and financial for utility
The return to the utility depends uponperformance, over achievement of theperformance criteria can increase returns for theutility while underachievement will decreasereturns
"Light Handed" regulation i.e. least interferenceby the regulators
Tariff Principles PBR
29
-
Establishment of extensive data base forbenchmarking performance criteria on the basisof industry best practices, historic data etc. areessential component for effective regulationunder this method
A form of PBR is in actual use in India, wheretariffs are based on normative parameters
PBR weakens the link between a utilitysregulated tariff and its costs by increasingregulatory lags which also provides incentivesfor cost reduction
Tariff Principles PBR
30
-
Regulation is intended to serve as an offset tothe monopoly situation
Regulatory agencies are charged withresponsibilities to balance the interest of bothcustomer and utility
Regulation strives to keep price as low aspossible for consumers while allowing theutility to earn a fair return on its investment
Tariff Principles
31
-
To achieve this balance, regulator generallyoperate from a position that prices should bebased upon costs
o Cost plus mechanism
To bring accountability and performanceenhancement PBR element is introduced in thecost plus structure
Electricity Pricing
32
-
Power Tariff Evolution In India
-
Single part Two part- K P Rao
ABTMarket Based
Mutually Agreed Govt. of India
Regulatory Commission
Evolution of Power Tariff
Competitive Bidding
34
-
Pricing of power prior to 1992 in India
The rate of power was fixed by GOI on the basis of
reasonable ROE at the then operating PLF level
Both Fixed Charges and Variable Charges realized in
one part as energy charge Existed before NTPC
Initially adopted for NTPC
The rates were very liberal and in favor of generators
Tariff was not related to availability or frequency
Calculated so as to cover both the fixed cost as well as
variable (energy) cost at a certain (normative)
generation level
Single Part Tariff
35
-
Single Part Tariff
36
-
Single Part Tariff was conducive neither toeconomic generation of power and itsabsorption by boards as per merit order, nor tosatisfactory operation of regional grid
Distorts Economic Dispatch (Merit Order Operation)
SEBs found that total cost to be paid to GENCOswas higher than the marginal cost of theirstation
Under drawal accrues monetary benefit tobeneficiaries
Shortcomings of Single Part Tariff
37
-
With Actual Generation Level much higher thannormative, collection of fixed charges was muchhigher than the fixed charges agreed
GENCOs resorted to dumping power even whenfrequency was high
Led to sharp difference between Central SectorGencos & SEBs on who should back down
Shortcomings of Single Part Tariff
38
-
The Central Government constituted a Committee in 1989 togo into the issues of Power Sector and recommend a tariffstructure
The Committee submitted its report on Principles and Normsfor Tariff Fixation of Central Sector Generating Stations inJune 1990
GOI adopted a Two Part Tariff formula for NTPC stations in1992 based on K. P. Rao Committee recommendations
Fixed Charges and Variable Charges computed separately
Fixed Charges compensate for the cost of capacity,including investment cost
Variable Charges compensates for cost of energy
Laid down fairly sound costing principles
K. P. Rao Committee
39
-
Fixed charges Return on equity O&M charges Interest on loans Interest on working
capital Depreciation
Variable Charge Primary fuel (Coal/Gas) Secondary fuel Oil
Recovery of charges Fixed charges recoverable at
62.8% PLF (i.e. actual generationplus deemed generation)
Incentive at the rate of 1paisa/kWh for every 1% increasein PLF above 68.5%
Disincentive at graded reductionin fixed charges below 62.8%subject to a minimum of 50% offixed charges at nil generation
Fixed charges and incentives/disincentive are paid bybeneficiaries in proportion totheir energy drawals
Variable charges in paisa/kWhsubject to fuel price adjustment
Recommendations
40
-
Two Part Tariff
41
-
Did nothing for promoting grid discipline Low frequency during peak hours High frequency during off-peak hours Rapid changes in frequency and fluctuating voltages
Reasons K. P. Rao Committee tackled only Central Generating Stations Conflicting commercial interest of stakeholders- SEBs/CGS 50% FC is assured to generating stations even at 0% PLF Lack of generating capacity and transmission systems No penalty for jeopardizing the GRID Over-drawals by SEBs during peak-load hours and under-
drawals during off-peak hours continued unabated, causingserious frequency excursions
Shortcomings of K. P. Rao
Committee Recommendations
42
-
SEBs/CGs have conflicting commercial interests
Absence of direct incentives or penalties to control this
Lack of generating capacity and transmission systems
One SEB suffers for nonperformance of other
Off-Peak
Peak
Did not encourage grid discipline
43
-
Problems in grid operation
Load
(MW)
Time (hours)
Low frequency:
48 48.5 Hz
Off-Peak
Peak
High frequency:
50.5 51 HzRapid change:
1 Hz in 5 10 minutes;
many hours everyday
1 2 3
Frequent grid disturbances:
Generator tripping, supply interruptions,
grid disintegration
4
Freq.
(Hz)
44
-
The Central Government considered further structuralreforms in bulk power and transmission tariff to inducebetter system operation and grid discipline through amechanism of commercial incentives and disincentives
M/S ECC of USA were commissioned under a grant fromADB to undertake comprehensive study of Indian powersystem and recommend a suitable tariff structure
ECC submitted its report in February, 1994, recommendedAvailability Tariff for generating stations, which wasaccepted in principle by GOI in November, 1994
A National Task Force (NTF) was constituted by MoP inFebruary, 1995 to oversee the implementation of ECCsrecommendations
Based on NTF deliberations between 1995 and 1998, MoPnotified a draft notification of ABT in 1999
Availability Based Tariff
45
-
Electricity Regulatory Commissions Act, 1998 Providesfor establishment of CERC at Central level and SERC atState levels
CERC was formed in May,1999
Date of implementation of ABT
oWestern region: 1.7.2002
o Northern region: 1.12.2002
o Southern region: 1.1.2003
o Eastern region: 1.4.2003
o North Eastern region: 1.11.2003
Availability Based Tariff
46
-
ISGS 500 MWe
Aux
30 MWe
470 MWe ex-bus
SEB1 SEB2
loss is distributed to
all the constituents in
proportion to
schedule
o Installed Capacity
o Aux Power (%)
o Declared Capability
o NAPAF (%)
o Scheduled Generation
o AFC (Rs.)
o ECR (Rs./kWh) on ex-bus basis
o GHR (kcal/kWh)
Relevant Terms
47
-
Auxiliary power consumption or AUX is the quantum of energyconsumed by auxiliary equipment and transformer losses withinthe generating station, expressed as a percentage of the sum ofgross energy generated at the generating terminals of all theunits of the generating station
Declared capacity (DC) means the capability of the generatingstation to deliver ex-bus electricity in MW declared by theGenco in relation to reference period considering availability ofFuel/ water
Plant Availability Factor (PAF) means the average of the dailydeclared capacities (DCs) expressed as a % of the installedcapacity in MW reduced by the normative auxiliary energyconsumption
Scheduled Generation (SG) with reference to any period is theschedule of generation in MW ex bus as given by Load DispatchCentre
Some Definitions
48
-
Gross Station Heat Rate means the heat energy inputin kcal required to generate one kWh of electricalenergy at generator terminals of a thermal generatingstation In case of coal stations:
(i) Coal consumed in kg/kWh is converted into kcal bymultiplying with GCV of coal
(ii) Heat due to oil consumption in kcal
Gross Calorific Value means the heat produced inkcal by complete combustion of one kilogram of solidfuel or one litre of liquid fuel or one standard cubicmeter of gaseous fuel, as the case may be;
Some Definitions..
49
-
For Thermal generating station
o Capacity Charge (for recovery of annual fixed cost)linked to availability and are recovered at Normativeavailability & pro-rata recovery below norm
o Energy charges (for recovery of primary fuel cost)linked to scheduled generation and are based onactual fuel cost and normative operating parameters
o UI charges (real time pricing) are linked to frequencyand are levied on deviations from schedules
Components of Tariff
50
-
UNSCHEDULED INTERCHANGE (UI) CHARGES
o Variation between actual generation or actual drawaland scheduled generation or scheduled drawalaccounted for through Unscheduled Interchange (UI)Charges
o UI for a generating station shall be equal to its actualgeneration minus its scheduled generation
o UI for a beneficiary shall be equal to its total actualdrawal minus its total scheduled drawal
o UI worked out for each 15 minute time block
o Charges for all UI transactions shall be based onaverage frequency of the time block
Availability Based Tariff concept
51
-
Unscheduled Interchange (UI)
Charges
Frequency (Hz)
UI C
ha
rge
s (
Pa
isa
)
52
-
Gen
Beneficiary
Load
Import = Load - Gen
For beneficiary: UI = Import Scheduled drawal
For CGs: UI = Actual sent out Scheduled generation
UI Charges
53
-
Encourage merit order
generation
Save natural resources
Help protect environment
Establish a level playing field
for all the constituents
No conflicting commercial
interests
Ensure grid stability
Protect equipments
Gen
Beneficiary
Load
Import = Load -
Gen
States additional power
requirement can be met by its
reserved generating stations
(DG, Pump storage, GT etc. or
import from CGs)
ABT Rational Tariff Structure
54
-
Energy is metered in 15 min Time Block
UI (Metered Scheduled) energy payments are made into and
from UI pool account operated by the concerned RLDC
Deviation from Schedule
55
-
Decentralised Scheduling
Availability
DeclarationEntitlements
S
L
D
C
Requisition &
Bilateral Agreements
Injection Schedule Drawal Schedule
Revision in DC Revision in Requisition
Final
Injection ScheduleFinal
Drawal Schedule
08:00
10:00
15:00
18:00
22:00
23:00
R
L
D
C
I
S
G
S
Time
Revisions during
Current dayRevisions during
Current day
0 to 24
hours 56
-
The station foresees a capability to deliver 900 MW(ex-bus) on the next day, and advises the same to theRLDC by 8 AM
The RLDC would break it up, and advise the SLDCs by10 AM that their entitlements in the CGS for the nextday
Entitlements in the other Central stations would alsobe advised by RLDC to the SLDCs similarly
Simultaneously, the SLDCs would receive availabilitystatus from their intra - state stations as well
Day by Day Scheduling
57
-
They would then carry out a detailed exercise as tohow best to meet the expected consumer demand intheir respective States
For this, they would compare the variable costs ofvarious intra - state power stations, and with energycharge rates of the CGS
The total dispatch schedule for the CGS of 900 MWduring the day time and 740 MW during the nighthours
Daily Scheduling Process
58
-
This would be issued by the RLDC by 5 PM, andwould be effective from the following midnightunless modified in the intervening hours
States A, B and C shall pay CC for the whole daycorresponding to DC of 270, 270 and 360 MW andthe GS would get CC corresponding to 900 MW
EC payments by the three States would be for 270 x24 MWh, 270 x 24 MWh, and (200 x 24 + 160 x 16)MWh at the specified EC rate of the generatingstation
Daily Scheduling Process
59
-
Daily Scheduling Process
60
-
The two areas marked X represent the off-peak
hour capability of the Central generating station
Back down the station during off-peak hours
The station gets CC for the day corresponding to
its DC (900 MW), and EC to fully recover its fuel
cost for generating the scheduled quantum of
energy
Options for Generating Stations
61
-
Find a buyer (other than State - C)
As long as the energy sale rate agreed upon ishigher than the fuel cost per kWh of the station
It would also reduce the technical problemsassociated with backing down of the station andimprove the stations efficiency
The agreement has to be non-firm or interruptible
Low price
Trading Opportunity for Generating
Stations
62
-
The station may accept the schedule given by the
RLDC, but generate power to its full capability of
900 MW even during off-peak hours
Earn UI*
Options for Generating Stations
63
-
The options for the generating station arise only in case
a State has not requisitioned its full entitlement
In fact, the same three options are available to State-C,
before they get passed on to the Central station
Requisition power from the Central station only as per
its own requirement, and draw power as per the
resulting schedule
Options for States
64
-
Requisition full entitlement of 360 MW from the
Central station for the entire 24 - hour period, find a
buyer for the off-peak surplus, and schedule a
bilateral sale
This would make sense as long as the sale rate
per kWh is more than the energy charge rate of
the Central station
Trading Opportunity for States
65
-
Requisition the full entitlement for the entire 24 -
hour period, but draw power only according to its
actual requirement
Earn UI*
Availability of various and similar options, both for
the beneficiaries and for the generating companies,
means that the mechanism is sound and equitable
Options for States
66
-
A frequency pattern would emerge depending on the daily
profile of the total system load and the generation mix
The corresponding UI rate profile shall reflect the daily pattern of
the system marginal cost
System Marginal Price Pattern
67
-
Frequency (Hz)
UI
rate
pa
ise
/kW
h
0
100
200
300
400
500
600
700
800
900
1000
279, 49.92132, 50.04
LC PH
Un
it lo
ad
(%
)
States marginal gen cost will move down towards the
prevailing UI rate
Gen station will maximize its gen as long f < its threshold f
UI Rate Vs System Marginal Cost
68
-
0100
200
300
400
500
600
700
800
900
1000
49.50
49.52
49.54
49.56
49.58
49.60
49.62
49.64
49.66
49.68
49.70
49.72
49.74
49.76
49.78
49.80
49.82
49.84
49.86
49.88
49.90
49.92
49.94
49.96
49.98
50.00
50.02
50.04
50.06
50.08
50.10
50.12
50.14
50.16
50.18
50.20
50.20
Frequency Based Dispatch
69
-
70