GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS...
-
Upload
earl-fitzgerald -
Category
Documents
-
view
214 -
download
0
Transcript of GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS...
![Page 1: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/1.jpg)
GEMI EHS-IMS Survey
PresentedJune 25, 2003
Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members
![Page 2: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/2.jpg)
2
Summary
28 companies responded Type of respondents Non-EHS providing input No. of facilities that apply to this
survey Min 2, Max 1500, Mean 176, Med 70
![Page 3: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/3.jpg)
3
7. Does the organization for which this survey is completed include domestic facilities, international facilities, or both?
Domestic26%
Both70%
International4%
![Page 4: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/4.jpg)
How EHS-IMS Fits into Environmental, Health,
and Safety Management
![Page 5: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/5.jpg)
5
8. Does your organization have an Environmental Management System in place?
No7%
Yes93%
![Page 6: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/6.jpg)
6
9. Is EHS-IMS an essential component of environmental management?
Integral58%Exists
19%
Absent23%
![Page 7: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/7.jpg)
7
10. Does your organization have a Health & Safety management system in place?
Yes92%
No8%
![Page 8: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/8.jpg)
8
11. Is EHS-IMS an essential component of your health and safety (H&S) management?
Integral54%Exists
25%
Absent21%
![Page 9: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/9.jpg)
9
12. What percentage of your environmental information needs are managed with the EHS-IMS?
Count – 27 Min - 0% Max - 80% Mean - 37% Median - 35%
![Page 10: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/10.jpg)
10
13. What percentage of your H&S information needs are managed with the EHS-IMS?
Count - 25 Min – 0% Max – 90% Mean – 38% Median – 25%
![Page 11: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/11.jpg)
EHS-IMS Vision
![Page 12: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/12.jpg)
12
14. Has your organization developed one over arching plan that defines a long-term, strategic direction for EHS-IMS within your entire organization?
No54%
Yes46%
![Page 13: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/13.jpg)
13
15. How far along is your organization in executing the plan?
Count – 13 Min – 5% Max – 100% Mean – 47% Median – 40%
![Page 14: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/14.jpg)
14
16. Does your EHS-IMS strategic plan provide general direction/goals or specific actions/timelines?
Other0%
Both54%
Specific8%
General38%
![Page 15: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/15.jpg)
15
17. Identify your greatest roadblock in fulfilling your EHS-IMS needs.
Resources44%
Budget21%
No Roadblocks14%
Other: Willingness of business units to migrate from local legacy systems; implementation
7%
Undefined Needs
7%
Technology7%
![Page 16: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/16.jpg)
16
18. What are the top three needs you would like to see fulfilled in the EHS-IMS market?
18/26 - Integration with internal data source systems (e.g. ERPs - includes SAP & PeopleSoft, HRPs, LIMS, CEMS, etc)
12/26 - Better ability to manage EHS information organization-wide 10/26 - Greater flexibility in applications to better match business
needs 9/26 - Move from client-server to web applications 7/26 - Lack of confidence in the viability / experience / longevity of
vendors in the marketplace 6/26 - Improvement in user-friendliness of applications 4/26 - Need for better Commercial Off-the-Shelf (COTS) applications 4/26 - Electronic Reporting – internal 3/26 – Other: Multi-language issues, more compelling cost-benefit
case, consensus business needs 2/26 - Electronic Reporting – agencies 2/26 - Interfacing with external systems (vendors, clients, etc.)
![Page 17: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/17.jpg)
System Justification
![Page 18: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/18.jpg)
18
19. Does your organization require justification to purchase and implement EHS-IMS?
No14%
Yes86%
![Page 19: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/19.jpg)
19
20. Is there a standard procedure you are required to follow when justifying any information management system?
No4%
Yes96%
![Page 20: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/20.jpg)
20
21. Which statement best describes your justification procedure?
50%38%
8%4% Standard developed
by IT dept.
Standard developedby depts. other thanIT
Standard developedby all or part of theEHS function
Other: Businesscase - cash flow rateof return and NPV
![Page 21: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/21.jpg)
21
22. What justification factor(s) must be met to get a system approved? (Choose all that apply)
18/24 - Compliance requirements 18/24 - Return on investment
demonstration (cost savings) 16/24 - Better alignment with other
initiatives (e.g. IT initiatives) 6/24 – Others: Value added and appears to work,
cost effectiveness for business needs, some of the above but not all, availability of resources to work on project, qualitative business case, business needs
![Page 22: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/22.jpg)
22
23. Are there systems that you need but are unable to purchase or develop?
No54%
Yes46%
![Page 23: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/23.jpg)
23
24. What tools do you currently use to meet those needs now?
Manual processes
13%
Spreadsheets and other non-EHS software packages
54%
Other33%
![Page 24: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/24.jpg)
24
25. What major justification factors are not being met for these systems?
No budget to move forward
31%
System not necessary
for compliance
31%
Other15%
No adequate return on
investment23%
![Page 25: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/25.jpg)
25
26. Provide a short description of one major or significant EHS-IMS you have implemented
Please refer to attached material
![Page 26: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/26.jpg)
26
27. In reference to the system you described in Question 26, what were the benefits (both financial and non-financial)? If you have not yet conducted a benefits analysis, but plan to, what do you anticipate the benefits analysis will show?
Less benefits
than expected
4%
No benefit0%
More benefits
than expected
26%
No benefit analysis
conducted40%
Benefits expected
30%
![Page 27: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/27.jpg)
EHS-IMS Structure
![Page 28: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/28.jpg)
28
28. Is the organization that supports your EHS IT needs across your organization…
4%4%
7%
19%
15%
51%
Completely centralized
More centralized thandecentralized
More decentralized thancentralized
Completely decentralized
Outsourced
Other: Centralized within onegroup assigned to EH&S;Internal to Env. Dept.
![Page 29: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/29.jpg)
29
29. For your organization, identify which EHS areas have automated data management systems (may include spreadsheets, independent databases and EHS-IMS) by selecting the highest level at which they exist - corporate/business unit OR facility. In addition, if the system is part of your EHS-IMS and not stand alone, check the box under "part of EHS-IMS".
EHS-IMS 66.7% (16/24)
• Incident Reporting 59.1% (13/22)
• Metric Roll Up 55.0% (11/20)
• MSDS Authorizing 52.2% (12/23)
• Audit and Follow-up Corrective Action
![Page 30: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/30.jpg)
30
29. For your organization, identify which EHS areas have automated data management systems (may include spreadsheets, independent databases and EHS-IMS) by selecting the highest level at which they exist - corporate/business unit OR facility. In addition, if the system is part of your EHS-IMS and not stand alone, check the box under "part of EHS-IMS".
Corporate/Business 95.7% (22/23)
• Audit and Follow-up Corrective Action 91.7% (22/24)
• Incident Reporting 91.3% (21/23)
• Safety - Employee 90.9% (20/22)
• Metric Roll Up
![Page 31: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/31.jpg)
31
29. For your organization, identify which EHS areas have automated data management systems (may include spreadsheets, independent databases and EHS-IMS) by selecting the highest level at which they exist - corporate/business unit OR facility. In addition, if the system is part of your EHS-IMS and not stand alone, check the box under "part of EHS-IMS".
Facility 82.4% (14/17)
• Asbestos 75.0% (12/16)
• PCB Management 75.0% (12/16)
• Stormwater 72.2% (13/18)
• Process Wastewater
![Page 32: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/32.jpg)
32
30. In general, what are the most valued functions provided by the systems referred to in Question 29? (choose no more than 3)
22/26 - Central repository for data 14/26 - Provide reports for analysis 14/26 - Provide internal/external distribution of EHS
information (non agency) 8/26 - Provide EHS-relevant notifications and reminders 7/26 - Provide reports for agency submittal 5/26 - Knowledge Retention 4/26 - Perform complex calculations 2/26 – Collaboration 1/26 – Other: Continuous improvement through performance
monitoring, trending and tracking of issues at the lowest level
![Page 33: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/33.jpg)
33
31. Where the systems referred to in 5.2 are not standardized across the organization, how is the information managed when consistent data formats are needed (e.g. roll up data)?
43%
15%
23%
15%
4%Each system administrator isresponsible for supplying dataoutput in standard format
Data is provided in the differentformats and made consistentonce collected
The roll up system interfacesdirectly with each differentsystem (0%)
Must be done manually
Combination of any of theabove
Other: EHS site reps key indata
![Page 34: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/34.jpg)
34
32. Where the systems referred to in Question 29 are not standardized across the organization, identify the major contributing factor.
Technical Factors
8%People Factors
42%
Business Factors
23%
Other: All of the above; business
justification; organizational
structure; specific differences
requiring judgement and
analysis27%
![Page 35: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/35.jpg)
35
33. What types of the following information management technologies and tools do you use or are planning to use for managing EHS needs? (Choose all that apply)
Use Now 85.7% (12/14)
• Collaboration Tools 70.6% (12/17)
• Web tools developed using .NET, J2EE, or other
70.0% (14/20)• Document Management
61.9% (13/21)• EHS Content
Management Tools 50.0% (10/20)
• Knowledge Management Tools
Plan To Use 60.0% (12/20)
• Knowledge Management Tools
42.9% (9/21)• EHS content
Management Tools 40.0% (8/20)
• Document Management 35.3% (6/17)
• Web tools developed using .NET, J2EE, or other
21.4% (3/14)• Collaboration Tools
![Page 36: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/36.jpg)
Non-EHS Systems Interfacing
![Page 37: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/37.jpg)
37
34. Do(es) your EHS-IMS interface directly to non-EHS systems for the purpose of retrieving and/or depositing data?
No46% Yes
54%
![Page 38: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/38.jpg)
38
35. What percentage of your EHS-IMS interface(s) to source data?
Count – 13 Min – 5% Max – 60% Mean – 19% Median – 10%
![Page 39: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/39.jpg)
39
36. In general, what type of data sources interface with your EHS-IMS? If you select ERP, also select the other options if they apply, such as HR, regardless of whether or not that option is part of the ERP. (choose all that apply)
9/14 - Human Resource Systems 6/14 - Enterprise Resource Planning System (includes
SAP & PeopleSoft) 5/14 - Purchasing Systems 4/14 - Manufacturing Resource Planning System 3/14 – Other: claims data, notes mail, security 2/14 - Financial Systems 2/14 - Process Controls 1/14 - Receiving Systems 1/14 - CEMS Systems 1/14 - Laboratory Information Management Systems
![Page 40: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/40.jpg)
40
37. Please provide any example(s) where your EHS information management systems use source data
Please refer to attached material
![Page 41: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/41.jpg)
Metrics Tracking
![Page 42: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/42.jpg)
42
38. Do you have a metric roll up program within your organization?
Yes85%
No15%
![Page 43: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/43.jpg)
43
39. For what purpose(s) are you rolling up metric data?
21/23 - Internal management reporting 20/23 - EHS or Sustainability reporting 17/23 - Analysis for optimization 14/23 - Shareholder reporting (annual
reports) 10/23 - Other non-agency external
reporting 9/23 - External agency reporting
![Page 44: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/44.jpg)
44
40. How are metrics used for roll-up collected?
14/22 - Spreadsheet consolidation 13/22 - Web-based metric input 10/22 - Email/Fax reporting 9/22 - Client-Server based metric input 4/22 - Data automatically "retrieved" from
other systems 1/22 - Other: CHESS program, Lotus Notes
![Page 45: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/45.jpg)
45
41. Identify your primary data sources for roll up metrics used for EHS performance. EHS performance includes areas beyond compliance, such as energy and water use. If you select (Enterprise Resource Planning) ERP systems, also select the other options if they apply, such as HR, regardless of whether or not that option is part of the ERP.
12/21 - EHS-IMS 9/21 - Human Resource Systems 8/21 - Other: Spreadsheets, Custom systems; In-house designed web-
based system (collection), Cognos Powerplay (reporting); Incident Mgmt. System; Security; Lotus Notes Databases; Plant Operations Data
7/21 - Enterprise Resource Planning System 5/21 - Purchasing Systems 5/21 - CEMS Systems 4/21 - Manufacturing Resource Planning System 4/21 - Financial Systems 3/21 - Receiving Systems 3/21 - Laboratory Information Management Systems 2/21 - Process Control Systems
![Page 46: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/46.jpg)
Computer-Based EHS Training
![Page 47: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/47.jpg)
47
42. Does your organization use CBT, to any extent, for EHS training needs?
No15%
Yes85%
![Page 48: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/48.jpg)
48
43. What percent of your EHS training needs are satisfied by CBT?
Count – 22 Min – 5% Max – 90% Mean – 40% Median – 40%
![Page 49: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/49.jpg)
49
44. How is CBT delivered to students?
19/23 - Web-based (internal) 12/23 - CD ROM 9/23 - Web-based (ASP) 6/23 - Client-Server based
![Page 50: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/50.jpg)
50
45. What types of CBT media are utilized?
20/22 - PowerPoint-type material 18/22 - Self-paced applications 6/22 - Digital Video (Local) 6/22 - Digital Video (Streaming) 1/22 - Interactive Satellite Feed 1/22 - Dreamweaver
![Page 51: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/51.jpg)
51
46. At this time, are you satisfied with the how CBT has met the training needs in your organization?
Yes57%
No43%
![Page 52: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/52.jpg)
52
47. Do any of the following factors limit your organization's ability to use CBT for EHS training needs?
11/23 – Other: Effectiveness and high costs; Need global programs; Infrastructure; Familiarization with CBT; E is more challenging that HS and general awareness is easier to provide than job-customized; Lack of financial support – low priority; Personnel ability to use systems; Language (foreign); Ability to create content in timely fashion; Resistance to change; Network and IS limitations
10/23 - Depersonalization of training 6/23 - Training regulatory requirements 3/23 - Privacy issues 3/23 - No limiting factors 2/23 - Union requirements
![Page 53: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/53.jpg)
53
48. In general, what percentage of each of the following resources do you use for development and implementation of your EHS-IMS? (total should add to 100%)
49. In general, what percentage of each of the following resources do you use for maintenance of your EHS-IMS? (total should add to 100%)
Please refer to attached material
![Page 54: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/54.jpg)
EHS-IMS Resources
![Page 55: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/55.jpg)
55
50. Over the last two years, has your organization increased or decreased use of outsourced resources for your EHS-IMS needs?
Resources not
outsourced8%
Increased31%
Decreased12%
Unchanged49%
![Page 56: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/56.jpg)
56
51. Over the last two years, has your organization increased or decreased use of internal resources for your EHS-IMS needs?
Decreased8%
Resources completely outsourced for past 2
years0%
Increased27%
Unchanged65%
![Page 57: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/57.jpg)
57
52. How much support and attention does the IT group used by your organization, whether internal, outsourced, or dedicated IT staff within EHS, provide to EHS applications vs. non-EHS applications?
EHS no support from IT
0%
EHS more than non-
EHS12%
EHS same as non-EHS
52%
EHS less than non-
EHS36%
![Page 58: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/58.jpg)
58
53. How does your organization manage the support of EHS-IMS? (IT support may be internal or outsourced)
11/25 - EHS-IMS is part of normal IT support processes
10/25 - EHS has personnel with EHS background trained to support EHS-IMS
8/25 - EHS has personnel with IT background trained to support EHS-IMS
3/25 - EHS-IMS is part of normal IT support processes, but has lower priority
1/25 - EHS manages EHS-IMS support without IT group support
1/25 - Other: Both EHS & IT support
![Page 59: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/59.jpg)
IT Alignment withEHS-IMS
![Page 60: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/60.jpg)
60
54. Are EHS-IMS platforms and applications required to align with internal IT standards?
Not required, but
voluntarily align0%
Not aligned, or no internal IT standards
4%
Required to align
96%
![Page 61: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/61.jpg)
61
55. Are there gaps between your current EHS-IMS and internal IT standards?
No IT standard
exists4%
No46%
Yes27%
Don't know23%
![Page 62: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/62.jpg)
62
56. Does your company's current IT infrastructure limit EHS-IMS initiatives?
Yes47%
No38%
Don't know15%
![Page 63: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/63.jpg)
63
57. At this time, is internal IT infrastructure changing significantly within your organization?
Yes35%
No65%
![Page 64: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/64.jpg)
64
58. Are changes affecting EHS-IMS initiatives?
Yes78%
No22%
![Page 65: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/65.jpg)
65
59. Does EHS have a strategy to keep up with changing IT infrastructure?
Yes67%
No33%
![Page 66: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/66.jpg)
Application Selection
![Page 67: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/67.jpg)
67
60. Does your organization currently have a process for evaluating and selecting EHS-IMS applications?
Yes78%
No22%
![Page 68: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/68.jpg)
68
61. How are applications evaluated within your organization?
Other0%
Individual or very few
stakeholders10% Internal
team and outside
consultants29%
Internal team61%
![Page 69: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/69.jpg)
69
62. If you were evaluating a Commercial, Off-the-Shelf EHS application, all else being equal, what would most likely be your organization's overriding factor for selecting one?
More closely
matching IT needs
14%
Cost19% More
closely matching
EHS needs67%
![Page 70: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/70.jpg)
Miscellaneous
![Page 71: GEMI EHS-IMS Survey Presented June 25, 2003 Developed in conjunction with Rick Mock of EDSG, the IMS Workgroup, and other participating GEMI members.](https://reader030.fdocuments.in/reader030/viewer/2022032803/56649e305503460f94b2034b/html5/thumbnails/71.jpg)
71
64. If you are using third party EHS-IMS for managing environmental or EHS information, list here if you would not mind sharing this information with other companies.
Please refer to attached material
63. If you are using third party software for managing EHS regulations and would not mind sharing this information with other GEMI companies, enter software name and if it is implemented at the corporate/business unit or facility level.